AUDIT REPORT ON THE ACCOUNTS OF WATER … AR 2003-2004 with...WATER AND POWER DEVELOPMENT AUTHORITY...
-
Upload
truongcong -
Category
Documents
-
view
213 -
download
1
Transcript of AUDIT REPORT ON THE ACCOUNTS OF WATER … AR 2003-2004 with...WATER AND POWER DEVELOPMENT AUTHORITY...
AUDIT REPORT
ON
THE ACCOUNTS OF
WATER AND POWER
DEVELOPMENT AUTHORITY
AUDIT YEAR 2003-04
AUDITOR-GENERAL OF PAKISTAN
CONTENTS
Page
No.
Acronyms ii
Preface iii
Executive Summary
Recommendations
1-2
3
Section-I
Audit Report
1. Water Wing
4-13
2. Power Wing 14-15
3. Residual Power Wing (RPW) 16-21
4. Jamshoro Power Generation Company (GENCO-I) 22-23
5. Central Power Generation Company (GENCO-II) 24-25
6. Northern Power Generation Company (GENCO-III) 26-27
7. Lakhra Power Generation Company (GENCO-IV) 28-29
8. National Transmission and Despatch Company (NTDC) 30-36
9. Faisalabad Electric Supply Company (FESCO) 37-38
10. Gujranwala Electric Power Company (GEPCO) 39-41
11. Hyderabad Electric Supply Company (HESCO) 42-46
12. Islamabad Electric Supply Company (IESCO) 47-51
13. Lahore Electric Supply Company (LESCO) 52-62
14. Multan Electric Power Company (MEPCO) 63-68
15. Peshawar Electric Supply Company (PESCO) 69-75
16. Quetta Electric Supply Company (QESCO) 76-81
Section-II
Comments on Internal Controls
82-84
ACRONYMS
BOQ Bill of Quantity
CCC Central Contract Cell
CRE Consultant Resident Engineer
DRB Disputes Review Board
DISCOs Distribution Companies
EIB European Investment Bank
EOT Extension of time
ERP Environment and Resettlement Panel
FC Foreign Currency
FAS Fuel Adjustment Surcharge
FEC Foreign Exchange Component
GBC Ghazi Barotha Contractor
GBHP Ghazi Barotha Hydro Power Project
GBTI Ghazi Barotha Taraqyati Idara
GENCOs Generation Companies
GWh Giga watt per hour
IBRD International Bank for Reconstruction & Development
IDB Islamic Development Bank
IPC Interim Payment Certificate
JBIC Japanese Bank for International Cooperation
KFW Kreditanstalt Fuer Wiederaufbau
KWh Kilo Watt per hour
LC Local Currency
LD Liquidated Damages
LAC Land Acquisition Collector
LC Letter of Credit
LIBOR London Inter Bank Offered Rate
M&E Monitoring & Evaluation
M&S Monitoring & Surveillance
MW Mega Watt
ME Contracts Mechanical & Electrical Contracts
MOU Memorandum of Understanding
NES PAK National Engineering Services of Pakistan
NGO Non-Governmental Organization
OECF Overseas Economic Cooperation Fund
PC-I Planning Commission Proforma-I
PIDA Punjab Irrigation & Drainage Authority
PHC Pakistan Hydro Consultants
POE Panel of Experts
RD Reduced Distance
RAP Resettlement Action Plan
SP Special Provision
VO Variation Order
SECTION-I
AUDIT REPORT
PREFACE
The audit of WAPDA and its corporate entities was conducted in pursuance of
Article 169 of the Constitution of Islamic Republic of Pakistan read with Section 8 and
other relevant provisions of the Auditor General’s (Functions, Powers and Terms and
Conditions of Service) Ordinance, 2001.
This report is based on the overview of financial statements of corporate entities
of WAPDA for the year 2003-04 and compliance with authority audit of the accounts of
WAPDA and its corporate entities for the years 2001-02 and 2002-03. The audit was
conducted by Directorate General of Audit WAPDA during 2003-04, on test check basis
of corporate entities and concurrent audit of the projects, with a view to report significant
findings to the stakeholders.
The findings indicate the need for adherence to the regulatory framework and
instituting and strengthening of the internal control framework especially to ensure
minimization of line losses, better management of receivables and timely completion of
projects. These measures are necessary to avoid recurrence of similar type of failures and
mis-management as well as violations and irregularities year after year.
Audit observations included in the report were discussed with the concerned
Principal Accounting Officer in the Departmental Accounts Committee meeting and have
been finalized in the light of written response and discussions.
The report is submitted to the President of Pakistan in pursuance of Article 171 of
the Constitution of the Islamic Republic of Pakistan.
Islamabad MUHAMMAD YUNIS KHAN
Dated: Auditor-General of Pakistan
EXECUTIVE SUMMARY
Directorate General of Audit WAPDA (Water and Power Development Authority)
carried out the audit of the accounts of WAPDA Water Wing, Residual Power Wing and
its corporate entities during the year 2003-04. WAPDA’s Power Wing underwent a major
restructuring in 1998 and since then fourteen corporate companies have been created and
registered under Companies Ordinance, 1984.
1. According to WAPDA the overall line losses of Power Wing decreased to 25.5%
during the year 2003-04 from 26.0% in 2002-03. These are still higher than
acceptable standards. Six distribution companies out of eight could not achieve the
target to control distribution losses fixed for the year 2003-04. Particularly, line losses
of Hyderabad Electric Supply Company (35.6%) and Peshawar Electric Supply
Company (31.4%) were very high against the assigned target of 30% and 27.6%
respectively. Line loss is one of the main reasons for WAPDA’s financial problems.
The financial impact of 1% line losses of WAPDA is more than Rs.2,500 million
per annum. [Para 2.2, 11.1, 15.1]
2. WAPDA’s trade debts increased by 18%, from Rs.58,906 million as on 30th June,
2003 to Rs.69,613 million as on 30th June, 2004, on account of failure of recovery
system. This debt is adversely impacting the cash flow. [Para 3.2]
3. Provision for doubtful trade debts made by all distribution companies, during the
year 2003-04, increased from previous year’s Rs.12,603 million
(19.8% of the trade debts) to Rs.21,914 million (31.56%). An increase of
Rs.9,311 million, during a single year (i.e. 4.7% of the sales), could not be
justified by the management. [Para 3.3]
4. Payables decreased from Rs.26,418 million as on 30th June, 2003 to
Rs.12,756 million at the end of the financial year 2003-04, mainly due to conversion
of Government of Pakistan debt servicing liability into equity. [Para 3.4]
5. All the distribution companies, except Faisalabad Electric Supply Company
and Lahore Electric Supply Company, were running in losses. [Para 2.1]
6. Physical progress of works concerning eight Water Resource Development
Projects being carried out by the Water Wing under Vision-2025 at an estimated
cost of Rs.164,856 million was lagging behind the schedule, ranging from 1.5% to
40.8%. [Para 1.1]
7. This report highlights five cases of poor contract management involving payment
of claims made to the contractor without due process, delay in projects
completion and over run expenditure (Rs.3,669 million).
[Para 1.2, 1.6, 1.8, 1.10, 8.2]
8. Eight cases of ineffective management have been reported which include non-
completion of IBRD assisted project, blockage of funds due to non-energizing the
feeder, theft of energy, undue favour to an industrial consumer and incorrect
application of tariff (Rs.2,882 million).
[Para 11.2, 12.2, 12.3, 13.2, 14.2, 15.2-3, 16.2]
9. Thirteen cases of ineffective internal controls have been reported such as payment
to the contractor through open cheques, non-adjustment of advances for land
acquisition, non-recovery of revenue and capital cost (Rs.1,635 million).
[Para 1.3, 1.4, 1.5, 1.9, 3.5, 11.3, 13.3, 13.5, 13.10-12, 15.5, 15.6]
10. There are five cases of lapse in financial management on account of payment of
demurrage charges, expenditure without approval of the budget and giving credit
to the consumers without adjusting the energy units (Rs.172 million).
[Para 1.7, 8.3-5, 16.3]
11. Fourteen cases pertaining to weak procurement and inventory management have
also been incorporated which include theft/shortage/non return of material, non-
utilization/non-disposal/non-accountal of material and purchase of defective
meters (Rs.137 million).
[Para 8.6, 12.4, 13.4, 13.6-9, 14.3, 14.4, 15.4, 15.7-8, 16.4-5]
A number of observations were settled during the course of finalization of the report
because requisite action, including recovery of Rs.445 million, was taken by the
management. The PAC directives are attached as Annexure-A.
