Ball Mill Audit and Optimization
Transcript of Ball Mill Audit and Optimization
-
8/20/2019 Ball Mill Audit and Optimization
1/82
Ball mill optimization
Dhaka, Bangladesh
21 March 2010
1
-
8/20/2019 Ball Mill Audit and Optimization
2/82
Introduction
Mr.Peramas Wajananawat
Experience: 13 Years (2 y in engineering,11 y in production) Engineering department Kiln and Burning system
Siam Cement (Ta Luang) Kiln system, Raw material grinding and Coal grinding
Siam Cement (Lampang) Cement grinding and Packing plant
The Siam Cement (Thung Song) Co,Ltd
Production Engineer
Cement grinding 7 lines
2 x Conventional mill 150 t/h (OPC) KHD
2 x Pre-grinding 100 t/h (OPC) Fuller
2 x Semi-finish grinding 270 t/h (OPC) KHD
1 x VRM 120 t/h Loesche (LM46.2 +2C)
Cement bag dispatching
Contact e-mail: [email protected]
2
-
8/20/2019 Ball Mill Audit and Optimization
3/82
Contents
1. Objective of Ball mill optimization
2. Mill performance test
3. Air flow and diaphragm
4. Separator performance test
3
-
8/20/2019 Ball Mill Audit and Optimization
4/82
Objective
1. Audit performance of grinding system
2. Show the key areas for optimization the ball
mill system3. Provide the basic information for changes or
modifications within grinding system
4. Reduce power consumption, Qualityimprovement or Production improvement
4
-
8/20/2019 Ball Mill Audit and Optimization
5/82
Ball mill optimization
5
Ball mill optimization
Mill charge Air flow & Diaphragm Separator
1.Mill sampling test2. Charge distribution3.Regular top-ups
1.Mill ventilation2. Water injection3.Diaphragms
1.Tromp curve2.Separator air flow3.Separator sealing
-
8/20/2019 Ball Mill Audit and Optimization
6/82
When: Do optimization
1. In some period (1 month, 1 Quarter, 1 Year or ???)
2. To assess the reason/cause of disturbance
When abnormal operation
Poor performance of grinding system Low mill output or poor quality product
High operation or maintenance costs
3. Keep operation in a good efficiency
6
-
8/20/2019 Ball Mill Audit and Optimization
7/82
Conventional grinding system
To Cement Silo
Cement Mill
Clinker Gypsum Limestone
Main Machine
1. Feeding system2. Tube mill
3. Dynamic separator4. Dedusting (BF/EP)
5. Transport equip.
7
-
8/20/2019 Ball Mill Audit and Optimization
8/82
Mill charge optimization
To Cement Silo
Cement Mill
Clinker Gypsum Limestone
8
-
8/20/2019 Ball Mill Audit and Optimization
9/82
What is function of mill?
9
M
Size reduction along the mill-Coarse grinding 1st compartmentNormal feed size 5% residue 25 mm.
Max feed size 0.5% residue 35 mm.-Fine grinding 2nd compartment
-
8/20/2019 Ball Mill Audit and Optimization
10/82
Piece weight (or knocking weight)
Average weight/piece of grinding
media in each compartment
(g/piece) Piece weight Impact force
Specific surface
Average surface area of (ball)
grinding media in each compartment
(m2/t) Specific surface Attrition force
10
Coarse material grindingCoarse material grinding Fine material grindingFine material grinding
Need large ball size
Need small ball size
-
8/20/2019 Ball Mill Audit and Optimization
11/82
Calculation (for steel ball)
Piece weight : i = [3.143/6] x d3
x 7.8 ;g/pcs.Specific surface : o = 123 / i (1/3) ; m2 /ton
Note : d = size of ball (cm)
Ball charge composition
11
-
8/20/2019 Ball Mill Audit and Optimization
12/82
Ball charge composition
Check piece weight and specific surface
Compartment1
Charge calculation
Fraction Weight, W weight Piece weight, I no., nSpecific surface,
oSurface, O
(mm), d (t) % (g) pcs. (m2/t) (m2)90 5.0 9% 2,989 1,673 8.5 4380 11.0 21% 2,099 5,240 9.6 10670 13.6 26% 1,406 9,671 11.0 14960 15.3 29% 886 17,277 12.8 196
50 5.6 11% 512 10,927 15.4 8640 2.5 5% 262 9,528 19.2 48
Total #1 53.0 100% 976 54,317 11.8 628
Compartment2
Charge calculation
Fraction Weight, W weight Piece weight, I no., nSpecific surface,
oSurface, O
(mm), d (t) % (g) pcs. (m2/t) (m2)50 0.0 0% 512 0 15.4 0
40 0.0 0% 262 0 19.2 030 5.0 4% 111 45,170 25.6 12825 48.0 35% 64 749,309 30.7 1,476
20 37.5 27% 331,143,35
438.4 1,441
17 46.5 34% 202,308,58
545.2 2,102
Total #1 137.0 100% 324,246,41
737.6 5,147
Piece weight: 976 g/pieceSpecific surface: 11.8 m2/t
Piece weight: 32 g/piece
Specific surface: 37.6 m2/t
12
-
8/20/2019 Ball Mill Audit and Optimization
13/82
Ball charge composition
General we use (Product Blaine 4,500 cm2/g) for “Conventional” Cpt.1 : Piece weight 1,500-1,600 g./piece
Cpt 2 : Specific surface 30-35 m2/t
For “Pre-grinding system” “R/P + Conventional”
