AWBD Fall Seminar 2009
Fort Bend County:
Municipal Utility Districts and Emergency Response
2 AWBD Fall Seminar 2009
OverviewOverview
Fort Bend County
Hurricane Ike
MUD Readiness Program
Senate Bill 361
Questions
3 AWBD Fall Seminar 2009
Fort Bend CountyFort Bend County
Quick Facts
Population – 530,000 886 Square Miles 30 miles from Gulf 18 jurisdictions 120+ Municipal Utility
Districts
4 AWBD Fall Seminar 2009
Fort Bend CountyFort Bend County
5 AWBD Fall Seminar 2009
Fort Bend CountyFort Bend County
6 AWBD Fall Seminar 2009
Hurricane IkeHurricane Ike
7 AWBD Fall Seminar 2009
9/1/08: Tropical Depression 9, 35 mph9/1/08: Tropical Depression 9, 35 mph
8 AWBD Fall Seminar 2009
9/13/08: Hurricane Ike Hits Galveston9/13/08: Hurricane Ike Hits Galveston
9 AWBD Fall Seminar 2009
Ike Landfall in Galveston, 110 mphIke Landfall in Galveston, 110 mph
Landfall in Galveston at 0200 on Saturday
In Fort Bend County, duration of tropical storm force winds approximately 14 hours
10 AWBD Fall Seminar 2009
County Experiences Significant DamageCounty Experiences Significant Damage
20 homes destroyed 7,000 homes damaged 130,000 homes affected 3 dead, 8 injured, 4 hospitalized
11 AWBD Fall Seminar 2009
County Implements Debris Mgmt PlanCounty Implements Debris Mgmt Plan
750,000 cubic yards of debris
12 AWBD Fall Seminar 2009
Widespread Electricity OutagesWidespread Electricity Outages
67% of electrical services out
One week later, still 25% of services out
Severe impacts to water and wastewater utilities
13 AWBD Fall Seminar 2009
Fort Bend County MUD Readiness ProgramFort Bend County MUD Readiness Program
14 AWBD Fall Seminar 2009
Leadership Leads to Identified ProblemsLeadership Leads to Identified Problems
Fort Bend County has a sophisticated emergency management system that runs from the State down to the Counties to the Cities to the Hospitals to the Schools. During Ike, it did not run down to the Municipal Utility Districts. It will in Fort Bend County during 2009 when we get to the Hurricane Season.
Robert Hebert, County Judge
15 AWBD Fall Seminar 2009
What is the County’s MUD Readiness Program?What is the County’s MUD Readiness Program?
Series of Actions to be Taken by MUDs to be more prepared for Hurricane Season
Improve Communication between MUDs and Emergency Management staff
Encourage MUDs to take responsibility for emergency management activities
16 AWBD Fall Seminar 2009
#1: Define Responder Status#1: Define Responder Status
Local government “Owns” the incident
MUD responsible for water and sewer services before, during, and after a storm; nobody from the County, State, or Federal Govt takes over the services
17 AWBD Fall Seminar 2009
#2: Communication Improvements#2: Communication Improvements
Designate three Key District Contacts
Supply Complete Contact Information to County OEM
Develop Redundant Procedures for Communication
18 AWBD Fall Seminar 2009
#3: NIMS Training#3: NIMS Training
Comply with National Incident Management System (NIMS)
MUDs and County working off of same playbook
Key MUD staff required to complete 4 NIMS courses
19 AWBD Fall Seminar 2009
#4: County Emergency Operations 101#4: County Emergency Operations 101
2 ½ Hour Session
Framework of State and County Emergency Mgmt
Resource Mgmt
Checklist of Emergency Mgmt Issues
20 AWBD Fall Seminar 2009
#5: Sharing of Critical Information#5: Sharing of Critical Information
Contact Information Service Areas SB 361 requirements will enhance the
level of information being collected Opportunity for future sharing of
additional information like GIS maps, plans, etc…
21 AWBD Fall Seminar 2009
#6: Annual Preparation Meeting#6: Annual Preparation Meeting
Held annually in May or June
NWS presentation Updates on Plans Review of Resource
Request Process Review Process for
Communications
22 AWBD Fall Seminar 2009
#7: MUD Representation in County EOC#7: MUD Representation in County EOC
Utilities Console Created in EOC
Will be staffed with representatives from MUD operating firms
Liaison to “talk the language of water and wastewater”
23 AWBD Fall Seminar 2009
Recognition of MUD Readiness Program GraduatesRecognition of MUD Readiness Program Graduates
24 AWBD Fall Seminar 2009
Senate Bill 361Senate Bill 361
25 AWBD Fall Seminar 2009
Collaboration to Meet SB 361 RequirementsCollaboration to Meet SB 361 Requirements
Fort Bend County coordinating with CenterPoint; MUD Law Firms; and Operating Companies to Gather Critical Data
Avoid Redundant Data Collection
26 AWBD Fall Seminar 2009
Development of Web Based ApplicationDevelopment of Web Based Application
Data Collection streamlined through use of web based program to collect critical load info
Application developed by County Judge’s Office, OEM, and IT Dept
27 AWBD Fall Seminar 2009
Meeting the Senate Bill 361 DeadlinesMeeting the Senate Bill 361 Deadlines
Before Feb 1st, County will submit all collected info to CenterPoint
By May 1st, CenterPoint will make critical load status determinations
28 AWBD Fall Seminar 2009
Thank YouThank You
Questions ?
Jeff D. BraunEmergency Management CoordinatorFort Bend County307 Fort Street Richmond, TX 77469