Transcript of Autostrada A1 Nowe Marzy, 25 August 2008. Autostrada A1 Nowe Marzy-Toruń Negotiations between...
Autostrada A1
Nowe Marzy, 25 August 2008
Autostrada A1 Nowe Marzy-Toruń
Negotiations between General Directorate of National Roads and Motorways and Gdańsk Transport Company were resume in February 2008.
On 30 June 2008 the preliminary agreement for realisation of the Motorway A1 Nowe Marzy – Toruń were signed between the Minister of Infrastructure and GTC.
On 12 August 2008 General Director of General Directorate of National Roads and Motorways handed over to GTC the right of way in order to commenced the construction works on the motorway.
Autostrada A1 in 2011
Total length of the A1Motorway - 569 km, including:
section Gdańsk -Toruń built in PPP model - 152 km
section Toruń - Łodź built in traditional model - 144 km
section Łódź - Pyrzowice built in PPP model - 180 km
Pyrzowice – boarder with Czech Republic built . in traditional model - 93 km
Autostrada A1 progress
Existing sections: 43 km section Rusocin – Swarożyn - 25 km
section Głuchów – Piotrków Trybunalski - 18 km
Currently under construction: 177,5 km Swarożyn – Nowe Marzy - 65 km
Nowe Marzy – Toruń 62,4 km
węzeł Sośnica - 2,2 km
Sośnica – Bełk - 15,4 km
Bełk – Świerklany 14,1 km
Świerklany – Gorzyczki - 18,3 km
Autostrada A1 progress
Currently ongoing tenders: 214,3 km A1 Stryków – Pyrzowice - 180 km
A1 Sośnica – Maciejów - 6 km
A1 Pyrzowice – Piekary Śląskie - 8,2 km
A1 Piekary Śląskie – Maciejów - 20,1 km
Tenders under preparation: 144 km A1 Czerniewice – Stryków I – the environmental
decision is awaiting
Autostrada A1Nowe Marzy - Toruń
Gdansk Transport Company SA is a special p purpose company set up in 1996 to pursue . the A1 motorway project
The company holds the concession to design, b build, operate and finance the most northern . stretch of the A1 motorway between Gdansk and . Toruń
The concession was issued for a specific term and . will expire in 2039
Gdańsk Transport Company
Gdańsk Transport Company
The present shareholders in Gdańsk Transport Company are:
NDI Autostrada 25,31%
Skanska ID 30%
John Laing Infrastructure 29,69%
Intertoll ID 15%
. Skanska Infrastructure . Development
.John Laing Infrastructure
. NDI Autostrada
. Intertoll Infrastructure . Developments
Autostrada A1
The construction of the A1 motorway is divided into two phases:
Phase 1 – 90 km stretch . of motorway between . Rusocin and Nowe . Marzy near Grudziądz.
. Completion - October 2008.
Phase 2 – planned 62 km stretch of motorway between n Nowe Marzy and
Czerniewice n near Toruń. . Completion - December 2011.
Construction works commenced in November 2005.
The first 25-km section Rusocin – Swarożyn was open . for traffic in December 2007. Completion of the . next 65 km of Phase 1 is scheduled for 15 October.
3 274 643 drivers have used the motorway till now, . currently average daily traffic oscillates around 20,5 . thousand cars, the highest traffic on the A1 was . 25 603 vehicles.
Phase I realisation
Project scope
Works includes construction of:
Completely new section of the . motorway from the junction Nowe . Marzy to the junction Lubicz . (51,72 km) and the bridge over . the Vistula River.
Modernisation of partly existing . section from the junction Lubicz . to Czerniewice (10,70 km) and . finishing construction of the two . bridges over the Vistula River . in Toruń and Drwęca River.
Project scope
Total length – 62 km
Interchanges - 5
Toll Stations - 6
Travellers Service Areas – 4 pairs
Motorway Maintenance Area - 1
Engineering Structures – 51
Modernisation of existing - 15
Environmental mitigation facilities
Road furniture
A1 Motorway route
Localisation of the bridge over the Vistula River near Toruń and the interchange „Czerniewice”
A1 Motorway route
Localisation of the MOP „Nowa Wieś” and the bridge over the Drwęca River
A1 Motorway route
Localisation of the interchange „Lubicz”
A1 Motorway route
Localisation of the interchange „Turzno”
A1 Motorway route
Localisation of the MOP „Nowy Dwór”
A1 Motorway route
Localisation of the Dźwierzyńskie Lake
A1 Motorway route
A1 Motorway route
Site organisation
South of Poland
Scotland, Scandinavia
Contract structure
Ministry of Infrastructure
GDDKiA
Lenders EIB, NIB
Shareholders Skanska ID, Intertoll ID, John Laing Infrastructure,
NDI Autostrada
Independent Engineer WS Atkins
Polska
EPC Contractor Skanska -NDI
Operations & Maintenance Intertoll Polska
Equipment Supplier Intertoll ID
Toll Plaza Contractor Intertoll Construction Polska
Construction Law Inspectors
www.a1.com.pl