Beam-lineOperationalSparesStrategyBI equipment status.

27/05/2014

Javier SIMÓN

Page 2: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

2

BI equipment status.

Sources of information Machines inspected Component statistics To be inspected Stored reserves (B879, 954, 955) Conclusion, global status.

27/05/2014

Page 3: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

3

Introduction

27/05/2014

Page 4: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

4

Introduction1954 2014

27/05/2014

Page 5: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

5

Sources of information

27/05/2014

Layout DB Layout drawings CDD Websites: OP, Optics, BI experts. DFS - Old drawings. Visual inspection.

Page 6: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

6

Inspected until now.

27/05/2014

Page 7: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

7

Lines in the Layout DB

27/05/2014

Page 8: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

8

PS Ring

27/05/2014

Page 9: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

9

PS Booster

27/05/2014

Page 10: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

10

Component statistics

27/05/2014

Instrumentation and types. Layout DB discrepancies. Amount of instrumentation in lines not

yet including in the layout. Total unregistered equipment. Drawing status.

Page 11: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

11

Component statistics

27/05/2014

Data registered in the layout. LHC: just the ring. SPS: ring TI2 TI8 TT10. PX: LEIR, proton lines up to FT16.

Page 12: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

12

Component statistics PS complex

27/05/2014

Page 13: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

13

Component statistics

27/05/2014

Disconnected instrumentation. Inside those 478, everything is working?

Page 14: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

14

Component statistics

27/05/2014

Disconnected instrumentation.

Page 15: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

15

Component statistics

27/05/2014

Equipment types Drawing Status.

Page 16: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

16

Component statistics

27/05/2014

Page 17: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

17

Component statistics

27/05/2014

PX drawings in numbers.

Page 18: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

18

To be inspected

Before LS1 end. SPS LHC

To be scheduled. AD, Isolde, target areas.

27/05/2014

Page 19: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

19

Stored reserves

27/05/2014

Page 20: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

20

Reserves (B879, 954, 955)

27/05/2014

Page 21: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

Javier SIMÓN

21

Global status.

In one word, heterogeneous. The documentation is stored in many

formats, places and with different naming conventions.

Amount of information: From correct and accurate, to no information, or “excessive” duplicated…

Descriptions need to be improved

27/05/2014

Page 22: B eam-line O perational S pares S trategy BI equipment status. 27/05/2014 Javier SIMÓN1.

22

Javier SIMÓN

27/05/2014

Thanks for your attention.

Question time.

Hope to se you in

BOSS 2.0