RECOMMENDATIONS
1. WAPDA should take necessary steps to evaluate, institute and strengthen the
management, budgeting and accounting controls to achieve the following control
objectives:
i. Minimization of line losses and dependence on Government subsidy;
ii. Better management of receivables for which a campaign needs to be initiated
to ensure timely recovery, particularly from the private consumers;
iii. Prevention of delay in completion of projects under Vision-2025 to avoid cost
overrun and deferment of envisaged benefits;
iv. Adherence to International Accounting Standards for provision of doubtful
debts;
v. Optimization of inventory procurement and utilization;
vi. Adjustment of advance payments made to the Government of the Punjab for
acquisition of land;
vii. Proper accountal of stores particularly serviceable material;
viii. Correct application of tariff, regularization of unauthorized extension of load
and removal of material from defaulters’ premises;
ix. Availability of adequate funds for early completion of incomplete
IBRD/OECF works.
1. WATER WING
Water Wing of WAPDA is responsible for development of water resources of the
country. It is headed by Member Water who controls the water sector of the entire
country divided into north, central and south zones.
1.1. Physical Status of Projects
Under Vision-2025 program, Water Sector has started eight projects namely, Mangla
Dam Raising, Greater Thal Canal, Rainee Canal, Kachhi Canal, Mirani Dam, Gomal Zam
Dam, Sabakzai Dam, and Satpara Dam. During the year 2003-04, Water Wing has spent
Rs.6,009.361 million on these National Water Resources Development Projects. These
are scheduled to be completed in 2006-07 to achieve the following objectives:
i) Development of water storages.
ii) Additional area brought under irrigated agriculture.
iii) Improvement in Hydel-Thermal Power mix.
iv) Social up-lift of the nation.
These projects were found behind the schedule as on 31st December, 2004 as given below:
Sr.
No. Name of Project Construction
Period
(Years)
Completion
Date Physical status on 31st
December, 2004 Planned
%
Achieved
%
1. Greater Thal Canal 6 June, 2006 13.6 10.85
2. Gomal Zam Dam 4 September, 2006 54.1 13.3
3. Sabakzai Dam 3 December, 2006 16 13
4. Kachhi Canal 5 June, 2007 9 5.5
5. Rainee Canal 5 June, 2007 10 7.5
6. Mirani Dam 4 June, 2006 60 55
7. Mangla Dam Raising
i) PC-II
ii) PC-I
4.5 December, 2007
94.9
8.6
82.9
7.1
8. Satpara Dam 4 June, 2006 22.72 14.29 Source: Progress Reports of the Projects.
Delay in completion of these projects appears inevitable which will increase the cost of
the projects and deprive the people from timely socio-economic benefits.
1.2 Payment of heavy claims of Rs.3,247.076 million without observing procedure
As per para 23 of GFR, Vol.-I and Instruction-III (Para-1) of “Guideline for Enforcing the
Responsibility for losses sustained by the Authority through fraud or negligence of
individuals, 1982”, the payment due to the negligence and irregularity on the part of
responsible needs investigation for accountability.
In Ghazi Barotha Hydro Power Project (GBHP), uptil June, 2004 seventy-nine claims
amounting to Rs.35,106.075 million were submitted by three main contractors on account
of stoppage of work, delay in payments, revision of drawings/designs, extension of time,
additional costs, depreciation and demurrage, additional testing charges in camp area,
unforeseen conditions and interpretation of contract etc. Out of these seventy-nine claims,
the Consultant/Engineer determined twenty-nine claims for Rs.3,247.076 million as
WAPDA was held responsible for the delay. Payment was made by the WAPDA on the
certification of the consultant without vetting and clearing of the same by Central Contract
Cell of WAPDA as per procedure. The amount of forty-six claims valuing Rs.31,282.291
million was not accepted by the Consultant while four claims valuing Rs.576.708 million
were yet to be determined.
The matter was referred to the management in April, 2003 and discussed in a meeting
held on 4th October, 2003. It was replied that the claims of contractors were raised under
clause 53 of contract and finalized either by amicable settlement between the employer
(WAPDA) and contractor or through dispute resolution process. Audit was of the view
that payment of such heavy amounts needed proper scrutiny by the WAPDA Central
Contract Cell. The draft para was issued to the Ministry in January, 2005. It was replied in
a meeting dated 10th February, 2005 that Authority has constituted a committee headed by
G.M (CCC), which will submit its report within 15 days but the same was not submitted. It
was discussed in DAC meeting held on 19th March, 2005 wherein DAC directed the
management that the decision of the Authority in the light of inquiry committee report,
when received, should be communicated to Audit. The decision of Authority was not
received till the finalization of this report.
1.3 Non-adjustment of account of Rs.1,145.170 million paid on account of land
compensation
As per clause K of Section XVI of Book of Financial Powers for WAPDA, the accounting
unit is required to record full details of land acquired and obtain the adjustment accounts of
advances given to Land Acquisition Collector/executing agencies.
In Greater Thal Canal Project, Rs.1,145.170 million were transferred from August, 2001 to
June, 2003 by WAPDA to Irrigation and Power Department, Government of Punjab for
acquisition of land. However, adjustment account containing details of payments of land
compensation was not received by the project authorities of WAPDA till finalization of
report to establish that the money was spent for the purpose for which it was advanced to the
Government of Punjab.
The matter was taken up with the Project authorities in July, 2002 and discussed but no
adjustment account was made available to Audit. The draft para was issued to the
Principal Accounting Officer (PAO) in November, 2003 and was also discussed in DAC
meeting held on 19th March, 2005 wherein the Management stated that the adjustment
account had been received and would be shown to Audit. The DAC directed the project
authorities to get the record verified from Audit by 6th April, 2005. The Management did
not produce the relevant record till the finalization of this report.
1.4 Irregular expenditure of Rs.217.011 million
Any increase over and above the BOQ is required to be regularized through variation orders
as provided in Section-V of Book of Financial Powers for WAPDA and contract clause 52.3
of contract No. C-01 in respect of Ghazi Barotha Hydro Power Project (GBHP).
a) Rs.242.810 million were paid, against the BOQ provision of Rs.50.400 million,
which was 382% more than provided sum, without approval of the variation order to
M/s GBC upto IPC-70 under BOQ item No. AO-012 for transportation and insurance of
Employer’s provided equipment
b) In another case Project authorities paid Rs.32.333 million against the BOQ
provision of Rs.7.732 million for track rail through unapproved variation order No.33.
This was 318% more than the provision.
Thus payment of Rs. 217.011 million (Rs. 192.410 + Rs.24.601 million), without
approval of variation order by the Central Contract Cell of WAPDA, was irregular.
The para was issued to the management in April, 2003 and was discussed on 4th October, 2003.
The project authorities stated in October, 2003 that the cost was influenced by external
factors and BOQ provision was just an estimate. It was further stated that situation could
not be foreseen at the time of tendering and change in quantity would be taken into
account in the final variation order. Audit was of the view that excess payment to the
extent of 382 % and 318 % above BOQ was not justified.
The draft para was referred to the Ministry in January, 2005. It was replied in
February, 2005 that increase in cost of transportation and insurance for employer’s
provided equipment was due to escalation in freight charges, cost of fuel, 9/11 incident and
revision of SROs. Increase in cost of track rails was due to Chinese Gantry Cranes which
were much heavier than assumed (i.e. ASTM Standard European Crane) at the tender stage.
DAC on 19th March, 2005 directed the management to submit a comprehensive and
detailed reply. Management did not furnish the reply till the finalization of this report.
1.5 Non-adjustment of account of Rs.194.882 million paid on account of land
compensation
As per clause K of Section XVI of Book of Financial Powers for WAPDA, the accounting
unit is required to record full details of land acquired and obtain the adjustment accounts of
advances given to Land Acquisition Collector/executing agencies.
In Kachhi Canal Project, Rs.259.137 million were transferred from December, 2002 to June,
2003 by WAPDA to Provincial Irrigation and Power Department, Government of Punjab for
acquisition of land. However, adjustment account containing details of payments of land
compensation was not received by the project authorities of WAPDA till finalization of this
report to establish that the money was spent for the purpose for which it was advanced to the
Government of Punjab.
The matter was taken up with the Project authorities in July, 2003 and discussed with
the General Manager (South) on 2nd December, 2003 but no adjustment account was
made available to Audit. The draft para was issued to the Principal Accounting
Officer (PAO) in January, 2004 and was also discussed in DAC meeting held on
19th March, 2005 wherein the management stated that adjustment account had been
received and would be shown to Audit. The DAC directed the project authorities to
get the relevant record verified from Audit by 6th April, 2005. The management did
not produce the relevant record till the finalization of this report.
1.6 Loss of Rs.96.986 million per day due to delay in completion of project
As per PC-I, Ghazi Barotha Hydro Power Project for generation of 1,450 MW electricity
was to be completed by June, 2000.
