Balancing Electricity Focus on Operational Management ...

23
Balancing Electricity Focus on Operational Management/ Frequency control Julia Matevosyan Lead Planning Engineer, Resource Adequacy dena-symposium A Global Perspective on Electricity Ancillary Service Berlin, November 2018

Transcript of Balancing Electricity Focus on Operational Management ...

Balancing Electricity – Focus on

Operational Management/ Frequency

control

Julia Matevosyan

Lead Planning Engineer, Resource Adequacy

dena-symposium

A Global Perspective on Electricity Ancillary

Service

Berlin, November 2018

PUBLIC

Outline

• What is ERCOT

• Wind and Solar Generation Capacity Charts

• ERCOT Compared to Other Systems

• Brief ERCOT Market Overview

• Primary Frequency Response Requirement

• Ancillary Services

• Load Participation in AS

• Key Takeaways

2

PUBLIC

What is ERCOT

3

The interconnected electrical system serving most of Texas, with limited external connections

• 90% of Texas electric load; 75% of Texas land

• 73,308 MW peak demand, July 19, 2018

• 570+ generation units

ERCOT connections to other grids are limited to ~1,250 MW of direct current (DC) ties, which allow control over the flow of electricity

600 MW with SPP

30 MW with CFE

at Eagle Pass

100 MW with CFE

at Laredo 300 MW with CFE at McAllen

220 MW with SPP

Texas RE

PUBLIC

ERCOT Energy Use and Generation Capacity

4

PUBLIC

Wind Generation Capacity – September 2018

5

Future outcomes uncertain

Installed Wind Capacity: 21,190 MW

Wind Generation Record (instantaneous):

Output: 17,541 MW

‒ Feb. 19, 2018, 10:05 p.m.

Penetration (load served): 54%

‒ Oct. 27, 2017, 4 a.m.

‒ Total Load = 28,416 MW

PUBLIC

Utility Scale Solar Generation Capacity – September 2018

6

Future outcomes uncertain

PUBLIC

0

20

40

60

80

100

120

140

160

180

200

SouthAustralia

Eirgrid HydroQuebec

Nordic TSOs ERCOT NG UK

Minumum Inertia Encountered (GW·s)

Min (GWs)

0

500

1000

1500

2000

2500

3000

ERCOT NG UK HydroQuebec

NordicTSOs

SouthAustralia

Eirgrid

Largest Contingency (MW)

Under-frequency side

ERCOT vs other systems with similar frequency control

challenges

7

Source: Survey on Inertia Related Challenges and Mitigation Measures, presentation

at Wind Integration Workshop 2017

PUBLIC

Nodal energy Market, 5-min Real Time Dispatch

• Voluntary Day-Ahead Market (DAM); Ancillary Services are procured in

DAM, co-optimized with energy

• Generator self-commitment; ERCOT makes residual reliability commitments

8

• All generators (including renewables)

submit offers for generation output

• Real-Time market clears every five

minutes, using the cheapest generation

to serve the load, subject to

transmission constraints.

• All generators (including renewables)

receive output level instructions and

locational marginal prices

PUBLIC

Primary Frequency Response (PFR) from All Generators

9

164

166

168

170

172

174

176

178

180

59,85

59,875

59,9

59,925

59,95

59,975

60

60,025

60,05

13:25 13:28 13:31 13:34 13:37 13:40

Wind Resource Response to Low Frequency 07/13/2016

Frequency Nominal Frequency MW

80

90

100

110

120

130

140

59,925

59,944

59,963

59,981

60,000

60,019

60,038

60,056

60,075

16:13 16:16 16:19 16:22 16:25 16:28

Wind Resource Response to High Frequency 08/25/2015

Frequency Nominal Frequency MW

• All Generators (excl. nuclear) in ERCOT are required to provide PFR with ±17

mHz deadband and 5% droop. Capacity reservation is not required, unless

providing AS.

• Requirement for all wind and solar resources with interconnection agreements

after 2008 to provide PFR (about 2000 MW of older plants are exempt);

PUBLIC

Ancillary Services

10

Regulation Up

157 to 687 MW*

Non-Spin967 to 2,361 MW

Responsive

Regulation Down

156 to 604 MW

1.Primary Frequency Response

2.Load Resources on Under Frequency

Relays (UFR)

2,300 to 3,200 MW

*The numbers are showing 2018 AS amounts

PUBLIC

Regulation (Up and Down)

• Provided from selected generators that

receive AGC signal from ERCOT every 4

seconds to move up or down to maintain

frequency between 5-minute dispatch

intervals;

• Requirement varies by hour of the day

and month based on historic 5-min net

load* variability.

*Net Load = Load – Wind – Solar

PUBLIC

Ancillary Services – Non-Spin

12

• Used to ensure sufficient capacity is

available to cover net load forecast

errors or replace deployed frequency

containment reserve

• 30 min deployment required but

mostly provided by 10 min quick

start or unloaded on-line

generation

• Quantity required varies by time of

the day and season based on

historic forecast error and risk of

large net load ramps

PUBLIC

Responsive Reserve Service (RRS)

13

• Used to ensure sufficient capacity is

available to respond to frequency

excursions due to unit trips

− Capacity reserved from

generators to provide RRS

through governor response

− Up to 60% of Responsive

requirement can be provided by

Loads with underfrequency relays

that trips at 59.7 Hz

PUBLIC

Inertial Effect

Initial rate of change of frequency

(prior to any resource response) is

solely a function of inertia

14

PUBLIC

Required RRS varies with Inertia

15

0

1000

2000

3000

4000

5000

6000

7000

8000

50 100 150 200 250 300 350 400

Prim

ary

Fre

quency R

esponse(M

W)

Inertia (GW∙s)

RRS Requirement if provided by Generators Primary Frequency Response(MW)

5/17/2017 UVIG

PUBLIC

Varying Responsive Reserve Requirement

165/17/2017 UVIG

Using Load Resources (with underfrequency

Relays) to provide 60% the RRS, decreases the

total RRS MW requirement at lower inertia levels

PUBLIC

Load Resources Providing RRS

Single site loads (no aggregation), 100-250 MW:

• Industrial process plants that produce chemicals, each site >150 MW, and

consist of several process lines each about 50 MW.