Cpt.1: PW ~1,100-1200 g/pc
Cpt.2: SS ~35-40 m2/t
**depend on product fineness!!
13
-
8/20/2019 Ball Mill Audit and Optimization
14/82
Maximum steel ball size (Bond equation)
B=36 x (F80)1/2 x [(SgxWi)/(100xCsxDe1/2)]
1/3
Where
B : Maximum ball size (mm.)
F80 : Feed material size for 80% pass (µm)
W i : Bond work index (kWh/t) Cs : N/Nc (normally ~ 0.7-0.75)
Sg : Specific gravity of raw material (t/m3)
De : Effective diameter of mill (m.)
F80 = log [(0.20)size residue(mm.)
]/log(%residue)
Example;
Given
• Feed size = 5% res. 25 mm.
• Wi = 13.0 kWh/t
• Cs = 0.7• Sg = 3.0 t/m
3
• De = 4.0 m.
• F80 = log(0.20)25 /log(0.05)
• F80
= 13.4 mm.
Find : Maximum ball size
B = 36x(13.4)1/2
x[(3x13)/(100x0.7x41/2
)]1/3
Maximum ball size = 86 mm.
14
-
8/20/2019 Ball Mill Audit and Optimization
15/82
Maximum steel ball size
0
20
40
60
80
100
120
140
160
180
2 5 10 15 20 25 30
M a x B a l l S i z e ( m m
. )
Feed Size (mm.), F80
Maximum ball size (mm.) : Clinker Wi 13.0 kWh/t, Cs 0.7, Sg 3
** Typical fresh clinker : 5% residue 25 mm. or F80 = 13.4 mm.
15
-
8/20/2019 Ball Mill Audit and Optimization
16/82
Example
Given• Feed size = 5% res. 20 mm.
• Wi = 12.0 kWh/t
• Cs = 0.7• Sg = 3.0 t/m
3
• De = 2.5 m.
Find: required maximum ball size
F80
Maximum ball size (mm.)
16
-
8/20/2019 Ball Mill Audit and Optimization
17/82
Mill performance testSteps
1. Recording of related operational data
2. Air flow measurement
3. Crash stop and visual inspection in mill
4. Sampling in mill
5. Evaluation of test
17
-
8/20/2019 Ball Mill Audit and Optimization
18/82
1. Recording of related operational data
Tube Mill Feed rate, Return, Grinding aids, Water injection, Mill drive
power (kW)
Static separator Vane position
Mill ventilation fan
Damper position, Air flow rate (if have instrument), Pressure Fan drive power
18
-
8/20/2019 Ball Mill Audit and Optimization
19/82
2. Air flow measurement
Air flow measurement Air flow rate
Temperature
Static pressure
To Cement Silo
Cement Mil l
Cl inker Gypsum Limestone
19
Mill ventilation air
-
8/20/2019 Ball Mill Audit and Optimization
20/82
Mill ventilation air
Purpose Forward movement of the material retention time
Take out fine particles and so diminish the risk of coating
Cooling of the material in mill Diminish coating / dehydrationof gypsum
Usual ranges of ventilation: Air speed in mill
Open circuit : 0.8 to 1.2 m/sec
Closed circuit : 1.2 to 1.5 m/sec
20
Mm/sec
**Min 0.5 m/s tend to result inefficient over grinding and excessiveheat generation with possible coating problem.**Max > 1.4 m/s drag particle out of mill before they have beensufficiency ground.
-
8/20/2019 Ball Mill Audit and Optimization
21/82
Agglomeration and ball coating
Cause:
Temperature too high tendency of thematerial forming agglomerates/coating ongrinding media and liner plates
Grinding efficiency will be reduceTemperature outlet mill range 110-120 C.