Project was actually completed in August, 2003 after a delay of 38 months. The project
consultants had estimated that any delay in the project would lead to an increase of
Rs.31.233 million per day in cost of construction. Generation loss was assessed at
Rs.65.753 million per day. According to the consultant, the project was delayed by
WAPDA as well as the contractor. The request of the contractor dated 28th July, 2001 for
extension of time was not accepted as he had already delayed the project by eleven months.
Liquidated Damages (LD) amounting to Rs.1,590 million were also imposed on the
contractor out of which a sum of Rs.210 million was recovered. The contractor left the site
in September, 2001. However, a supplementary agreement was signed in April, 2002 by
WAPDA with the same contractor (M/s GBC). According to the supplementary agreement
not only the time extension was allowed but already imposed LD was also waived off.
Audit was of the view that overall delay in completion of the project by thirty-eight months
caused cumulative financial loss of Rs.110,564 million (approximately).
The matter was reported to management in April, 2003 and to Ministry in February, 2005. It
was discussed in DAC meeting held on 19th March, 2005 wherein management stated that
the project could not be completed in time due to delay in arrangement of finances, land
acquisition, late delivery of mechanical and electrical equipment and 9/11 incident. Audit did
not agree with the reply as it was the responsibility of the management to ensure all such
arrangements in time. Discussions in the DAC meeting remained inconclusive and the
Committee referred the matter to PAC for further deliberation.
1.7 Expenditure of Rs.32.216 million incurred without the provision of Budget
In the light of note given below Clause-B Section VIII of Book of Financial Powers for
WAPDA, transfer of funds from one project to another can not be made.
In SCARP Monitoring Organization, WAPDA, an expenditure of Rs.32.216 million was
incurred during the years 2001-02 and 2002-03 without provision of budget. Funds
of other projects were utilized for executing the project, thus the entire expenditure
was irregular.
The matter was taken up with the project authorities in October, 2003. It was stated that
there was no need of approval as the expenditure was incurred from the saving of other
projects. The reply was not convincing as saving of one project could not be utilized on
other project. The draft para was issued to the Ministry in September, 2004. It was
replied in December, 2004 that PC-II of SMO (SCARP Monitoring Organization) for the
years 2001-02 and 2002-03 regarding Revenue Budget was prepared and submitted to
Ministry of Water & Power for approval. Its approval was regretted on account
of delayed submission. Later on, the same was approved by Member (Water) on
30th June, 2003.
DAC on 19th March, 2005 directed that revised reply be provided to Audit by 30th March,
2005 but no response was received till the finalization of this report.
1.8 Extra expenditure of Rs.16.092 million due to exploitation of material from
non-designated source
As mentioned in clause SP 19.30 of contract C-01 of GBHP the quarries of riprap
material located near Topi and Swabi Road were designated as possible sources. It was
further clarified in clause SP 20 that the contractor may purchase at his own option and at
no additional cost to the employer, explore, locate, investigate and develop quarry on
other sites.
On the contrary the contractor purchased 610,292 metric ton riprap from Burhan, other
than the designated source, @ Rs.35-45 per ton, whereas the same could have been
exploited @ Rs.15 per ton from designated source.
The employer had to pay extra expenses of Rs.16.092 million due to higher rates. In
addition to it, export tax of Rs.1.319 million for July, 1998 to November, 1999 was also
paid which stood abolished in June, 1998.
The matter was reported in April, 2003. Project authorities replied that as per contract,
contractor may purchase at his own option and at no additional cost to the employer,
explore, locate, investigate and develop these or other quarry sites to meet the requirement
under the contract. Therefore, by selecting Burhan, no violation of the contract has
been committed.
The reply was not accepted as the additional cost of Rs.16.092 million was paid to the
contractor in contravention of contract provisions. Audit would have no objection to
selection of Burhan as a source provided that no additional cost was borne by the
employer. The draft para was issued to the Ministry in January, 2005 and discussed in
DAC meeting held on 19th March, 2005 wherein management stated that detailed reply
had been furnished to Audit. DAC directed Audit to comment upon the reply submitted
by the management. Audit was of the view that the extra expenditure borne by the
employer on this account was against the contract clause.
1.9 Loss of Rs.9.911 million due to issuance of open cheques to contractor
As per para 22 of WAPDA Accounting Manual, payment is to be made through crossed
cheques. In Deg Drainage Project (Contract No.SDB-14) the contractor nominated an
Attorney to receive payment through crossed cheques. The project authorities issued
thirteen open cheques, amounting to Rs.16 million, instead of crossed cheques, in
violation of Authority’s instructions on the subject. The contractor did not acknowledge
the payment of Rs.9.911 million in respect of nine cheques and asked the project
authorities for payment of the same.
The matter was reported to the management in October, 2003 and discussed in a meeting
held in December, 2003. It was replied that a civil suit against the attorney of the contractor
has been filed and action against the officials has been taken. No documentary evidence
in support of reply was produced. The draft para was reported to the Ministry in
December, 2004. Management replied in February, 2005 that Inquiry Committee was
constituted which recommended disciplinary action against persons at fault and to file a
suit for recovery against the Attorney. It was discussed in the DAC meeting held on 19th
March, 2005 wherein management stated that case was with NAB. The DAC directed that
latest position of the case be intimated to Audit. No progress was received till the
finalization of this report.
1.10 Inordinate delay in completion of water supply system costing Rs.2.143 million
In the light of work order No. AF-X/C-II/10/99-239 dated 06.03.1999, the work of laying
and fixing of PVC Pipe valuing Rs.1.793 million in Tarbela Dam Project was to be
completed within 2 months. PVC Pipe valuing Rs.1.793 million was purchased against
supply order No. 98-7 dated 1st January, 1999. The pipe was required to be laid for a new
water supply line at Sobra City because the old pipe line was demolished due to
construction of Ghazi Barotha Hydro Power Project. For laying and fixing of this pipe, a
contract was awarded in March, 1999 at a cost of Rs.0.522 million with the completion
period of two months. Against the work, the contractor was paid a sum of Rs.0.350 million
by September, 1999. However, the work was incomplete even after expiry of five years.
Audit was of the view that the very purpose for which the pipe was purchased was not
achieved and the expenditure of Rs.2.143 million (1.793 + 0.350) had gone waste.
The matter was taken up with the project authorities in December, 2002 and March, 2003.
It was discussed in a meeting held on 24th June, 2004 wherein it was replied that efforts
were being made to purchase the pipe and valve required to complete the work within a
month. The reply was not acceptable as the action was being taken after lapse of five years
and would require more funds and extension in completion period. The draft para was
issued to the Ministry in September, 2004. It was replied in November, 2004 that the work
could not be completed in time as some material relating to the work could not be arranged
due to very high bids and competent authority decided to complete remaining work
departmentally upto March, 2005. The case was also discussed in DAC meeting held on
19th March, 2005 wherein management explained that the work was being carried out
departmentally and there was no wastage of money. It was also stated that there would be
no extra expenditure and it would be within sanctioned estimate. The DAC directed that
latest reply be given within a week and to complete the work upto 30th March, 2005. No
progress in this regard was intimated till finalization of the report.
2. POWER WING
Power Wing is responsible for preparing schemes for the generation, transmission and
distribution of power. It is also responsible for the construction, maintenance and
operation of power houses/grids. This Wing is headed by Member Power.
2.1 OVERVIEW OF FINANCIAL STATEMENTS
After administrative restructuring of Power Wing in 1998, fourteen corporate companies
and Residual Power Wing have been carved out of the WAPDA Power Wing. As each
company has started preparing its own financial statements, therefore, consolidated
financial statements for the whole Wing are not prepared by the Authority. Hence, it was
difficult to make an assessment of the overall financial health and performance of the
Power Wing. However, consolidated Profit/Loss of all the companies and the Residual
Power Wing for the last four years was worked out by Audit from the Financial
Statements of various entities of Power Wing for analysis as given below:
CONSOLIDATED PROFIT/LOSS
(Rs. in million) 2000-01 2001-02 2002-03 2003-04
A. Residual Power Wing 10,856 4,907 20,397 13,248
B. Corporate Companies
1. GENCO-I 1 (27) (384) (0.172)
2. GENCO-II (14) (2) (6) (8)
3. GENCO-III (5) (0.141) (59) (80)
4. GENCO-IV - - - (76)
5. NTDC (4,290) (7,392) (2,746) (1,875)
6. FESCO (480) (788) (400) 182
7. GEPCO (334) (358) (25) (313)
8. HESCO (762) (2,662) (4,150) (1,128)
9. IESCO (302) (503) (312) (139)
10. LESCO (880) (848) (793) 482
11. MEPCO (665) (904) (135) (19)
12. PESCO (493) (2,574) (1,794) (5,451)
13. QESCO (1,313) (1,388) (2,848) (1,114)
14. TESCO - - - (2,915)
Total (9,537) (17,446) (13,652) (12,454)
[A+B] Consolidated Profit/(Loss) 1,319 (12,539) 6,745 794
During 2000-01 the Power Wing earned Net Profit of Rs.1,319 million. In 2001-02 it
sustained a loss of Rs.12,539 million. To bail WAPDA out of financial crisis a subsidy of
Rs.11,600 million was injected by the Government during 2002-03. In 2003-04 WAPDA
financial statements reflected a profit of Rs.794 million.
