BAB I
DATA TEKNIS
1
-
8/18/2019 Bar Bending Scheduler
2/40
2
-
8/18/2019 Bar Bending Scheduler
3/40
BAB II
PERHITUNGAN TULANGAN
1. Perhitungan Tulangan Kolom
1. Tulangan 00 !a"
Diameter Tulangan = 19 mm
Panjang/ lente = 11,95 m
Jumlah Kolom = 20
Total Tulangan Utama Kolom = 8 x 20 = 160 tulangan
Panjang Kolom = 500 ! 2x"0# = 500 ! 2x"0$19% = 5,02 m
. Tulangan 01 !a#$%"
Diameter Tulangan = 8 mm
Panjang/ lente = 11,95 m
Jumlah Kolom = 20
Jumlah &eng'ang/ 'olom = "9
Total Tulangan &eng'ang = 20 x "9 = 980 tulangan
( = "20 mm
() = "20 * ",5# = "20 * ",5 $8% = 8" mm
PanjangSengkang=4 L' +2.6 d+3. 14 π .3,5d+2. 3
8 π .3,5d
PanjangSengkang=4(384)+2.6 (8)+3.1
4 π .3,5(8)+2.
3
8 π .3,5(8)
PanjangSengkang=1763,95mm≈1764mm = 1,+6" m
3
-
8/18/2019 Bar Bending Scheduler
4/40
Ta#el Bar Bending Scheduler Tulangan Kolom
. Perhitungan Tulangan Balo&
' Tulangan 0 !a#$%"
Diameter Tulangan = 8 mm
Panjang/ lente = 11,95 mJumlah &eng'ang/ ortal memanjang = 8 x " = 152 tulangan
Jumlah &eng'ang/ ortal memen#e' = $0 x 2% ! 11 = +1 tulangan
Total Tulangan &eng'ang untu' -eluruh .alo' in#u' = $152 x "% ! $+1 x 5% = 96
tulangan
(1 = 20 mm
(1) = 20 * ",5# = "0 * ",5 $8% = 28" mm
(2 = 520 mm
(2) = 520 * ",5# = "0 * ",5 $8% = "8" mm
4
-
8/18/2019 Bar Bending Scheduler
5/40
PanjangSengkang=2 L1' +2 L2' +2.6d+3.1
4 π .3,5d+2.
3
8 π .3,5d
PanjangSengkang=2 (284)+2 (484 )+2.6(8)+3. 14 π .3,5(8)+2.
3
8 π .3,5(8)
PanjangSengkang=1763,95mm≈1764mm = 1,+6" m
A. Balo& In%u& Arah (eman)ang
( = 5500 mm
( total = 22000 ! 2$0,5 x 500% = 22500 mm
(n = ( * 2x0,5x500 = 5500 * 500 = 5000 mm
1. Tulangan 001
a. Tulangan 001 !a# * #a"
Jumlah alo' n#u' = "
Jumlah Tulangan = $" x % x 2 = 2" tulangan
Panjang/Tulangan =12# !1
4 π .3,5d
! $"12 ! "0% ! 5500 !1
4 ln
!
"0#
= 12 $16% !14 π .3,5(16) ! $"12!"0% ! 5500 !
1
4(5000)
! "0$16%
= 192 ! ",98 ! "52 ! 5500 ! 1250 ! 6"0
= 80++,98 mm 80+8 mm = 8,0+8 m
#. Tulangan 001 !$"Jumlah alo' n#u' = "
Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = $2x0,+5 x (n% !500 !2x"0#
= 2x0,+5 $5000% ! 500 !2x"0 $16%
= 9280 mm = 9,28 m
. Tulangan 00
a. Tulangan 00 !a# * #a"
5
b b
a a
-
8/18/2019 Bar Bending Scheduler
6/40
Jumlah alo' n#u' = "
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan = 12# !1
4 π .3,5d
! $"12 ! "0% !1
4 ln
! 15#
= 12 $16% !1
4 π .3,5(16)
! $"12 ! "0% !
