Aurum Pride Towers Progress Pictures

13
Comments : AURUM PHASE 02 Photo Report Key Plan showing the Camera positions , Click on the Icon to review respective status: 1 2 3 5 4 6 AURUM_Photo Report - Phase 02

Transcript of Aurum Pride Towers Progress Pictures

Page 1: Aurum   Pride Towers Progress Pictures

Comments :

AURUM – PHASE 02 – Photo Report

• Key Plan showing the Camera positions , Click on the Icon to review respective status:

1

2

3

5

4

6

AURUM_Photo Report - Phase 02

Page 2: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower A & B ;; no progress

Phase 02 – Photo report Position - 01

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 3: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower A : no progress.

Phase 02 – Photo report Position - 02

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 4: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower A & D : no progress.

Phase 02 – Photo report Position - 03

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 5: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower D : no progress.

Phase 02 – Photo report Position - 04

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 6: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower A : no progress.

Phase 02 – Photo report Position - 05

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 7: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower B : 1st & 2nd floor plastering work is in progress.

Phase 02 – Photo report Position - 06

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 8: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Phase 1 & 2 : intermediate position

Phase 02 – Photo report Position - 07

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 9: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower B : 1st floor plastering work is progress inside of the tower.

Phase 02 – Photo report Position - 08

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 10: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower B : 1st floor plastering work is progress inside of the tower.

Phase 02 – Photo report Position - 08

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 11: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower B : 1st floor plastering preparation work is progress inside of the tower.

Phase 02 – Photo report Position - 08

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 12: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower B : 1st floor plastering preparation work is progress inside of the tower.

Phase 02 – Photo report Position - 08

1

23

5

4

6

AURUM_Photo Report - Phase 02

Page 13: Aurum   Pride Towers Progress Pictures

Key Plan

Comments :

• Tower B : New hoist erection work is in progress.

Phase 02 – Photo report Position - 08

1

23

5

4

6

AURUM_Photo Report - Phase 02