Balancing Reservoirs

download Balancing Reservoirs

of 20

Transcript of Balancing Reservoirs

  • 7/27/2019 Balancing Reservoirs

    1/20

    BALANCING RESERVOIR

    PRESENTED BY-YOGESH KUMAR

    ENROLL. NO-12512030

    M.TECH(AHES)

  • 7/27/2019 Balancing Reservoirs

    2/20

    1. Introduction

    2. Reservoir and its types.

    -Service reservoir

    -Balancing Reservoir

    3. Purpose of Balancing Reservoir.4. Dependency of Balancing Reservoir.

    5. How to fix capacity of Balancing Reservoir.

    6. Mass Curve Method.

    7. Steps required for Mass Curve MethoD8. Examples for Mass Curve Method.

    10. Precautions needed during construction ofBalancing Reservoir.

    11. Conclusion.

  • 7/27/2019 Balancing Reservoirs

    3/20

    Reservoir are the most important and expensive

    elements in any hydro power plant.

    So, one needs to optimize its design (or capacity)

    carefully ,

    to avoid the future problems.

  • 7/27/2019 Balancing Reservoirs

    4/20

    Service Reservoir-

    When supply from the source is not continuousfor all the 24 hours ,then supply from the source isstored in a storage reservoir (whenever it is

    available) and then supplied to the consumersaccording to the schedule.

    Balancing Reservoir-

    When the supply from the source is continuousfor all the 24 hours, then during the lean demand

    period excess supply from the source is stored in thestorage reservoir and during peak demand period ,water from this source as well as from the storagereservoir is used to meet the required demand.

  • 7/27/2019 Balancing Reservoirs

    5/20

    The quantity of water required to be stored in thereservoir for equalising or balancing fluctuating

    demand against constant supply is known as the

    balancing reservoir.

  • 7/27/2019 Balancing Reservoirs

    6/20

    The main purpose is to store the water during offpeak hours to supply the same during peak hours and

    so meeting variable power demand.

  • 7/27/2019 Balancing Reservoirs

    7/20

    Water Supply Fluctuation

    - Seasonal fluctuation

    Demand Fluctuation

    -Seasonal

    -Daily

    -Hourly

    Effect of flow fluctuations on system design

    -Size of balancing reservoirs

  • 7/27/2019 Balancing Reservoirs

    8/20

    Variable supply

    Variable demand

    Analyze historic record to search for worst

    case conditionsUse same Mass Balance analysis

    Include variable demand analysis

    It must be designed for daily or hourlyfluctuations.

  • 7/27/2019 Balancing Reservoirs

    9/20

    Prepare mass inflow curve:

    - for all 24 hours for typical days.

    (maximum , average and minimum)

    Prepare mass curve for demand accordingly.

    Superimpose both curve on the same scale.

    Take the max difference between demand andsupply discharge as the capacity of the balancing

    reservoir

  • 7/27/2019 Balancing Reservoirs

    10/20

    Available discharge (during lean season) = 5 m^3/s

    Available Head = 110m Overall Efficiency = 0.8

    Demand Required:-

    Hours (Demand)Load(MW)

    0-8 1

    8-10 2

    10-15 5

    15-21 10

    21-24 1.2

  • 7/27/2019 Balancing Reservoirs

    11/20

    Hour (Demand)

    Load(MW)

    Discharge

    (m3/s)

    Discharge

    (m3)

    Cumulative

    demanddischarge

    (m3)

    0-8 1 1.158 33350 33350

    8-10 2 2.32 16680 50030

    10-15 5 5.80 104400 154430

    15-21 10 11.58 250210 404640

    21-24 1.2 1.4 15120 419760

  • 7/27/2019 Balancing Reservoirs

    12/20

    Available discharge (during lean season) = 5 m^3/s

    i.e. = 18000m^3/hr

    Hour(hr) Available

    discharge(m3)

    Cumulative available

    discharge(m3)

    Cumulative

    demand(m3)

    0-8 144000 144000 33350

    8-10 36000 180000 50030

    10-15 90000 270000 154430

    15-21 108000 378000 404640

    21-24 54000 432000 419760

  • 7/27/2019 Balancing Reservoirs

    13/20

    0

    50000

    100000

    150000

    200000

    250000

    300000

    350000

    400000

    450000

    0 5 10 15 20 25 30

    CUMULATIVE

    DEMAND (m3)

    AVAILABLE CUMULATIVE

    DISCHARGE (m3)

    TIME (HOURS)

    DISCHARGEVOLUME(m3)

    Determination of reservoircapacity

  • 7/27/2019 Balancing Reservoirs

    14/20

    Calculation for Reservoir Capacity

    From the table ,

    during 8-10 hours ,

    Required Demand = 50030 cubic meter

    But, actual available = 180000 cubic meter

    Therefore ,

    required reservoir volume = 180000 - 50030= 129970 cubicmeter

  • 7/27/2019 Balancing Reservoirs

    15/20

    Inner surface of Balancing Reservoir being in contact

    with water should be lined to prevent seepage loss.

    Spilling arrangements should be there.

    Some preventive measures in form of excluder and

    desilting

    chamber are used to avoid the problem of silt .

    Location of balancing reservoir.

  • 7/27/2019 Balancing Reservoirs

    16/20

  • 7/27/2019 Balancing Reservoirs

    17/20

  • 7/27/2019 Balancing Reservoirs

    18/20

    Used in isolated type hydro power plant.

    Capacity(or size) of balancing reservoir depends on :

    -variable supply and variable demand.

    But economic comparison is also necessary to

    determine optimum storage capacity by adding cost

    of reservoirs and pipelines.

  • 7/27/2019 Balancing Reservoirs

    19/20

    http://www.thewatertreatments.com/water/service-

    reservoirs-function-type-volume

    http://nptel.iitm.ac.in/courses/Webcourse-contents/IIT-

    KANPUR/wasteWater/Lecture%2014.htm

    http://nptel.iitm.ac.in/courses/Webcourse-contents/IIT-KANPUR/wasteWater/mass%20curve%20method.htm

    o5-reservoirs:-

    http://www.slidefinder.net/r/reservoirs_balancing_supply_demand/23826463

    Irrigation and water power engineering(B.C.Punmia &

    P.B.Basi Lal).

  • 7/27/2019 Balancing Reservoirs

    20/20

    THANK YOU