21
-
8/20/2019 Ball Mill Audit and Optimization
22/82
Test 2
Mill dimension
Inside diameter 3 m.
Degree of filling 28% in both compartment Mill ventilation check
Flow 22,000 m3/h
Check Air ventilation speed in mill ?
22
Mm/sec
-
8/20/2019 Ball Mill Audit and Optimization
23/82
3. Crash stop and visual inspection
Stable operation before crash stop
Emergency stop or Crash stop Tube mill / A ll auxiliary equipment
Mill Ventilation
Disconnect main circuit breaker (Safety !)
Preparation of sampling equipment (shovel, scoop, plastic bag, meter,
lighting etc.)
23
-
8/20/2019 Ball Mill Audit and Optimization
24/82
Preparation of sampling equipment
Lighting Shovel
Scoop
Meter
Meter
Plastic bagLock switch
PPE
Crash stop
24
-
8/20/2019 Ball Mill Audit and Optimization
25/82
3. Crash stop and visual inspection
Visual inspection Liner and Diaphragm condition wear, block
Ball size distribution along the mill classify liner
Water spray nozzle condition clogging
Foreign material ? Ball charge condition agglomeration, coating
Clogging
Liner
Ball charge
Diaphragm
Clean block slot
25
-
8/20/2019 Ball Mill Audit and Optimization
26/82
3. Crash stop and visual inspection
Material level in compartment #1 and #2
M
26
-
8/20/2019 Ball Mill Audit and Optimization
27/82
3. Crash stop and visual inspection
Ball charge quantity (Filling degree)
Measurement by free height Measure average internal diameter, Di
Measure height, h, in three different points along axis for each grinding
compartment
M
Inside diameter, Di
Free height, h
Effect ive length, L
27
-
8/20/2019 Ball Mill Audit and Optimization
28/82
Ball charge quantity (Filling degree)
0.0
10.0
20.0
30.0
40.0
50.0
60.0
0.000 0.100 0.200 0.300 0.400 0.500
D
e g r e e o f f i l l i n g
( % )
h/De
h
HDe
Meter
Normal range 28-32%
Ball level
h = H- (De /2)
28
-
8/20/2019 Ball Mill Audit and Optimization
29/82
4. Sampling inside mill (mill test)
Sampling of material
Take ~1 kg sample every 1 m along mill axis
Each sample collected from 3 point in the same cross section
Removed some balls and taken sample
First and last sample in each compartment should be takenfrom 0.5 m off the wall or diaphragms
1m 0.5 0.50.5 1m 1m 1m 1m 1m 0.51m
1.1
1m 1m
1.2 1.3 1.4 2.1 2.2 2.3 2.4 2.5 2.6 2.71.1 1.2 1.3 1.4
Deep 20 cm.
Take sampling Material sampling point in mill
29
-
8/20/2019 Ball Mill Audit and Optimization
30/82
1m 0.5 0.50.5 1m 1m 1m 1m 1m 0.51m
1.1
1m 1m
1.2 1.3 1.4 2.1 2.2 2.3 2.4 2.5 2.6 2.71.1 1.2 1.3 1.4
Top view
1
1
1
0.5 m.
2
2
2
3
3
3
4
4
4
5
5
5
6
6
6
7
7
7
8
8
8
9
9
9
10
10
10
11
11
11
0.5 m.
