BASE London – DE panel discussion 11 th July 2013

9
1 BASE London – DE panel discussion 11 th July 2013 District Energy strategy into reality Turning

description

BASE London – DE panel discussion 11 th July 2013 . District Energy strategy . Turning. into reality. BASE London – DE panel discussion 11 th July 2013 . Contents . Context Connection Capital Capacity. BASE London – DE panel discussion 11 th July 2013 . Why District Energy ?. - PowerPoint PPT Presentation

Transcript of BASE London – DE panel discussion 11 th July 2013

Page 1: BASE London – DE panel discussion  11 th  July 2013

1

BASE London – DE panel discussion 11th July 2013

District Energy strategy into reality

Turning

Page 2: BASE London – DE panel discussion  11 th  July 2013

2

Contents BASE London – DE panel discussion 11th July 2013

1. Context2. Connection3. Capital4. Capacity

Page 3: BASE London – DE panel discussion  11 th  July 2013

3

• 80% carbon reduction by 2050

• Heat responsible for half national energy use

BASE London – DE panel discussion 11th July 2013

Why District Energy ?

Page 4: BASE London – DE panel discussion  11 th  July 2013

4

DECC’s 2050 vision for heat BASE London – DE panel discussion 11th July 2013

Rural density –Biomass boilers

Suburban density – heat pumps

High density urban areas – heat networks

Page 5: BASE London – DE panel discussion  11 th  July 2013

5

DECC heat networks growth projectionBASE London – DE panel discussion 11th July 2013

Chart 17: TWh/year of heat demand that could be met by heat networks

Page 6: BASE London – DE panel discussion  11 th  July 2013

6

BASE London – DE panel discussion 11th July 2013

Delivering DE’s potential

Connection Capacity

Capital

District Energy

Page 7: BASE London – DE panel discussion  11 th  July 2013

7

BASE London – DE panel discussion 11th July 2013

Delivering DE’s potential – getting connected

District Energy

Connection

• Planning compliance London Plan Borough policies

• Perceived as risky not DNO, not Transco?

• Agreements are bespoke, more complex (expensive)

• Impact on liquidity?

• How big should it be?

Page 8: BASE London – DE panel discussion  11 th  July 2013

8

District Energy

BASE London – DE panel discussion 11th July 2013

Delivering DE’s potential - funding

• Networks are expensive – it’s infrastructure!

• Funders are unfamiliar with the technology

• Connection charges – can’t pre-fund network expansion

• Role for ESCOs ? bring funding bring technical know-how can manage risks

Capital

Page 9: BASE London – DE panel discussion  11 th  July 2013

9

BASE London – DE panel discussion 11th July 2013

Delivering DE’s potential

• Nascent market• Supply chain competence

and capacity issues

• Designers• Contractors• Customers and their advisors

District Energy

Capacity