Auditor General's Report 2011 - Synopsis (English)
-
Upload
openidotvx6n9h -
Category
Documents
-
view
216 -
download
0
Transcript of Auditor General's Report 2011 - Synopsis (English)
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
1/100
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
2/100
ii
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
3/100
SYNOPSIS
AUDITOR GENERALS REPORTFOR THE YEAR 2011
ON THE AUDIT OF THE FEDERAL
GOVERNMENTS FINANCIAL STATEMENT,FINANCIAL MANAGEMENT, ACTIVITIES OFTHE FEDERAL MINISTRIES/DEPARTMENTSAND MANAGEMENT OF THE GOVERNMENT
COMPANIES
NATIONAL AUDIT DEPARTMENTMALAYSIA
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
4/100
ii
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
5/100
CONTENTS
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
6/100
iv
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
7/100
v
CONTENTS
PAGE
CONTENTS v
SECTION I
THE FEDERAL GOVERNMENTS FINANCIAL STATEMENT ANDFINANCIAL MANAGEMENT OF THE FEDERALMINISTRIES/DEPARTMENTS
PREFACE 7
Synopsis
PART I - Certification Of The Federal Governments Financial StatementFor The Year Ended 31 December 2011 13
PART II - Financial Management Of The Federal Government 13- Overall Financial Management Performance 13- Financial Management Of The Federal Ministries/Departments 13
POSTSCRIPT 17
SECTION II
ACTIVITIES OF THE FEDERAL MINISTRIES/DEPARTMENTS ANDMANAGEMENT OF THE GOVERNMENT COMPANIES
PREFACE 25
Synopsis
PART I - Implementation Of Activities By The Federal Ministries/Departments 29
PRIME MINISTERS DEPARTMENT
Legal Affairs DivisionMalaysia Department of Insolvency1. Management Of Bankruptcy And Company Winding Up Cases 29
Federal Court Chief Registrars Office2. Maintenance Of The Kuala Lumpur Court Complex 30
Public Private Partnership Unit3. Management Of Tourism Development At Corridor Economic Region 31
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
8/100
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
9/100
vii
MINISTRY OF TOURISM29. Management Of Providing/Upgrading Tourism Facilities Programme 5530. Upgrading Of Penang Hill Railway Project, Penang 56
MINISTRY OF FEDERAL TERRITORIES AND URBAN WELLBEING
Kuala Lumpur City Hall31. Management Of Integrated Transport Information System Project 57
MINISTRY OF EDUCATION MALAYSIA32. Solar Hybrid System Project For Rural Schools 5833. Management Of Quarters 5934. Procurement Of Equipment For Vocational Subjects At
Technical/Vocational Secondary Schools 6135. Management of Cooked Food Supply To Boarding Schools,
Technical/Vocational Secondary Schools And Government AssistedReligious Schools 61
MINISTRY OF HEALTH MALAYSIA36. Management Of Medical And Non Medical Supplies 6237. Registration, Licensing And Enforcement Activity Of Pharmaceutical
Product 6338. Management Of Hospital Equipment 6439. Construction Project Of The Kluang Hospital, Johor 6540. Linen And Laundry Service Management 6641. Maintenance Services Of Hospital Information System 6742. Management Of Flying Doctor Service Programme In The State Of Sarawak 68
MINISTRY OF HUMAN RESOURCESManpower Department43. Construction Management And Equipment Procurement At Advance
Technology Training Centre 69
MINISTRY OF INFORMATION COMMUNICATION AND CULTURENational Department Of Heritage44. Conservation And Preservation Of Heritage Programme 70
MINISTRY OF WOMEN, FAMILY AND COMMUNITY DEVELOPMENT
Department Of Social Welfare45. Social Assistance Programme 71
MINISTRY OF HIGHER EDUCATION46. Academic Training Scheme For Institution of Higher Education 71
MINISTRY OF DEFENCE47. Married Quarters Facilities For Malaysian Armed Forces 72
National Service Training Department48. Management Of National Service Training Programme 73
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
10/100
viii
MINISTRY OF HOME AFFAIRS49. Construction And Management Of Johor Ministry Of Home Affairs
Complex 74
Anti-Smuggling Unit
50. Management Of Enforcement Activities 75
Royal Malaysian Police Force51. The Management Of Undeveloped Land 7652. Construction Of The Marine Police Base Lahad Datu, Sabah 76
Department Of Civil Defence, Malaysia53. Management Of Emergency Relief Equipment Procurement 78
PART II - Management Of The Government Companies
54. Institut Terjemahan Dan Buku Malaysia 7855. SIRIM Berhad 7956. Pengurusan Aset Air Berhad 8057. Rangkaian Pengangkutan Integrasi Deras Sdn. Bhd. 8158. UDA Holdings Berhad 8259. Malaysia International Franchise Sdn. Bhd. 8360. Indah Water Konsortium Sdn. Bhd. 83
POSTSCRIPT 87
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
11/100
1
SECTION I
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
12/100
2
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
13/100
5
SYNOPSIS
AUDITOR GENERALS REPORTFOR THE YEAR 2011
AUDITOR GENERALS REPORT 2011ON THE FEDERAL GOVERNMENTS
FINANCIAL STATEMENT ANDFINANCIAL MANAGEMENT OF
THE FEDERAL MINISTRIES/DEPARTMENTS
NATIONAL AUDIT DEPARTMENT
MALAYSIA
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
14/100
6
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
15/100
7
PREFACE
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
16/100
8
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
17/100
7
PREFACE
1. Articles 106 and 107 of the Federal Constitution and the Audit Act 1957 require the
Auditor General to audit the Federal Governments Financial Statement, financial
management, activities of the Ministries/Departments as well as management of the
Federal Government companies and submit his reports to His Majesty, Seri Paduka
Baginda Yang di-Pertuan Agong and obtain his assent before tabling them in
Parliament. To fulfil these responsibilities, the National Audit Department needs to carry
out 4 types of audit as follows:
1.1. Attestation Audit - to give an opinion as to whether the Federal Governments
Financial Statement for the year concerned shows a true and fair view as well as its
accounting records are maintained properly and kept up to date.
1.2. Compliance Audit - to evaluate whether the financial management of the
Federal Ministries/Departments is in accordance with relevant financial laws and
regulations.
1.3. Performance Audit - to evaluate whether Federal Governments
activities/programmes/projects have been carried out efficiently, economically and
achieved its desired objectives/goals.
1.4. Government Companies Management Audit - to evaluate whether the
Federal Government companies have been managed in a proper manner.
2. My report on the Financial Statement and Financial Management of the Federal
Governments Ministries/Departments for the Year 2011 consists of the following:
Part I : Certification Of The Federal Governments Financial
Statement For The Year Ended 31 December 2011
Part II : Financial Management Of The Federal Government
Part III : National Audit Departments Involvement In
Various Activities Towards Enhancing
Accountability Of Public Financial Management
Part IV : General Matters
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
18/100
8
3. Audit on the Federal Governments Financial Statement for the Year 2011
revealed that the Statement as a whole reflected a true and fair view on the financial
position of the Federal Government as at 31 December 2011, its operational income
and cash flow for the year concerned as well as its accounting records were being
maintained properly and kept up to date. As for financial management, audit findingsrevealed that several Ministries and Departments still did not follow financial regulations
fully. Among others, these weaknesses were due to insufficient manpower, lack of
training in financial management, inadequate supervision and lax in monitoring.
4. All the matters reported in this report had been brought to the attention of the
Heads of Department for their confirmation. The National Audit Department also took
several approaches to help the Federal Governments Ministries/Departments to
improve their financial management. Among the approaches that had been taken were
as follows:
4.1. Implementing a rating system based on Accountability Index (AI). Through
this rating system, marks will be given for compliance with financial regulations for 6
main elements. These elements are management control, budgetary control,
receipts control, expenditure control, management of trust funds and deposits as
well as management of assets and stores. The Federal Ministries/Departments
which have been rated as excellent become role models. This will motivate others to
diligently improve and enhance their financial management.
4.2. Treasury Instructions require all Heads of Ministry/Department to ensure thatresponsible officers safeguard public money, stamps or other valuable items in
safety boxes, vaults, cash boxes or other receptacles. They must ensure that
records kept are complete, up to date and periodically checked by senior officers. In
order to ascertain to what extent this has been complied with, the National Audit
Department had also carried out surprise checks in 301 Federal offices throughout
the country.