Take 1 sample
•Get total 11 collectedsamples along the mill•1 kg per sample
Side view Front view
30
-
8/20/2019 Ball Mill Audit and Optimization
31/82
4. Sampling inside mill (mill test) –cont.
After work inside the mill Calculation quantity of ball charge and filling degree
Sample sieve analysis
1st compartment◊ Sieve : 16 , 10 , 6 , 2 , 1.25 , 0.5 , 0.2 mm
2nd compartment◊ Sieve : 1.25 , 0.5 , 0.2 , 0.12 , 0.09 , 0.06 mm., Blaine Fineness
Plot size reduction chart (graph)
31
-
8/20/2019 Ball Mill Audit and Optimization
32/82
Sieve test equipment
32
-
8/20/2019 Ball Mill Audit and Optimization
33/82
Results: Sieve and Fineness analysis from mill test
Sample Location % residue on sieve (by weight) Blaine 32 16 8 4 2 1 0.50 0.20 0.09
Position m. cm2/g mm mm mm mm mm mm mm mm mm
Compt 1 t.1 0.5 7.00 18.00 34.00 47.00 57.00 64.00 71.00 81.00 90.50
1.0 9.00 21.00 36.00 45.00 52.00 60.00 69.00 79.00 89.00
2.0 3.00 7.00 13.00 18.00 20.50 31.00 48.00 67.00 83.00
3.0 0.50 1.00 3.00 5.50 8.00 19.50 29.50 52.00 71.00
t.2 4.0 0.10 3.00 5.00 7.00 8.00 10.50 22.00 46.00 65.00
t.3 4.5 0.05 4.00 7.50 9.00 10.50 12.50 28.00 48.50 68.00
artition **
Compt 2 t.1 0.5 940 1.00 8.00 32.00 56.00
t.2 1.0 1080 2.00 9.00 33.00 59.00
2.0 1260 0.50 7.00 24.00 50.00
3.0 1300 0.01 4.00 18.00 42.00
4.0 1500 0.00 1.50 12.00 39.00
5.0 1600 0.00 1.00 9.00 32.00
6.0 1700 0.00 0.50 5.00 27.00
t.3 7.0 1880 0.00 0.22 4.00 21.00
t.4 8.0 2000 0.00 0.01 3.00 19.50
9.0 2120 0.00 0.01 1.50 18.50
t.5 9.5 0.00 0.00 2.00 19.00
33
-
8/20/2019 Ball Mill Audit and Optimization
34/82
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
2800
0
10
20
30
40
50
60
70
80
90
100
0.5 1.0 2.0 3.0 4.0 4.5 ** 0.5 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 9.5
B l a i n e ( c m ^ 2
/ g )
% R
e s i d u e o n s i e v e
Length (m.)
Size Reduction Progress32.000 mm
16.000 mm
8.000 mm
4.000 mm
2.000 mm
1.000 mm
0.500 mm
0.200 mm
0.090 mm
Blaine cm2/g
Comp. 1 Comp. 2
0.5 4 4.
5
321 0.
5
4 5321 6 9.5987
0.5 m 0.5 mTypical grinding diagram : OPC 3000 cm2 /g
34
-
8/20/2019 Ball Mill Audit and Optimization
35/82
5. Evaluation of performance test
Grinding efficiency Data for evaluation
Result from visual inspection inside tube mill
Sample analysis from longitudinal sampling inside tube mill Size
reduction graph
Cement MillCement Mill
35
-
8/20/2019 Ball Mill Audit and Optimization
36/82
Evaluation of mill test standard reference
Size reduction along mill axis
Sieve residues and Blaine value in front of the diaphragms
Compartme
nt
Particle size FLSmidth Holderbank Slegten
First comp.
+0.5 mm. 15-25% 12-25% -
+0.6 mm. 10-20% - -
+1.0 mm. 7-14% - -
+2.0 mm. Max 4% Max 3% Max 5% (at 2.5mm.)
Second comp.
+0.2 mm. 20-30% 20-30% 15-25% (at 0.1mm.)
+0.5 mm. Max 5% Max 5% -
Blaine(cm2/g)
- 2,100 -
36
-
8/20/2019 Ball Mill Audit and Optimization
37/82
Evaluation of mill test
Compartment
Particlesize
FLSmidth Holderbank
Slegten Mill test Result OK?
First comp.
+0.5 mm. 15-25% 12-25% - 28% Little muchcoarse
particle sizefrom
compartmen
t 1
+0.6 mm. 10-20% - - -
+1.0 mm. 7-14% - - 12.5%
+2.0 mm. Max 4% Max 3%Max 5%
(at 2.5
mm.)
10.5%
Secondcomp.
+0.2 mm. 20-30% 20-30% 15-25% (at 0.1mm.)
2%
Good!+0.5 mm. Max 5% Max 5% - 0%
Blaine
(cm2/g)
- 2,100 - 2,120
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
2800
0
10
20
30
40
50
60
70
80
90
100
0.5 1.0 2.0 3.0 4.0 4.5 ** 0.5 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 9.5
B l a i n e ( c m ^ 2 / g )
% R
e s i d u e o n s i e v e
Length (m.)
Size Reduction Progress32.000 mm
16.000 mm
8.000 mm
4.000 mm
2.000 mm
1.000 mm
0.500 mm
0.200 mm
0.090 mm
Blaine cm2/g
Comp. 1 Comp. 2
37
-
8/20/2019 Ball Mill Audit and Optimization
38/82
Evaluation of mill test
Test result : provide information to Improvement of ball charge composition
Maximum ball size and composition
Charge composition (PW and SS) Modification/Replace inside grinding compartment
Liners
Diaphragms
OperationMill ventilation
Clear diaphragm slot
38
-
8/20/2019 Ball Mill Audit and Optimization
39/82
39
Bad condition step liner
Broken liner
Good condition liner
Slot blockage
Inspection
-
8/20/2019 Ball Mill Audit and Optimization
40/82
Common problems!
