Automated Machine Guidance / Stringless PavingLeica iCon Pave. 11 Paving with Multiple Computers. 12...
Transcript of Automated Machine Guidance / Stringless PavingLeica iCon Pave. 11 Paving with Multiple Computers. 12...
-
Automated Machine Guidance / Stringless Paving
Tim Tometich
Manatt’s, Inc
-
2
Topics of Discussion
➢Types of Machine Control
➢File Types used in Machine Control /
Electronic Needs
➢Accuracies of Machine Control Equipment
➢Electronic Needs
➢Challenges using AMG
➢Survey Needs
-
3
GPS Machine Control Grading –
Adoption
-
4
Crush and Pave
GPS Grade
-
5
Trimmer Guided by Total Station
Pavesmart Software
-
6
Profile Milling Operations
-
Paver Guided by Total Station
Pavesmart / iCon Software
-
8
How does Stringless Paving work?
-
9
Pavesmart
-
Leica iCon Pave
-
11
Paving with Multiple Computers
-
12
Electronic File Needs
-
13
Electronic File Needs➢ For Machine Control Grading (Dozers, Motorgraders,
Excavators)
➢ Surface (Triangular Irregular Network(TIN))
➢ Linework File (Horizontal Only)
➢ File Types – XML’s or .DXF’s
➢ For Machine Control Paving, Milling, Trimming
➢ 3D Alignment Models or 3D Polylines - XML’s or
DXF’s
➢ Alignment – XML’s
➢ Transition Locations (Supers)
-
14
Electronic File Needs
-
15
3D Models - TIN (Triangular Irregular Network)
Primarily used for GPS Grading
-
16
3D Models
-
17
3D Models - Stringlines (3D Polylines or Breaklines)
Primarily used for Stringless Operations
-
18
3D Models - Stringlines (3D Polylines or Breaklines)
Primarily used for Stringless Operations
-
19
3D Models - IRI Profile Testing
-
20
3D Models - IRI Profile TestingStart Station End Station IRI (in/mi) Classification
10630+00.00 10635+28.00 5.25 Smoothest
10635+28.00 10640+56.00 5.41 Smoothest
10640+56.00 10645+84.00 5.62 Smoothest
10645+84.00 10651+12.00 1.90 Smoothest
10651+12.00 10656+40.00 1.50 Smoothest
10656+40.00 10661+68.00 7.77 Smoothest
10661+68.00 10666+96.00 7.53 Smoothest
10666+96.00 10672+24.00 7.87 Smoothest
10672+24.00 10677+52.00 6.58 Smoothest
10677+52.00 10682+80.00 4.57 Smoothest
10682+80.00 10688+08.00 4.74 Smoothest
10688+08.00 10693+36.00 5.15 Smoothest
10693+36.00 10698+64.00 5.98 Smoothest
10698+64.00 10703+92.00 9.19 Smoothest
10703+92.00 10709+20.00 6.73 Smoothest
10709+20.00 10714+48.00 0.37 Smoothest
10714+48.00 10719+76.00 0.37 Smoothest
10719+76.00 10725+04.00 1.78 Smoothest
10725+04.00 10730+32.00 4.46 Smoothest
10730+32.00 10735+60.00 4.20 Smoothest
10735+60.00 10740+88.00 4.15 Smoothest
10740+88.00 10746+16.00 4.20 Smoothest
10746+16.00 10751+44.00 4.60 Smoothest
10751+44.00 10756+72.00 1.85 Smoothest
10756+72.00 10762+00.00 0.35 Smoothest
10762+00.00 10767+28.00 0.89 Smoothest
10767+28.00 10772+56.00 6.81 Smoothest
10772+56.00 10777+84.00 6.98 Smoothest
10777+84.00 10783+12.00 7.29 Smoothest
10783+12.00 10788+40.00 4.35 Smoothest
10788+40.00 10793+68.00 1.12 Smoothest
10793+68.00 10798+96.00 1.10 Smoothest
10798+96.00 10804+24.00 10.63 Smoothest
10804+24.00 10809+52.00 7.56 Smoothest
10809+52.00 10810+43.96 18.49 Smooth
Tue Oct 17 19:29:27 2017
International Roughness Index Report
-
21
Electronic File Challenges➢ Files do not reflect actual field conditions
➢ “Field Verify” – Should be a thing of past
➢ File sizes can be a challenge
➢ Road Projects- Typically thin out the vertices
➢ Lines overlapping each other
➢ For stringless operations, polylines crossing
eachother
➢ Run-in and Run outs
-
22
Electronic File Challenges➢ Electronic information doesn’t include special
case areas – special shaping
➢ Recently had a project tying into a Rairlroad
o File didn’t represent the cross slopes
➢ Storm Sewer protruding through bottom of
concrete
o Made a quick profile change, exported the
new 3D file, placed rock, trimmed and
continued paving
-
23
Electronic File Challenges➢ Intersecting roads or ramps not tied in
correctly.
