Bachelor in quantity surveying 2
-
Upload
arthur-wilson -
Category
Documents
-
view
407 -
download
0
Transcript of Bachelor in quantity surveying 2
=
Bachelor in Quantity Surveying
Site Report
Name: Liew Yong Sheng 0315108
Lecturer: Mrs Ang [Measurement]
Mrs Azrina [Construction Technology]
Mrs Aishah[Building Material]
Subject: Measurement.
Construction Technology.
Building Material
Abstract
Perhaps there are more to study in the construction site itself than reading from the context
of a book or websites. The following site report holds not only the observation made during
the trip to the unfinished La’tour residence but also research made for two specific part of
the construction project. One of which is the discussion in temporary works where
formwork types including traditional timber formworks and engineered formwork system
are discussed through research, observation and interviews made with the workers on site.
Another would be the discussion in concrete where concrete grade 40 and their advantages
as well as disadvantages are discussed while at the same time a comparison with concrete
grade 30 was made. The following site report also includes the learning outcome as well as
the observation taken from site and a summarized discussion was made for each
observation made.
Table of Content
Introduction 1
Nature of Building and Its Surrounding 3
Construction Technology 5
Building Material 12
Conclusion 15
Appendix 17
Reference 25
1
Introduction
This is a report on a site visit to a construction site incorporating the objectives of the site
visit, the introduction of the site and technical observations made on site including the
proposed learning outcome of the site visit. The site visit was held on 21st November 2014 at
9:00 am sharp at D’Latour Soho, organized by Mrs. Ang Fuey Lin and guided by Mrs Ang
Fuey Lin, Mrs Azrina bt Mhb Yaakob and Mrs Aishah Kamarazaly. Special gratitude are to be
given to the member of the construction project for guiding us safely around the
construction site and providing us knowledge required not only for the sake of the project
but also for the sake of our thirst for knowing. Also, special thanks include these companies
for the construction and also for allowing us to enter the site with responsibility of our
safety on their shoulder:
Developer: DK-MY PROPERTIES SDN.BHD
Architect: RDA-Harris Architects Sdn Bhd
Mechanical and electrical engineer: PERUNDING BERKAT
Structural engineer: PERUNDING OCS
Quantity surveyors: ALPHA-OMEGA MATRIX
Contractor: PASUKHAS CONSTRUCTION SDN BHD
2
Objective
The following are the proposed objective of the assignment.
1. Understand the basics of the construction process.
2. Understand the practical aspect of construction techniques in comparison to the theory
aspect in books and its application on site.
3. Exposure to actual working environment on site including uncertainty circumstances e.g.
weather.
4. Ability to communicate with the construction team members on site and to see the
importance of teamwork in the building team.
5. Witness the usage of construction equipment on site including mechanical plants.
6. Explore and identify various types of building materials and technology on site.
7. Awareness of the importance of safety on site and understanding of safety problems
and site conditions.
8. Recognize the items measurable for sub-structure and reinforced concrete frame works.
3
Nature of the Project and Its Surrounding
The site is located at the back of Taylor’s Lakeside
University and beside Senza Residence serving as
phase B of the residence. Currently the only road
that leads to Latour Soho is Taylor’s Road while
the road on the opposite side is a toll that
separates Bandar Sunway and Puchong.
As seen in the Figure 1.2, the building is planned
to be a tall building. The project is, according to
MPSJ’s “Tajuk Projek”, to be built with two blocks
with 27 floors of Soho and 28 floors apartment
service. The above includes 4 floor stage and 3
floor basement that includes the following:
Figure 1.1 Map of D’Latour
Figure 1.2 a 3D model in perspective of the Soho
4
1. Block A with 629 units of soho and block B with 232 units of apartment service including
“roof garden”.
2. Hall for versatility, surau, gymnasium, café, kindergarten, labour, swimming pool, health
suite, study room and office in level 4.
3. Security house in bottom floor
4. Parking lot in lower floor 1 and 2
5. Parking lot from bottom floor until 3rd floor
6. Business space in bottom floor and mezzanine floor
7. Mechanical room in below ground floor and also above 17th floor.
Currently, as comparable in
figure 1.3, 1.4 and 1.5, the
construction project is halfway
to the top of the basement
parking lot.
Figure 1.3, 1.4 and 1.5 Construction Site in perspective
5
Construction Technology
Temporary Work
As seen in figure 2.1, the building’s main component in its structural support is concrete.
The concrete in these bottom floors serve as a very important support to the tall building
above, supporting at least two block with 27 and 28 floors high. Before diving into the
sections of Formwork and scaffolding, it is important to understand the definition of its
general category: Temporary Works.