Compartment Result Ball charge Liner/Diaphragm Operation Mill vent.
First comp.
Over limit of particle size in
front of diaphragm1st comp.
-Increase impactforce in 1st comp.
-Revise ballcharge and need
larger ball size(piece weight)
-Low lift ingefficiency (visual
inspection)-Clean block at
diaphragm (nib)
-Feed too much(visual
inspection)
-Too high velocity(check air flow)
Second comp.
Over limit of particle size in
front of diaphragm
2nd comp.
-Wait for revisecharge in 1st
comp.
-Wait for improveliner in 1st comp.
1st comp. OK but2nd comp. over
limit of particle sizein front of
diaphragm
-Revise ballcharge and may
need to increasespecific surface
or Piece weight
-Check ballcharge
distribut ion alongthe mill
-Classifier linerefficiency-Clean block at
diaphragm
-Feed too much(visual
inspection)
-Too high velocity(check air flow)
40
-
8/20/2019 Ball Mill Audit and Optimization
41/82
Case mill test, CM6 STS (Aug,2008)
1,4871,626
1,739
1,927
1,807
2,058
2,333 2,314
0
500
1000
1500
2000
2500
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
0 2 4 6 8 10 12 14
5.6 mm. 2 mm. 0.5 mm. 0.212 mm. 0.09 mm. 0.075 mm. 0.045 mm. blaine
D i a p h r a g m
D i a p h r a g m
% r
e s i d u e
B l a i n e ( c m 2 / g )
abnormal
41
-
8/20/2019 Ball Mill Audit and Optimization
42/82
Evaluate and correction
ompartment
Particlesize
FLSmidthHolderba
nk Slegten
Milltest
Result OK?
First comp.
+0.5 mm. 15-25% 12-25% - 31% Abnormal size reduction(in front of diaphragm),
should clear blockagediaphragm slot
+0.6 mm. 10-20% - - -
+1.0 mm. 7-14% - - -
+2.0 mm. Max 4% Max 3%Max 5%
(at 2.5 mm.)23%
Secondcomp.
+0.2 mm. 20-30% 20-30%15-25%
(at 0.1 mm.) 52% Abnormal size reduction(in front of diaphragm),should clear blockage
diaphragm slot+0.5 mm. Max 5% Max 5% - 51%
Blaine(cm2/g)
- 2,100 - 2,314
Reference standard
42
C Mill f VDZ 2009
-
8/20/2019 Ball Mill Audit and Optimization
43/82
Case Mill test from : VDZ congress 2009
43
Cement plant in Europe
• Chamber 1 : good size reduction efficiency• Chamber 2 : 45 micron shown results that grinding hasstopped midway through the 2nd chamber
E l t d ti
-
8/20/2019 Ball Mill Audit and Optimization
44/82
Evaluate and correction
44
• Average ball size in chamber 2 is too small (average 16 mm, PW 17 g.)• Take charge distribution more coarse to increase PW and average ballsize diameter (to 42 g. and 22 mm.)
S t f t t
-
8/20/2019 Ball Mill Audit and Optimization
45/82
Separator performance test
To Cement Silo
Cement Mill
Clinker Gypsum Limestone
45
Wh t i t ?
-
8/20/2019 Ball Mill Audit and Optimization
46/82
What is separator?
