  • LUAS VOLUMESTA 0+000 18.60

    552 m3STA 0+030 18.20

    543 m3STA 0+060 18.00

    532.5 m3STA 0+090 17.50

    507.5 m3STA 0+119 17.50

    50.1 m3STA 0+122 15.90

    2185.10 m3

    POTONGAN SALURAN

    La 3.5 2185.10 m3Lb 1.5 8.1 m3T 1.2 2177.00 m3

    2.7 1830.438.1 1397.69

    Volume ADD 3228.12Sisa Volume 1051.12 49.41796

    Panjang 50.00 M

  • STA 0+000

    Luas Area 18.60

    STA 0+030 552M3

    Luas Area 18.20

    (18.60+18.20) X 302

  • STA 0+030

    Luas Area 18.20

    STA 0+060 543M3

    Luas Area 18.00

    (18.20+18.00) X 302

  • STA 0+060

    Luas Area 18.00

    STA 0+090 532.5M3

    Luas Area 17.50

    (18.00+17.50) X 302

  • STA 0+090

    Luas Area 17.50

    STA 0+119 507.5M3

    Luas Area 17.50

    (17.50+17.50) X 292

  • STA 0+119

    Luas Area 17.50

    STA 0+122 50.1M3

    Luas Area 15.90

    Volume Reaslisasi 2185.10M3

    (17.50+15.90) X 32

  • Panjang 2.7 Mtr

    Potongan Saluran STA 0+060 - STA 0+090

    = 8.1 M3

    Tot. Vol 2185.10Pot. Sal 8.1

    Total Volume Realisasi 2177.00M3

    (3.5+.1.5 X 1.2 X 2.72

    Konsultan PengawasCV. Cicuba Consultant

    AANDRYChief Inspector

    Kontraktor PeLaksanaPT. MUDA JAYA GROUP

    SAFRIZAL

    PPTKDinas Pengairan Kab. Nagan Raya

    MISTAR, STNip. 19750627 200803 1 001

  • Kontraktor PeLaksanaPT. MUDA JAYA GROUP

    SAFRIZAL