Automated Machine Guidance / Stringless PavingLeica iCon Pave. 11 Paving with Multiple Computers. 12...

38
Automated Machine Guidance / Stringless Paving Tim Tometich Manatt’s, Inc

Transcript of Automated Machine Guidance / Stringless PavingLeica iCon Pave. 11 Paving with Multiple Computers. 12...

  • Automated Machine Guidance / Stringless Paving

    Tim Tometich

    Manatt’s, Inc

  • 2

    Topics of Discussion

    ➢Types of Machine Control

    ➢File Types used in Machine Control /

    Electronic Needs

    ➢Accuracies of Machine Control Equipment

    ➢Electronic Needs

    ➢Challenges using AMG

    ➢Survey Needs

  • 3

    GPS Machine Control Grading –

    Adoption

  • 4

    Crush and Pave

    GPS Grade

  • 5

    Trimmer Guided by Total Station

    Pavesmart Software

  • 6

    Profile Milling Operations

  • Paver Guided by Total Station

    Pavesmart / iCon Software

  • 8

    How does Stringless Paving work?

  • 9

    Pavesmart

  • Leica iCon Pave

  • 11

    Paving with Multiple Computers

  • 12

    Electronic File Needs

  • 13

    Electronic File Needs➢ For Machine Control Grading (Dozers, Motorgraders,

    Excavators)

    ➢ Surface (Triangular Irregular Network(TIN))

    ➢ Linework File (Horizontal Only)

    ➢ File Types – XML’s or .DXF’s

    ➢ For Machine Control Paving, Milling, Trimming

    ➢ 3D Alignment Models or 3D Polylines - XML’s or

    DXF’s

    ➢ Alignment – XML’s

    ➢ Transition Locations (Supers)

  • 14

    Electronic File Needs

  • 15

    3D Models - TIN (Triangular Irregular Network)

    Primarily used for GPS Grading

  • 16

    3D Models

  • 17

    3D Models - Stringlines (3D Polylines or Breaklines)

    Primarily used for Stringless Operations

  • 18

    3D Models - Stringlines (3D Polylines or Breaklines)

    Primarily used for Stringless Operations

  • 19

    3D Models - IRI Profile Testing

  • 20

    3D Models - IRI Profile TestingStart Station End Station IRI (in/mi) Classification