4.3. The National Audit Department also continued to implement the Adoption
Programme which was introduced in 2003. Under this programme, several
Government offices which had been identified as being weak in financial
management were selected and given advice to assist them in rectifying
weaknesses especially in maintenance of accounting records. In 2011, the National
Audit Department carried out the Adoption Programme in 11 Federal offices across
the country. Generally, financial management at these offices had improved after
being given guidance and training.
4.4. The National Audit Department continued to be involved in the evaluation of
the performance of Premier Grade Officers on financial management as part of their
confirmation exercise. A total of 60 Heads of Department were evaluated from
January to April 2011. These evaluations have indirectly contributed towards the
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
19/100
9
enhancement of the financial management as promotion of Heads of Department
would only be considered by the Public Service Department after the National Audit
Department confirmed that corrective actions on the weaknesses raised had been
taken by the officers.
5. I would like to express my thanks to all the officers in the various Federal
Ministries/Departments who have given their full cooperation to my officers during the
audit. I would also like to record my appreciation and thanks to my officers who have
shown total commitment and worked diligently to complete this report.
( TAN SRI DATO SETIA HAJI AMBRIN BIN BUANG )
Auditor General of Malaysia
Putrajaya
12 June 2012
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
20/100
10
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
21/100
11
SYNOPSIS
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
22/100
12
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
23/100
13
SYNOPSIS
PART I - CERTIFICATION OF THE FEDERAL GOVERNMENTS FINANCIALSTATEMENT FOR THE YEAR ENDED 31 DECEMBER 2011
1. The Federal Governments Financial Statement for the year ended 31 December
2011 as a whole reflected a true and fair view of the financial position of the Federal
Government and the accounting records were also properly maintained and kept up-to-
date.
PART II - FINANCIAL MANAGEMENT OF THE FEDERAL GOVERNMENT
Overall Financial Management Performance
2. For the year 2011, the Federal Government received revenue totalling
RM185.42 billion, which was an increase of RM25.77 billion (16.1%) as compared to
RM159.65 billion for the year 2010. This was the highest income in 5 years since 2007.
The Inland Revenue Board of Malaysia alone managed to collect revenue of RM109.61
billion in 2011, which was an increase of 26.7% as compared to RM86.50 billion in
2010. In the meantime, the Royal Malaysian Customs Department had also successfully
collected revenue totalling RM30.38 billion in 2011, which showed an increase of 7.9%
as compared to RM28.15 billion in 2010. In the same year, the Government had
approved allocation of operating expenditure amounting to RM177.98 billion, which was
the highest approved allocation in 5 years. However, the allocation was insufficient to
cover the operating expenses amounting to RM182.59 billion. On 30 May 2012, an
additional allocation was approved by the Parliament to cover the deficit. As for the
development expenditure, Federal Ministries/Departments had spent RM46.42 billion
(93.9%) out of RM49.42 billion of the approved allocation.
Financial Management Of The Federal Ministries And Departments
3. The National Audit Department had audited 25 Federal Ministries and 42
Federal Departments in 2011 in order to ascertain whether their financial management
was in accordance with established laws and financial regulations. Audit findings
revealed that the overall financial performance at Ministries/Departments level for 2011
had improved as compared to 2010 and previous years. In 2011, the performance of 19
Ministries and 21 Departments in their financial management was rated as excellent,
which was an increase of 2 Ministries (11.8%) and 8 Departments (61.5%) as compared
to 17 Ministries and 13 Departments in 2010. On the other hand, 6 Ministries and 20
Departments were rated as good and one Department was rated as average. Besides
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
24/100
14
that, the Headquarters and 14 state branches of the Royal Malaysian Police, as well as
14 Malaysian Missions Overseas under the Ministry of Foreign Affairs were also
assessed.
4. As required under the Treasury Instructions, all Controlling Officers/Heads ofDepartment must ensure that the responsible officers safeguard public money, stamps
or other valuable of any kind in safety boxes, vaults, cash boxes or other receptacles.
They must carry out periodic inspections and maintain complete and updated records.
In order to ensure that such duties were carried out by the Controlling Officers/Heads of
Department, the National Audit Department had carried out surprise inspections in 301
Federal Departments/Offices at state and district levels. Audit findings revealed that
there were some instances where public money and other valuable items were not kept
safely, delays in banking-in collections and cash balances in hand differed from records.
The report on the findings had been submitted to the relevant heads of department/statefor further action.
5. Besides conducting mandatory audit as provided under the law, the National
Audit Department also implemented the Adoption Programme and carried out special
evaluation on the financial management performance of Premier Grade Officers in
various Ministries/Departments/Agencies. In 2011, the National Audit Department had
carried out the Adoption Programme at 11 Federal Offices whereas from January 2011
to April 2012, a total of 60 Premier Grade Officers had been evaluated.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
25/100
15
POSTSCRIPT
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
26/100
16
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
27/100
17
POSTSCRIPT
In general, the financial management of Ministries/Departments in 2011 showed a better
performance as compared to 2010. This was evident with 19 Ministries being rated as
excellent in 2011 as compared to 17 Ministries in 2010. The financial management at
the Departments level was also very encouraging with 21 Departments being rated as
excellent as compared to 13 Departments in 2010. However, such performance could
still be further enhanced if the Controlling Officers/Heads of Department not only take
action to rectify the weaknesses as highlighted by Audit but also take preventive actions
to ensure that the same weaknesses do not recur. With regard to this, the followings are
recommended to further strengthen the performance of financial management:
a. Controlling Officers/Heads of Department should conduct a comprehensive
check to determine whether the weaknesses highlighted by Audit also occur in
other areas and thereafter take corrective actions since audits conducted by the
National Audit Department are based on samples and specific scopes.
b. Ministries/Departments should enhance the effectiveness of Internal Audit Units
(UAD). Among others, they should ensure that the UAD staff get sufficient
training and guidance, prepare the annual audit plan so that auditing could be
carried out according to priorities, evaluate objectively and independently notonly on internal controls but also on risk management and organizational
governance, report on significant findings as well as giving recommendations
that give impact to the organization.
c. In order to enable issues highlighted by Audit to be discussed with greater focus,
Audit Committees should be set up in all Ministries in accordance with Treasury
Secretary Generals Directive dated 5 May 2009 requiring corrective and
preventive actions to be taken. The Audit Committee should report the results of
its discussion to the Financial Management and Accounts Committee chaired by
the Controlling Officer.
d. In order to further improve financial management, the involvement of Controlling
Officers/Heads of Department should be increased. They should be involved
hands-on on financial matters.
e. Secretary Generals/Heads of Department should chair every Exit Conference
together with the officers from the National Audit Department so that they could
know Audit issues beforehand and urgently take positive actions apart from
making improvements.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
28/100
18
f. In the implementation of eSPKB, the payment transactions are done at
Responsibility Centres and the supporting documents are kept at the respective
offices. In order to ensure that payment is done properly, supported by sufficient
documents and approved by authorised officers, the Accountant General
Department needs to ensure that its Inspectorate Unit carries out inspection onResponsibility Centres as planned.
g. All Departments policies, instructions and delegation of powers should be done
in written form so that they are more transparent and accountable. The
Departments Client Charter should be reviewed and updated constantly so that
services are delivered as promised.
h. Heads of Department should establish a check and balance system, supervise
closely and conduct surprise checks, conduct periodic assessment on skills and
capabilities of officers and give training to officers who are involved with financialmanagement so as to improve their efficiency. This is to avoid officers who are
less experienced and skilled from using their discretion when making decisions.
i. Records on asset and inventory should always be updated by the
Ministries/Departments in preparation for the Federal Government to move
towards accrual accounting in 2015.
j. Impose surcharge on those who failed to collect revenue/make improper
payment. Surcharge should also be imposed on Heads of Department/Division
for failing to take action against their staff who failed to carry out theirresponsibilities.
