Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of...

42
Balance 1 Assembly Line Balance

Transcript of Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of...

Page 1: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 1

Assembly Line Balance

Page 2: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 2

Assembly analysis

Assembly ChartIt shows the sequence of operations in putting

the product together. Using the exploded drawing and the parts list, the layout designer will diagram the assembly process.

The sequence of assembly may have several alternatives.

Time standards are required to decide which sequence is best. This process is known as assembly line balancing.

Page 3: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 3

The Assembly Chart

The assembly chart of a toolbox

Page 4: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 4

Time Standards Are Required for Every Task

Page 5: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 5

Plant Rate and Conveyor Speed

Conveyor speed is dependent on the number and units needed per minute, the size of the unit, the space between units. Conveyor belt speed is recorded in feet per minute.

Example: Charcoal grill are in cartons 30X30X24 inches high. A total of 2,400 grills are required every day.

Page 6: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 6

Plant Rate and Conveyor Speed

Page 7: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 7

Assembly line balancing

The purpose of the assembly line balancing technique is: 1. To equalize the work load among the assemblers2. To identify the bottleneck operation3. To establish the speed of the assembly line4. To determine the number of workstations5. To determine the labor cost of assembly and packout6. To establish the percentage workload of each operator7. To assist in plant layout8. To reduce production cost The assembly line balancing technique builds on:

The assembly chart;Time standards;Takt time (minutes/piece) (Plant rate, R value,

Pieces/minutes).

Page 8: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 8

Initial assembly line balancing of toolbox

Takt time (for 2,000 units per shift, considering 10% downtime and 80% efficiency) = .173 minutes per unit.

Page 9: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 9

Assembly line balancing

1.Cost of balancingSubassemblies that cost too high can be taken off the

line.

SA3 could be taken off the assembly line and handled completely separate from the main line and we can save money. SA3 .250 = 240 pieces per hour and .00417 hour each. If balanced, the standard would be 180 pieces per hour and .00557 hour each.

.0057 balanced cost- .00417 by itself cost

.00140 savings hour per unit X 500,000 units per year

700 hours per year@ $15.00 per hour= $10,500.00 per year savings

Page 10: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 10

Assembly line balancing

Subassemblies that can be taken off the line must be:

1. Poorly loaded. The less percent that is loaded. For example, a 60 percent load on the assembly line balance would indicate 40 percent lost time. If we take this job off the assembly line (not tied to the other operators), we could save 40 percent of the cost.

2. Small parts that are easily stacked and stored. 3. Easily moved. The cost of transportation and the

inventory cost will go up, but because of better labor utilization, total cost must go down.

Page 11: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 11

Assembly line balancing

2. Improvement of assembly line Improve the busiest (100 percent) workstation first.

(a) The busiest workstation is P.O. It has .167 minute of work to do per packer. The next closest station is A1 with .155 minute of work. As soon as we identify the busiest workstation, we identify it as the 100 percent station, and communicate that this time standard is the only time standard used on this line from now on. Every other workstation is limited to 360 pieces per hour. Even though other workstations could work faster, the 100 percent station limits the output of the whole assembly line.(b) The total hours required to assemble one finished toolbox is .06960 hour. The average hourly wage rate times .06960 hour per unit gives us the assembly and packout labor cost. Again, the lower this cost is the better the line balance is.

Page 12: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 12

Assembly line balancing

Page 13: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 13

Assembly line balancing

Page 14: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 14

Assembly line balancing

2. Improvement of assembly line Improve the busiest (100 percent) workstation first.

Look at the 100 percent station (P.O.).

If we add a fourth packer, we will eliminate the 100 percent station at P.O.

Now the new 100 percent (bottleneck station) is A1 (93 percent). By adding this person, we will save 7 percent of 25 people or 1.75 people and increase the percent load of everyone on the assembly line (except P.O.). We might now combine A1 and A2, and further reduce the 100 percent.