As defined in Illingworth J.R.’s Construction Methods and Planning, temporary works are any
temporary construction necessary to assist the execution of permanent work and which will
be removed from site on completion. It is made necessary to enable plant and labour to
perform duty for efficiency and safety.
For in-situ concrete, there is a need of
temporary works as a provision
adequate enough to prevent concrete
pressure arising as well as supporting
loads until the concrete are self-
supporting. This temporary work is also
known as Formwork.
Figure 2.1 Façade of the Construction
6
Formwork
In the site there are two type of formwork used observed during the site visit. One of which
is steel formwork where, as shown in figure 2.2, is used for larger usage of concrete such as
the floor itself and timber formwork, in figure 2.3, used for smaller details such as road
blocks and so on.
Figure 2.2 (top) Steel formwork for concrete floors
Figure 2.3 (right) Timber formwork for smaller details
7
Engineered Formwork System
As mentioned above, steel formwork is generally used in larger construction project such as
high rise buildings and heavy construction such as damps and tunnels or in situation where
re-uses of the same
shuttering (in this case, the
floor) is possible. Aside from
those, it is also suitable for
circular or curved shaped
structures such as columns
or tanks. The use of
Engineered Formwork
System which are formwork
that are prefabricated
modules with metal frame
which could be steel or aluminium
depending on the choice of the engineer and covered on the application side which in this
case, concrete, with material such as steel are considerably advantageous in its usage. One
of the major advantages in its usage would be the reduction of time needed to assemble it.
It is this factor that leads engineer into considering the usage of engineered formwork
system for repetitive flooring.
Technically speaking, engineered formwork system formwork are strong, durable and also
have longer lifespan. It produces concrete that are much smoother than traditional timber
formwork. Engineered formwork system also decreases the amount of wastage with its
reusability characteristics. Due to the fact that it is metal, it does not absorb moisture from
concrete mixture which maintains concrete mixture closest at its initial ratio (depending on
the temperature of the environment). Thanks to this characteristic, engineered formwork
system do not shrink as easily as timber.
However, there are a few consideration required in its usage. The initial cost and handling
cost are higher in engineered formwork system. Despite its reusability, it is unwise to spend
high cost over smaller details in the constructions. It also requires more advanced planning
to fabricate the formwork and requires pre-calculated precision and accuracy.
Figure 2.4 Flat panel formwork
8
Traditional Timber Formwork
Traditional timber formwork is
considerably the most basic as well as
traditional among all other type
formwork. Its usage could be dated far
back to even 1200-1400BC of Ancient
Greece though not as extensively as the
Roman Empire in the 300BC. Traditional
timber formwork is the best choice for
complicated sections of buildings with
needs great amount of attention to small
detail or smaller scale of concrete pouring
in smaller construction projects such as
residential construction or home improvement activity.
There are important characteristics required to be overviewed when choosing the right type
of timber. Depending on the type of timber used and concrete poured, it must be relatively
durable and treatable. Preferably light-weight and also well-seasoned without warping yet
holds sufficient strength characteristics to support concrete pressure. In the construction
site, they used a reinforcement bar as an additional support to the formwork.
Characteristic in Traditional timber formwork which are the most advantageous to
construction project would be the cost. It can be constructed at a lower initial cost as
compared to engineered formwork system due to higher availability as well as cheaper
production cost. The cost of timber varies depending on the quality and treatment of the
wood. On unrelated note, for smaller construction project, it is possible to scavenge for
available lumber and oiling it to make it easier to be removed making it cheaper as well as
effective. Practically speaking, timber formwork is easier to handle compared to engineered
formwork system as there are no need for special tools nor high level of construction
experience. It also is easier to handle due to the light weightiness.
However, the production of traditional timber formwork is not smooth which could be
solved by using panels of material such as plywood to make a smoother surface as well as
Figure 2.5 Use of reinforcement bar, raking brace and horizontal
brace as support
9
have closer characteristics to timber formwork. Wood also degrade faster in multiple
formwork uses unless it is treated.
10
Scaffolding
Illingworth J.R. praised that scaffolding
could be called as ‘the maid-of-all-work’ in
construction field. It is considered to be the
most crucial item in construction project to
be had because it ensures that operatives
can access to parts of construction safely
and effectively. Henceforth, it is required
by law to have scaffold required as well as
its standards laid down by regulation along
with netting to stop falling materials and
ensures public safety.