2.2 Line Losses
Line losses is one of the main reasons for WAPDA’s financial problems because financial
impact of 1% line losses of WAPDA is more than Rs.2,500 million per annum. Due to its
huge financial impact WAPDA has been trying to control its excessive line losses but major
reduction has not been achieved as yet.
Overall line losses of the whole WAPDA system decreased from previous year’s 26.0% to
25.5% during the year 2003-04. Line losses were still very high. (Indonesia 14.11%,
Malaysia 13.97%, Philippines 20.9%, Sri Lanka 18.8% and Vietnam 18.2% (Source: Electric
Power in Asia and Pacific, 2001-02). Six distribution companies out of eight could not
achieve the target of line losses fixed for the year 2003-04. Particularly, distribution losses of
Hyderabad Electric Supply Company and Peshawar Electric Supply Company were very
high as given below:
S.
No.
Company 2002-03 2003-04 Over the
target
(2003-04)
Amount
(Rs. in
million) Actual Target Actual Target
1 FESCO 11.20 12.00 10.40 10.20 0.20% 57.02
2 GEPCO 13.00 14.00 11.90 12.00 0 0
3 HESCO 34.92 27.00 35.36 30.00 5.36% 1,169.70
4 IESCO 10.95 10.00 10.90 10.00 0.90% 196.00
5 LESCO 14.70 14.00 14.10 13.20 0.90% 433.78
6 MEPCO 17.50 17.30 16.96 16.00 0.96% 312.50
7 PESCO 32.03 23.00 31.41 27.60 3.80% 1,100.00
8 QESCO 18.10 17.00 16.00 17.00 0 0
3. RESIDUAL POWER WING
Residual Power Wing consist of those formations which remained with the Authority
after restructuring of WAPDA Power Wing into fourteen companies in 1998.
Main function of this Wing is to construct and maintain various Hydro Power projects.
It also operates those small thermal power stations which have not been transferred to the
Generation Companies (GENCOs). It also arranges payments for Independent Power
Producers (IPPs) for the energy purchased by National Transmission & Despatch
Company (NTDC).
After restructuring of the Power Wing in 1998, the WAPDA is preparing the financial
statements of Residual Power Wing only.
3.1 OVERVIEW OF FINANCIAL STATEMENTS
As transfer price/tariff for supply of power by NTDC to DISCOs has not been determined
by NEPRA, as provided under Electricity Regulatory Act 1997, the financial statements
prepared on the basis of provisional transfer price determined by WAPDA do not present
true affairs of the Residual Power Wing.
An overview of financial statements of Residual Power Wing is given below:
(Rs. in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 87,683 116,084 121,246 121,628
Total Operating Cost 86,233 116,376 119,775 107,619
OPERATING PROFIT/(LOSS) 1,450 (292) 1,471 14,009
Other Income 13,172 9,227 10,586 8,121
Financial Charges 3,766 4,028 3,260 8,882
NET PROFIT/(LOSS) 10,856 4,907 8,797
*20,397
13,248
Source: Financial Statements of the Residual Power Wing for the financial years 2000-01 to 2003-04
* Including Rs. 11,600 million subsidy received from Govt. of Pakistan during the year 2002-03 against cash shortfall of WAPDA.
Since 2001-02 net profit has been increasing. Main reasons for the increase in net profit
from Rs.8,797 million in 2002-03 to Rs.13,248 million in 2003-04 were as under:
i) Electricity sale increased by 0.31% due to increase in number of units sold i.e.
62,582 million in 2002-03 to 67,350 million in 2003-04.
ii) Cost of electricity decreased by 13% i.e. from Rs.111,010 million in 2002-03 to
Rs.96,581 million in 2003-04 on account of the following factors:
Decrease in purchase of electricity as well as reduction in rate by IPPs i.e.
22,045 million units purchased @ Rs.5.0014/unit in 2002-03 as compared
to 20,292 million units @ Rs.4.7896/unit in 2003-04.
Increase in hydel generation from 22,208 million units in 2002-03 to
27,281 million units in 2003-04.
3.2 RECEIVABLES
Analysis of receivables as detailed below revealed that Rs.58,906 million were outstanding
on 30th June, 2003 which rose to Rs.69,613 million on 30th June, 2004. Persistent rise in
receivables during the last four years is causing serious cash flow problems for WAPDA.
RECEIVABLES
(Rs. in million)
CATEGORY As on
30th June,
2001
As on
30th June,
2002
As on
30th June,
2003
As on
30th June,
2004
A. Federal Government:
Deptt./Agencies
Defence
AJ&K
1,414
2,675
1,559
419
17
1,676
338
677
594
585
375
(31)
Sub Total 5,648 2,112 1,609 991
B. Provincial Governments:
Punjab
NWFP
Sindh
Balochistan
547
891
3,573
(115)
(251)
(131)
316
38
(335)
1,352
506
67
146
98
532
277
Sub Total 4,896 (28) 1,590 1,053
C. (i) FATA
(ii) T/Wells in
Balochistan
5,477
376
12,425
393
26,876
464
36,783
633
Sub Total 5,853 12,818 27,340 37,416
D. (i) KESC
(ii) Other Private
Consumers
10,396
17,092
7,014
24,432
3,515
24,267
2,286
27,184
Sub Total 27,448 31,446 27,782 29,470
E. Autonomous bodies under
Federal Government
-
300
409
449
Sub Total - 300 409 449
F. Others (W&P) 53 176 295
Sub Total - 53 176 295
Grand Total (A to F) 43,885 46,701 58,906 69,613 Source: 2003-04 MIS-13 WAPDA and World Bank
Receivables from “Other Private Consumers” which were Rs. 24,267 million on 30th June,
2003 increased to Rs. 27,184 million on 30th June, 2004 need to be taken special note of by
the Government and the PAC. It effects the liquidity position of the Wing and completely
distorts its financial position. Management was asked to identify reasons for outstanding
amounts against “Other Private Consumers” but no clarification was given.
3.3 PROVISION FOR DOUBTFUL DEBTS
At the end of the year 2003-04, status of doubtful debts of the distribution companies
was as under:
(Rs. in million)
As on 30th June, 2003 As on 30th June, 2004
Name of
Company
Trade
Debts
Provision Percentage
(%)
Trade
Debts
Provision Percentage
(%)
FESCO 2,178 130 5.97 2,476 117 4.73
GEPCO 3,007 239 7.95 2,858 241 8.43
HESCO 5,199 4,244 81.63 5,756 5,215 90.60
IESCO 2,695 839 31.13 2,960 829 28.01
LESCO 6,208 1,690 27.22 5,896 1,688 28.63
MEPCO 3,699 1,213 32.79 3,675 1,211 32.95
QESCO 4,494 2,650 58.97 5,054 3,312 65.53
PESCO 36,118 1,598 4.42 8,420 3,508 41.66
TESCO - - - 32,350 5,793 17.91
Total 63,598 12,603 19.82 69,445 21,914 31.56
Source: Manager Finance (HQ) Power, WAPDA.
The companies made heavy provisions for doubtful debts during the year 2003-04
ranging from 4.7% to 90 %. Cumulative provision as on 30th June, 2004 was
Rs.21,914 million which was 31.56% of total trade debts. An increase of 11.74% in this
provision during 2003-04 needs proper justifications. WAPDA’s liquidity problems can
be mitigated considerably if its receivables, particularly from the private consumers, are
brought down through aggressive recovery campaigns.
3.4 PAYABLES
Comparative position of payables is as under: (Rs. in million)
Description As on 30th
June, 2001
As on 30th
June, 2002
As on 30th
June, 2003
As on 30th
June, 2004
Oil Companies - - 2,108 2,713
Gas 1,738 4,517 - -
IPPs 6,941 6,147 496 -
KAPCO-Settlement 7,687 7,401 - -
Misc-Operating 2,491 170 - -
Development 133 - - -
DSL-GOP 2,572 21,615 22,329 10,043
Water Wing/Other etc. 1,769 1,526 1,485 -
Total 23,331 41,376 26,418 12,756
Source: D.D. CPCC/1334 Dt: 04th February, 2005.