National Audit DepartmentMalaysia
Putrajaya12 June 2012
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
29/100
19
SECTION II
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
30/100
20
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
31/100
21
SYNOPSIS
AUDITOR GENERALS REPORTFOR THE YEAR 2011
ON ACTIVITIES OF THE FEDERAL
MINISTRIES/DEPARTMENTS ANDMANAGEMENT OF THE GOVERNMENT
COMPANIES
NATIONAL AUDIT DEPARTMENTMALAYSIA
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
32/100
22
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
33/100
23
PREFACE
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
34/100
24
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
35/100
25
PREFACE
1. Articles 106 and 107 of the Federal Constitution require the Auditor General to
audit the Federal Governments Financial Statement, financial management, activities
as well as management of Federal Government Companies and submit his reports to
His Majesty, Seri Paduka Baginda Yang di-Pertuan Agong and obtain his assent before
tabling them in Parliament. To fulfil these responsibilities, the National Audit Department
needs to carry out 4 types of audit as follows:
1.1. Attestation Audit - to give an opinion as to whether the Federal
Governments Financial Statement for the year concerned shows a true and fair
view as well as its accounting records are maintained properly and kept up to date.
1.2. Compliance Audit - to evaluate whether the financial management of the
Federal Ministries/Departments is in accordance with relevant financial laws and
regulations.
1.3. Performance Audit - to evaluate whether Federal Government activities
have been carried out efficiently and economically to achieve its desired
objectives/goals.
1.4. Government Companies Management Audit - to evaluate whether the
Federal Government Companies have been managed in a proper manner.
2. My report on the implementation of activities of the Federal
Ministries/Departments and the management of Government Companies for the year
2011 consists of 3 parts as follows:
Part I : Implementation Of Activities Of The FederalMinistries/Departments
Part II : Management Of Federal Government Companies
Part III : Status Of Follow-Up Actions Which Have Not Been Taken
By The Ministries/Departments/Government CompaniesOn The Recommendations Highlighted In The Auditor
Generals Report For 2009 And 2010
3. Section 6(d) of the Audit Act 1957 requires the Auditor General to carry out audit
to evaluate whether Government activities have been managed efficiently, economically
and in accordance with their stated objectives. The audit encompasses various activities
such as construction, infrastructure, maintenance, asset management, law enforcement,
procurement, revenue management, education, health, agriculture, human capital and
socio-economic upgrading programmes. This report contains observations from the
audit of 58 activities/projects of 28 Federal Ministries/Departments and management of7 Government Companies. Generally, weaknesses observed are such as improper
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
36/100
26
payment; work/procurement did not follow specifications; unreasonable delays;
wastage; weaknesses in revenue management and management of Governments
assets. The said weaknesses were due to negligence when complying with
Governments rules/procedure; programmes/projects and scopes/specifications were
not planned and identified properly; work of contractors/vendors/consultants was not
monitored and supervised closely; poor project management skills; decisions on
procurement were made late; information systems of the Departments/Agencies were
incomplete and not updated; outcome/impact of programmes/projects was not given
due attention; shortage of funds for asset maintenance; and insufficient officers to
collect revenue.
4. Apart from that, this report also highlights the financial performance of 47
Government companies for the period 2008 to 2010 based on the analysis done on the
data obtained from their audited financial statements. A total of 23 companies recorded
profit before tax for 3 consecutive years amounting to RM255.834 billion while 9
companies suffered accumulated losses amounting to RM2.446 billion for 3 consecutive
years. However, from the 23 companies which recorded profits, only 10 companies paid
dividend amounting to RM109.364 billion to the Government for 3 consecutive years
while 4 companies only paid dividend in specific years. A total of 20 out of the 25
companies paid tax amounting to RM81.382 billion to the Government for 3 consecutive
years.
5. In order to help the Ministries/Departments/Government Companies to rectify the
weaknesses which were highlighted in the Auditor Generals Report 2009 and 2010, a
total of 547 recommendations were made. Until 30 April 2012, follow up Audit revealed
that appropriate actions had been taken on 241 (96.4%) from 250 recommendationsmade in the 2009 Auditor Generals Report. As for 2010, action had been taken on 220
(74.1%) from the 297 recommendations made. In 2011, a total of 356 recommendations
were made in the Auditor Generals Report to the related
Ministries/Departments/Government Companies for corrective actions or to prevent the
same weaknesses from recurring. The National Audit Department will monitor
continuously to ensure appropriate actions will be taken by the relevant parties and will
report the updated status in the 2012 Auditor Generals Report.
6. I would like to express my thanks to all the officers of the
Ministries/Departments/Government Companies who have given their cooperation to myofficers during the audit. I also wish to express my appreciation and thanks to my
officers who have given their commitment and worked diligently to complete this report.
(TAN SRI DATO SETIA HAJI AMBRIN BIN BUANG )
Auditor General of MalaysiaPutrajaya
25 July 2012
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
37/100
27
SYNOPSIS
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
38/100
28
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
39/100
29
SYNOPSIS
PART I - IMPLEMENTATION OF ACTIVITIES BY THE FEDERALMINISTRIES/DEPARTMENTS
PRIME MINISTERS DEPARTMENT
Legal Affairs DivisionMalaysia Department of Insolvency1. Management Of Bankruptcy And Company Winding Up Cases
a. Malaysia Department of Insolvency (MdI) is responsible for the operation,
administration, service, compliance and enforcement of insolvency law in Malaysia.
The number of resolved cases and total revenue collection from insolvency
administration showed a significant increase for the years 2009 to 2011 resulting
from the comprehensive implementation of the Organisational Transformation
Programme since April 2009 by MdI. However, Audit findings revealed that the
management of bankruptcy and company winding up cases at the offices visited
was unsatisfactory and needed further improvement. Among the weaknesses
identified were as follows:
i. process/work flow chart was not updated with rules/instructions/time norms;
ii. delay in taking further action;
iii. insufficient training in insolvency management to enhance skills/competencies of
officers; and
iv. storage/maintenance of files/documents of winding up cases of the company
was not in order.
b. It is recommended that MdI takes the following actions:
i. update the process/work flow chart in accordance with Acts and instructions set
by the Department and set time norms for recording bankruptcy cases into CaseManagement System/preparation of indexes/issuance of First Notification
Letter/issuance of reminder letters on attendance/filing Statement of
Affairs/instalment payments;
ii. conduct site visits to the premises so that the process of property disclosure
could be done immediately;
iii. establish a monitoring system for the issuance of First Notification
Letter/reminder letters on attendance to the bankrupts/directors, filing Statement
of Affairs/instalment payments so that the application of Warrant of Arrest could
be done;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
40/100
30
iv. provide adequate training in order to enhance skills and competencies of
officers/staff who are involved in the management of bankruptcy and company
winding up cases; and
v. keep/organise files and documents relating to company winding up cases
properly and systematically to facilitate reference and monitoring purposes aswell as to ensure the physical safety of documents.
Federal CourtChief Registrars Office2. Maintenance Of The Kuala Lumpur Court Complex
a. The Kuala Lumpur Court Complex (KMKL) was built in February 2007 and started
operation on 3 May 2007. It was necessary for maintenance to be carried out to
maintain, restore and repair building facilities and surroundings. The Federal Court
Chief Registrars Office (PKPMP) was responsible for implementing and supervising
maintenance of the KMKL building. Kemuncak Facilities Management Sdn. Bhd.(KFM) was appointed by the Ministry of Finance through direct negotiation to carry
out the maintenance works. The maintenance agreement was signed on 14
September 2007 for a period of 3 years (1 July 2007 to 30 June 2010) for a contract
sum of RM30.28 million. This agreement was extended for another 2 years (1 July
2010 to 30 June 2012) for a contract sum of RM20.19 million. The scope of
maintenance works carried out at KMKL was for building conservation that was
comprehensive maintenance operation covering works on mechanical, electrical,
civil and structure as well as general works. Audit findings revealed that
maintenance works at KMKL was satisfactory. However, there were weaknesses asfollows:
i. there were some aspects in maintenance works which needed improvement in
order to increase maintenance effectiveness and to ensure that KMKL buildings
were in good condition;
ii. physical performance of maintenance works was unsatisfactory since there were
cracks and leakages in the buildings; and
iii. terms of contract were not clear, for example, value for each type of work was
not in detail and there was no provision of quality measurements, penalties and
Key Performance Indicators (KPIs).
b. It is recommended that PKPMP and responsible parties take the following actions:
i. periodically monitor maintenance works conducted by KFM to ensure good
quality, works done are effective and in accordance with specifications and
maintenance plans;
ii. provide penalty clauses, quality measurement mechanism and KPIs in future
maintenance agreements;
iii. repair cracks immediately before they worsen and ensure that leakages do notrecur;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
41/100
31
iv. request for technical advice from JKR to identify causes of continuous cracks
and leakages;
v. ensure that value of works is prepared in detail to avoid lump sum payments in
future maintenance contracts. This includes payment claims that are more
detailed and clear; andvi. appoint technical officer immediately to monitor verification and certification of
works.