1
4(5000)
! 15$16%
= 192 ! ",98 ! "52 ! 1250 ! 2"0
= 21++,98 mm 21+8 mm = 2,1+8 m
#. Tulangan 00 !$"
Jumlah alo' n#u' = "
Jumlah Tulangan = $" x 2% x = 2" tulangan
Panjang/Tulangan =$2 x1
4 x
(n% ! 500 !$2 x 15#%
= $2 x1
4 x 5000% ! 500 !$2 x 15 x 16%
= 2500! 500 !"80
= "80 mm = ,"8 m
+. Tulangan 00+
a. Tulangan 00+ !a"
Jumlah alo' n#u' = "Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan = $"12 ! "0% ! 5500 !1
4 ln
! "0#
= $"12 ! "0% ! 5500 !1
4(5000)
! "0$16%
= "52 ! 5500 ! 1250 ! 6"0
= +8"2 mm = +,8"2 m
#. Tulangan 00+ !#"
6
c
-
8/18/2019 Bar Bending Scheduler
7/40
Jumlah alo' n#u' = "
Jumlah Tulangan = $" x 2% = 8 tulangan
Panjang/Tulangan = $2 x0,+5 x (n% ! 500 !2x"0#
= 2x0,+5 $5000% ! 500 !2x"0 $16%
= 9280 mm = 9,28 m
,. Tulangan 00,
a. Tulangan 00, !a# * #a"
Jumlah alo' n#u' = "
Jumlah Tulangan = $" x % x 2 = 2" tulangan
Panjang/Tulangan = 12# !1
4 π .3,5d
! $"12 ! "0% ! 5500 !1
4 ln
!
"0#
= 12 $16% !1
4 π .3,5(16)
! $"12 ! "0% ! 5500 !
1
4(5000)
! "0$16%
= 192 ! ",98 ! "52 ! 5500 ! 1250 ! 6"0
= 80++,98 mm 80+8 mm = 8,0+8 m
#. Tulangan 00, !$"
Jumlah alo' n#u' = "
Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = $2 x0,+5 x (n% ! 500 !2x"0#
= 2x0,+5 $5000% ! 500 !2x"0$16%
= 9280 mm = 9,28 m
-. Tulangan 00- !a"
Jumlah alo' n#u' = "
Jumlah Tulangan = $" x 2% x " = 2 tulangan
Panjang/Tulangan =1
2 ln
! 2x20#
=1
2(5000)
! 2x20$16%
= 2500 ! 6"0
= 1"0 mm = ,1" m
7
a
-
8/18/2019 Bar Bending Scheduler
8/40
B. Balo& In%u& Arah (emen%e&
(1 = "500 mm
(n1 = (1 * 2x0,5x500 = "500 * 500 = "000 mm
(2 = 2000 mm
(n2 = (2 * 2x0,5x500 = 2000 * 500 = 1500 mm
( total = 2x"500 ! 2000 ! 2$0,5 x 500% = 11500 mm
1. Tulangan 00 !a#a"
Jumlah alo' n#u' = 5Jumlah Tulangan = 5 x = 15 tulangan
Panjang/Tulangan = 2x12# !2x$1
4 π .3,5d ¿
! 2x $250 *"08% ! 2x(1 ! (2
= 2x12$16% !2x$1
4 π .3,5.16 ¿
! 2x $202% ! 2x"500 ! 2000
= 8" ! 8+,96! "0" ! 9000 ! 2000
= 118+5,96mm 118+6 mm = 11,8+6 m
. Tulangan 00/
a. Tulangan 00/ !a# * #a"
Jumlah alo' n#u' = 5
Jumlah Tulangan = $5 x 2% x 2 = 20 tulangan
Panjang/Tulangan = 12# !
1
4
π .3,5d
! $"12 ! "0% !
1
4
ln 1
! 15#
= 12 $16% !1
4 π .3,5(16)
! $"12 ! "0% !
1
4(4000)
! 15$16%
= 192 ! ",98 ! "52 ! 1000 ! 2"0
= 192+,98 mm 1928 mm = 1,928 m
8
b
aa
b b
a a
-
8/18/2019 Bar Bending Scheduler
9/40
#. Tulangan 00/ !$"
Jumlah alo' n#u' = 5
Jumlah Tulangan = $5 x 2% x 2 = 20 tulangan
Panjang/Tulangan =1
4 x
(n1 !1
4 x
(n2! 500 !$2 x 15#%
=$
1
4 x "000% !$
1
4 x 1500% ! 500 !$2 x 15 x 16%
= 1000! +5 ! 500 !"80
= 255 mm = 2,55 m
+. Tulangan 00 !a"
Jumlah alo' n#u' = 5
Jumlah Tulangan = 5 x 2 = 10 tulangan
Panjang/Tulangan = 2x $250 *"08% ! 2x(1 ! (2= 2x$202% ! 2x"500 ! 2000
= "0" ! 9000 ! 2000
= 11"0" mm = 11,"0" m
,. Tulangan 00 !a#a"
Jumlah alo' n#u' = 5
Jumlah Tulangan = 5 x = 15 tulangan
Panjang/Tulangan = 2x12# !2x$14 π .3,5d¿ ! 2x $250 *"08% ! 2x(1 ! (2
= 2x12$16% !2x$1
4 π .3,5.16¿
! 2x $202% ! 2x"500 !