The total outstanding liabilities have gradually decreased from Rs.41,376 million in the
year 2001-02 to Rs.12,756 million in the year 2003-04 mainly due to conversion of debt
servicing liability of WAPDA into Government of Pakistan’s equity.
3.5 Non-recovery of Rs.4.116 million from contractor on account of supplying
sub-standard material
According to section-VI of Book of Financial Powers for WAPDA, the payment of
purchase order is subject to inspection of material by Chief Engineer Inspection and
Surveillance WAPDA and Factory test reports.
A contract (under IBRD Loan Scheme) was awarded by MD (Power) for manufacturing
of 7,599 LT & 4,120 HT pre-stressed cement concrete poles to M/s Sind Precast and
Pre-stressing Industries Karachi. Payment of these poles amounting to Rs.4.630 million
was made in July, 1997 to the contractor without proper inspection of the material. The
material was found sub-standard on inspection and an enquiry committee was constituted
for inspection of material which was jointly inspected by WAPDA and contractor’s
representatives in May, 2002 who also found the material as sub-standard. On the
recommendation of enquiry committee, in July, 2003 General Manager (C&M) ordered
recovery valuing Rs.4.116 million from contractor. The penal amount was not recovered
from the contractor which resulted into loss to WAPDA to the tune of Rs.4.116 million.
The matter was taken up with the Authority in January, 2004 followed by reminder to
discuss the same in February, 2004. No response received from the management and
a draft para was issued to the Principal Accounting Officer (PAO) in June, 2004. The
draft para was discussed in DAC meeting on 19th March, 2005. DAC directed to file a
court case against the contractor.
4. JAMSHORO POWER GENERATION
COMPANY
Jamshoro Power Generation Company (GENCO-I) was incorporated in August, 1998 and
started its commercial operations from March, 1999. Its principal activity is to generate
thermal power for selling it to NTDC.
The Company took over all the properties, rights, assets, obligations and liabilities
of Thermal Power Stations at Jamshoro, Lakhra and Kotri, owned by WAPDA and
such other assets and liabilities as agreed upon. However, from July, 2002 all the
assets and liabilities relating to Lakhra Power Station were transferred back to WAPDA
at book value.
4.1 OVERVIEW OF FINANCIAL STATEMENTS
Sales revenue of the Company has been accounted for at the rate of Rs.2.31/kWh (2003:
Rs.2.44) for energy charges and Rs.199.69/kwh/month (2003: Rs.196.69) for capacity
charges. The rate was determined on the basis of full cost recovery of the Company as
agreed with NTDC till finalization of tariff and power purchase agreement. In the
absence of tariff determination by NEPRA, the financial statements prepared on the basis
of full cost recovery method do not present true financial picture of the Company.
An overview of the financial statements of the Company in tabulated form is
given below:
(Rs.in million) 2000-01 2001-02
(Restated)
2002-03 2003-04
Total Revenue 8,138 10,690 11,060 10,564.609
Total Operating Cost 6,237 9,892 10,703 9,943.876
Operating Profit/(Loss) 1,901 798 357 620.733
Other Income 8 8 13 9.708
Financial Charges 1,908 833 754 630.613
Net Profit/(Loss) 1 (27) (384) (0.172)
Source: Financial Statements of the Company for the years 2000-01 to 2003-04
Net loss increased from Rs.27 million in 2001-02 to Rs.384 million in 2002-03 but it
decreased to Rs.0.172 million in the year 2003-04. Reasons for decrease in loss were
as under:-
i) Decrease in average price of furnace oil during the year (Rs.10,773/MT) as
compared to the previous year (Rs.11,039/MT)
ii) The electricity generation on gas increased by 21.56% as compared to the last
year. Gas/Furnace Oil mix was 79:21 during 2003-04 as compared to 66:34
during the last year.
iii) Decrease in establishment cost due to reversal of Rs.136.7 million provision made
for compensated absences as worked out by Actuarial Consultant.
iv) Reduction in interest charges from Rs.723.497 million in 2002-03 to
Rs.595.68 million in 2003-04 (i.e. Rs.173.81 million).
Further efforts are required to be made by the management to turn the company into an
efficient and profit earning organization.
Evaluation of Assets
As per Chartered Accountant’s (M/s Taseer Hadi Khalid & Co.) report on the company’s
accounts for the year 2003-04, the valuation and title of assets & liabilities transferred to
the company could not be finalized due to non-revision of loan agreement with the
lenders in the light of Business Transfer Agreement and Supplementary Business
Transfer Agreement.
5. CENTRAL POWER GENERATION COMPANY
Central Power Generation Company (GENCO-II) was incorporated in October, 1998 and
started its commercial operations in March, 1999. Its principal activity is to generate
thermal power for selling it to NTDC.
The Company took over all the properties, rights, assets, obligations and liabilities of
Thermal Power Stations at Guddu, Sukkur and Quetta owned by WAPDA and such other
assets and liabilities as agreed upon.
5.1 OVERVIEW OF FINANCIAL STATEMENTS
Electricity tariff with NTDC, which is sole purchaser of the electricity from the
Company, was not finalized during the year 2003-2004. Provisional tariff approved by
WAPDA was as under:-
Energy Purchase price Rs.1.7145/kWh
Capacity purchase price Rs.138.178/kWh/Month
However, the tariff petition has been approved by NEPRA and intimated to Federal
Government on 29th March, 2004 and has become effective w.e.f. 26th July, 2004.
An overview of the financial statements of the Company in tabulated form is
given below:-
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 14,000 14,377 15,591 16,251
Total Operating Cost 13,049 13,664 14,962 15,760
OPERATING
PROFIT/(LOSS)
951 713 629 491
Other Income 30 52 24 74
Financial Charges 995 767 660 573
NET PROFIT/(LOSS) (14) (2) (7) (8) Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
Net loss of the Company decreased from Rs.14 million in 2000-01 to Rs.8 million in
2003-04. However, it increased as compared to 2001-02 & 2002-03. Total revenue in the
year 2003-04 increased by 4.23% with respect to the year 2002-03 but on the other hand
the total operating cost increased by 5.33% during the same period. The main reasons of
increase in total operating cost were as following:-
i) Increase in number of units of electricity produced which shows improvement in
the performance.
ii) Increase in retirement benefits of employees due to change in policy based on
Actuarial Report carried on as at 30th June, 2004.
Evaluation of Assets
As per Chartered Accountant’s (M/s M. Yousaf Adil Saleem & Co.) report on the accounts
pertaining to the year 2003-04 no reliable record was available with the Company from
where the Auditors could verify/check the value of Company’s fixed assets and capital
work-in-progress.
6. NORTHERN POWER GENERATION
COMPANY
Northern Power Generation Company (GENCO-III) was incorporated in October, 1998.
Its principal activity is to generate power through seven thermal power stations located at
Muzaffargarh, Multan, Shahdrah and Faisalabad, and to sell it to NTDC. It took over all
the properties, rights, assets, obligations and liabilities from WAPDA and such other
assets and liabilities as agreed upon.
6.1 OVERVIEW OF FINANCIAL STATEMENTS
Electricity tariff with NTDC, the sole purchaser of the power from the Company, is yet to
be finalized. Provisional tariff approved by WAPDA for the year 2003-04 was as under:-
Energy Purchase price Rs.2.33083/kWh
Capacity purchase price Rs.104.83199/kWh/Month
The tariff petition was filed with NEPRA, approval of which was awaited. Hence, the
financial statements prepared on the basis of provisional tariff did not depict true
financial picture of the Company.
An overview of the financial statements of the Company in tabulated form is
given below:- (Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 21,691 19,455 22,221 19,872
Total Operating Cost 17,888 18,457 21,890 19,602
OPERATING PROFIT/(LOSS) 3,803 998 331 270
Other Income 32 63 214 93
Financial Charges 3,840 1,062 605 443
NET PROFIT/(LOSS) (5) (1) (60) (80)
Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
The Company sold 7,671.65 gWh units during year 2003-04 which were 6.2% higher
than the previous year. It sustained a loss of Rs.80 million during the year 2003-04 which
was Rs.20 million higher than the previous year. Major reasons for increase in loss were:-
i) Decrease in revenue generation by 10.57% due to reduction in provisional tariff
applied by WAPDA i.e. energy purchase price reduced from Rs.2.7728/kWh
in 2002-03 to Rs.2.33083/kWh in 2003-04 and capacity purchase price from
Rs.116.478 in 2002-03 to Rs.104.83199/kWh/Month in 2003-04.
ii) Other income decreased from Rs.214 million to Rs.93 million.
iii) Recognition of loss of Rs.21.185 million during the year 2003-04 due to foreign
currency fluctuations as compared to gain of Rs.89.67 million in 2002-03.
