Bangladesh Country Presentation at ACEF 2014
Click here to load reader
-
Upload
energy-for-all-asian-development-bank -
Category
Government & Nonprofit
-
view
153 -
download
0
description
Transcript of Bangladesh Country Presentation at ACEF 2014
Progress and Future Plans for SE4ALL in Bangladesh
Md. Nazrul IslamJoint Chief, Power Division
Ministry of Power, Energy and Mineral Resources&
M. Saifullah PannaSr. Assistant Secretary, Finance Division
Government of Bangladesh17 June 2014
2
Energy Access Need• The Government of Bangladesh has worked for over a year with
the United States and international partners to develop an action oriented program to advance the three SE4ALL objectives: energy access, energy efficiency and renewable energy.
• Bangladesh faces tremendous pressure to expand energy supply with a rapidly growing economy and population nearing 160 million.
• Bangladesh has made significant progress in expanding access but still has a way to go as 38% of the population does not have access to electricity and 90% relies on traditional fuels for cooking.
3
Energy for All Vision• The Government adopted Vision 2021 - an “electricity for
all” plan that largely relies on conventional fuels.
• The Government is promoting a renewable energy target of at least 5% power from renewable sources by 2015 and 10% by 2021.
• The Government has set energy efficiency targets of 10% by 2015, 15% by the 2021, and 20% by 2030.
• A feed-in tariff for renewable energy is under development.
4
Major Achievements• Infrastructure Development Company Limited (IDCOL)
has spearhead government and donor efforts to achieve:– Almost 3 million SHSs installed; over 70,000 /month– 36,000 biogas digesters built– 38 solar pumps in operation, 150 approved, 1,500 targeted – 1 million cookstoves targeted by 2017
• The Sustainable and Renewable Energy Agency (SREDA) has been formalized in law and is being set-up.
Planned Renewable Energy ProjectsTechnology Summary
Solar Park (Grid Tied) 8 systems with 160 MW total capacity
Solar Park (Mini Grid) 7 systems from 100 kW to 7 MW - solar and hybrid
Solar Irrigation Program by IDCOL and projects by Rural Electrification Board and a private developer
Solar Home System IDCOL SHS program and solar lanterns for poor
Solar Roof-Top 3 grid-tied systems for government and public sector buildings
Wind 6 projects under development and wind mapping at another 13 sites
5
SE4ALL Development Process
6
Follow-on Work
March 2013 Mission
Established dialogue with government and
private sector stakeholders
Produced Aide Memoire
Developed a preliminary Investment Prospectus Framework
for each SE4ALL objective area
November 2013 Mission
Workshop with public and private sector
stakeholders
Identify/review details of potential projects for
the Investment Prospectus
Produced an Investment Framework document to
define SE4ALL project types and request project
proposals for the Investment Prospectus
July 2013 Mission
Continued dialogue with stakeholders and discussed Investment
Prospectus Framework
Reviewed and revised Investment Prospectus
Framework for Bangladesh
Designed a process for developing the
Investment Prospectus and started due
diligence on potential projects
Activities
Outputs
May 2014 Mission
Met with project proponents to collect/validate
information received
Evaluated project opportunities for the
Investment Prospectus
Prepared draft Investment
Prospectus for review by stakeholders
7
Critical Process Steps• SE4ALL Team: U.S. Government lead, World Bank, ADB,
German Government, IFC, UNDP• SE4ALL Team coordinating with: Government of Bangladesh,
IDCOL, GIZ and many private-sector and NGO stakeholders.• The Aide Memoire identified key focal areas for SE4ALL
activities.• Development of the Investment Prospectus Framework
provided public and private stakeholders with:1. A list of potential SE4ALL investment opportunities for each focal
area
2. A template for proponents to submit project proposals
3. Opportunity to provide inputs through focal area roundtable discussions with all stakeholders
8
First Round of ProjectsTwenty projects were submitted – all are in the due diligence stage – the furthest along are:• Clean Cooking – two projects that are first of their
kind in the country• Third Generation SHS upgrades – expansion of
successful program• Mini-grids – three projects ranging from 3kw to
100kw• Waste to Energy and organic fertilizer• LED manufacturing facility• Brick kiln technology upgrade
9
Overview of First Round Projects
• 17 projects were submitted by the private sector, 2 by NGOs, and 1 by an independent state owned non-bank financial institution
• Financing requirements range from $750,000 to $120 million
• Targeted investors are venture capitalists, impact investors, development finance institutions, commercial banks and program related investment of foundations.
10
Critical Issues Going Forward• Confidentiality is critical to the process, and there has
been an undertaking by the SE4ALL project team only to share detailed information with potential investors.
• On-going work includes identifying and holding discussions with potential investors (“match-making”), talking to government agencies about reducing barriers, and talking to financial agencies about de-risking mechanisms.
• The process is a pipeline for opportunities as they become ready rather than formal request for proposal process.
11
Development Steps Going Forward
Follow-on Work
Fall 2014 Mission
1st Bangladesh-specific Investor Forum to present opportunities
identified in the Investment Prospectus
Match interested investors with specific
opportunities
Develop approaches to address barriers and provide
support to interested investors
On-Going
Continue to review projects and discuss with appropriate
investors
Create draft Investment Prospectus and plan for
Investor Forum in coordination with ADB
Finalize and distribute Investment Prospectus and
start organizing Investor Forum
Activities
Outputs
Follow-up workshops with public and private
sector stakeholders
12
Why invest in Bangladesh?• Project agreements are of international standard with
properly allocated risks.• IPPs are operating about 50 % of total generation and
making profit.• IPPs and BPDB (power purchaser) have met their
obligations under the PPA without problems or controversy.
• Many IPPs are operating their businesses with local managers, engineers, and technical staff to the benefit of all concerned.
• One stop service in Board of Investment (BOI) for licensing and permits.
• Independent Regulator to protect industry and consumer’s interest.