2000
= 8" ! 8+,96! "0" ! 9000 ! 2000
= 118+5,96mm 118+6 mm = 11,8+6 m
-. Tulangan 010
a. Tulangan 010 !a"
9
c
a
aba
aa
-
8/18/2019 Bar Bending Scheduler
10/40
Jumlah alo' n#u' = 5
Jumlah Tulangan = $5 x 2% x 2 = 20 tulangan
Panjang/Tulangan =1
2 ln 1 ! 2x20#
=1
2(4000)
! 2x20$16%
= 2000 ! 6"0
= 26"0 mm = 2,6" m
#. Tulangan 010 !#"
Jumlah alo' n#u' = 5
Jumlah Tulangan = $5 x 2% x 1 = 10 tulangan
Panjang/Tulangan =1
2 ln 2
! 2x20#
=1
2(1500)
! 2x20$16%
= +50 ! 6"0
= 190 mm = 1,9 m
Ta#el Bar Bending Scheduler Tulangan Balo& In%u&
10
b
-
8/18/2019 Bar Bending Scheduler
11/40
11
-
8/18/2019 Bar Bending Scheduler
12/40
12
-
8/18/2019 Bar Bending Scheduler
13/40
+. Perhitungan Tulangan Balo& Ana&
(1 = "500 mm
(n1 = (1 * 2x0,5x500 = "500 * 500 = "000 mm
(2 = 2000 mm
(n2 = (2 * 2x0,5x500 = 2000 * 500 = 1500 mm
( total = 2x"500 ! 2000 ! 2$0,5 x 500% = 11500 mm
1. Tulangan 011 !a#a"
Jumlah alo' 3na' = "Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = 2x12# !2x$1
4 π .3,5d¿
! 2x $250 *"08% ! 2x(1 ! (2
= 2x12$16% ! 2x$1
4 π .3,5.16¿
! 2x$202% ! 2x"500 !
2000
= 8" ! 8+,96! "0" ! 9000 ! 2000
= 118+5,96mm 118+6 mm = 11,8+6 m
. Tulangan 01
a. Tulangan 01 !a# * #a"
Jumlah alo' 3na' = "
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan = 12# !1
4 π .3,5d
! $"12 ! "0% !1
4 ln 1
! 15#
= 12 $16% !1
4 π .3,5(16)
! $"12 ! "0% !1
4(4000)
! 15$16%
= 192 ! ",98 ! "52 ! 1000 ! 2"0
= 192+,98 mm 1928 mm = 1,928 m
13
b
aa
bb
aa
-
8/18/2019 Bar Bending Scheduler
14/40
#. Tulangan 01 !$"
Jumlah alo' 3na' = "
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan =1
4 x
(n1 !1
4 x
(n2! 500 !$2 x 15#%
=$1
4 x "000% !$1
4 x 1500% ! 500 !$2 x 15 x 16%
= 1000! +5 ! 500 !"80
= 255 mm = 2,55 m
+. Tulangan 01+ !a"
Jumlah alo' = "
Jumlah Tulangan = " x 2 = 8 tulangan
Panjang/Tulangan = 2x $250 *"08% ! 2x(1 ! (2
= 2x$202% ! 2x"500 ! 2000
= "0" ! 9000 ! 2000
= 11"0" mm = 11,"0" m,. Tulangan 01, !a#"
Jumlah alo' n#u' = "
Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = 2x12# !2x$
1
4
π .3,5d¿! 2x $250 *"08% ! 2x(1 ! (2
= 2x12$16% !2x$1
4 π .3,5.16¿
! 2x $202% ! 2x"500 !
2000
= 8" ! 8+,96! "0" ! 9000 ! 2000
= 118+5,96mm 118+6 mm = 11,8+6 m
-. Tulangan 01-
a. Tulangan 01- !a"
14
c
a
ab
a
aa
-
8/18/2019 Bar Bending Scheduler
15/40
Jumlah alo' n#u' = "
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan =1
2 ln 1
! 2x20#
=1
2(4000)
! 2x20$16%
= 2000 ! 6"0
= 26"0 mm = 2,6" m
#. Tulangan 01- !#"
Jumlah alo' 3na' = "
Jumlah Tulangan = $" x 2% x 1 = 8 tulangan
Panjang/Tulangan =1
2 ln 2
! 2x20#
=1
2(1500)
! 2x20$16%
= +50 ! 6"0= 190 mm = 1,9 m
. Tulangan 0+ !a#$%"
15
b
-
8/18/2019 Bar Bending Scheduler
16/40
Diameter Tulangan = 8 mm
Panjang/ lente = 11,95 m
Jumlah &eng'ang/ ortal memen#e' = $0 x 2% ! 11 = +1 tulangan
Total Tulangan &eng'ang untu' -eluruh .alo' ana' = +1 x " = 28" tulangan
(1 = 220 mm
(1) = 220 * ",5# = 220 * ",5 $8% = 18" mm
(2 = 20 mm
(2) = 20 * ",5# = 20 * ",5 $8% = 28" mm
PanjangSengkang=2 L1' +2 L2' +2.6d+3.1
4 π .3,5d+2.