The best answer to an assembly line balance problem is the lowest total number of hours per unit. If we add an additional person, that person’s time is in the total hours.

Page 15: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 15

Step-by-step procedure for completing the assembly line balancing form

Page 16: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 16

Step-by-step procedure for completing the assembly line balancing form

9. R value The R value goes behind each operation. The plant rate is the goal of each workstation, and by putting the R value on each line (operation), one keeps that goal clearly in focus.

10. Cycle time The time standard.

11. Number of stations

12. Average cycle timeR

timecycle stations ofnumber

stations of #

timecycle timecycle ave.

Page 17: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 17

Step-by-step procedure for completing the assembly line balancing form

13. Percentage load: The percentage load tells how busy each workstation is

compared to the busiest workstation. The highest number in the average cycle time column 12 is

the busiest workstation and, therefore, is called the 100 percent station.

Now every other station is compared to this 100 percent station by dividing the 100 percent average station time into every other average station time. The percent load is an indication of where more work is needed or where cost reduction efforts will be most fruitful. if the 100 percent station can be reduced by 1 percent, then we will save 1 percent for every workstation on the line.

Page 18: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 18

Step-by-step procedure for completing the assembly line balancing form

13. Percentage load:

Example: percent load of the toolbox assembly line balance

In Figure 4-11, the average cycle times reveals that .167 is the largest number and is designated the 100 percent workstation.

The percentage load of every other workstation is determined by dividing .167 into every other average cycle time:

Operation SSSA1 = .153 / .167 = 92 percent SSA1 = .146 / .167 = 87 percent SSA2 = .130 / .167 = 78 percent

and so on.

Page 19: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 19

Step-by-step procedure for completing the assembly line balancing form

14. Hours per unit:

  

Example: Hours per unit of the toolbox assembly line balance

The .167 time standard is for one person, if considering the people number, the hour per unit will be:

Two people = .00557 hour per unitThree people = .00835 hour per unitFour people = .01113 hour per unit

hourper minutes 60

timecycle average % 100 h.p.u.

unitper hour .00278 60

.167 h.p.u.

Page 20: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 20

Step-by-step procedure for completing the assembly line balancing form

15. Piece per hour: Inversion of hours per unit.

16. Total hours per unit Sum of the elements in column 14. For this example is .0696 hour.

17. Average hourly wage rate, say $15 per hour

18. Labor cost per unitTotal hours X average hourly wage

19. Total cycle time It tells us what a perfect line balance would be. Our example 3.494 minutes divided by 60 minutes per hour equals .05823 hour per unit.

Page 21: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 21

Efficiency of the assembly line

%100balance line 1000per hours of Sum

1000per hours of Sum efficiency Line

%100balance lineunit per hours of Sum

unitper hours of Sum efficiency Line

or

For our example:

%84%1000.06960

0.05823 efficiency Line

Page 22: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 22

Analysis of single model assembly lines

shw

ap HS

D R50

Production Rate is given by

where Rp = average hourly production rate, units/hr;

Da = annual demand, units/year;

Sw = number of shifts/week;

Hsh = hrs/shift.

This equation assume 50 weeks per year.

Page 23: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 23

Analysis of single model assembly lines

pc R

E T60

The cycle time can be determined as

where Tc = cycle time of the line, min./cycle;

Rp = production rate, units/hr;

E = line efficiency;

Page 24: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 24

Analysis of single model assembly lines

The cycle rate can be determined as

where Rc = cycle rate, cycles/hr;

Tc is in min./cycle;

Line efficiency E therefore defined as:

cc T

R60

p

c

c

p

T

T

R

R E

Page 25: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 25

Analysis of single model assembly lines

The number of workers on the line can be determined as

where w = number of workers on the line;

WL = workload to be accomplished in a given time period.

AT = available time in the period.

AT

WL w

wcpT RWL TWc = work content time, min/piece.