Figure 2.5 Use of netting around scaffold
Figure 2.6 (top) Independent tied Scaffold constructed
Figure 2.7 (top right) ratio of scaffold with human height
Figure 2.8 (right) Assemble of scaffold up close
11
Methods are based on the use of tube and fitting method are covered in MS 1462: 1999
Specification for Engineered formwork system Frames tubes and fittings used in tubular
scaffolding.
There are various types of scaffolding available for construction usage such as:
1. Putlog scaffolds where one line of standards to support the outside of the scaffold deck,
the inside edge is supported from wall being built. This consist of scaffold tube transom
member with a flattened end to rest on brickwork, masonry or block walling.
2. Independent tied scaffold, by contrast, two row of standard supporting the working
deck. In this case, transom are not built into the structure. The whole scaffold structure
is independent from what is being built.
3. Free standing scaffolds, form of moveable tower although not necessarily so. Must be
stable against overturning without any attachment to any structure.
4. Slung scaffold are those hanging from a structure overhead but incapable of being
moved sideways or lowered.
5. Suspended scaffolds comprise working platforms suspended on wired ropes from a
suitable structure above such that they can be raised and lowered but not move
sideways.
6. Proprietary scaffolding system, in contrast with tube and fitting scaffold, it is designed to
avoid use of loose fitting and modular in concept and load carrying capacity and
structural stability work on a deemed to satisfy basis after extensive testing to validate
performance figures supplied by maker in question.
Based on the structure of the scaffold in construction site, I have come to a conclusion of
using Independent tie Scaffold. The proposal of the use of scaffold, as according to one of
the worker, is due to the fact that it is more stable as compared to putlog scaffoldings and
thus required by the law and regulation to construct them in such a way. Compared to using
putlog whereby using constructed walls as support, independent tie scaffold have a vertical
support due to the additional foundation and greater lateral stability. Putlog is only used as
a preferred scaffolding when the walls are continuous as the transoms are directly tied into
the constructed wall. As seen in figures above, the walls are not continuous and thus are not
wise to use such scaffoldings.
12
Building Material
Concrete
Mentioned in James Ambrose’s Simplified Design of Concrete Structure, concrete consists of
mixture that contains a mass of loose, inert particle of graded size held together in solid
form by a binding agent. Generally, there are three method of concrete usage; one of which
is site cast concrete where wet concrete mix is deposited in forms at location where it is to
be used. Another, precast concrete where mix is deposited in forms at location away from
desired location. Finally, used as masonry construction called concrete masonry units used
in similar manner as brick or stones.
On site, two methods are used; one would be site cast concrete and concrete masonry units
as proven in figure below.
Figure 3.1 (top left) use of concrete masonry unit
Figure 3.2 (top) in site Concrete beam and column
Figure 3.3 (left) reinforcement bar in concrete
13
The grade chosen by the engineer is, according to the worker on site, Grade 40. This means
that the mix in which quantity by weight of cement ,sand, aggregate & if admixture required
are mixed as per design proportion to produce 40 N/mm^2 cube strength in 28 days.
Various factor such as the bearing capacity of soil and load affects and forces designer to
use a greater concrete grades of greater compressive strength.
In comparison to other grades, in this case, the closest of which is C30. Grade 40 concrete
have equal size of maximum aggregate size in millimetre as to C30 as to the maximum
cement content in kilogram per cubic meter. However, the minimum cement content in
kilogram per cubic meter is greater in C40 compared to C30. In contrast, the maximum free
water/cement ratio in C40 is lower than C30. As result, C40 have better compressive
strength than C30.
In the application of grades in this construction site, as seen in figure 1.2, the building is
planned to be a tall building and will contains two blocks that holds 28 floors and 27 floors
respectively. It is natural for the designer to choose concrete with grade 40 to support the
building of such height. The concrete of grade 40 are also further reinforced by the
reinforcement bars within to increase general strength within concrete. However, the use of
cement content is higher compared to lower grades. This means that the cost of using this
grade would be relatively higher than using other grades.
It is mentioned by one of the worker in the construction site that the engineer exaggerated
the use of concrete grade. Technically speaking, it is possible to use concrete with grade 30
to construct even the basement. Financially, this makes construction project a lot cheaper
Figure 3.4 Concrete test area
14
since the major component of the building is made of concrete. However, we were told that
the engineer preferred to use Grade 40 instead to ensure the safety of the users in the
future and avoid risks. This proves that grade 40 is a lot stronger than grade 30 even though
more expensive.
Figure 3.5 and 3.6 cement bags
15
Conclusion
We can assume that we understand how hard it is to get up from a fall, we can imagine how
beautiful a scenery would be through description of words and images but nothing worth
more than experiencing it ourselves. Similarly, we read books and listened from lecturers in
lectures and tutorial about how construction project during its construction phase works but
diagrams and plans can only tell that much. The feeling of excitement before even entering
the site, thirst for answer that fills our curiosity of how things really looked like. When we
entered the site, things are far different from what we imagined such as the additional
consideration towards the worker’s living place and so on.