• Air separation plants that extract industrial gasses, each site ≤ 100 MW

• Natural gas compression sites that are part of pipeline operation

• Oil field loads (from couple of kW to tens of MW),

• Industrial process loads (i.e. cement plants, manufacturing plants),

• Very few large commercial sites, mainly data centers.

The participation from broader range of customers is limited due to:

• Instantaneous interruption that a Resource should be able to withstand and

• Costs of real time telemetry equipment (a requirement for participation is to

add dedicated communication systems to send site data to ERCOT).

17

PUBLIC

Load Resources Providing RRS

18

402

984

1350

17011824

1975

2114 2136

2275

2429

2597

2878

3117

33403422

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

2400

2600

2800

3000

3200

3400

3600

June2002

June2003

June2004

June2005

June2006

June2007

June2008

June2009

June2010

June2011

June2012

June2013

June2014

June2015

June2016

Load Resource MW registered

Deployed as Responsive Reserves, via:

• Manual dispatch, 10-minute ramp requirement

• Instantaneous trip via Under-Frequency Relay

Procurement capped at 60% of RRS

PUBLIC

Load Resources Providing RRS

• Currently over 300 Load Resources registered with total capacity of about

4200MW

• Participation rates are 1600-1700 MW of offers and about 1400 MW of awards

every day

• To participate in RRS, a Load Resource must go through a qualification test

with ERCOT.

• Biannual relay testing of registered resources or a recent event is used in lieu

of the test.

• ERCOT uses nearest PMU or high speed recorder data to verify Load

Resource performance after an event.

• The frequency trigger for Load Resources is set relatively low (for really large

events), they respond only one or two times a year, while carrying the reserve

and being paid for it every hour of the year.

• As system inertia is decreasing this may change and they’ll be triggered more

often.

19

PUBLIC

Reliability Risk Desk, Situational Awareness

Inertia Monitoring and Forecasting

Critical Inertia alerts

Reserve Sufficiency Monitoring

Overall Capacity Availability Tool

20

PUBLIC

Current Framework

Proposed Ancillary Service Framework Changes, 2018

21

NPRR 863 With STEC Comments (4/26, 8/2) and ERCOT Steel Suggestions

Load Resources on UFR

Primary Frequency Response (PFR)

Fast Frequency Response (FFR)

ERCOT Contingency Reserve

Service (ECRS)

Load Resources

may or may not be on UFR

10 minute ramp

Responsive Reserve Service

1. Primary Frequency

Response

2. Load Resources on Under

Frequency Relay (UFR)

3. 10 minute ramp

2,300 to 3,200 MW*

No ChangeRegulationRegulation

157 to 687 MW* 157 to 687 MW*

2,300 to 3,200 MW*

508 to 1,644 MW**

Responsive Reserve Service (RRS)

Non-Spin

Non-Spin967 to 2,361 MW*

0 to 1,180 MW*

*Quantities computed/estimated using 2018 Ancillary Service Methodology. **Quantities estimated using this reference.

For Discussion Purposes Only. The intent of this slide is to represent NPRR 863 (with ERCOT comments from 7/6/2018). Protocol language prevails to the extent of any inconsistency with this one page summary.

Overall A/S: 3,807 to 5,958 MW* Overall A/S: 3,807 to 5,958 MW*

Last Edited on /16/2018

FFR

• Triggered at 59.85 Hz and full response in 15 cycles

• Once deployed, sustain for up to 15 mins. Once recalled, restore within 15 mins

PFR

• PFR capable capacity reserved on generators or Controllable Load Resources

(CLR)

• Minimum 1,150 MW must be provided by resources capable of PFR

Load Resources on UFR

• Triggered at 59.70 Hz and full response in 30 cycles

• Sustain until recalled. Once recalled, restore within 3 hours

• Beyond the minimum PFR, up to 60% of total FRS can come from Load

Resources on UFR or FFR.

Generation• Online or offline capacity that can be converted to energy within 10 minutes

• Dispatched by SCED

Load Resources (UFR not required)• Up to 50% of ECRS capacity can come from Load Resources with or without UFR

• Once deployed, must respond within 10 minutes. Restoration within 3 hours

No protocol changes. • Proposed methodology for Non-Spin Reserve Service quantities in this framework -

quantities computed using 2018 A/S Methodology are reduced by ECRS

quantities.

PUBLIC

Key Takeaways

As the generation mix is changing, ERCOT takes a proactive role

introducing gradual changes to frequency response mechanisms:

• All generators including wind and solar are required to provide primary

frequency response (without capacity reservation);

• RRS requirements is based on expected inertia conditions;

• Load Resource providing RRS are very effective in low inertia

conditions;

• System inertia and RRS sufficiency is monitored in the Day Ahead and

into Real Time;

• Alternative AS Framework proposal is being discussed, includes fast

frequency response service;

• Wind and Solar Generators started seeking qualification for Ancillary

Services;

22

PUBLIC

Thank you! Questions?

23

Julia Matevosyan

[email protected]