Public Private Partnership Unit3. Management Of Tourism Development At Corridor Economic Region
a. The Public Private Partnership Unit (UKAS) of the Prime Ministers Department is
the central agency which is responsible for coordinating privatisation projects and
public-private sector collaboration projects that have impact on the economy and is
eligible to receive the Facilitation Fund. Among the UKAS functions are to analyse,plan, supervise, control, facilitate and evaluate the implementation of corridor
development programme. The development of the Corridor Economic Region is one
of the Government initiatives under the Ninth Malaysia Plan to improve the
relationship of all states by reducing the gap between differences in structure and
socio-economy within the regions. The objectives of the Tourism Development
Programme at the Corridor Economic Region were to increase the number of tourist
arrivals by providing world class facilities and to narrow the gaps between the
regions. Audit findings revealed that the overall management of tourism
development at the Corridor Economic Region was satisfactory in terms of strategicplanning for Corridor Authorities (PBK) and studies were carried out before project
implementation. However, there were several weaknesses as follows:
i. Rhinoceros Breeding Project at Lahad Datu, Sabah was completed late with 2
Extensions of Time of 252 days;
ii. low quality in construction works;
iii. performance evaluation was not carried out; and
iv. information on allocation/expenses was not updated.
b. It is recommended that UKAS and PBK take the following actions:
i. monitor rectification works of construction and upgrading projects;
ii. monitor project implementation to ensure success of programme;
iii. emphasize on project achievements by evaluating the outcome so that the
performance of the implementation authority (PBK) could be assessed more
effectively and could assist in future project planning; and
iv. update financial information and project implementation status to ensure
effective monitoring and supervision on the programme.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
42/100
32
MINISTRY OF FINANCE
Housing Loan Management Division4. Management Of Housing Loan
a. In 1971, the Government had established a Housing Loans Fund (KWPP) through
Housing Loans Fund Act 1971 (Act 42) which was managed by Housing LoanManagement Division (HLMD) with the aim of providing housing loan to public
servants. By the end of 2011, KWPP had a balance amounting to RM1.908 billion.
The objective of HLMD was to manage public sector housing loan with
professionalism, integrity and prudence in line with the Governments policy to assist
public servants to have own houses. Audit on HLMDs activity revealed that the
objective had been achieved. However, there were several weaknesses in the
management of housing loan as follows:
i. data on number of borrowers and loan balance could not be verified;
ii. non-compliance with loan application requirements;
iii. delay in remitting payment to developers/lawyers;
iv. arrears in loan repayment; and
v. delay in taking action against loan defaulters and problem in releasing title
documents.
b. It is recommended that HLMD takes the following actions:
i. develop an integrated computer system which could generate accurate report on
housing loan;
ii. ensure that work processes are done properly and establish an effective
monitoring mechanism to ensure borrowers abide by all the loan requirements;
iii. ensure that repayment of the loan is made within the stipulated time frame;
iv. seek legal advice on prolonged cases of arrears in loan repayment; and
v. ensure that all title documents are kept in safe custody and return to the rightful
owner after full settlement of loan.
INLAND REVENUE BOARD OF MALAYSIA5. Management Of Information On Fees And Commissions Recipients
a. The Inland Revenue Board of Malaysia (IRBM) has the power under Section 81,
Income Tax Act (ITA) 1967 to request certain agencies to provide information on
recipients of income from those agencies. The information relates to payments
made to individuals or companies such as payment of commissions to insurance
agents/representatives, distributors/wholesalers/dealers/stockists and remisiers/
brokers and other payment of fees such as royalties to authors/writers, part-time
instructors, suppliers/consultants and others. The Detection Unit Information System
(SMUP) was developed to enable efficient compilation of taxpayers information
where every information providers will be registered to facilitate monitoring. Auditfindings revealed some weaknesses as follows:
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
43/100
33
i. information providers did not submit information on the recipients of fees and
commissions;
ii. taxpayers did not declare/under declare amount of fees or commissions received
in the Income Tax Return Form for the year of assessment under review;
iii. taxpayers did not submit Income Tax Return Form although they received feesand commissions income; and
iv. taxpayers were not selected for tax audit.
b. It is recommended that IRBM takes the following actions:
i. make it compulsory for information providers to submit information on the
recipients of fees and commissions within the stipulated time;
ii. prosecute information providers who fail to comply;
iii. ensure that the SMUPwhich has been developedcould be used as a reliable
source of information; andiv. conduct desk audit or field audit on recipients of substantial fees and
commissions who fail to report their correct income to ensure level of tax
compliance.
6. Management On Income Tax Of Property Owners
a. Section 13 of the Real Property Gains Tax Act 1976 requires that every person who
acquires asset to notify such acquisition to the Inland Revenue Board of Malaysia
(IRBM). At IRBM, information on real property ownership captured through stamping
process of the Sales and Purchase Agreement at IRBM Stamping Office is uploaded
to IRBM data warehouse through the Detection Unit Information System (SMUP).
This information will be used by the Detection Unit to detect individuals who do not
have income tax file in order to broaden the tax base. As for information on cars
ownership, it is handled by the Road Transport Department (RTD). Audit findings
revealed some weaknesses as follows:
i. some property owners did not have income tax file;
ii. information was not uploaded into the Enterprise Taxpayer Profile (ETP);
iii. actions were not taken to track down the property owners;iv. selection of cases for tax audit either by field audit or desk audit on property
ownership was not given due attention; and
v. restriction orders from leaving the country were not issued and civil suit actions
were not taken against property owners with tax arrears.
b. To improve the management of income tax on property owners, it is recommended
that IRBM takes the following actions:
i. cooperate with Government/private agencies in the sharing of information in
order to broaden the tax base and strengthen tax collection;
ii. enhance action to identify individuals who evade tax;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
44/100
34
iii. extend the criteria for the selection of cases for tax audit to include property
ownership in order to avoid any incorrect tax returns, loss of revenue and also to
prevent tax evasion; and
iv. issue restriction orders to prevent property owners with tax arrears from leaving
the country and take civil suit actions against them.
7. Management Of Desk Audit Activity At The Non-Resident Branch
a. According to the Malaysian Income Tax Act (ITA) 1967, non-resident individuals are
those who stay less than 182 days in Malaysia in a year, regardless of their
citizenship or nationality. In general, the chargeable income of a non-resident
individual in Malaysia is taxed at the flat rate of 26% with effect from year of
assessment 2010 with no deduction for personal tax reliefs and rebates. Whereas
non-resident companies are companies which carry out business through a
permanent establishment in Malaysia and assessable on income accruing or
deriving from Malaysia. In general, the chargeable income of a non-resident
company in Malaysia is taxed at the flat rate of 25% with effect from year of
assessment 2009. The Non-Resident Branch of the Inland Revenue Board of
Malaysia (IRBM) manages the income tax of non-resident companies and
individuals in Malaysia. Under the Self Assessment System (SAS), tax audit
becomes an essential activity of IRBM to enhance voluntary compliance with the
laws. IRBM carries out two types of tax audit, namely desk audit and field audit.