    10630+00.00 10635+28.00 5.25 Smoothest

    10635+28.00 10640+56.00 5.41 Smoothest

    10640+56.00 10645+84.00 5.62 Smoothest

    10645+84.00 10651+12.00 1.90 Smoothest

    10651+12.00 10656+40.00 1.50 Smoothest

    10656+40.00 10661+68.00 7.77 Smoothest

    10661+68.00 10666+96.00 7.53 Smoothest

    10666+96.00 10672+24.00 7.87 Smoothest

    10672+24.00 10677+52.00 6.58 Smoothest

    10677+52.00 10682+80.00 4.57 Smoothest

    10682+80.00 10688+08.00 4.74 Smoothest

    10688+08.00 10693+36.00 5.15 Smoothest

    10693+36.00 10698+64.00 5.98 Smoothest

    10698+64.00 10703+92.00 9.19 Smoothest

    10703+92.00 10709+20.00 6.73 Smoothest

    10709+20.00 10714+48.00 0.37 Smoothest

    10714+48.00 10719+76.00 0.37 Smoothest

    10719+76.00 10725+04.00 1.78 Smoothest

    10725+04.00 10730+32.00 4.46 Smoothest

    10730+32.00 10735+60.00 4.20 Smoothest

    10735+60.00 10740+88.00 4.15 Smoothest

    10740+88.00 10746+16.00 4.20 Smoothest

    10746+16.00 10751+44.00 4.60 Smoothest

    10751+44.00 10756+72.00 1.85 Smoothest

    10756+72.00 10762+00.00 0.35 Smoothest

    10762+00.00 10767+28.00 0.89 Smoothest

    10767+28.00 10772+56.00 6.81 Smoothest

    10772+56.00 10777+84.00 6.98 Smoothest

    10777+84.00 10783+12.00 7.29 Smoothest

    10783+12.00 10788+40.00 4.35 Smoothest

    10788+40.00 10793+68.00 1.12 Smoothest

    10793+68.00 10798+96.00 1.10 Smoothest

    10798+96.00 10804+24.00 10.63 Smoothest

    10804+24.00 10809+52.00 7.56 Smoothest

    10809+52.00 10810+43.96 18.49 Smooth

    Tue Oct 17 19:29:27 2017

    International Roughness Index Report

  • 21

    Electronic File Challenges➢ Files do not reflect actual field conditions

    ➢ “Field Verify” – Should be a thing of past

    ➢ File sizes can be a challenge

    ➢ Road Projects- Typically thin out the vertices

    ➢ Lines overlapping each other

    ➢ For stringless operations, polylines crossing

    eachother

    ➢ Run-in and Run outs

  • 22

    Electronic File Challenges➢ Electronic information doesn’t include special

    case areas – special shaping

    ➢ Recently had a project tying into a Rairlroad

    o File didn’t represent the cross slopes

    ➢ Storm Sewer protruding through bottom of

    concrete

    o Made a quick profile change, exported the

    new 3D file, placed rock, trimmed and

    continued paving

  • 23

    Electronic File Challenges➢ Intersecting roads or ramps not tied in

    correctly.

    ➢ T-intersection – Crown is not transitioned

    correctly into the intersecting road

    ➢ Designs that do not align with paving

    operations. Designers don’t always understand

    a paver’s capabilities or incapability's

    ➢ Grading operations – ditch profiles not

    matching pipe inlets elevations, etc…

  • 24

    Stringless Paving Challenges➢ Iowa DOT projects

    ▪ Not all detour pavements or cross-overs are

    electronically designed – Contractor Design

    ➢ Iowa DOT and County Overlays- Contractor

    Design

    ▪ Time-consuming if topo is performed after

    nominal milling

  • 25

    Survey Needs

    ➢ For GPS Grading

    • Control Points that surround the working

    area (Minimum of 4 points)

    • For Linear (road) Projects – points should be

    placed as wide as possible

  • 26

    Survey Needs

    ➢ For Stringless Machine Control (Total Station)

    • Control points spaced every 500 ft on each

    side of road staggered.

    • Tie-in locations shot and verified

    • Horizontal and Verticals as tight as possible

  • 27

    Survey Needs

  • 28

    Survey Issues

    ➢ GPS Control not matching Paving Control

    ➢ Paving Control set in the fall to be used in the

    spring - Freeze Thaw Cycle

    ➢ Paving Control too loose – set with longer

    distances

    ➢ Topo cross-sections spaced too far apart

    ➢ Topo shot with incorrect control

    ➢ 3D Models don’t match field conditions

  • 29

    PCC Overlays – To mill or not to mill

    ➢ Every project is unique.

    ➢ Projects requiring pavement scarification

    ❖What is profile milling?

    ✓ Is it just cutting a nominal depth with a

    cross slope? Maybe? Up for

    Interpretation??

    ✓ Does it need to follow the same profile of

    the PCC Pavement top minus the

    thickness of concrete?

  • 30

    Profile Milling Operations

  • 31

    PCC Overlays – To mill or not to mill?

    ➢ From a contractors perspective –

    ➢ We believe the cost savings in concrete

    yield outweighs the cost of 3D Profile Milling

    ▪ We have seen savings from of 120-125%

    yields down to 105-110% yields

    ▪ Produces a more consistent slab and can

    better utilize the materials

  • 32

    PCC Overlays – To mill or not to mill?-

    Continued

    ➢ From a contractors perspective –

    ➢ Less disruption in traffic – wait time on

    survey and design model is less

    ➢ Re-invest in the slab thickness

  • 33

    Preliminary Survey Collection

    Leica TS16

    Insert Scanning

    Picture here

  • 34

    Preliminary Survey Collection

  • 35

    Electronic Files used in Bidding➢ Primarily used to help speed up the Estimating

    Process

    ➢ Calculation of earthwork, earthwork balancing

    and haul distances

    ➢ Verifying quantities and helping to plan the

    project.

    ➢ Calculation of Paving Runs (Mainline Paving

    vs. Handwork)

    ➢ Calculation of Materials

  • 36

    Conclusion - Machine Control

    Benefits from a Contractor’s Perspective

    ▪ Increased Productivity – 10 % Avg - as much as 100%

    ▪ Increased Accuracy – 0.01-0.02 ft with right tools

    ▪ Increased ability to make changes quickly

    ▪ Safer Projects / Shorter Schedules

    ▪ Operators and Supervisors can be more empowered

    ▪ More Cost Effective Projects

    ▪ More Satisfied Owners

  • 37

    ▪ Gives the Contractor Real Time Information in the Field

    ▪ Allows the Contractor and Inspector to verify work

    efficiently

    ▪ If the 3D Model is not provided, Contractors have proved

    they will pay for it to prepared

    ▪ Survey Costs are greatly reduced – 50% in some instances

    ▪ Shifts some survey work from the field back to the office for

    Design. 90% in field reduced to 40%

    Conclusion

    Benefits Continued – Contractor’s Perspective

  • 38

    QUESTIONS / COMMENTS ??