Backlog NSR and RESULTS Data Quality Assurance
Monitoring
Land Based Investment Strategy (LBIS):
Current Reforestation Planning and Delivery Workshop
September 18, 2013
Richmond, BC
Matt Leroy
Caroline MacLeodResource Practices Branch
2
Goals and Objectives
• Backlog NSR Updates• Data Requirement and RISS
» Current published RISS-gf and upcoming changes (Wildfire, Carbon)
• Data Quality» FFT Submissions » Caribou GAR Planning» Gaps – How do we make data quality a priority
• Training
2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/20140
20
40
60
80
100
120
140
160
180
200
Outstanding backlog NSR hectares, Provincial Rollup
outstanding backlog hectares
Fiscal Year
Th
ou
san
ds
of
Hec
tare
s
100
Mile
Hou
se T
SA
Arrow/B
ound
ary
TSA
Arrowsm
ith/S
trath
cona
TSA
Bulkley
TSA
Cassia
r/Kisp
iox/B
ulkley
TSA
Dawso
n Cre
ek T
SA
Fort S
t. Jo
hn T
SA
Frase
r TSA
Golden
/Rev
elsto
ke T
SA
Inve
rmer
e/Cra
nbro
ok T
SA
Kalum
/Nas
s TSA
Kingco
me
TSA
Koote
nay
Lake
TSA
Lilloo
et T
SA
Mer
ritt T
SA
Mid
Coast
TSA
Mor
ice/L
akes
TSA
North
Coa
st T
SA
Peace
TSA
Quesn
el TSA
Robso
n Vall
ey T
SA
Soo T
SA
Willi
ams
Lake
TSA
Willi
ams
Lake
TSA (w
est p
art)
0
500
1000
1500
2000
2500
3000
3500
4000
Outsanding backlog NSR hectares by TSA
outsanding hectares
5
Data Quality Assurance MonitoringData Quality Assurance Monitoring
DABDCH
DCODCS
DHWDKA
DKMDM
KDNI
DPCDQC
DRMDSI
DSSRSI
0
1000
2000
3000
4000
5000
6000
7000
8000
FFT or FIA Funded Activities - Reporting Review 2013
Sum of 9-Data OK
Sum of 8-Openings No Plnd No Actual
Sum of 7-Planned Activities with No Completed Activivities
Sum of 6-No OP Spatial
Sum of 5-No InterAgency No
Sum of 4-FE No Map
Sum of 3-Field Base Treatement No SU
Sum of 2-FC Update No FC Map
Sum of 1-No FC Update
Activity or Update Fiscal Year
Nu
mb
er o
f A
ctiv
itie
s/R
eco
rds
6
Data Quality Assurance MonitoringData Quality Assurance Monitoring
DABDCH
DCODCS
DHWDKA
DKMDM
KDNI
DPCDQC
DRMDSI
DSSRSI
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
FFT or FIA Funded Activities - Reporting Review 2013Sum of 9-Data OK
Sum of 8-Openings No Plnd No Actual
Sum of 7-Planned Activities with No Completed Activivities
Sum of 6-No OP Spatial
Sum of 5-No InterAgency No
Sum of 4-FE No Map
Sum of 3-Field Base Treatement No SU
Sum of 2-FC Update No FC Map
Sum of 1-No FC Update
Activity or Update Fiscal Year
Pro
po
rtio
n o
f A
ctiv
itie
s (%
)
7
Data Quality Assurance MonitoringData Quality Assurance Monitoring
2006 2007 2008 2009 2010 2011 2012 2013 (blank)0
1000
2000
3000
4000
5000
6000
7000
FFT and FIA Funded Activities - Reporting Review 2013
Sum of 9-Data OK
Sum of 8-Openings No Plnd No Actual
Sum of 7-Planned Activities with No Completed Activivities
Sum of 6-No OP Spatial
Sum of 5-No InterAgency No
Sum of 4-FE No Map
Sum of 3-Field Base Treatement No SU
Sum of 2-FC Update No FC Map
Sum of 1-No FC Update
Activity/Update Fiscal Year
Nu
mb
er o
f A
ctiv
ity/
Rec
ord
s
8
Data Quality Assurance MonitoringData Quality Assurance Monitoring
2006 2007 2008 2009 2010 2011 2012 2013 (blank)0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
FFT and FIA Funded Activities - Reporting Review 2013
Sum of 9-Data OK
Sum of 8-Openings No Plnd No Actual
Sum of 7-Planned Activities with No Completed Activivities
Sum of 6-No OP Spatial
Sum of 5-No InterAgency No
Sum of 4-FE No Map
Sum of 3-Field Base Treatement No SU
Sum of 2-FC Update No FC Map
Sum of 1-No FC Update
Activity/Update Fiscal Year
Pro
po
rtio
n o
f A
ctiv
ity/
Rec
ord
s (%
)
9
RESULTS – Caribou GARRESULTS – Caribou GAR
DCC DCO DHO DMH DQU DWL0
5
10
15
20
25
30
GAR Openings with No Planned Activities
Nu
nb
er o
f O
pen
ing
s
Data Quality - Gaps?
Issue 1 Missing FC
Update
Issue 2 FC Up-date w/o Spatial
Issue 3 Missing Stocking
Standards
Issue 4 FE
w/o Activity Spatial
Issue 5 Incorrect DN, JS
Shell Open-ings
Issue 6 No
Opening Sp.
Issue 7 JS
w/o Activity Spatial
Issue 8 FE
with Opening
Sp.
Issue 9 In-correct FE
or JS Shells
Issue 10
New Open-ing Re-
quired for PL
0%
5%
10%
15%
20%
25%
30%
Review of FTM and FTL Reporting - Issues Identified Comparison of two periods: Jan 1, 2011 to Feb 4, 2013 and Jan 1, 2011 and Sept 4, 2013
Jan 1, 2011 to Feb 4, 2013 % Issues
Jan 1, 2011 to Sept 4, 2013 % Issues
Issue Type
Prop
orti
on o
f Pop
ulati
on w
ith
Issu
es (%
)
Data Quality - Gaps?
0.0%
2.5%
5.0%
7.5%
10.0%
12.5%
15.0%
17.5%
20.0%
22.5%
25.0%
27.5%
30.0%
148
16242
90
27
255
43110
21
9
All Identified Issues in FTM and FTL - Funded Activities
Sept, 2013 % Change Since Feb 4, 2013
% S
ub
mit
ted
Ac
tiv
itie
s w
ith
Iss
ue
s
“There are currently no incentives to improve the data quality”
How do we make data quality a priority?
District Funding Responsibility Continuous Improvement – Training/Communication Report Cards
Data Quality - Gaps?
13
RESULTS Training
• New Training Software (Go To Training);
• Core Modules Updates and Delivery;
• Existing training material and recorded sessions and future recordings;
• Customized sessions.
14
Summary
• Need for better data• Need for complete planning activities in RESULTS• Need for continuous training