46
• Advantage of grinding systemwith separator
• Reduce the number of fine particle to
be ground in mill• Increase production capacity and
Reduce mill power consumption• Increase % of Active particle in fine
particle of Cement
Advantage of grinding system with separator
-
8/20/2019 Ball Mill Audit and Optimization
47/82
Advantage of grinding system with separator
47
“Maximized separator performance” “Maximized power saving”
Separator performance test
-
8/20/2019 Ball Mill Audit and Optimization
48/82
Separator performance testSteps
1. Recording of related operational data
2. Air flow measurement
3. Sampling within grinding system
4. Evaluation of test
48
1 Recording of related operational data
-
8/20/2019 Ball Mill Audit and Optimization
49/82
1. Recording of related operational data
Tube Mill Feed rate, Return, Grinding aids, Water injection, Mill drive
power (kW)
Dynamic separator Rotor speed, Damper/vane position
Separator drive power (kW)
Separator circulating fan & Separator ventilation
Flow rate (if have instrument), Damper position
Separator fan power (kW)
49
2 Air flow measurement
-
8/20/2019 Ball Mill Audit and Optimization
50/82
2. Air flow measurement
Air flow measurement Air flow rate
Temperature
Static pressure
To Cement Silo
Cement Mil l
Cl inker Gypsum Limestone
Separator circulating air
50
Dynamic Separator circulating air
-
8/20/2019 Ball Mill Audit and Optimization
51/82
Dynamic Separator circulating air
Purpose Distribute and disperse cement dust
Classify cement dust at rotor
Take out fine particle from separator to be product
Usual ranges of circulating airDepend on separator feed and production rate
Separator load 1.8-2.5 kg feed / m3
= Separator feed / Circulating air
Dust load (fine) less than 0.75-0.8 kg fine / m3
= Fine product / Circulating air
51
3 Sampling within grinding system
-
8/20/2019 Ball Mill Audit and Optimization
52/82
3. Sampling within grinding system
Operation period Determined suitable sampling point
Stable operation
6-12 hours duration of performance test Taking samples every ~1 hour
52
Sampling plan (stable operation period)
-
8/20/2019 Ball Mill Audit and Optimization
53/82
Sampling plan (stable operation period)
To Cement Silo
Cement Mill
Clinker Gypsum Limestone
Sampling
1
2
3
53
Sampling point in process
-
8/20/2019 Ball Mill Audit and Optimization
54/82
Sampling point in process
Separator feedor mill output
Return (reject) Fine product
Scoop
54
Sampling test
-
8/20/2019 Ball Mill Audit and Optimization
55/82
Sampling test
Point Sampling point Weight Required sieve analysis
1 Separator feed “m” 0.5 kg PSD Laser test, Blaine (cm2/g)
2 Separator return “g” 0.5 kg PSD Laser test, Blaine (cm2/g)
3 Separator fine “f” 0.5 kg PSD Laser test, Blaine (cm2/g)
55
PSD analysis equipment
-
8/20/2019 Ball Mill Audit and Optimization
56/82
PSD analysis equipment
Particle size distribution analysis
56
-
8/20/2019 Ball Mill Audit and Optimization
57/82
ThungSong PlantResult: from “Laser analysis” -Range 1.8-350 um
-Test time
-
8/20/2019 Ball Mill Audit and Optimization
58/82
( )Rm Rf Rg
Size (um) Feed
%residue
Fines
%residue
Rejects
%residue
1 96.4 95.1 98.1
2 93.9 91.7 96.5
4 89.0 85.3 93.7
8 81.5 74.6 89.9
16 68.8 55.1 85.6
24 60.3 41.2 83.9
32 52.2 28.9 80.9
48 39.4 13.0 71.9
64 32.3 7.4 62.9
96 18.2 0.0 40.5200 4.9 0.0 11.0
TOTAL: 636.9 492.3 814.9
% % %
58
-
8/20/2019 Ball Mill Audit and Optimization
59/82
Meaning sieve size 32 um 52.2% of separator feed
residue on sieve size 32 um
80.9% of reject residue onsieve size 32 um
Rm Rf Rg
Size (um) Feed
%residue
Fines
%residue
Rejects
%residue
1 96.4 95.1 98.1
2 93.9 91.7 96.5
4 89.0 85.3 93.7
8 81.5 74.6 89.9
16 68.8 55.1 85.6
24 60.3 41.2 83.9
32 52.2 28.9 80.9
48 39.4 13.0 71.9
64 32.3 7.4 62.9
96 18.2 0.0 40.5200 4.9 0.0 11.0
TOTAL: 636.9 492.3 814.9
59
4. Evaluation of performance test
-
8/20/2019 Ball Mill Audit and Optimization
60/82
Separator efficiency Data for evaluation
Particles size analysis of sample within grinding system◊ - Separator feed R m
◊- Separator fine R f
◊ - Separator tailing or Reject R g
Tromp curve or Fractional recovery The tromp curve shows what fraction of particles of different sizes in the
feed material is going in to the coarse fraction (often called Return or
Tailing) Separator specific loads / Dust Load
60
Tromp curve
-
8/20/2019 Ball Mill Audit and Optimization
61/82
p
Calculation Circulation factor (CF)