7. LAKHRA POWER GENERATION COMPANY
Lakhra Power Generation Company (GENCO-IV) was incorporated in February, 2002
and started its commercial operations in July, 2002. Its main objective is to generate
electricity from coal and sell it to NTDC.
The Company took over all the properties, rights, assets, obligations and liabilities of
Thermal Power Station Lakhra from WAPDA and such other assets and liabilities as
agreed upon. It remained attached with Jamshoro Power Company Ltd for about three
years. An application for grant of power generation license was submitted to NEPRA in
April, 2004 which has not yet been granted.
7.1 OVERVIEW OF FINANCIAL STATEMENTS
Sales revenue of the Company has been accounted for at the rate of Rs.1.15/kWh
(2002-03: Rs.0.95/kWh) as energy charges and Rs.442/kWh/month (2002-03: Rs.546.31)
as capacity charges. This rate was determined on the basis of full cost recovery of the
Company as agreed with NTDC till finalization of tariff and power purchase agreement.
Due to non-determination of tariff by NEPRA, the financial statements prepared on the basis
of full cost recovery method did not present true picture of the Company’s financial affairs.
An overview of the financial statements of the Company is given below: (Rs.in million)
21st February, 2002
to 30th June, 2003
2003-04
Total Revenue 678 585
Total Operating Cost 589 602
OPERATING PROFIT/(LOSS) 89 (17)
Other Income 4 7
Financial Charges 97 66
NET PROFIT/(LOSS) (4) (76)
Source: Financial Statements of the Company for the years 1999-2000 to 2003-04
During the year 2003-04 Company sold 139.457 gWh units of electricity for
Rs.585 million to NTDC which was more than the sale price calculated for the previous
year i.e. 125.557 gWh (167.4/16x12) for Rs.509 million. However, the net loss increased
from Rs.4 million in the period starting from 21st February, 2002 to 30th June, 2003 to
Rs.76 million in 2003-04. Main reason for increase in loss was increase in cost of sales. It
was 87% of sales during the previous period but in 2003-04 it increased to 103% of sales
mainly due to charging of excess depreciation of Rs.109 million as compared to the
previous year.
Efforts should be made to earn profit in the coming years and turn it into a financially
viable organization.
Evaluation of Assets
The Chartered Accountant’s (M/s Taseer Hadi Khalid & Co.) report on the accounts
pertaining to the year 2003-04 indicated that properties, rights, assets/obligations have
been transferred through a Business Transfer Agreement as amended by Supplementary
Business Transfer Agreement. The said agreement could not be executed due to non-
completion of formalities.
8. NATIONAL TRANSMISSION AND DESPATCH
COMPANY
National Transmission and Despatch Company (NTDC) was incorporated in
November, 1998. Its main objective is to purchase electricity from the Residual Power
Wing, GENCOs and IPPs and to sell it to the Distribution Companies (DISCOs). It also
constructs grid stations and installs transmission lines besides providing technical
services and training to DISCOs staff. The Company took over all the properties, rights,
assets, obligations and liabilities relating to Transmission and Grid Divisions from
WAPDA and such other assets and liabilities as agreed upon.
8.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity sold by NTDC to different DISCOs during the year 2003-04 had been
accounted for at different provisional rates ranging from Rs.1.680 to Rs.3.490/kWh
(Rs.2.116 to Rs.3.490/kWh for the year 2002-03). Sales to KESC have been made at rate
ranging from Rs.3.69 to 3.80/Kwh during 2003-04 (Rs.3.47 to 3.8/kWh during
2002-03). The sale rates, except for KESC, are subject to confirmation from National
Electric Power Regulatory Authority (NEPRA).
The purchase of electricity has also been accounted for at the provisional rate ranging from
Rs.1.147 to 2.331/Kwh during 2003-04 (Rs.2.213 to 4.049/Kwh for the year 2002-03). These
rates except for IPPs and KESC, are subject to confirmation from NEPRA.
The tariff petition was filed with NEPRA but approval was awaited. Hence, the financial
statements prepared on the basis of provisional tariff did not depict true financial affairs
of the Company.
An overview of the financial statements of the Company is given below:- (Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 135,557 157,872 173,305 185,342
Total Operating Cost 133,795 163,749 174,476 184,437
Operating Profit/(Loss) 1,762 (5,877) (1,171) 905
Other Income 1,434 1,530 743 157
Financial Charges 7,486 3,045 2,318 2,937
Net Profit/(Loss) (4,290) (7,392) (2,746) (1,875) Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
In the year 2003-04 the Company sustained a net loss of Rs.1,875 million which was
Rs.871 million less than the previous year. The total revenue in the year 2003-04
increased by 36.72% with respect to the year 2000-01 but on the other hand the total
Operating Cost also increased by 37.85% during the same period. Major reasons of this
decrease in loss were following:-
i) Decrease in transmission losses i.e. from 7.8% (4,908/62,694) in 2002-03 to 7.5%
(5,054/67,694) in 2003-04.
ii) Decrease in number of units purchased from and per unit average rate charged by
IPP. i.e. 22,045 million units @ Rs.5.0014 in 2002-03 to 20,292 million units
@ Rs.4.789 in 2003-04.
However, the expenditure under “operating expenses” significantly increased i.e. from
Rs.3,412 million in 2002-03 to Rs.15,543 million in 2003-04 due to recognition of
Rs.11,869 million as bad debts.
Evaluation of Assets
The Chartered Accountant’s (M/s Ford Rhodes Sidat Hyder & Co.) report on the
accounts pertaining to the year 2003-04 indicated that no reliable record was available
with the Company from where the Auditors could verify/check the value of Company’s
fixed assets and capital work-in-progress.
8.2 Blockage of funds of Rs.306.353 million due to poor contract management
As per letter No. 8985-92/CE/EHV/N dated 2nd November, 1998 regarding award of
contract of 500 KV Muzaffargarh-Gatti transmission line (Package-II), the construction and
commissioning of line was to be completed within 18 months from the date of
commencement of work at a cost of US$ 44.558 million FCC and Rs.390.460 million. The
contractor did not undertake the work. It was re-awarded to the same firm on 20th
December, 2001 at the same price with the grant of 10% advance of contract price and
extension of time period from 18 months to 22 months. Again contractor did not start the
work by 18th August 2004 which was required to be started in December, 2001. The project
Authority did not take any action regarding forfeiting of performance security bond in the
light of Para-V of Notice of award of contract. Resultantly the Authority’s funds to the tune
of Rs.306.353 million were blocked due to poor contract management.
The matter was reported to the project authorities in August, 2004, it was replied
in September, 2004 that advance payment was made to avoid expiry of foreign loan
facility (i.e. target date 15th March, 2003) The reply was not accepted, as the contractor
enjoyed the financial benefits for more than one and half year without starting the
work. The management replied in February, 2005 that mode of financing would be
changed to local financing due to favourable interest rate. NTDC’s Board of Directors
had also approved it and negotiations with local Banks/Financial Institutions were under
way. It was discussed in DAC meeting on 19th March, 2005, wherein management
promised to submit a revised reply but the DAC decided to refer the issue to the
Public Accounts Committee.
8.3 Loss of Rs.79.779 million on account of demurrage charges
Resident Representative Karachi, an organization of WAPDA, is responsible for timely
clearance of imported consignment from custom authorities through clearing agents and
arranges its transportation to the ultimate consignee to avoid payment of demurrage
charges. During 2002-03 Demurrage Committee held WAPDA responsible for the delay
in arranging funds for custom clearance and decided that a sum of Rs.79.779 million
should be borne by WAPDA, out of the total demurrage charges of Rs.90.094 million.
Thus the Authority sustained a loss to the stated extent.
The matter was taken up with the RRK in April, 2004. It was replied that case for writing
off the loss was being initiated with the concerned authorities. It was also discussed with
the management on 28th July, 2004 who replied that regularization action was in process.
The draft para was issued to the Ministry in December, 2004. It was discussed in DAC
meeting in March, 2005 wherein management stated that this para is the duplication of
para 4.1 of Special Audit Report-162 (SAR). DAC directed the Audit to verify this
aspect. On verification by Audit it was found that there was no duplication because the
contents of this para relates to demurrage claims decided in 2002-03 whereas para 4.1 of
SAR-162 relates to the cases of previous years. The management was intimated
accordingly but no response received from the management.
8.4 Non-recovery of Rs.20.310 million from Clearing Agents, Suppliers &
Transporters
Resident Representative Karachi is responsible for timely clearance of imported consignment
from custom authorities through clearing agents and arranges its transportation to the ultimate
consignee to avoid payment of demurrage charges. During 2002-2003 Demurrage
Committee held clearing agent, supplier and transporter responsible for the delay in custom
clearance and its transportation and decided that a sum of Rs. 20.310 million should be
recovered. The said amount could not be recovered from them. Thus the authority
sustained a loss to the stated extent.
