BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20...

12
Installing the BAL Waterproofing Kit over a Sealux Reg 20 Joint Sealing Profile 25

Transcript of BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20...

Page 1: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

Installing the BAL Waterproofing Kit overa Sealux Reg 20 Joint Sealing Profile

25

Page 2: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

Waterproofing Kit Materials

1) APD Priming Coat2) WP1 Waterproofing Coat3) Polyester Tape4) Polyester Matting

Min App. Temp. = 5°

Toolsrequired.

26

27

Page 3: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

Mark out splash zone. Splash zone should extend 100mm outside shower area and upward to shoulder height.

Brush wall to remove loose particles.

Wall surfaces should be smooth. Flush fill

all recesses with filler.

28

29

30

Page 4: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

Apply masking tape over strip and ledge surfaces.

Mask pipes and fitting protrusions.

Prepare the polyester reinforcing tape while the primer is drying (30 mins).

Primewalls

stroking brush in various

directions over all

surfaces.

31

32

33

34

Page 5: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

Notch the polyester tape to form a leg that can extend

around corners and maintain a seal

between meeting strip up-stands.

In a 3 sided installation the middle length may have 2 legs, or each side length just 1 leg.

35

36

39

40

41

37

38

Page 6: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

Laying the polyester tape against a wall for support, fold it into two halves pressing the

Substrate transition joints should also be reinforced with polyester tape.

Reinforce all pipes and fitting protrusions.

fold firmly to form a permanent crease

line that will ease the application process.

42

43

44

45

46

Page 7: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

47

48

49

50

51

Paint WP1 onto the wall and strip up-stand for polyester base tapes.

Bed the first polyester basetape (keeping

leg folded) ontothe WP1 coating.

Unfold and bed the leg onto the adjacent wall.

Paint the leg with WP1.

Bed second base tape onto the WP1 coating.

Page 8: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

52

53

54

55Paint a WP1 undercoat onto the corner walls for the polyester corner tape.

working in an upward direction, bed the polyester corner tape

onto WP1 coating maintaining the fold, and keeping the crease line tight against the wall corner.

Starting just above the strip

up-stand and

Use the brush to open fold and bed it onto the adjacent WP1 coated wall.

Page 9: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

57

58

56

Apply a second coat of WP1 over the polyester tape brushing it firmly to ensure

the polyester tape is fully embedded between the first and second WP1

waterproof coatings.

Page 10: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

60

59

62

61

All pipes, fitting protrusions, and transition joints should be reinforced with polyester tape or

matting in a similar manner. Once complete, the walls are ready for waterproofing with BAL WP1.

Page 11: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

6563

64

66

Apply a first coat of WP1over all surfaces strokingthe brush in vertical direction. After the first coat has dried, apply a second coat of WP1 stroking thebrush in an oppositehorizontal direction.

Remove masking tape and clean the ledge.

6768

Page 12: BAL WP1 Tanking over Sealux Reg 20 - Waterproofing Showers · 2017. 3. 28. · a Sealux Reg 20 Joint Sealing Profile 25. Waterproofing Kit Materials 1) APD Priming Coat 2) WP1 Waterproofing

69 The waterproofing is now complete. After the second WP1

coat has dried tiling may commence using:

1. BAL supercover rapid flex2. BAL micromax wall & floor grout

Remember, these are just general guidelines reflecting typical site conditions.

If you have any queries please contact:

IRL Tel: (01) 880 9210Email: [email protected]: www.bal.ie

UK Tel: 0845 600 1 222Email: [email protected]

IRL Tel: (01) 2989 121UK Tel: 0870 876 0 121Email: [email protected]: www.sealux.com

© Sealux