3
8 π .3,5d
PanjangSengkang=2 (184)+2 (284)+2.6 (8)+3.1
4 π .3,5(8)+2.
3
8 π .3,5(8)
PanjangSengkang=1163,95mm≈1164mm = 1,16" m
16
-
8/18/2019 Bar Bending Scheduler
17/40
Ta#el Bar Bending Scheduler Tulangan Balo& Ana&
17
-
8/18/2019 Bar Bending Scheduler
18/40
+. Perhitungan Tulangan Pelat Lantai
Diameter Tulangan = 10 mm
Jara' antar tulangan -um.u x = 10 4m
Jara' antar tulangan -um.u = 10 4m
Jumlah tulangan -um.u x = 50 x " = 200 tulangan
Jumlah tulangan -um.u = "0 x 2 ! 15 = 95 tulangan
A. Arah (emen%e& !2"1 Tulangan 0016 $a.a%
¿11000+(2 ) (250−40−8−2,25d )+(2 ) 1
4 πd+(80−4,5d ) (2 )+ (2 )
3
8 πd+(2 )6 d
¿11000+359+15,71+70+23,56+120
¿11588,27mm≈11589mm=11,589m
1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,589=0,361m
Jumlah lente ¿200 lente
Total -i-a tulangan ¿200 lente x 0,61 = +2,2 m
2 Tulangan 01+ $a%
¿11000+(2 ) (250−40−8−2,25d )+(2 ) 3
8 πd+ (2 )6d
¿11000+359+11,78+120
¿11490,78mm≈11491mm=11,491m
1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,491=0,459m
Jumlah lente ¿200 lente
Total -i-a tulangan
¿200×0,459=91,8m
18
b
aa
a
-
8/18/2019 Bar Bending Scheduler
19/40
B. Arah (eman)ang !3"
1 Tulangan 018 $a. .a%
¿11000+ (250−40−8−2,25d )+ 14 πd+ (60−4,5d )+3
8 πd (2 )+6d (2 )+40d
¿11000+179,5+15,71+15+23,56+120
¿11353,77mm≈11354mm=11,354m
1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,354=0,596m
Jumlah lente ¿95 x2=190 lente
Total -i-a tulangan ¿190×0,596=113,24m
2 Tulangan 019 $a%
¿11000+ (250−40−8−2,25d )+3
8 πd (2 )+6d (2 )+40d
¿11000+179,5+23,56+120+400¿11723,06mm≈11724mm=11,724m
1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,724=0,226m
Jumlah lente = 95 x2=190 lente
Total -i-a tulangan ¿190×0,226=42,94m
19
-
8/18/2019 Bar Bending Scheduler
20/40
-
8/18/2019 Bar Bending Scheduler
21/40
. Tulangan Diameter 1 mm
A. Balo& In%u& Arah (eman)ang
1. Tulangan 001
a. Tulangan 001 !a# * #a"
Jumlah Tulangan = $" x % x 2 = 2" tulangan
Panjang/Tulangan= 8,0+8 m1 lente #iguna'an untu' 1 tulangan #engan -i-a / lente = 11,95 * 8,0+8 =
,8+2 m ! 5i5a ter6a&ai untu& 00 !$" "
Jumlah (ente =24
1 =24 lente
Total -i-a = 2" x ,8+2 = 92,928 m
#. Tulangan 001 !$"Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = 9,28 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a / lente = 11,95 * 9,28 = 2,6+
m ! 5i5a ter6a&ai untu& 00 !a# * #a" "
Jumlah (ente =12
1 =12 lente
Total -i-a = 12 x 2,6+ = 2,0" m
. Tulangan 00
a. Tulangan 00 !a# * #a"
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan = 2,1+8 m
12 tulangan mengguna'an -i-a #ari tulangan 001 $4% = 2,6+ m
21
b b
a a
-
8/18/2019 Bar Bending Scheduler
22/40
-i-a/ tulangan = 2,6+ * 2,1+8 = 0,"92 m
Total -i-a = 0,"92 x 12 = 5,90" m
&i-a Tulangan = 16 12 = " tulangan
" tulangan mengguna'an -i-a #ari tulangan 00 $.% = 2,6+ m
-i-a/ tulangan = 2,6+ * 2,1+8 = 0,"92 m
Total -i-a = 0,"92 x " = 1,968 m
#. Tulangan 00 !$"
Jumlah Tulangan = $" x 2% x = 2" tulanganPanjang/Tulangan = ,"8 m