The matter was taken up with the RRK in April, 2004 but no response was received. The
draft para was issued to the Ministry in December, 2004. It was replied in February, 2005
that out of Rs.20.310 million, an amount of Rs.18.961 million was recoverable from
M/s Transglobe (a clearing agent). The firm went into litigation, but the case was decided
against the firm. The firm then lodged an appeal against the court decision. Out of the
remaining amount of Rs.1.348 million (20.310 – 18.961), an amount of Rs.1.028 million
had already been debited to suppliers for recovery but no recovery had been intimated so
far. A balance amount Rs.0.32 million pertains to Ex-transporters against whom a suit
had been lodged. An inquiry committee had been constituted to investigate the matter and
to fix the responsibility. The para was discussed in DAC meeting held on 19th March,
2005, wherein management repeated their above reply. DAC directed to complete the
inquiry proceedings under intimation to Audit but no progress was intimated to audit.
8.5 Loss of Rs.20.200 million due to mismanagement
Resident Representative Karachi is responsible for timely clearance of imported consignment
from custom authorities through clearing agents and arranges its transportation to the ultimate
consignee to avoid payment of demurrage charges.
A sum of Rs.73.194 million was imposed as demurrage charges/Warehouse charges due
to delay in clearance of imported material on the part of Resident Representative Karachi
(RRK). The case for the waiver of demurrage was filed and rejected by the KPT
in February, 1998. The matter was taken up with Ministry of Communication and
deferment was allowed by making payment of Rs.20.200 million, out of the total
demurrage charges of Rs.73.194 million. Thus the material was released and WAPDA had
to suffer loss of Rs.20.200 million.
The matter was reported to RRK in April, 2004 and discussed on 28th July, 2004. It
transpired that the case was delayed due to expiry of license of Bonded Warehouses at
Multan & Faisalabad, agreement with Clearing Agent and non-availability of funds. It was
further replied that RRK was not responsible for the delay as the Warehouses were not
under its control. Reply was not tenable as it was the responsibility of RRK and NTDC to
update validity of the Licenses & Agreement. The draft para was issued to the Ministry in
December, 2004. It was replied in February, 2005 that inquiry committee had been
constituted in January, 2005 to investigate the matter and to fix responsibility. The para was
also discussed in DAC meeting on 19th March, 2005 wherein management stated that the
proceeding of inquiry committee constituted by Member (Finance) was in progress. The
DAC directed that inquiry be got completed by 15th April, 2005 and audit be intimated but
DAC’s directives were not complied with till finalization of the report.
8.6 Non-utilization of electrical equipment amounting to Rs.7.886 million
According to clause 6.1 of Computerized Store Inventory System Operating Procedures,
the dismantled material is required to be returned to store.
In PESCO as a result of augmentation of Grid Stations, electrical equipment valuing
Rs.7.886 million was removed. The dismantled material was not returned to the store for
utilization. The same was lying unutilized at various sites which resulted in blockage
of resources.
The matter was reported to the PESCO authorities in March, 2004 and discussed in
May, 2004. It was replied that the matter would be taken up at Authority level but no
progress in this regard was intimated. The draft para was issued to the Ministry in
August, 2004 and discussed in DAC meeting held on 19th March, 2005. Chief Executive
PESCO explained that para is related to NTDC. DAC directed that para be transferred
to NTDC and record be produced to Audit by 30th March, 2005. Record pertaining
to utilization of stores costing Rs.3.514 million only was produced by NTDC which
was verified but stores worth Rs.7.886 million had not been utilized till the finalization
of the report.
9. FAISALABAD ELECTRIC SUPPLY COMPANY
Faisalabad Electric Supply Company (FESCO) started its commercial operations as a
Public Limited Company in July, 1998. Its objectives are to purchase electricity from
NTDC and sell it to the consumers, to plan and execute new works and to maintain
distribution system & grid stations under its jurisdiction. All the properties, rights, assets,
obligations and liabilities of Faisalabad Area Electricity Board, were transferred to FESCO.
9.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity purchased during the year i.e. 2003-04 was invoiced by the NTDC at the
provisional rate of Rs.3.262/kWh (2003: 7052 million units @ Rs.3.206/kWh).
Adjustment, if any, is to be made on finalization of rate and reflected in the accounts for
the year in which the rate is finalized. As transfer price has not been determined by
NEPRA, the financial statements prepared on the basis of provisional transfer price
determined by WAPDA did not present the actual financial standing of the Company.
An overview of the financial statements of the Company in tabulated form is
given below:
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 20,032 22,253 24,959 27,813
Total Operating Cost 20,369 22,947 25,606 27,765
Operating Profit/(Loss) (337) (694) (647) 48
Other Income 499 444 941 635
Financial Charges 642 538 693 501
Net Profit/(Loss) (480) (788) (399) 182 Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
FESCO sustained financial losses for the last three years but it became a profitable
organization during the year 2003-04 despite the higher provisional tariff rate charged
by NTDC.
The main reasons for better financial performance of the company were as follows:
i. Decrease in distribution losses (11.17% in 2003 to 10.44% in 2004).
ii. Increase in sale revenue by 11.6%.
iii. Decrease in financial charges by 27.7% due to repayment of debts.
iv. Reversal of provision for doubtful debts of Rs.13.5 million in the current year
credited to “other income”.
Distribution Losses
Distribution losses of FESCO during the year 2003-04 were as under:
Units Received 7,644 million
Units Billed 6,846 million
Units Lost 798 million
Percentage losses during the year 10.4%
Target for the year 10.2%
Losses above the target 0.25%
Monetary loss (7644 x 0.2 / 100) x 3.73 57.02 million
The distribution losses decreased considerably from 11.17% in 2002-03 to 10.4 % in
2003-04 but remained behind the target, marginally. Further efforts should be made to
reduce the losses to bring it to the level of given target.
Receivables
Position of trade debts during the last four years was as under:
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
657 2,015 2,178 2,476 Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
There were trade debts of Rs.2,015 million as on 30th June, 2002, which increased to
Rs.2,476 million on 30th June, 2004. This increase was mainly due to slow pace of
recovery from private sector and permanently disconnected consumers. During the year
2003-04 Rs.117 million i.e. 4.7% of the total trade debts was placed under the head
“Doubtful Trade Debts”.
10. GUJRANWALA ELECTRIC POWER
COMPANY
Gujranwala Electric Power Company (GEPCO) started its commercial operations as a
Public Limited Company in July, 1998. Its objectives are to purchase electricity from
NTDC and to sell it to the consumers, to plan and execute new works and to maintain
distribution system & power grid stations under its jurisdiction. All the properties, rights,
assets, obligations and liabilities of Gujranwala Area Electricity Board, were transferred
to GEPCO.
10.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity purchased during the year 2003-04 was invoiced by the NTDC at the
provisional rate of Rs.3.034/kWh (2002-03: Rs.2.907/kWh). Adjustment, if any, is to be
made on finalization of rate and reflected in the accounts for the year in which the rate is
finalized. As transfer price of electricity from NTDC to DISCOs has not been determined
by NEPRA, the financial statements prepared on the basis of provisional transfer price
determined by WAPDA did not present true financial picture of the Company.
An overview of the financial statements of the Company in tabulated form is
given below:
(Rs.in million)
2000-01 2001-02 2002-03
Restated
2003-04
Total Revenue 13,601 15,766 17,561 19,979
Total Operating Cost 13,727 16,210 18328 20,367
Operating Profit/(Loss) (126) (444) (767) (387)
Other Income 321 484 820 461
Financial Charges 529 398 475 387
Net Profit/(Loss) (334) (358) (422) (313) Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
There was persistent increase in loss during the financial year 2000-01 to 2002-03.
However, the Company has sustained a loss of Rs.313 million in the financial year 2003-04
which was Rs.109 million less than the previous year. The main reasons of decrease
in loss were as under:
i) Decrease in distribution losses from 13% in 2002-03 to 11.9% in 2003-04 (within
the given target).
ii) Electricity sales increased by 13.78% as compared to the previous year, due to
increase in number of consumers by 83,736 (1,959,849-1,876,113).
iii) Decrease in other operating cost by 4.59% as compared to previous year i.e.
Rs.2,371 million in 2002-03 & Rs.2,262 million in 2003-04
Distribution Losses
Distribution losses of GEPCO decreased during the year 2003-04 i.e 11.9% (within target
of 12.0%) as compared to 13.0% in the year 2002-03.
