Babcock Borsig Steinmüller GmbH Best practices in ... · Babcock Borsig Steinmüller GmbH DESIGN...
Transcript of Babcock Borsig Steinmüller GmbH Best practices in ... · Babcock Borsig Steinmüller GmbH DESIGN...
Best practices in rehabilitation of existing
power plants in Europe - Rehabilitation of
Belchatow Power Plant Dr.-Ing. Ralf Peter / Mechthild Angleys
Babcock Borsig Steinmüller GmbH
Johannesburg, November 05, 2012
Seite 2
The Power Plant Bełchatów
Babcock Borsig Steinmüller
The power plant Bełchatów belongs to the largest
electricity producer of Poland, the PGE Górnictwo i
Energetyka Konwencjonalna S.A.
The installed power plant capacity of the PGE is
approximately 12,3 GW
The power plant Bełchatów originally had an
installed capacity of 12 x 360 MW
Starting from 2004 retrofit of old units by added
20 MW per unit
Seite 3
Retrofit of coal fired power plants
Babcock Borsig Steinmüller
The European power plant capacity needs to be replaced or modernized.
Due to the nuclear phase-out quick actions have to be taken
Renewables can not replace the nuclear capacity
Political acceptance for new Power Plants is critical
>>> one possible solution is the retrofit of old coal fired power plants.
The Bilfinger Berger Power Services Group set an example at Bełchatów Power Pant in
Poland. Babcock Borsig Steinmüller retrofitted the boilers 3 to 5 until 2011 and will modernize
the boilers 7 to 12 until 2016.
Seite 4
Steps of the complex modernisation programme
Babcock Borsig Steinmüller
Step 1
• Extending life time
• Increasing availability
Step 2
• Reducing emissions
• Complying with international environmental standards
Step 3
• Boosting capacity
• Increasing plant efficiency
Step 4
• Reduction of fuel consumption
• Extension of coal mine life time
Seite 5
Belchatow PP, the biggest PP in Poland, originally equipped with
12 x 360 MW identical units.
Main equipments of units are:
• Boiler, type BB-1150,
• Turbine, type 18K360
• Generator, type GTHW360.
Turbine type 18K360 – delivered by Zamech , BBC licence
Commissioning: - unit #1 1982
- unit #12 1988 Blading system profiles 1000
LP exhaust D54 / ND37
Technical parameters:
Power output - 360 MW/370 MW
Live / reheat steam pressure - 17,6/4,0 MPa
Live / reheat steam temperature - 535 °C/ 535 °C
Live steam mass flow - 302.5 kg/s
Condenser pressure - 0,0068 MPa
Boiler, type BB-1150 delivered by RAFAKO
Original technical data :
Nominal capacity - 1150 t/h
Nominal thermal power - 750 Gcal/h
Nominal live steam pressure - 18,6 MPa
Nominal live steam temperature - 540 °C
Nominal reheat steam pressure - 4,5 MPa
Nominal reheat steam temperature - 540 °C
Nominal boiler efficiency - 88%
The main environmental installations:
- Electrostatic precipitator, type 2 HE-2x42-2x1600/3x5x11,6/300, delivered
by ELWO.
- FGD system, delivered by RAFAKO (units 3-12)
Generator type GTHW 360 delivered by Dolmel Wroclaw ,BBC license
Technical data:
Apparent power - 426 MVA
Active power - 370 MW
Voltage - 22 kV
Current - 11180 A
Power factor - 0,85
The Power Plant Bełchatów
Seite 6
Optimising circulation process
Modernisation HP and MP turbine parts
Raising the SH and RH temperatures
Boosting the feed water temperature by installing HP- preheater 3
Boosting the steam generator efficiency
Babcock Borsig Steinmüller
Seite 7
Fundamental information of the boiler
Babcock Borsig Steinmüller
Data Original
After modernization of boiler no. ….