2" tulangan mengguna'an -i-a #ari tulangan 001 $a. .a% = ,8+2 m
-i-a/ tulangan = ,8+2 * ,"8 = 0,92 m
Total -i-a = 0,92 x 2" = 9,"08 m
+. Tulangan 00+
a. Tulangan 00+ !a"
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan = +,8"2 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a/ lente = 11,95 * +,8"2 =
",108 m !5i5a ter6a&ai untu& tulangan 00-!a" %an 00/ !a#*#a" "
Jumlah (ente =16
1 =16 lente
Total -i-a = ",108 x 16 = 65,+28 m
#. Tulangan 00+ !#"
Jumlah Tulangan = $" x 2% x 2 = 8 tulangan
Panjang/Tulangan = 9,28 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a / lente = 11,95 * 9,28 = 2,6+
m !5i5a ter6a&ai untu& tulangan 00 !a#" %an 00/ !a#""
Jumlah (ente =8
1=8 lente
Total -i-a = 8 x 2,6+ = 21,6 m
22
c
-
8/18/2019 Bar Bending Scheduler
23/40
,. Tulangan 00,
a. Tulangan 00, !a# * #a"
Jumlah Tulangan = $" x % x 2 = 2" tulangan
Panjang/Tulangan = 8,0+8 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a / lente = 11,95 * 8,0+8 =
,8+2 m !5i5a ter6a&ai untu& tulangan 00- !a""
Jumlah (ente =24
1 =24 lente
Total -i-a = 2" x ,8+2 = 92,928 m
#. Tulangan 00, !$"
Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = 9,28 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a / lente = 11,95 * 9,28 = 2,6+
m !5i5a ter6a&ai untu& tulangan 00/ !$""
Jumlah (ente =12
1 =12 lente
Total -i-a = 12 x 2,6+ = 2,0" m
-. Tulangan 00- !a"
Jumlah Tulangan = $" x 2% x " = 2 tulangan
Panjang/Tulangan = ,1" m
2" tulangan mengguna'an -i-a #ari tulangan 00" $a..a% = ,8+2 m
-i-a/ tulangan = ,8+2 * ,1" = 0,+2 m
Total -i-a = 0,+2 x 2" = 1+,568 m
&i-a Tulangan = 2 2" = 8 tulangan
8 tulangan mengguna'an -i-a #ari tulangan 00 $a% = ",108 m-i-a/ tulangan = ",108 * ,1" = 0,968 m
23
a
-
8/18/2019 Bar Bending Scheduler
24/40
Total -i-a = 0,968 x 8 = +,+"" m
B. Balo& In%u& Arah (emen%e&
1. Tulangan 00 !a#a"
Jumlah Tulangan =5 x = 15 tulangan
Panjang/Tulangan = 11,8+6 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a/ lente =11,95*11,8+6 = 0,0+" m
Jumlah (ente =15
1 =15lente
Total -i-a = 15 x 0,0+" = 1,11 m
. Tulangan 00/
a. Tulangan 00/ !a# * #a"
Jumlah Tulangan = $5 x 2% x 2 = 20 tulangan
Panjang/Tulangan = 1,928 m
16 tulangan mengguna'an -i-a #ari 8 tulangan 00 $a% = ",108 m
1 .atang -i-a #iguna'an untu' 2 tulangan #engan -i-a/ tulangan = ",108 * 2x
1,928 = 0,252 m
Total -i-a = 0,252 x 8 = 2,016 m
&i-a Tulangan = 20 16 = " tulangan
" tulangan mengguna'an -i-a #ari tulangan 00 $.% = 2,6+ m
-i-a/ tulangan = 2,6+ * 1,928 = 0,+"2 m
Total -i-a = 0,+"2 x " = 2,968 m
#. Tulangan 00/ !$"
24
b
aa
b b
a a
c
-
8/18/2019 Bar Bending Scheduler
25/40
Jumlah Tulangan = $5 x 2% x 2 = 20 tulangan
Panjang/Tulangan = 2,55 m
12 tulangan mengguna'an -i-a #ari tulangan 00" $4% = 2,6+ m
-i-a/ tulangan= 2,6+ * 2,55 = 0,15 m
Total -i-a = 0,15 x 12 = ,+8 m
&i-a Tulangan = 20 12 = 8 tulangan
1 lente #iguna'an untu' 5 tulangan = 5 x 2,55 m = 11,++5 m
Jumlah (ente = 8/ 5 = 1,6 1 ! 1 lente = 2 lente
