Auditorium Brick Work and Plastering - Method Statement

3
IBSL Project – Colombo 08 Method Statement – Auditorium Masonry work Method Statement for Masonry work 1.0 Objective The purpose of this section is to describe the important steps related to the Masonry work in Auditorium. 2.0 Setting out Initial setting out will be carried-out by using necessary survey equipments under supervision of Site Engineer/Engineer Assistant. This will be done methodically with all sorts of cross checking and computations, as per the drawings received from the consultant. 100mm offline will be marked from internal side of the 225mm brick wall and 200mm offline will be marked from the internal side from the block wall. 3.0 leveling 1000mm Structural finished level would be marked on the brick wall. Exact measurement of Sill and Lintel levels would be taken from this line. 4.0 Stiffener Column/Beams 225 mm Brick/100 mm Block walls No stiffener Column/Beams would be done as per the Engineer’s instruction. 5.0 Quality Assurance/Quality Control Our Quality Assurance Engineer/Technical officer will check the quality of the bricks/blocks and standard test also been done prior to the unloading. All the bricks would be properly cured prior the laying. Sierra Construction (Pvt) Ltd 1

description

method statement

Transcript of Auditorium Brick Work and Plastering - Method Statement

IBSL Project Colombo 08Method Statement Auditorium Masonry workMethod Statement for Masonry work1.0 Objectivehe !ur!ose o" this section is to describe the im!ortant ste!s related to the Masonry workin Auditorium#2.0 Setting outInitial settin$ out will be carried%out by usin$ necessary sur&ey e'ui!ments undersu!er&ision o" Site (n$ineer)(n$ineer Assistant# his willbe done methodically with allsorts o" cross checkin$ and com!utations* as !er the drawin$s recei&ed "romtheconsultant# +00mm o,ine will be marked "rom internal side o" the --.mm brick wall and-00mm o,ine will be marked "rom the internal side "rom the block wall# 3.0 leveling+000mm Structural /nished le&el would be marked on the brick wall# (0act measuremento" Sill and Lintel le&els would be taken "rom this line# .0 Sti!ener "olumn#$eams225 mm Brick/100 mm Block walls1o sti2ener Column)Beams would be done as !er the (n$ineer3s instruction#%.0 &uality 'ssurance#&uality "ontrol4ur 5uality Assurance (n$ineer)echnical o6cer will check the 'uality o" the bricks)blocksand standard test also been done !rior to the unloadin$#All the bricks would be !ro!erly cured !rior the layin$#All the works done under 'uali/ed sta2 member and continuous 'uality checkin$ wouldbe done by our 5uality Assurance (n$ineer)echnical sta2 durin$ the work# (.0 "ement ) Sand Mortar Mi* Brick worksMi0!ro!ortiono"+7.Cement7Sand* mortarwouldbeuse"orthebrickwork# Mortarwould be used within -hrs a"ter mi0in$ with water# Sierra Construction 8P&t9 Ltd +IBSL Project Colombo 08Method Statement Auditorium Masonry work Plastering worksMi0!ro!ortiono" +7.Cement 7 Sand* mortar wouldbeused"or the!lasterin$work#Alteration to the lime* 80ml +-0ml o" Cebe0%:++- 8:eoMi0);ebMi09 would be added toeach .0k$ o" cement# +.0 $ond ,y-e(n$lish bone ty!e will be "ollowed in brick layin$#..0 /lacing ,ie0bar-mm thick erticality will be measured in each layer o" the brick usin$ !lumb bob#PlasteringLe&el !e$s on walls will be /0ed in minimum o" +?mm with re"erence to the o2 lines toblock walls set out in @oors# 10.0 Surface /re-aration#3m-roving 4oints of $rick 5all 6 Structural "oncreteSur"ace o" the walls would be !ro!erly cleaned# Concrete sur"ace will be !ro!erly rou$henor a!!ly +7+ mi0 o" cement 7 sand slurry with chemi/0 !rior to the !lasterin$ work# Beambottom to wall will be sto! by maintainin$ -mm $a! as !er the consultants instruction#Sierra Construction 8P&t9 Ltd -IBSL Project Colombo 08Method Statement Auditorium Masonry workSierra Construction 8P&t9 Ltd A