Page 26: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 26

Analysis of single model assembly lines

Using the previous equation, we also have

The available time in the period, AT.

c

wc

T

ET WL60

AT = 60E

Substitute these terms for WL and AT into w equation, we can state:

c

wc

T

T w integerminimun *

If we assume one worker per station, then this ratio also gives the theoretical minimum number of workstations on the line.

Page 27: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 27

Analysis of single model assembly lines

Example

A small electrical appliance is to be produced on a single model assembly line. The work content of assembling the product has been reduced to the work elements listed in table below along with other information. The line is to be balanced for an annual demand of 100,000 units per year. The line will be operated 50 weeks/yr, 5 shifts/wk, and 7.5 hrs/shift. Manning level will be one worker per station. Previous experience suggests that the uptime efficiency for the line will be 96%, and repositioning time lost per cycle will be 0.08 min. Determine (a) total work content time Twc, (b) required hourly production rate Rp to achieve the annual demand, (c) Cycle time, and (e) service time Ts to which the line must be balanced.

Page 28: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 28

Analysis of single model assembly lines

Example

Page 29: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 29

Analysis of single model assembly lines

Example

Page 30: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 30

Analysis of single model assembly lines

Solution:

units/hr 33.53)5.7)(5(50

000,100pR

(b) The production rate is:

(c) The cycle time Tc with an uptime efficiency of 96% is:

(a) The total work content time is:

Twc = 4.0 min.

.min08.133.53

)96.0(60CT

Page 31: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 31

Analysis of single model assembly lines

Solution:

4 3.7intmin* c

wc

T

Tw

(e) The average service time against which the line must be balanced is:

(d) The theoretical minimum number of workers is given by:

.min00.108.008.1 Rcs TTT

Page 32: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 32

Analysis of single model assembly lines

The objective in line balancing is to distribute the total workload on the assembly line as evenly as possible among the workers

w

1is ) minimizeor )( minimize siwcs T(TTwT

subject to:

ik

ek (1) sTT

and

(2) all precedence requirements are obeyed.

Page 33: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 33

Analysis of single model assembly lines

The algorithms are:

1)Largest Candidate Rule

2)Kilbridge and Wester method

3)Ranked positional weights

Page 34: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 34

Largest Candidate Rule

Step 1: Rank the Teks in the descending order.

Step 2: Assign the elements to the worker at first station by starting at the top of the list and selecting the first element that satisfies precedence requirements and does not cause the total sum of Tek at that station to exceed the allowable Ts; when an element is selected for assignment to the station, start back at the top of the list for subsequent assignments.

Step 3: when no more element can be assigned without exceeding Ts, then proceed to the next station.

Step 4: repeat steps 2 and 3 for as many additional stations as necessary until all elements have been assigned.

Page 35: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 35

Largest Candidate Rule

Work elements sorted in descending order

Page 36: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 36

Largest Candidate Rule

Solution:

The largest candidate algorithm is carried out as presented in table below. 5 workers and stations are required in the solution. Balance efficiency is computed as:

8.0)0.1(5

0.4

s

wc

wT

T E

Page 37: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 37

Largest Candidate Rule

Work elements assigned to stations by LCR

Page 38: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 38

Analysis of single model assembly lines

Example

Page 39: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 39

Analysis of single model assembly lines

Kilbridge and Wester method

Page 40: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 40

Analysis of single model assembly lines

Ranked positional weights

Page 41: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 41

Analysis of single model assembly lines

Ranked positional weights

Kilbridge and Wester method

Largest Candidate Rule

Page 42: Balance1 Assembly Line Balance. Balance2 Assembly analysis Assembly Chart It shows the sequence of operations in putting the product together. Using the.

Balance 42

Analysis of single model assembly lines

Automation, Production Systems, and Computer-Integrated Manufacturing, By Mikell P. Groover, 3rd edition, c2008.

Manufacturing Facilities Design and Material Handling, By F. E. Meyers and M. P. Stephens, 4th Edition, Prentice-Hall, Inc., 2010