EPPC 11 Conference Altea (Spain) 23 rd -25 th May 2011 © Iberdrola 2011 1 EPCC-11 Altea (Spain) May 2011 J.Martí, J.Gutierrez, E. de Gabriel (Iberdrola) C.Richter, E.Beiglboeck, V.Moise (Siemens) ( ) Aislamiento y Reposición Automática * Automatic Isolation and Restoration

Transcript of Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues...

Page 1: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

1

EPCC-11 Altea (Spain) May 2011

J.Martí, J.Gutierrez, E. de Gabriel (Iberdrola)

C.Richter, E.Beiglboeck, V.Moise (Siemens)

( ) Aislamiento y Reposición Automática*

Automatic Isolation and Restoration

Page 2: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Control Centre (CC)

Bilbao

Valencia

Alicante

Toledo

Madrid

Valladolid

6000 RTUs:

1200 Main Substations

2600 Secondary substations

2100 pole RTUs

~ 500.000 RTU points

Control Structure

• 6 Systems of equivalent size covering ~2M customer

• Each of them operates hierarchically all voltage levels within the Region: from Transmission

(meshed) to Distribution (radial)

• Hot/stand-by plus emergency configuration

• Same system version, integrating SCADA/DMS/OMS functionality except for EMS-NA only

running Bilbao but operated remotely from the other CC

IBERDROLA Distribución

Page 2

Page 3: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Page 3

Automatic Isolation and Restoration program

• MOTIVATION: Improve the QoS.

• CHALLENGE: Assume automatic commands from Spectrum

• PREREQUISITES for the utility

1. Change the “business as usual” operation

2. Improve the model of the MV network

3. Improve the quality of measurements

4. Increase the penetration of local automation

• CONDITIONS in Spectrum

• Avoid complex typification nor complex decision rules to be maintained

• 100% reliable program (network topology, considers tags, etc..)

• Must work in all Iberdrola Distribución

• EXPECTED RESULTS: reduce down to less than 3 minutes (regulatory limit) the first

restoration actions. Operator’s response time can vary depending on the situation.

Main Coordinates

Page 4: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Motivation: penalties

Page 4

Page 5: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Algorithm description

DEF.

Trip?

Warns

Operator

All Autom.

to MANUAL

Fault

Isolation

FDs

or

50%?

From the

same FH

Start

Highlights

affected

zone

Isolation Restoration

Wait for

overloads

From other

FH

Admits

?

Restores

Wait for

overloads

Admits

?

Stop

Tag Ctrl Inh

isolated

segment

Normalization

No No

yes Yes

yes

No

No, End

of possibilities

FH admits?

Disconnect

Generators

Bottle

necks?

No

yes

Normalizes

Autom &

Generators

Successful isolation

Not successful isolationPage 5

Warns

Operator

Wait for

network

stability

Page 6: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Fault close to the FH = ST CALPE /20kV /L08 CANUTA (Blue)

Basic example, no FD

Tries 50% of the line

Restores from another FH

Fault happens close to the FH

Page 6

Page 7: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Once STOPPED ARA will tag the isolated segment

Page 7

Page 8: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Page 8

• ARA can also be used manually to disconnect the Generators via SPM

when an open action is to be performed at the FH

• ARA can be disabled at switch bay level or station level

Page 9: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Basic example, fault close to the FH = ST CALPE /20kV /L08 CANUTA

Fault

Warns the dispatcher (button blinks)

Page 10: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Page 10

• All actions are associated to a sequence number, (in this case 22)

• Wait for overloads is parametrizable (now one minute) as other timings

• In the OMS all actions are associated to the same outage

• In case of not successful isolation all actions done were always in the

right direction

ARA response time was 2:22 minutes vs 5:38 dispatchers reaction

Isolation& restoration done from another FH = ST CALPE /20kV /L21 IFACH

Page 10

Page 11: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Fault happens in aerial line

ST FUENSANTA /20kV /L07 NERPIO

(Red circuit)

Page 11

Second example with FD indicating the fault

Page 12: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Page 12

The Dispatcher is

warned and the

deenergized circuit

is highlighted

Page 13: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Once the isolation

is effectively done

the restoration starts

from Cyan feeder

Page 13

Page 14: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Still restoration is

possible. Green

feeder takes rest of

the market

Page 14

Page 15: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

The outage is created and the crew is on

the way. The Dispatcher will coordinate the

works

Page 15

The isolated segment is tagged with

CtrlInh with a predefined text

Page 16: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Description of ARA main parameters

Page 16

• Waiting time to start ARA after the definitive trip, network stable

• Waiting time for overloads after a restoration action

• End time, to avoid endless loops in case of errors

• Number of command retries after command failure.

• Parameters to displace the 50% rule

• Available capacity (in %) before restoring from an other FH

• Maximum number of breaker closing actions against fault

ARA is defined to work only in the distribution radial network

• When checking other FH capacity to resupply it uses the last hour

average flow and evaluates the capacity to be restored (faster and more

reliable than using DNA at this point)

Page 17: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Experience with ARA in Iberdrola

Page 17

• FAT passed in May 2010 in Madrid

• During FAT 15 parallel cases were successfully run simulating storm mode

ARA restoration time is always less than 3 minutes since the

definitive trip occurrence

• In July 2010 ARA first prototype was installed in Alicante CC

• Since January 2011 it is available in the 6 CC at Iberdrola, but only used

in the emergency system (disabled in the real time system)

• All definitive trips have been simulated and analyzed, helping Dispatchers

to get confidence with the tool

• Dispatchers are receiving training on ARA

• In this time ARA has been successfully tested in many scenarios and no

major problems have been detected at system level

Page 18: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Conclusions : ARA vs Dispatchers

Page 18

• Differences on response time ARA vs Dispatchers average 4 minutes

• ARA is always faster than the Dispatcher

• In some situations the difference is more than 30 minutes (storms, parallel

outages etc…) ARA more important

vs

However, it’s wrong to consider ARA vs Dispatchers

• It’s expected ARA to make life of the Dispatchers easier, reduce their

stress, and let them concentrate in managing crews to solve outages

Regarding QoS and penalties the impact of ARA is significant

Page 19: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Conclusions: ARA and Automation

Page 19

• Iberdrola is in the process of a large deployment of automation connected

to the AMI project.

• Higher degree of automation ARA more selective less affected market

• In normal operation both ARA and Dispatchers can be dramatically

affected by poor reliability of automation:

Command retries increase unnecessarily the response time

Wrong information from fault detectors can be handled but reduces

the efficiency of ARA significantly

Page 20: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

ARA Next steps

Still some technical issues are been discussed in Iberdrola

• Closing actions with switches? Initially done only with breakers

• Reclosing strategy is evaluated: Reducing reclosing actions to just one

retry and let ARA solve faster

• Using ARA in underground cables?

• Definitive trip signal not existing in old substations

• Checking bottleneck information

• Some response times could be reduced and optimized

If these issues are solved and the program behaves satisfactory in all

control centers, the target is to have a first prototype operative in the

3rdQ of 2011 and progressively in the other 5 CC

Page 20

For Iberdrola Distribution it will be the first time to deploy

automatic network commands from a control system in close loop

Page 21: Automatic Isolation and Restoration 8 Marti (p).pdf · ARA Next steps Still some technical issues are been discussed in Iberdrola • Closing actions with switches? Initially done

EPPC 11 ConferenceAltea (Spain) 23rd-25th May 2011

© Iberdrola 2011

Thank you