3 4 5 7 bis 12
Live steam temperature 545
C 550
C 550
C 570
C 560
C
Live steam pressure 18,7 MPa 18,2 MPa 18,2 MPa 18,5 MPa 18,7 MPa
Live steam flow mass 1.090 t/h 1.100 t/h 1.100 t/h 1.120 t/h 1.125t/h
Reheatet temperature 545
C 570
C 570
C 570
C 570
C
Feed water temperature 255
C 255
C 255
C 275
C 255
C
Flue gas temperature after
Eco 305
C 305
C 305
C 305
C 305
C
NOx [mg/Nm³] 400 <200 <200 <200 <200
CO [mg/Nm³] 200 <200 200 <200 <200
▪ SULZER – once-through – single-pass boiler with circulation overlaid of the type BB-1150
▪ Ash extraction with 2 chain grates
▪ Start-up and stabilisation firing with MAZUT – burners
▪ 8 coal dust burner for lignite
▪ Coal quality: Heating value 6.500 – 8.700 kJ/kg; w = 47 – 56 %; a = 8,7 – 18,4 %
Seite 8
Modernising the steam generator
Babcock Borsig Steinmüller
Enlarging the SH1 superheater
Adjusting the RH1 reheater surface
Replacing the final superheater
Eco heating surface – replacing the
pipe elbows and adjusting the
heating surface
Replacement of connection pipes
and valves
Seite 9
vor dem Umbau nach dem Umbau
Materialadaption of Pressure Parts
Existing Boiler New Boiler
surface
area
outer
diameter Material
surface
area
outer
diameter Material
m² mm m² mm
Eco 21813 38 16M 16350 38
16M
16 Mo 3 Partly replacement
P1B 20977 38 15HM 32000 38
16M 15 HM
13 Cr Mo 4-5
M1 6438 51 16M / 15HM /
10H2M 11050 51
16Mo3 10CrMo9-10
VM12
P4 3731 38 X20CrMoV12.1 3777 38 X8CrNi19-11
M2 2870 51 15HM / 10H2M / X20CrMoV12.1
3138 51 10CrMo9-10
P3 3120 44,5 15HM /
X20CrMoV12.1 2876
44,5 10CrMo9-10
P1A 184 44,5 15HM 369 44,5 10CrMo9-10
Seite 10
Modernising the steam generator
Emission-reduction measures Babcock Borsig Steinmüller
Adjusting mill housing
Replacing the classifiers
Replacing the coal dust ducts
Installing a new coal dust burner
Installing over-fire air level 1
(18 double nozzles)
Installing over-fire air level 2
(10 lances)
Replacing the burnout grate
(2 opposed travelling grates)
Seite 11
Burners and over-fire air lances (OFA2)
Babcock Borsig Steinmüller
Unit 3 coal dust burner Over-fire air lances (OFA2)
Seite 12
Timeschedule of contract execution
Babcock Borsig Steinmüller
Main Scope data
▪ Dismantling mass in total: 3.494 to
▪ Number of welding joints: 88.000 pieces
▪ Assembly mass in total: 4.200 to
▪ New insulation: 46.200 m²
▪ Scaffolding: 55.000 m³
Timeschedule
▪ Engineering and delivery: 24 month
▪ Assembly period ( boiler outage ): 8 month
▪ Synchronisation 3 month
▪ Commissioning until PAC 2 month
Seite 13
Dismantling and assembling of 750 to of heating
surfaces in 40 calendar days Babcock Borsig Steinmüller
Letting down of old modules
Completion of
one module
before lifting
Special goods
vehicle
Seite 14
Results of the furnace optimisation Unit capacity and half-hour average CO and NOx values
Babcock Borsig Steinmüller
NOx average value for day: 171 mg/Nm³
CO average value for day: 144 mg/Nm³
Seite 15
Gas – Gas - Heater
Babcock Borsig Steinmüller GmbH
Heat recovery system: using the flue gas heat at FGD
inlet for clean gas reheating downstream of FGD
Seite 16
Gas-Gas Heater
Belchatow PP Babcock Borsig Steinmüller GmbH
DESIGN DATA:
FLUE GAS COOLER
Flue gas flow 1.700.000 Nm³/h f.
Temperature in/out 160 / 148
C
Water mass flow 153 kg/s
Temperature in/out 107 / 120
C
Heat duty 8,1 MW
CLEAN GAS REHEATER
Clean gas flow 1.820.000 Nm³/h
f.
Temperature in/out 66 / 76
C
Water mass flow 153 kg/s
Temperature in/out 120 / 107
C
Heat duty 8,1 MW
GENERAL
Reduction of CO2 11 t
Electrical Performance 2,5 MW el
Commissioning 20010 / 11
Gas Gas Heater around FGD
•Efficiency increase 0,8 %
•Reduction of coal consumption
21000 to per year
Seite 17
Gas Gas Heater
Belchatow Power Plant Babcock Borsig Steinmüller GmbH
Timeschedule
•Realizationtime - 2 Month Basic-Engineering
- 13 month delivery and assembly
•Extreme narrow space condition
Seite 18
Improvement of Boiler and Plant Efficiency
Babcock Borsig Steinmüller
Data Original
After modernization of boiler no. ….
3 4 5 7 to 12
Live steam temperature 545
C 550
C 550
C 570
C 560
C
Live steam pressure 17,6 MPa 18,2 MPa 18,2 MPa 18,5 MPa 18,7 MPa
Live steam flow mass 1.090 t/h 1.100 t/h 1.100 t/h 1.120 t/h 1.125 t/h
Reheat temperature 545
C 570
C 570
C 570
C 570
C
Feed water temperature 255
C 255
C 255
C 275
C 255
C
Coal consumption 442 t/h 449 t/h 449 t/h 431 t/h 460 t/h
El. Output 360 MW 380 MW 380 MW 380 MW 390 MW
Efficiency 38,1 % 39,3 % 39,3 % 41,0 % 40,2 %
▪ SULZER – once-through – single-pass boiler with circulation overlaid of the type BB-1150
▪ Tangential firing system with 8 burner compartments
▪ Coal quality: Heating value 6.500 – 8.700 kJ/kg; w = 47 – 56 %; a = 8,7 – 18,4 %
Seite 19
Results of the complex modernisation
Reduction of fuel consumption Babcock Borsig Steinmüller
Fuel consumption between now and 2045 has been cut by 70.9 million tons,
increasing the useful live time of the open-cast mines by approx. 1.5 years!
Seite 20
Summary
Babcock Borsig Steinmüller
▪ Emissions reduced to match international environmental
standards
▪ Lifetime extention by a further 200,000 h operating hours
▪ Unit efficiency increased by approx. 2%
▪ 71-million-ton reduction in lignite consumption increases
operating lifetimes of the open-cast mines and power station by
approx. 1.5 years
▪ Reduction of specific CO2 Emission from 1040 gr/kWh
to 961 gr/kWh
Thank you very much for your kind
attention! Mechthild Angleys, Babcock Borsig Steinmüller, Johannesburg
Babcock Borsig Steinmüller GmbH