&i-a/ lente $untu' 1 lente% = 11,95 * 11,++5 = 0,1+5 m
Total &i-a Tulangan = 1 x 0,1+5 = 0,1+5 m !Si5a ti%a& ter6a&ai"
&i-a tulangan = 8 * 5 = tulangan
1 lente #iguna'an untu' tulangan = x 2,55 m = +,065 m = +,065 m
&i-a/ lente $untu' 1 lente% = 11,95 * +,065 = ",885 m !5i5a ter6a&ai untu&
tulangan 01 !a#""
Total &i-a Tulangan = 1 x ",885 = ",885 m
+. Tulangan 00 !a"
Jumlah Tulangan = 5 x 2 = 10 tulanganPanjang/Tulangan = 11,"0" m
1 lente #iguna'an untu' 1 tulangan #engan -i-a/ lente =11,95*11,"0" = 0,5"6 m
Jumlah (ente =10
1 =10lente
Total -i-a = 0,5"6 x 10 = 5,"6 m !Si5a ti%a& ter6a&ai"
,. Tulangan 00 !a#a"
Jumlah Tulangan = 5 x = 15 tulangan
Panjang/Tulangan = 11,8+6 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a/ lente =11,95*11,8+6 = 0,0+" m
Jumlah (ente =15
1 =15lente
Total -i-a = 15 x 0,0+" = 1,11 m !5i5a ti%a& ter6a&ai"
-. Tulangan 010
a. Tulangan 010 !a"
25
a
aa
b
-
8/18/2019 Bar Bending Scheduler
26/40
Jumlah Tulangan = $5 x 2% x 2 = 20 tulangan
Panjang/Tulangan = 2,6" m
1 lente #iguna'an untu' " tulangan #engan -i-a / lente = 11,95 * "x2,6" =
1,9 m !5i5a ter6a&ai untu& tulangan 010 !#""
Jumlah (ente =20
4 =5lente
Total -i-a = 5 x 1,9 = 6,95 m
#. Tulangan 010 !#"
Jumlah Tulangan = $5 x 2% x 1 = 10 tulangan
Panjang/Tulangan = 1,9 m
5 tulangan mengguna'an -i-a #ari tulangan 010 $a% = 1,9 m
-i-a/ tulangan = 1,9 * 1,9 = 0 m
Total -i-a = 0 x 5 = 0 m
&i-a Tulangan = 10 5 = 5 tulangan
1 lente #iguna'an untu' 5 tulangan #engan -i-a / lente = 11,95 * 5 x 1,9 = 5
m !5i5a ter6a&ai untu& tulangan 01 !#a""
Jumlah (ente =5
5=1lente
Total -i-a = 1 x 5 = 5 m
7. Balo& Ana&
1. Tulangan 011 !a#a"
Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = 11,8+6 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a/ lente =11,95*11,8+6 = 0,0+" m
Jumlah (ente =12
1 =12 lente
26
aa
b
b
aa
-
8/18/2019 Bar Bending Scheduler
27/40
Total -i-a = 12 x 0,0+" = 0,888 m !Si5a ti%a& ter6a&ai"
. Tulangan 01
a. Tulangan 01 !a# * #a"
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan = 1,928 m
1 lente #iguna'an untu' 6 tulangan #engan -i-a / lente = 11,95 * 6x1,928 =
0,82 m
Jumlah (ente =12
6 =2 lente
Total -i-a = 2 x 0,82 = 0,+6" m !5i5a ti%a& ter6a&ai"
&i-a Tulangan = 16 12 = " tulangan
2 tulangan mengguna'an -i-a #ari tulangan 00+ $4% = ",885 m
-i-a/ tulangan = ",885 * 2x1,928 = 1,029 m
Total -i-a = 1,029 x 1 = 1,029 m
&i-a Tulangan = " 2 = 2 tulangan
2 tulangan mengguna'an -i-a #ari tulangan 010 $.% = 5 m
-i-a/ tulangan = 5 * 2x1,928 = 1,1"" m
Total -i-a = 1,1"" x 1 = 1,1"" m
#. Tulangan 01 !$"
Jumlah Tulangan = $" x 2% x 2 = 16 tulanganPanjang/Tulangan = 2,55 m
2 tulangan mengguna'an -i-a #ari tulangan 015 $.% = 6,9 m
-i-a/ tulangan = 6,9 * 2x2,55 = 1,68 m
Total -i-a = 1,68 x 1 = 1,68 m
&i-a Tulangan = 16 2 = 1" tulangan
1 lente #iguna'an untu' 5 tulangan = 5 x 2,55 m = 11,++5 m
Jumlah (ente = 1"/ 5 = 2,8 2 ! 1 lente = lente
&i-a/ lente $untu' 2 lente% = 11,95 * 11,++5 = 0,1+5 m