With the aid of both research as well as the site visit, the experience and knowledge
doubles. It is now possible to relate and understand the terms and description written in
books or website because of the site visit. This aids us not only in the practical usage but
also makes reading and research a greater ease compared to researching through books and
website blindly.
Aside from the above observation and research made, there are more knowledge to be
gained from the site such as the use of reinforcement bar as a support in formwork and
more. These little details are not readable from books nor would lecturers have the time to
mention (more interesting images and details will be included in Appendix section).
In final addition, we also learnt safety precautions during a site visit. Even though it was
mentioned repetitively before the site visit including the process of achieving our green
Figure 4.1 place where worker lives
Figure 4.2 where security made to ensure public do not enter without authority
16
card. We still managed to gain more knowledge about safety precaution during the worker’s
briefing. There are also signboards at the front of the entrance to ensure that not only
visitor read this but also the workers are reminded to wear these safety helmets. Rather
prevent than cure, they said.
Overall, this site visit holds more gain than loss. I am now more prepared to be a quantity
surveyor all thanks to the privileges my university, lecturer and also the company given to
me. I am truly grateful towards what they have done to allow me gain such great knowledge
and experience that other people in other country could not. For this reason, I gave a
thousand thanks to those who made me enjoyed the trip and gave me the knowledge I
needed to be a better quantity surveyor.
17
Dress code of a construction worker. Main
component would be helmet and boots.
Cloth are covered around face to reduce
dust from entering the nose and thermal
contact.
Tubes and bars for steel frame formwork.
Signs for safety precaution and regulation
for outsider and for workers.
Appendix
18
Overview and closer view of the
construction site.
Hoarding used to prevent object from
falling to the other side of the road and
trespassers.
(Bottom)
Reinforcement bars made of copper (left)
and steel (right). For different purpose
and usage.
19
Pathway to the construction site. Note the
cloth hanging on the right and the
motorcycle on the left. Showing that living
space for worker should be considered.
Scaffold used for easy access as well as
support to structures temporarily.
Close-up of the scaffold connected using
nail.
20
Description on cement bag
The difference in view from behind the
net and without the net.
21
Stirrups in formwork without concrete
cast
Tubes of scaffold placed in the
construction site.
Briefing towards safety precaution
needed to take note from one of the
construction worker.
22
Concrete beams and columns.
Scaffold placed in front of the
construction site and formwork beside it.
Reinforcement bar tensioning in the
concrete to increase strength of concrete.
23
Scaffold used to support water tank
with wood plank as medium
Stiffeners from concrete for stiffening
future masonry usage.
24
Memories that will never be
Forgotten
sasa
25
Reference
1. Civil Engineering. (n.d.). Retrieved November 23, 2014, from http://civil-
resources.blogspot.com/2010/06/formwork.html
2. Concrete Formwork & Types Of Formwork - CivilDigital - Johnny. (n.d.). Retrieved
November 23, 2014, from http://civildigital.com/concrete-formwork-types-of-
formwork/
3. Metal formwork system , Preform System,. (n.d.). Retrieved November 23, 2014, from
http://www.marcegaglia.com/ponteggi/eng/edilizia/casseforme.html
4. Engineered formwork system formwork. (n.d.). Retrieved November 23, 2014, from
http://www.slideshare.net/arigatouz/Engineered formwork system -formwork-
23440015
5. What are Formwork Systems? (n.d.). Retrieved November 23, 2014, from
http://www.brighthubengineering.com/building-construction-design/49443-the-
latest-formwork-systems/
6. What is M20/40 grade concrete ? Is it new specification other than M20 grade
concrete ? - Yahoo Answers. (n.d.). Retrieved November 23, 2014, from
https://in.answers.yahoo.com/question/index?qid=20120425021605AAcH6lS
7. Illingworth, J. (2000).Chapter 3 Construction methods and planning (2nd ed.) p35-41.
London: E & FN Spon
8. Illingworth, J. (2000).Chapter 4 Construction methods and planning (2nd ed.) p48-51.
London: E & FN Spon
9. Simmons, H., & Simmons, H. (2007). Olin's construction: Principles, materials, and
methods (8th ed.) p76. Hoboken: J. Wiley & Sons.
10. Parker, H., & Ambrose, J. (1984) Chapter 1.Simplified design of reinforced concrete(5th
ed.)p10. New York ; Toronto: J. Wiley.