Audit conducted by National Audit Department on the desk audit activity of the Non-
Resident Branch of IRBM revealed that the overall management of the desk audit
activities was satisfactory where performance had improved from non-achievement
of target in the year 2010 to over-achievement of target in the year 2011. However,
from the implementation aspect of its activities, there were some weaknesses as
follows:
i. delay in the registration of cases;
ii. weaknesses in the management of tax collection resulting in tax arrears of
RM3.36 million within the period of one month to 132 months;
iii. tax increase was not raised/under imposed; and
iv. restriction orders from leaving the country were not issued and civil suit actions
were not taken against taxpayers with tax arrears.
b. It is recommended that IRBM takes the following actions:
i. enhance monitoring of the management of desk audit activity to ensure that
every cases is registered and settled within the stipulated time period;
ii. enhance the awareness campaign on taxpayers to increase tax compliance;
iii. ensure that tax increase on tax arrears are correctly imposed; and
iv. issue restriction orders to prevent tax payers with tax arrears from leaving thecountry and take civil suit actions against them.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
45/100
35
8. Management On Tax Audit Activity For Individuals With Business Income
a. The Inland Revenue Board of Malaysia (IRBM) implemented the Self-Assessment
System (SAS) for individuals with business income with effect from year 2004. The
purpose of implementing this system is to encourage taxpayers to declare and pay
tax voluntarily. In order to confirm the accuracy of income tax declared by
individuals with business income through SAS, IRBM conducted tax audit activity
through Field Audit and Desk Audit to trace the level of taxpayers compliance with
tax rules and inculcate continuous voluntary compliance in taxpayers. Audit
conducted by National Audit Department revealed that 12 (70.6%) out of 17
branches managed to achieve/exceed their Key Performance Indicators(KPI) target
of files set on audit activity of individuals with business income. However, the KPI
achievement of Field Audit Officers need to be improved since only one branch had
all its Field Audit Officers achieving KPI for the years 2010 and 2011. As for 5 other
branches, Field Audit Officers only managed to achieve the KPI either for year 2010
or 2011. Audit conducted by National Audit Department on the management of tax
audit activity revealed several weaknesses as follows:
i. 1,244 (7.3%) of 17,085 individuals audited have their cases closed without audit
findings because there was no evidence of tax evasion even though their cases
were selected by the risk analysis methodology;
ii. 1,073 (57.3%) of 1,873 individual files checked at 17 IRBM branches showed
that additional tax raised and penalties imposed amounted to RM33.24 million
were resolved late between 6 to 941 days;iii. additional taxes raised as a result from field audit findings as well as estimated
assessment amounted to RM1.21 million were not issued to 36 taxpayers; and
iv. increase in tax was not imposed on cases of tax arrears and failure to comply
with tax instalment payment scheme resulting in loss of revenue to the
Government.
b. It is recommended that IRBM takes the following actions:
i. benchmark against the standards set in neighbouring countries to determine the
percentage of individuals with business income that need to be carried out field
audit and to set an appropriate percentage as yearly target;
ii. determine the number of Field Audit Officer post that is needed in line with the
increase in target on field audit activity;
iii. ensure the accuracy of taxpayers information so that the selection of field audit
cases based on the risk analysis methodology is correctly done;
iv. propose to the Department of Statistics Malaysia from time to time on the type of
business/service which needs to be given specific business code to ensure that
the business code is complete and updated. The Malaysian Income Tax Act
1967 should provide a section that allows penalty to be imposed on taxpayers
who do not fill in their business code or who fill in incorrect business code;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
46/100
36
v. Notice Of Additional Tax Assessment should be issued immediately for cases
completed which have been approved by senior officer to ensure prompt
collection of tax; and
vi. enhance the capability of the computer system such as ensuring the existing
Self-Assessment System to automatically generate estimated assessment andalso tax increase on tax arrears and failure to comply with tax instalment
payment scheme.
ROYAL MALAYSIAN CUSTOMS DEPARTMENT
9. Management Of Import Duties Assessment
a. Through laws and regulations, the Royal Malaysian Customs Department (RMCD) is
responsible for the collection of indirect taxes such as import/export/excise duties,
sales/service tax and also levy imposed on commercial and industrial transactions
carried out in Malaysia. In order to carry out such responsibilities, RMCD had also
issued Customs Standing Orders, Departmental General Orders and State Work
Procedures detailing the work process of assessment of import duties. Overall, Audit
conducted from May to October 2011 revealed that the management of import
duties assessment was satisfactory where the customs declaration forms had been
properly processed and duties were correctly collected. In 2011, RMCD collected
import duties amounting to RM8.704 billion, an increase of RM2.739 billion as
compared to RM5.965 billion in 2007. This represented the highest revenue
collected for the last 5 years. However, there were some weaknesses in the
management of import duties assessment as follows:
i. forwarding agents could still hand over customs declaration forms (K1 forms)
from one custom process to the next;
ii. out of 19 container scanners procured from 2001 to September 2010, three had
been written off and only 6 from the remaining 16 could produce a clear image;
iii. verification on K1 forms was not carried out by 3 State Customs Offices and
there were delays in reconciling import manifest;
iv. shortage of officers in the Post Clearance Audit Branch; and
v. poor performance on the collection of under-collected duties/taxes by PostClearance Audit Branch and the Verification and Profiling Branch.
b. It is recommended that RMCD takes the following actions:
i. ensure that all registered K1 forms are only handled by Customs officers and
supervise/monitor as well as taking action against Customs Stations that still
allow forwarding agents to personally hand over K1 forms from one custom
process to the next;
ii. ensure that all scanners could function properly and consider the acquisition of
new scanners for all Customs Stations that process the imports of critical goods;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
47/100
37
iii. ensure reconciliation of import manifest are carried out within the stipulated
period to properly control all imported goods; and
iv. strengthen the Post Clearance Audit Branch and improve the performance on
the collection of under-collected duties/taxes.
10. Management Of Quarters
a. The Royal Malaysian Customs Department (RMCD) had provided housing facilities
for its staff according to officers grades as spelt out in General Orders (Chapter E).
From 2009 to 2011, RMCD had spent a total of RM43.56 million for the maintenance
of quarters. Audit findings revealed that housing facilities provided for 58.3% of
RMCD employees did not achieve its objectives where 2,000 (31.6%) from 6,320
departmental quarters were not occupied as at December 2011. Among them were
33 units that had not been occupied since its completion in 2000. In addition, there
were weaknesses in the management of quarters as follows:
i. no action was taken against officers who vacate quarters and left them in a
mess;
ii. damaged quarters were not repaired or preventive maintenance not done as
there was no specific allocation provided; and
iii. weak enforcement in collection of rental arrears and no monitoring on the State
Housing Committee to ensure that meetings were held according to schedule
and matters discussed were reported.
b. It is recommended that RMCD takes the following actions:
i. ensure that the occupants of quarters comply with General Orders (Chapter E)
and the quarters are always in good condition;
ii. implement the operation and maintenance of assets as stipulated in the
Government Total Asset Management Manual. In addition, establish a
scheduled maintenance plan that includes preventive and corrective
maintenance of all quarters as required by General Circular No. 2 of 1995.
Adequate allocation for maintenance of quarters should be applied to the
Treasury;
iii. take prompt action to collect rental arrears to ensure that Government revenue is
collected effectively; and
iv. ensure that all State Housing Committees meet and report on a regular basis.
11. Procurement Of Working Tools For Enforcement Activities
a. To address the problem of smuggling, the Enforcement Division of the Royal
Malaysian Customs Department (RMCD) is responsible for the planning and
carrying out of enforcement operations such as roadblocks, patrolling the sea/land,
raids and surveillance at major ports and border entry points. From 2009 to 2011,
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
48/100
38
the Enforcement Division seized goods valued at RM1.371 billion with unpaid taxes
and duties amounting to RM1.318 billion. Operations and patrols conducted by the
Enforcement Division involved the usage of equipment such as weapons and
ammunition, drug sniffer dogs and other working tools. For the purpose of procuring
such equipment, the Government had approved a development expenditureallocation of RM20.20 million under the Ninth Malaysia Plan. Audit findings revealed
that procurement of working tools for enforcement activities was not carried out
satisfactorily as it was not managed efficiently, economically and properly. Among
the weaknesses identified were as follows:
i. incidents of improper payment such as procurement through operating
expenditure for RM9.94 million worth of working tools without the approval of the
Controlling Officer and procurement of working tools valued at RM2.25 million
without adequate allocation which resulted in payment through Treasury
Instruction 59;
ii. receiving officers could not confirm the specifications and quality of working tools
received as relevant information (such as brand, model and specification) was
not stated in the catalogue, invoice or Local Purchase Order;
iii. improper registration of assets and as a consequence a total of 21 units of
working tools valued at RM109,700 could not be detected; and
iv. working tools valued at RM4.44 million were not utilised optimally.