Total &i-a Tulangan = 2 x 0,1+5 = 0,5 m !5i5a ti%a& ter6a&ai"
27
bb
aa
c
-
8/18/2019 Bar Bending Scheduler
28/40
&i-a tulangan = 1" * 2x5 = " tulangan
1 lente #iguna'an untu' " tulangan = " x 2,55 m = 9,"2 m
&i-a/ lente $untu' 1 lente% = 11,95 * 9,"2 = 2,5 m
Total &i-a Tulangan = 1 x 2,5 = 2,5 m !5i5a ti%a& ter6a&ai"
+. Tulangan 01+ !a"
Jumlah Tulangan = " x 2 = 8 tulangan
Panjang/Tulangan = 11,"0" m
1 lente #iguna'an untu' 1 tulangan #engan -i-a/ lente = 11,95*11,"0" =0,5"6 m
Jumlah (ente =8
1=8 lente
Total -i-a = 0,5"6 x 8 = ",68 m !5i5a ti%a& ter6a&ai"
,. Tulangan 01, !a#a"
Jumlah Tulangan = " x = 12 tulangan
Panjang/Tulangan = 11,8+6 m
1 lente #iguna'an untu' 1 tulangan #engan -i-a/ lente =11,95*11,8+6 = 0,0+" m
Jumlah (ente =12
1 =12 lente
Total -i-a = 12 x 0,0+" = 0,888 m !5i5a ti%a& ter6a&ai"
-. Tulangan 01-
a. Tulangan 01- !a"
Jumlah Tulangan = $" x 2% x 2 = 16 tulangan
Panjang/Tulangan = 2,6" m
1 lente #iguna'an untu' " tulangan #engan -i-a / lente = 11,95 * "x2,6" =
1,9 m !5i5a ter6a&ai untu& 01- !#""
28
a
aba
aa
-
8/18/2019 Bar Bending Scheduler
29/40
Jumlah (ente =16
4 =4 lente
Total -i-a = " x 1,9 = 5,56 m
#. Tulangan 01- !#"
Jumlah Tulangan =$" x 2% x 1 = 8 tulangan
Panjang/Tulangan = 1,9 m
" tulangan mengguna'an -i-a #ari tulangan 015 $a% = 1,9 m
-i-a/ tulangan = 1,9 * 1,9 = 0 m
Total -i-a = 0 x " = 0 m
&i-a Tulangan = 8 " = " tulangan
1 lente #iguna'an untu' " tulangan #engan -i-a / lente = 11,95 * " x 1,9 =
6,9 m !5i5a ter6a&ai untu& tulangan 01 !$""
Jumlah (ente =4
4=1 lente
Total -i-a = 1 x 6,9 = 6,9 m
29
b
-
8/18/2019 Bar Bending Scheduler
30/40
Ta#el Bar Bending Scheduler Tulangan Diameter 1 mm
30
-
8/18/2019 Bar Bending Scheduler
31/40
+. Tulangan Diameter 10 mm
A. Pelat Lantai Arah (emen%e& !2"
Diameter Tulangan = 10 mm
Jara' antar tulangan -um.u x = 10 4m
Jara' antar tulangan -um.u = 10 4m
Jumlah tulangan -um.u x = 50 x " = 200 tulangan
Jumlah tulangan -um.u = "0 x 2 ! 15 = 95 tulangan
1 Tulangan 016 $a.a%
Panjang Tulangan ¿11,589m
1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,589=0,361m
Jumlah lente ¿200 lente
Total -i-a tulangan ¿200 lente x 0,61 = +2,2 m
2 Tulangan 01+ $a.%
Panjang Tulangan ¿11,491m1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,491=0,459m
Jumlah lente ¿200 lente
Total -i-a tulangan ¿200×0,459=91,8m
B. Arah (eman)ang
Diameter Tulangan = 10 mm
Jara' antar tulangan -um.u x = 10 4m
Jara' antar tulangan -um.u = 10 4m
Jumlah tulangan -um.u x = 50 x " = 200 tulangan
Jumlah tulangan -um.u = "0 x 2 ! 15 = 95 tulangan
Tulangan 018 $a. .a%
31
b
aa
a
-
8/18/2019 Bar Bending Scheduler
32/40
Panjang Tulangan ¿11,354m
1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,354=0,596m
Jumlah lente
¿95 lente
Total -i-a tulangan ¿95×0,596=56,62m
" Tulangan 019 $a%
Panjang Tulangan = 11,724m
1 lente #iguna'an untu' 1 tulangan elat lantai #engan -i-a/lente7¿11,95−11,724=0,226m
Jumlah lente = 95 lente