➢ T-intersection – Crown is not transitioned
correctly into the intersecting road
➢ Designs that do not align with paving
operations. Designers don’t always understand
a paver’s capabilities or incapability's
➢ Grading operations – ditch profiles not
matching pipe inlets elevations, etc…
-
24
Stringless Paving Challenges➢ Iowa DOT projects
▪ Not all detour pavements or cross-overs are
electronically designed – Contractor Design
➢ Iowa DOT and County Overlays- Contractor
Design
▪ Time-consuming if topo is performed after
nominal milling
-
25
Survey Needs
➢ For GPS Grading
• Control Points that surround the working
area (Minimum of 4 points)
• For Linear (road) Projects – points should be
placed as wide as possible
-
26
Survey Needs
➢ For Stringless Machine Control (Total Station)
• Control points spaced every 500 ft on each
side of road staggered.
• Tie-in locations shot and verified
• Horizontal and Verticals as tight as possible
-
27
Survey Needs
-
28
Survey Issues
➢ GPS Control not matching Paving Control
➢ Paving Control set in the fall to be used in the
spring - Freeze Thaw Cycle
➢ Paving Control too loose – set with longer
distances
➢ Topo cross-sections spaced too far apart
➢ Topo shot with incorrect control
➢ 3D Models don’t match field conditions
-
29
PCC Overlays – To mill or not to mill
➢ Every project is unique.
➢ Projects requiring pavement scarification
❖What is profile milling?
✓ Is it just cutting a nominal depth with a
cross slope? Maybe? Up for
Interpretation??
✓ Does it need to follow the same profile of
the PCC Pavement top minus the
thickness of concrete?
-
30
Profile Milling Operations
-
31
PCC Overlays – To mill or not to mill?
➢ From a contractors perspective –
➢ We believe the cost savings in concrete
yield outweighs the cost of 3D Profile Milling
▪ We have seen savings from of 120-125%
yields down to 105-110% yields
▪ Produces a more consistent slab and can
better utilize the materials
-
32
PCC Overlays – To mill or not to mill?-
Continued
➢ From a contractors perspective –
➢ Less disruption in traffic – wait time on
survey and design model is less
➢ Re-invest in the slab thickness
-
33
Preliminary Survey Collection
Leica TS16
Insert Scanning
Picture here
-
34
Preliminary Survey Collection
-
35
Electronic Files used in Bidding➢ Primarily used to help speed up the Estimating
Process
➢ Calculation of earthwork, earthwork balancing
and haul distances
➢ Verifying quantities and helping to plan the
project.
➢ Calculation of Paving Runs (Mainline Paving
vs. Handwork)
➢ Calculation of Materials
-
36
Conclusion - Machine Control
Benefits from a Contractor’s Perspective
▪ Increased Productivity – 10 % Avg - as much as 100%
▪ Increased Accuracy – 0.01-0.02 ft with right tools
▪ Increased ability to make changes quickly
▪ Safer Projects / Shorter Schedules
▪ Operators and Supervisors can be more empowered
▪ More Cost Effective Projects
▪ More Satisfied Owners
-
37
▪ Gives the Contractor Real Time Information in the Field
▪ Allows the Contractor and Inspector to verify work
efficiently
▪ If the 3D Model is not provided, Contractors have proved
they will pay for it to prepared
▪ Survey Costs are greatly reduced – 50% in some instances
▪ Shifts some survey work from the field back to the office for
Design. 90% in field reduced to 40%
Conclusion
Benefits Continued – Contractor’s Perspective
-
38
QUESTIONS / COMMENTS ??