CF = (R f - R g)/(R m - R g)
where
R f = % residue on sieve of fine
R g = % residue on sieve of coarse
R m = % residue on sieve of feed
In this case (size 48 um)
Circulation Factor = 1.81
61
Tromp curve
-
8/20/2019 Ball Mill Audit and Optimization
62/82
Calculation Tromp value
Tromp (range d1,d2) = [(R g1-R g2)/(R m1-R m2)]x[1-(1/CF)]x100
where
Tromp (range d1,d2) : Fraction of particles size between d1 and d2
R g = % residue on sieve of coarse (return/reject)
R m = % residue on sieve of separator feed
In this case
Tromp value (32-48 um) = 31.5%
62
Example Find Circulation factor (CF) of
-
8/20/2019 Ball Mill Audit and Optimization
63/82
Find Circulation factor (CF) of
particle size 32 um and 48 um CF = (R f - R g)/(R m - R g)where
R f = % residue on sieve of fine
R g = % residue on sieve of coarse
R m = % residue on sieve of feed
Find Tromp value of size in range32-48 um Tr (d1,d2)=[(R g1-R g2)/(R m1-R m2)]x[1-
(1/CF)]x100
where Tromp (range d1,d2) : Fract ion of particles size
between d1 and d2
R g= % residue on sieve of coarse (return/reject)
R m = % residue on sieve of separator feed
Rm Rf Rg
Size (um) Feed
%residue
Fines
%residue
Rejects
%residue
1 96.4 95.1 98.1
2 93.9 91.7 96.5
4 89.0 85.3 93.7
8 81.5 74.6 89.9
16 68.8 55.1 85.6
24 60.3 41.2 83.9
32 52.2 28.9 80.9
48 39.4 13.0 71.9
64 32.3 7.4 62.9
96 18.2 0.0 40.5200 4.9 0.0 11.0
TOTAL: 636.9 492.3 814.9
63
Tromp value meaning “Tromp value (32-48 um) = 31.5%”
-
8/20/2019 Ball Mill Audit and Optimization
64/82
For separator feed size between 32-48 um = 100 % “Separator feed”
Separator
31.5% to coarse fraction “Reject/Return”
68.5% to fine fraction “Fine product”
64
Tromp value Plot “Tromp curve”
-
8/20/2019 Ball Mill Audit and Optimization
65/82
65
Rm Rf Rg
Size (um) Feed
%residue Fines
%residue Rejects
%residue CF
Size avg(um)
Trompvalue
1 96.4 95.1 98.1 1.76 0.5 22.9
2 93.9 91.7 96.5 1.85 1.5 29.34 89.0 85.3 93.7 1.79 3 25.2
8 81.5 74.6 89.9 1.82 6 22.8
16 68.8 55.1 85.6 1.82 12 15.2
24 60.3 41.2 83.9 1.81 20 8.932 52.2 28.9 80.9 1.81 28 16.6
48 39.4 13.0 71.9 1.81 40 31.5
64 32.3 7.4 62.9 1.81 56 56.9
96 18.2 0.0 40.5 1.82 80 71.4
200 4.9 0.0 11.0 1.80 148 98.8
TOTAL: 636.9 492.3 814.9 1.81 TOTAL:
Plot “Tromp curve”
-
8/20/2019 Ball Mill Audit and Optimization
66/82
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000
% r e c o v e r y t o r e t u r n ( r e j e c t )
Sieve size (um)
Particle size in range 32-48 um-31.5% go to be “Return” -68.5% go to be “Fine product”
Particle size in range 8-16 um-15.2% go to be “Return” -84.8% go to be “Fine product”
Particle size in range 2-4 um-25.2% go to be “Return” -74.8% go to be “Fine product”
66
Tromp curve of “Ideal and Actual separator”
-
8/20/2019 Ball Mill Audit and Optimization
67/82
Ideal separatorNo coarse in product and No fine in
return/reject
Actual separator
Have some coarse in product and Have
some fine in return/reject
0
10
20
30
40
50
60
70
80
90
100
1
% r e c o v e r y t o r e t u r n ( r e j e c t )
Sieve size (um)
Ideal separator Actual separator
67
Tromp curve
-
8/20/2019 Ball Mill Audit and Optimization
68/82
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000
% r e c o v e r y t o r e t u r n ( r e j e c t )
Sieve size (um)
d50
Cut size : d50 = 60 um•The cut size of the separationbeing made is the particle sizewhere the tromp value is 50%•Meaning : Size 60 um has anequal chance to go either toproduct or to rejects
68
Tromp value meaning Cut size (d50)
-
8/20/2019 Ball Mill Audit and Optimization
69/82
For separator feed size between 48-64 um = 100 % “Separator feed”
Separator
50% to coarse fraction “Reject/Return”
50% to fine fraction “Fine product”
Size ~ 60 um: equal chance to goeither to product or to rejects
69
Tromp curve
-
8/20/2019 Ball Mill Audit and Optimization
70/82
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000
% r e c o v e r y t o r e t u r n ( r e j e c t )
Sieve size (um)
d75
Sharpness = d25/d75•Sharpness = 0.38•Steeper tromp curve, the betterthe separation
•Ideal separator sharpness = 1
d25
70
Tromp curve
-
8/20/2019 Ball Mill Audit and Optimization
71/82
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000
% r e c o v e r y t o r e t u r n ( r e j e c t )
Sieve size (um)
Minimum value
Bypass = 8.9%•Meaning : Bypass is anindication of the amount ofmaterial that essentiallybypasses the separator.•The lower the bypass, the moreefficiency the separation.