b. It is recommended that RMCD takes the following actions:
i. establish a special committee to investigate cases of improper payment;
ii. ensure that all Local Orders and invoices from supplier come with detailed
information such as type, brand, model and specification of working tools to
facilitate the Receiving Officer in confirming the actual quality and specification
of equipment received. A special team should also be established to investigate
the procurement of working tools under the Ninth Malaysia Plan and to ensure
that the type, brand, model and specification of equipment received and paid for
were based on stipulated quality and specification. A report on the investigation
should then be submitted to the Secretary General of the Ministry of Finance and
the National Audit Department;
iii. ensure that all assets are registered properly and if assets are distributed to
State Customs Offices, the relevant registration cards (KEW.PA-2/KEW.PA-3)
must be sent together;
iv. ensure that the usage of working tools is properly recorded in KEW.PA-6 and
take proactive actions to ensure that all working tools are fully utilized, and
v. carry out immediate physical examination of all working tools and submit initial
reports for cases of loss of working tools.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
49/100
39
12. Management Of Seized And Forfeited Goods
a. The Customs Act 1967 empowers Customs officers to seize any goods suspected to
have contravened the Customs Act. Goods seized will be kept in Enforcement
Stores under the custody of Customs officers. Whereas forfeited goods comprise all
kinds of items seized and forfeited to the Government. The Enforcement Divisionseized goods ranging from high-risk commodities such as cigarettes, liquor, vehicles
and textiles. From 2009 to 2011, the Division seized goods valued at RM1.365
billion involving unpaid taxes and duties amounting to RM1.316 billion. Audit
conducted at the Headquarters of the Enforcement Division and 5 states (Malacca,
Pahang, Perak, Perlis and Federal Territory of Kuala Lumpur) revealed the following
weaknesses:
i. in general, the management of seized and forfeited goods had achieved the
objectives set. Proceeds from the sale of forfeited vehicles and goods had
increased by 388.9% from RM3.15 million in 2009 to RM15.40 million in 2011;
ii. inefficient disposition of investigation cases;
iii. weaknesses in maintenance of registers/records, cleanliness and safety of
stores; and
iv. ineffective enforcement and monitoring.
b. It is recommended that RMCD takes the following actions:
i. set a time frame for the disposition of investigation papers, especially for cases
involving arrests by taking into account the complexity of such cases;ii. set a specific time for long outstanding investigation papers to be completed so
that the relevant seized goods could be immediately disposed of;
iii. ensure that the Register of Goods Seized and Monthly Statement on
Confiscation of Goods are maintained in accordance with the regulations;
iv. ensure that the stores and goods/vehicle seized are clean and well maintained
to retain the quality of seized goods/vehicles; and
v. ensure that equipment for the security systems (CCTV) are placed in a more
suitable location so that they can function effectively.
MINISTRY OF AGRICULTURE AND AGRO-BASED INDUSTRY13. Management Of Parliamentary Area Agriculture Project
a. Two out of 4 components under the Parliamentary Area Agriculture Project are
Small-scale Parliamentary Area Project (PKPP) and Agriculture Project of
Parliamentary Area Agriculture Development Committee (MPPP). Each
parliamentary constituency was allocated a sum of RM100,000 per annum to
implement each component of the project. The objectives of PKPP were to involve
members of parliament in planning and monitoring the implementation of small-scale
agriculture project and to aid target group specifically farmers, livestock breeders
and fishermen in improving their income. Whereas the objectives of MPPP
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
50/100
40
establishment were to obtain ideas through forum, identify arising problems,
promote opportunities and facilities of agriculture projects. Audit conducted on these
2 components revealed that the project had been implemented as planned.
However, there were several weaknesses in the implementation as follows:
i. the effectiveness of the project could not be determined due to incomplete
project records maintained by the Ministry of Agriculture And Agro-based
Industry (Ministry);
ii. one of the objectives of this programme which is to help target groups in
improving their income has not been fully achieved;
iii. a total of RM11.39 million (35.5%) out of RM32.09 million allocated for four
states from 2009 to 2011 was not yet spent by the implementing agency;
iv. there was no clear and comprehensive guideline;
v. unsatisfactory infrastructure/supplies;
vi. underutilised project/equipment; and
vii. ineffective monitoring system.
b. It is recommended that the responsible parties take the following actions:
i. the Ministry/implementing agency should assess the outcome and impact of the
project/programme;
ii. the Ministry should improve the existing guideline so that it is more
comprehensive;
iii. the implementing agency should ensure that this programme benefits the targetgroup and is fully utilised by the aid recipients to avoid wastage of Governments
spending; and
iv. the Ministry should conduct periodic monitoring on the projects to ensure that
they are implemented according to specifications and of quality.
14. Management Of Rice Subsidies To BERNAS And Private Manufacturers
a. The Rice Subsidy Programme of 15% broken rice which was implemented since 1
September 2008 was to ensure a controlled supply and price of the said rice to the
low income group. The objectives of the programme are to supply Super Tempatan
ST15% rice (Peninsular Malaysia) and S15% rice (Sabah and Sarawak) to meet
rising consumer demand, maintain controlled subsidised rice price at RM1.65 to
RM1.80 per kg by zone and cover losses incurred by subsidised rice manufacturers.
The programme started with Phase I and continued to Phase II until now. Audit
findings revealed that the objectives of the programme were not fully achieved
where there was no proper mechanism to ensure that the target group benefited
from this programme. Besides that, there were several weaknesses as follows:
i. targeted group/consumer in Peninsular Malaysia was not attainable;
ii. insufficient allocation to pay subsidy claims;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
51/100
41
iii. unclear and incomprehensive guideline;
iv. delay in signing the contract between the Ministry of Agriculture and Agro-based
Industry (Ministry) and BERNAS and there were also contracts signed after the
contracts had expired; and
v. insufficient officers to monitor the programme.
b. It is recommended that the Ministry takes the following actions:
i. re-evaluate the Rice Subsidy Programme based on its existing objectives;
ii. assess the needs to collaborate with the Department of Social Welfare to ensure
the effectiveness of distribution of subsidised rice to the poor;
iii. sign agreement with BERNAS and wholesalers immediately. The Ministry should
also clearly outline the responsibilities and actions to be taken against
wholesalers who breach the agreement; and
iv. the Ministry should provide a clear and comprehensive guideline to ensure that
the programme achieves its objectives.
15. Management Of The Seaweed Industry Development
a. The seaweed industry in Malaysia has started since 1978 in Sabah and currently
active in the district of Semporna, Kunak, Lahad Datu, Banggi, Kudat and Tawau.
The sea water in these areas is suitable for seaweed cultivation. The seaweed
industry is listed in the Entry Point Project (EPP) 3 under the National Key Economic
Areas (NKEAs) to enhance profit of Small and Medium Enterprises (SMEs) by
emphasising on modernisation, big-scale production and increase in productivity
through latest technologies as well as more efficient methods. The objectives of the
Seaweed Industry Development are to produce seaweed for upstream and
downstream industry which is led by private sectors, reduce dependency on
imported seaweed and improve quality as well as controlling the seaweed price.
Under the Ninth Malaysia Plan, the Government has approved RM7.20 million to
develop the seaweed project including procurement of equipment as well as building
and upgrading of platforms. Meanwhile, under the Tenth Malaysia Plan, a total of
RM46.07 million has been approved under the Economic Transformation
Programme (ETP) for mini estate development, research programme, apprentice
manufacturing plant and operational expenses. Audit findings revealed that the
Department/NKEAs targeted increase in the production of dried seaweed from 2009
to 2011 had been achieved. However, the mini estate project under NKEA was still
underdeveloped. Besides that, there were several weaknesses in the project
management as follows:
i. most of the allocation for seaweed development was not yet spent;
ii. construction of seaweed processing/drying platforms was unsatisfactory; and
iii. equipment supplied were underutilised/damaged.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
52/100
42
b. It is recommended that the Ministry of Agriculture and Agro-Based
Industry/Department takes the following actions:
i. improve work progress of the implementing agency so that the desired
output/outcome could be achieved;ii. ensure that projects are carefully planned by taking into account user needs so
that projects could be completed as scheduled;
iii. ensure that the contractor rectifies all defects immediately;
iv. distribute the remaining boats/sampan to the operators as soon as possible to
avoid wastage; and
v. conduct impact assessment study to ensure sustainable outcome.