Total -i-a tulangan ¿95×0,226=21,47m
Ta#el Bar Bending Scheduler Tulangan Diameter 10 mm
,. Tulangan Diameter mm
a. Tulangan 01 !a#$%"
32
-
8/18/2019 Bar Bending Scheduler
33/40
Diameter Tulangan = 8 mm
Panjang/ lente = 11,95 m
Jumlah 'olom = 20 'olom
Total &eng'ang/ 'olom = "9 tulangan
Total Tulangan &eng'ang 'olom = 20 x "9 = 980 tulangan
Panjang &eng'ang = 1,+6" m
1 lente #iguna'an untu' 6 tulangan -eng'ang = 6 x 1,+6" m = 10,58" m
Jumlah (ente = 980/ 6 = 16, 16 ! 1 lente = 16" lente
&i-a/ lente $untu' 16 lente% = 11,95 * 10,58" = 1,66 m
Total &i-a Tulangan = 16 x 1,66 = 222,658 m
&i-a -eng'ang = 980 * 16x6 = 2 -eng'ang
1 lente #iguna'an untu' 2 tulangan -eng'ang = 2 x 1,+6" m = ,528 m
&i-a/ lente $untu' 1 lente% = 11,95 * ,528 = 8,"22 m!5i5a ter6a&ai"
Total &i-a Tulangan = 1 x 8,"22 = 8,"22 m
#. Tulangan 0 !a#$%"
Jumlah &eng'ang/ ortal memanjang = 8 x " = 152 tulangan
Jumlah &eng'ang/ ortal memen#e' = $0 x 2% ! 11 = +1 tulangan
Total Tulangan &eng'ang untu' -eluruh .alo' in#u' = $152 x "% ! $+1 x 5% =
96 tulangan
Panjang &eng'ang= 1,+6" m
1 lente #iguna'an untu' 6 tulangan -eng'ang = 6 x 1,+6" m = 10,58" m
Jumlah (ente = 96/ 6 = 160,5 160 ! 1 lente = 161 lente
&i-a/ lente $untu' 160 lente% = 11,95 * 10,58" =1,66 m
33
-
8/18/2019 Bar Bending Scheduler
34/40
Total &i-a Tulangan = 160 x 1,66 = 218,56 m
&i-a -eng'ang = 96 * 160x6 = -eng'ang
tulangan mengguna'an -i-a #ari tulangan -eng'ang 'olom $&KK% = 8,"22 m
&i-a/ tulangan = 8,"22 * x1,+6" = ,1 m
Total -i-a = 1 x ,1 = ,1 m
$. Tulangan 0+ !a#$%"
Panjang/ lente = 11,95 m
Jumlah &eng'ang/ ortal memen#e' = $0 x 2% ! 11 = +1 tulangan
Total Tulangan &eng'ang untu' -eluruh .alo' ana' = +1 x " = 28" tulangan
Panjang &eng'ang = 1,16" m
1 lente #iguna'an untu' 10 tulangan -eng'ang = 10 x 1,16" m = 11,6"0 m
Jumlah (ente = 28"/ 10 = 28," 28 ! 1 lente = 29 lente
&i-a/ lente $untu' 28 lente% = 11,95 * 11,6"0 = 0,1 m
Total &i-a Tulangan = 28 x 0,1 = 8,68 m
&i-a -eng'ang = 28" * 28x10 = " -eng'ang
1 lente #iguna'an untu' " tulangan -eng'ang = " x 1,16" m = ",656 m
&i-a/ lente $untu' 1 lente% = 11,95 * ",656 = +,29" m
Total &i-a Tulangan = 1 x +,29" = +,29" m
Ta#el Bar Bending Scheduler Tulangan Diameter mm
34
-
8/18/2019 Bar Bending Scheduler
35/40
35
-
8/18/2019 Bar Bending Scheduler
36/40
BAB I8
KESI(PULAN
er#a-ar'an erhitungan tulangan ang telah #ila'u'an, ma'a #i#aat #ata
-e.agai .eri'ut7
36
-
8/18/2019 Bar Bending Scheduler
37/40
37
-
8/18/2019 Bar Bending Scheduler
38/40
er#a-ar'an ta.el #iata- ma'a #i#aat 'e-imulan .aha -i-a tulangan #iameter 10
mm #an 16 mm le.ih 'e4il #ari 10: -ehingga #i'ategori'an hemat #alam
ema'aianna -e#ang'an -i-a tulangan #iameter 8 mm #an 19 mm le.ih .e-ar #ari
10: -ehingga tulangan ang #ia'ai ter-e.ut #i'ategori'an .oro- #alam
ema'aianna
38
-
8/18/2019 Bar Bending Scheduler
39/40
DA9TAR PUSTAKA
&; 0+20522002 Baja Tulangan Beton
&; 28"+7201. Persyaratan beton struktural untuk bangunangedung
39
-