•3rd generation bypass < 15%
71
Evaluation of separator performance test
-
8/20/2019 Ball Mill Audit and Optimization
72/82
Item Units Typical range Result Evaluate
Circulation factor - 2-3 1.81 little less
Cut size(d50) microndepend on rotor speed
and fineness level 60 micron seems high
Sharpness (d25/d75) - 0.5 0.38 little less
Bypass % 5-15% 8.90% OK
Separator load kg/m3 1.8-2.5 1.7 OK
Product load kg/m3 0.75 0.6 OK
Action :1. Increase circulation factor (CF) Separator load has available2. Need to increase speed of rotor (due to higher CF coarser separator feed)
3. Tromp curve move to finer side and d50 change to be less than 60 um.4. Bypass slightly increase5. Power consumption of mill went down.
72
Improvement Tromp curve
-
8/20/2019 Ball Mill Audit and Optimization
73/82
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000
% r e c o v e r y t o r e t u r n ( r e j e c t )
Sieve size (um)
1. Improve product: Reduce cut size
-Increase circulation factor to 2-3-Increase rotor rotation speed-%Bypass may slightly increase OK
-Check separator load and dust load ?
Result:-Better active particle size of product-Strength improve
Ideal separator Actual separator
1
73
Improvement Tromp curve
-
8/20/2019 Ball Mill Audit and Optimization
74/82
0
10
20
30
40
50
60
70
80
90
100
1 10 100 1000
% r
e c o v e r y t o r e t u r n ( r e j e c t )
Sieve size (um)
2. Improve production rate: Reduce
%bypass-Improve separator feed distribution
-Check separator load and dust load ?-Separator ventilation flow
-Check mechanical seal or leak-Check guide vane and rotor blade ?
Result:-Increase production rate-Reduce power consumption
Ideal separator Actual separator
2
74
-
8/20/2019 Ball Mill Audit and Optimization
75/82
General separator improvement
-
8/20/2019 Ball Mill Audit and Optimization
76/82
•Separator feed chuteo 100% feed on dispersion plate(over the rotor) good distribution
76
Feed point and dispersion plate
General separator improvement
-
8/20/2019 Ball Mill Audit and Optimization
77/82
•Make sure symmetry feed on rotor good distribution
77
KHD “Sepmaster” and Fuller “O-Sepa”
General separator improvement
-
8/20/2019 Ball Mill Audit and Optimization
78/82
• Adjust guide vane good air flowdistribution to rotor
78
Guide vane
General separator improvement
-
8/20/2019 Ball Mill Audit and Optimization
79/82
•Check rotor blade condition (wear anddeform) normal classification
79
Rotor blade condition
General separator improvement
-
8/20/2019 Ball Mill Audit and Optimization
80/82
•Upper and Lower seal condition goodclassification•Grinding aids goodclassification/reduce bypass
80
Summary
-
8/20/2019 Ball Mill Audit and Optimization
81/82
81
Ball mill optimization
Mill charge Air flow & Diaphragm Separator
1.Mill sampling test
2. Charge distribution3.Regular top-ups
1.Mill ventilation
2. Water injection3.Diaphragms
1.Tromp curve
2.Separator air flow3.Separator sealing
1. Every 6 months
2. Every 1 Year3. 1,000 hours
1. Check and maintain
2. 1,000 hours check 3. 1,000 hours check
1. Every 3 months
2. Optimized and maintain3. Every 3 months
Q & A
-
8/20/2019 Ball Mill Audit and Optimization
82/82
Performance test Mill test and Separator test
Evaluation
Visual inspection Size reduction graph and Tromp curve
Improvement
Charge composition, Operation, ect.
Results Energy saving, Quality improvement
82