16 Permanent Food Production Park Programme
a. The Permanent Food Production Park (TKPM) Programme was introduced in 2000
to improve the internal food production sector. TKPM was also a strategy developed
under the Third National Agriculture Policy to transform agriculture sector by
encouraging big-scaled agriculture project, commercialisation and high technology
by the entrepreneur and private sector. As at 2011, 55 TKPM which covered
7,631.90 hectares were established with 964 participants. Production output by end
of 2011 had reached 58,504 metric tonne worth RM63.5 million. The objectives of
the programme were to establish permanent food production zone, produce food
production entrepreneurs, increase participation of entrepreneurs and private sector
in food production, enhance sustainability and quality of national food productionand improve net income of participants/farmers to at least RM3,000 a month. In
order to achieve the objectives, the Ministry of Agriculture and Agro-based Industry
(Ministry) had planned a few strategies such as development based on zoning
approach, cluster food industry and market driven as well as establishing food chain
in crop industry. Audit findings revealed the following weaknesses:
i. gazette and title of the TKPM land were not yet finalised;
ii. improper management of participant agreements;
iii. project implementation was not according to plan;
iv. unsatisfactory utilisation of facilities by participants;
v. targeted income for participants was not fully achieved; and
vi. improper records management.
b. It is recommended that the responsible parties take the following actions:
i. the Ministry should periodically and continuously evaluate the output and
outcome of the TKPM;
ii. monitor the production performance in a more effective manner;
iii. the Ministry and State Government should take immediate action to finalise the
status and title of land to ensure smooth planting activities by participants;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
53/100
43
iv. agreement between the Government and participants should be duly signed and
the Ministry should monitor compliance of terms and conditions of the
agreement;
v. the Ministry should ensure that the appointed anchor company duly signed an
agreement with the Government and complies with its terms and conditions to
ensure TKPM programme objectives could be achieved effectively; and
vi. the Ministry should ensure that project implementation is in accordance with the
business plan and monitor its implementation so that the participants
performances are in line with the objectives and targets of TKPM programme.
MINISTRY OF RURAL AND REGIONAL DEVELOPMENT17. Agropolitan Project Under Rural Quantum Leap Programme
a. The Rural Quantum Leap Programme was an integrated and comprehensive
programme under the Ninth Malaysia Plan and its implementation continued underthe Tenth Malaysia Plan. The objectives of this programme were to eliminate rural
poverty through increment of income and to bring them out from the poverty threshold
as well as to accelerate development of less developed, isolated and abandoned
areas. In order to achieve these objectives, the Ministry of Rural and Regional
Development (Ministry) had implemented the Agropolitan Project with three main
components. Eleven Agropolitan Projects had been implemented targeting a total of
4,445 participants who were below the poverty threshold. An allocation of
RM289.35 million under the Ninth and Tenth Malaysia Plans was given to FELCRA
Berhad, Rubber Industry Smallholder Development Authority (RISDA) and Kedah
Regional Development Authority (KEDA) which were appointed by the Ministry as the
implementing/paying agencies. Audit findings revealed that management of the
Agropolitan Project was satisfactory. However, there were some weaknesses as
follows:
i. development allocation had been disbursed to the implementing agencies
without taking into account the progress of the projects;
ii. projects implemented under the economic component were not
viable/sustainable;
iii. late preparation of guidelines for projects implementation;iv. agreements between the participants and implementing agencies were yet to be
signed; and
v. development of the physical components of the project was
unsatisfactory/problematic.
b. It is recommended that the Ministry takes the following actions:
i. ensure that development allocations are disbursed to implementing/paying
agencies based on the progress of project and ensure that the initial target is
achieved with the expenditure incurred;
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
54/100
44
ii. review the implementation of economic component projects to ascertain whether
it is viable, resilient and able to generate revenue as planned so that its aims to
pay dividend to the participants could be achieved. In this regard, each
participant should be identified and selected before any economic component
project is implemented;iii. ensure that the agreement between the Government and participants is
finalised/signed to safeguard the interests of each party involved with the project.
Hence, conditions stipulated in the agreement could be taken against
participants who do not comply with the terms of participation;
iv. ensure that infrastructures/facilities provided are maintained and fully utilised
according to its objectives; and
v. prepare short/long term plans for maintenance of Agropolitan Projects
settlement areas and provide the areas with modern and quality facilities to
improve the well-being of participants.
18. Construction And Upgrading Of Rural Road Projects In Sarawak
a. The construction and upgrading of rural road projects were approved during the
Ninth Malaysia Plan and from 2010, the projects were continued under the National
Key Result Area (NKRA) in order to speed up the construction of more rural roads to
meet the needs of the rural community. From 2006 to 2010, the Ministry Of Rural
And Regional Development approved an allocation of RM1.727 billion for the
implementation of 175 road projects. Out of the 175 projects, 146 projects costingRM1.104 billion were implemented by the Public Works Department Sarawak and
the remaining 29 projects costing RM622.84 million were implemented by the
Drainage and Irrigation Department Sarawak. The actual expenditure for these road
projects as at 31 December 2011 amounted to RM1.024 billion. Audit findings
revealed that in general, the construction and upgrading of rural roads projects in
Sarawak were not satisfactory. The following were several weaknesses being
observed:
i. projects implementation performance was rather unsatisfactory because 38
projects (37.6%) costing RM178.94 million out of 101 completed projects
amounting to RM437.57 million were delayed in completion ranging from 15 to
242 days from the original schedule;
ii. 13 projects (17.6%) out of 74 projects costing RM229.27 million under
construction were behind schedule by more than 20%;
iii. construction and upgrading of roads did not follow contract specifications; and
iv. customer feedback results indicate that road users were not satisfied with the
quality, safety and comfortability aspects of the roads.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
55/100
45
b. It is recommended that the responsible authorities take the following actions:
i. the Ministry of Rural and Regional Development should ensure that road
construction and upgrading projects are properly planned to avoid unnecessary
disruption;
ii. the implementing agencies should have holistic planning for road constructionand upgrading projects to include all aspects of road construction to achieve
value for money and positive outcome (impact) to users;
iii. the implementing agencies should ensure that road construction and upgrading
projects strictly follow specifications, standard and quality of works as stipulated
in the contract agreements so as to provide comfortability to road users and to
rectify poorly built roads; and
iv. the implementing agencies and consultants should strictly supervise and monitor
the implementation and construction process to ensure that the quality control is
in place until the Certificate Of Practical Completion (CPC) is issued.
MINISTRY OF NATURAL RESOURCES AND ENVIRONMENT
Department Of Irrigation And Drainage Malaysia19. Management Of Dam Operations
a. Dams have various functions and needs such as providing flood mitigation, water
irrigation to agricultural areas, raw water supply, power generation and sediment
retention. A completed dam structure requires the operation, maintenance,
monitoring and inspection to be properly conducted in accordance with proceduresset by the Dam Manual. As at 31 December 2011, there were 16 dams which were
completed between 1906 to 2004 and operating under the purview of the
Department of Irrigation and Drainage (DID) in Peninsular Malaysia. Dams are
classified based on the level of potential hazards which they face in the event of
dam failure. Under the Ninth Malaysia Plan, a total of RM34.41 million was spent on
surveillance and rehabilitation activities of the dam whereas no budget was
approved for the first Rolling Plan under the Tenth Malaysia Plan. Audit findings
revealed that as a whole the management of the dam was satisfactory where
monitoring and minor maintenance works had been performed accordingly,submission of instrumentation data and the Periodic Safety Inspection Report were
carried out according to the stipulated time. However, there were some weaknesses
in the management of the dam operations, maintenance and monitoring as follows:
i. delay in updating the Operations and Maintenance Manual;
ii. absence of Standard Operating Procedure for handling of equipment/hydraulic
components and the existing Emergency Action Plan was not comprehensive;
iii. emergency training had not been implemented;
iv. water surface of reservoirs and flood regulating outlets were not maintained,
routine maintenance was not carried out according to the stipulated period,
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
56/100
46
reservoir pool areas and catchment areas of the dam had been encroached,
monitoring of sediment had not been implemented since 2000;
v. instrumentation at the dam could not be detected, 46.4% instrumentation at the
visited dam were damaged and not repaired;
vi. gazetting of the land and the conversion of land titles for the acquired reservedlands were not fully made, and
vii. absence of a regulatory body to monitor and control the management of dam
operations of all dams.
b. It is recommended that the responsible parties take the following remedial actions:
i. the Government should provide sufficient financial and human resources to
ensure proper operation of dams;
ii. the Ministry of Natural Resources and Environment should establish
policies/procedures relating to the responsibilities and roles of DID at the
headquarters and the State in matters relating to the operation, maintenance
and monitoring of the dams;
iii. the Government should review the eligibility criteria of security guards and
consider to place armed security personnel to control the dam operation areas
and the dam catchment areas;
iv. DID should ensure that monitoring and supervisions are carried out more
effectively to overcome the problem of encroachment on the land of DID and
quickly resolve problems related to the impaired instrumentations;
v. DID should promote public awareness programmes through electronic and mass
media about the implications of encroachment activities in reservoir pool areas
and catchment areas of the dams;
vi. the Ministry should update information on land ownership and also coordinates
matters related to gazetting of land and land ownership;
vii. the Government should assess the needs to establish a dam regulatory body to
ensure that all dams are managed efficiently and effectively to ensure the
integrity of the dams; and
viii. the Government should hold discussions with the State Government, State DID
and water supply companies to provide some budgets for maintenance and
rehabilitation of the dams.
Department Of Irrigation And Drainage Malaysia20. Management Of Urban Drainage Project
a. Urban drainage system is implemented by the Department of Irrigation and Drainage
Malaysia (DID) through 2 methods which are conventional system (rapid disposal)
and storm water management system which addresses environmental impact.
Under the Ninth Malaysian Plan, the Federal Government spent a total of RM130.79
million on urban drainage projects throughout the country. Audit findings revealed
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
57/100
47
that the projects in few locations were able to achieve the objectives set for storm
water management problems such as reducing flood (quantity control) and
controlling the water from contamination (quality control). However, there were some
locations having problem in controlling the water quantity and quality. Among the
weaknesses identified were as follows:
i. some drainage components which were installed/constructed such as detention
ponds, conveyance as well as rubbish and sediment control components were
not functioning as intended because flooding still occurred at the project sites;
ii. quality of water was contaminated;
iii. some components were not utilised and left obsolete;
iv. insufficient capacity of the detention ponds;
v. some modified/replaced components were not suitable to be used;
vi. conveyance could not make the water flow properly and some components
which had been paid were not used; and
vii. Master Plan which had been prepared was not fully beneficial.
b. It is recommended that the responsible parties take remedial actions as follows:
i. DID should plan and ensure that the Master Plan is prepared based on the
priority of critical locations and projects are implemented based on the Master
Plan;
ii. DID should take immediate actions to identify the maintenance requirements of
each urban drainage project which has been built. Information such as type ofmaintenance, frequency of maintenance, maintenance costs, required labour
and the implications if maintenance work is not carried accordingly should be
provided in order to serve as a guide to the DID/local authority;
iii. the Ministry of Finance should provide adequate maintenance budget to ensure
that each Government project could be fully utilised by the target group for a
justified period of time;
iv. the Ministry and DID should prepare integrated policies relating to the
management of drainage operations which include jurisdiction and
responsibilities of parties in terms of operation and maintenance of drainage,
type of costs to be incurred and required manpower;
v. the Ministry and DID should adopt the Blue Ocean Strategy by establishing a
coordination committee between the Government and other responsible
agencies to discuss problems related to the management of the drainage
operations and should supervise and monitor the projects effectively; and
vi. DID should plan carefully in determining the projects costs in order to ensure
that all critical components of the project are taken into account.
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
58/100
48
MINISTRY OF INTERNATIONAL TRADE AND INDUSTRY21. Student Entrepreneurship Programme
a. The National Entrepreneurship Institute (NEI) is an agency under the Ministry of
International Trade and Industry (MITI) which is responsible for implementing
Student Entrepreneurship Programme (SME). The main objective of the programmeis to provide exposure and generate interest in entrepreneurship among university
students. Students are given exposure to business opportunities, preparation of
business plans and business foundation. To date, a total of 19 Public Institutions of
Higher Learning (IPTA) and a Private Institute of Higher Learning (IPTS) have been
involved in this programme. Programmes under the SME consist of Basic Student
Entrepreneurship Student Course, Student Mall, Student in Free Enterprise and
Graduate Entrepreneurship Scheme. Audit findings revealed that the objectives of
this programme in term of efforts to cultivate entrepreneurship among university
students have been achieved. However, there were some weaknesses in the
implementation of the programme as follows:
i. targets set in terms of number of series of Basic Student Entrepreneurship
Course were not fully achieved in 2009 and 2010;
ii. performance of the development of construction/acquisition of Student Mall kiosk
was unsatisfactory because the university took a long time between 1 to 4 years
to start construction/acquisition after receiving funds from NEI;
iii. as for the Graduate Entrepreneurship Scheme, the percentage of participants
who applied for and was approved financing from Student Entrepreneurship
Fund was low which was at only 26.3%; andiv. there were some weaknesses in the management of the programme as
conditions/terms of reference of the programme were not fully complied with;
allocations were not fully utilised and accounts/records were not properly
maintained.
b. It is recommended that MITI and NEI take the following actions:
i. plan carefully and identify the real needs before allocation of funds is made.
Allocation should be given in stages according to the needs/development of
programmes;ii. perform continuous monitoring to ensure that allocations given to universities are
fully spent in order to achieve the objectives of the programme; and
iii. create a comprehensive and constantly updated database of programme
participants to evaluate the effectiveness of the programme and facilitate
monitoring.
MINISTRY OF WORKS22. The Construction Of Sultan Yahya Petra Second Bridge, Kota Bahru, Kelantan
a. Sultan Yahya Petra Bridge is a major link between Kota Bahru Town and Tumpat.The economic and social activities of Tumpat and part of Pasir Panjang is very much
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
59/100
49
dependent on the bridge which was constructed in 1967 with a design capacity of
only 11 tonnes. A new second bridge had been approved under the Ninth Malaysian
Plan as an alternative to reduce traffic congestion as well as to provide safety and
comfort to users. Public Works Department (PWD) was the implementing agency of
this project. Konsortium I.S Resources Sdn. Bhd. RIS Capital Sdn. Bhd. wasappointed through direct negotiation to implement and complete the project in 30
months from 18 June 2007 to 17 December 2009 at a cost of RM143 million.
However, this project had been re-assigned to Aneka Prestij Sdn. Bhd. in March
2010 to complete the remaining works after approval by PWD. As at 31 December
2011, the work progress was only 76.5%. Overall, the construction of this project
was not satisfactory due to weaknessess in the project planning and
implementation. Among the weaknesses identified were as follows:
i. failure to complete the works on schedule where 4 Certificates of Delay And
Extension of Time totalling 891 days had been approved until 30 August 2012;
ii. current value of contract was expected to increase to RM177.76 million
representing a total increase of RM34.76 million (24.3%) from the original
contract value of RM143 million;
iii. problems with the design of bore pile system took 2 years to be resolved which
contributed significantly to the delay of the project and increase in cost;
iv. works at the river side could not be completed on schedule due to the delay of
construction of the temporary bridge; and
v. appointment of an inexperienced contractor.
b. It is recommended that the Ministry of Works/PWD take the following actions:
i. ensure that the problems arising at work site are immediately resolved so that
works could be implemented according to schedule;
ii. improve coordination between Local Authority, utility providers and other
agencies involved so that problems at work site could be resolved immediately
and effectively;
iii. ensure that problems on design of bore pile system are resolved immediately to
avoid any delay in construction works;
iv. appoint a lead consultant to ensure better implementation of the project; and
v. PWD should ensure that the contractor build the temporary bridge on schedule
as works at the river side is the most critical component of this project.
23. Management Of The Registration Of Contractors By The Contractor ServiceCentre
a. The Contractor Service Centre (PKK) was established on 30 June 1981. It was then
known as the Contractor Service Coordination Centre (PUSAKABUMI) and was
placed under the Implementation and Coordination Unit of the Prime Ministers
Department. Effective from 1 January 1987, it was renamed as Contractor Service
-
7/31/2019 Auditor General's Report 2011 - Synopsis (English)
60/100
50
Centre (PKK) in line with the expansion of its functions and authority. In April 2009,
PKK was placed under the Ministry of Works. As at 30 June 2011, the number of
contractors registered with PKK stood at 44,630, which consisted of 41,006 civil
works contractors and 3,624 electrical contractors. The roles and responsibilities of
PKK include being a registration centre for contractors at Federal and State level,awarding Bumiputera status to qualified contractors, being a reference centre for
contractors and providing advisory services to Bumiputera contractors in
implementing contracts. This is limited to contracts for services at Government
departments/agencies that do not have such advisory services. Audit findings
revealed that the management of the registration of contractors was not satisfactory
due to the following weaknesses:
i. Client Charter was not achieved;
ii. fees charged and the registration