Receivables
Position of trade debts during the last four years was as under: (Rs.in million)
2000-01 2001-02 2002-03 2003-04
1,337 2,739 3,007 2858
Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
The receivables have marginally decreased during 2003-04. Out of the total amount of
Rs.2,858 million, Rs.241 million was placed under doubtful debts, which was 8.43% of
receivables. The main reason for receivables was slow pace recovery from private sector
& permanently disconnected consumers. Aggressive campaign and commitment is
required by the management to recover the Company receivables.
Evaluation of Assets
As per Chartered Accountant’s (M/s Ford Rhodes Sidat Hyder & Co.) report on the
accounts pertaining to the year 2003-04 no reliable record was available with the
Company from where the Auditors could verify/check the value of Company’s fixed
assets and capital work-in-progress.
11. HYDERABAD ELECTRIC SUPPLY COMPANY
Hyderabad Electric Supply Company (HESCO) started its commercial operations as a Public
Limited Company in July, 1998. Its objectives are to purchase electricity from NTDC and to
sell it to the consumers, to plan and execute new works and to maintain distribution system &
power grid stations under its jurisdiction. All the properties, rights, assets, obligations and
liabilities of Hyderabad Area Electricity Board were transferred to HESCO.
11.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity purchased during the year 2003-04 was invoiced by the NTDC at the
provisional rate of Rs.2.152/kWh (2003: Rs.2.271). Adjustment, if any, is to be made on
finalization of rate and reflected in the accounts for the year in which the rate is finalized.
As transfer price of electricity from NTDC to DISCOs has not been determined by
NEPRA, the financial statements prepared on the basis of provisional transfer price
determined by WAPDA did not present true affairs of the Company.
An overview of the financial statements of the Company in tabulated form is
given below:
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 15,223 15,409 15,091 16,272
Total Operating Cost 13,314 17,592 18,679 16,879
Operating Profit/(Loss) 1,909 (2,183) (3,588) (607)
Other Income 152 171 85 177
Financial Charges 2,824 650 647 698
Net Profit/(Loss) (763) (2,662) (4,150) (1,128) Source: Financial Statements of the Company for the financial years 2000-2001 to 2003-04
HESCO suffered losses during the last three years However, the net loss of the company
decreased by Rs.3,022 million during the year 2003-04 as compared to previous year.
The main reasons of this decrease in net loss were as under:
i) Increase in sale revenue by 7.82% due to increase in consumption.
ii) Decrease in other operating cost (Rs.5,950 million in 2002-03, Rs.3,965 million
in 2003-04)
Receivables
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
8,697 5,156 5,200 5,756 Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
Company’s receivables increased by Rs.556 million during the year 2003-04. Main
reasons for this increase of receivables were non-recovery from public, private sectors
and permanently disconnected consumers.
During the year 2003-04, the management placed Rs.5,215 million under the head
“doubtful debts”. It was 91% of the total receivables which was alarmingly high and
needs detailed investigation.
Evaluation of Assets
As per Chartered Accountant’s (M/s Taseer Hadi Khalid & Co.) report on the accounts
pertaining to the year 2003-04 the transfer of assets to the Company under Business
Transfer Agreement (BTA) as amended by Supplementary Business Transfer Agreement
and other related agreement is conditional to receipt of the lender’s consent in respect of
transfer of various loans to the Company and any applicable exemptions to provincial and
other taxes. The title of WAPDA in respect of certain assets is also conditional to
successful negotiations with relevant authorities. No reliable record was available with
the Company from which the Auditors could have verified/physically checked the value
of Company’s fixed assets and capital work-in-progress.
Distribution Losses
Distribution losses in HESCO during the year 2003-04 were as under:
Units Received 5,804.006 million
Units Billed 3,751.429 million
Units Lost 2,052.577 million
Percentage losses during the year 35.36%
Target for the year 30%
Losses above the target 5.36%
Monetary loss (5,804 x 5.36 / 100) x 3.76 1.169.7 million
The distribution losses increased from 34.92% in 2002-03 to 35.36% in 2003-04
and were exceptionally high as compared to other sister companies. Special attention
of HESCO management is required to control technical and non-technical
distribution losses. .
11.2 Loss of revenue amounting to Rs.11.781 million due to incorrect application
of tariff
As per Schedule of Tariff, the commercial tariff A-2 is applicable to Telephone Exchanges
and Petrol Pumps.
In violation of the schedule of tariff, certain formations of HESCO applied industrial tariff
B-2 to the telephone exchanges and petrol pumps instead of Commercial tariff A-2 which
resulted in less billing of Rs.12.729 million as detailed below:
Sr. No. Name of Formation Less Billing (Rs)
1. XEN/R.O. Shikarpur 695,512
2. XEN/R.O. Shikarpur 49,008
3. XEN/R.O. Sukkur 219,033
4. XEN/R.O. Naushero Feroze 754,636
5. XEN/R.O. Tando Adam 825,323
6. XEN/R.O. Tando Adam 52,662
7. XEN/R.O. Tando Muhammad Khan 286,818
8. XEN/R.O. Kotri 1,060,457
9. XEN/R.O. Tando Allah Yar 102,015
10. XEN/R.O. Garikhata 8,631,728
11. XEN/R.O. Sanghar 51,592
Total 12,728,784
The executive authorities stated that R.Os concerned had been directed to change the
tariff and debit the difference to the consumers. The matter was reported to the Chief
Executive Officer, HESCO in August, 2003 but no progress towards recovery was
intimated. Draft para was issued to the Ministry in October, 2003. In March, 2005 it was
replied that tariff of one consumer had been changed and amount of Rs.84,892 was
debited. Original record in support of reply was not produced. The para was discussed in
DAC meeting held on 19th March, 2005 and management was directed to get the recovery
verified from Audit. Management could only produce record relating to recovery of
Rs.0.948 million but no satisfactory response was given for the balance amount of
Rs.11.781 million.
11.3 Loss of Rs.2.393 million due to non-recovery of sharing cost of grid-station
and transmission line
The Authority vide its circular letter dated 21st April, 2001 required that sharing cost of
grid station and transmission line @ of Rs.4.93 million per MW of the ultimate demand
of load of a housing society would be recovered from the housing society.
Contrary to this, HESCO did not recover the sharing cost from four housing societies
resulting in loss of Rs.2.393 million to the Company.
It was replied by the management that the amount in question would be recovered by the
concerned field formations before energizing/connecting these housing societies with the
HESCO system. The matter was also reported to the Chief Executive Officer, HESCO in
August, 2003 but audit was not informed about progress regarding recovery of the
outstanding dues. The Draft Para was sent to Principal Accounting Officer in October,
2003 and discussed in DAC meeting held on 19th March, 2005. The management replied
that an amount of Rs.1.836 million had been recovered while Rs.0.130 million is yet to
be recovered and the balance of Rs.0.427 million was not recoverable. The DAC directed
to get the record verified from Audit. Management remained un-responsive till the
finalization of this report and could not produce any record in support of its reply.
12. ISLAMABAD ELECTRIC SUPPLY COMPANY
Islamabad Electric Supply Company (IESCO) started its commercial operations as a Public
Limited Company in July, 1998. Its objectives are to purchase electricity from NTDC and
to sell it to the consumers, to plan and execute new works and to maintain distribution
system & power grid stations under its jurisdiction. All the properties, rights, assets,
obligations and liabilities of Islamabad Area Electricity Board, were transferred to IESCO.
12.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity purchased during the year 2003-04 was invoiced by the NTDC at the
provisional rate of Rs.3.49/kWh (same rate was charged during 2002-03). Adjustment,
if any, is to be made on finalization of rate and reflected in the accounts for the year
in which the rate is finalized. As transfer price of electricity from NTDC to DISCOs
has not been determined by NEPRA, the financial statements prepared on the basis
of provisional transfer price determined by WAPDA did not present true affairs
of the Company.
An overview of the financial statements of the Company in tabulated form is
given below:
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 17,614 18,837 20,627 23,012
Total Operating Cost 17,725 19,106 20,678 23,043
OPERATING PROFIT/(LOSS) (111) (269) (51) (31)
Other Income 732 277 298 355
Financial Charges 923 511 560 463
NET PROFIT/(LOSS) (302) (503) (313) (139) Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04.
IESCO sustained net loss during the last three years. However, the net loss of the
company decreased from the year 2001-02 to 2003-04. The main reasons of this decrease
in loss were as under:
i) Increase in sale revenue by 11.6% due to increase in consumption.
ii) Decrease in distribution losses i.e. 10.95% in 2002-03 to 10.9% in 2003-04.
iii) Decrease in financial charges by Rs.97 million (from Rs.560 million in 2002-03
to Rs.463 million in 2003-04) due to repayment of loans.
iv) Increase in other income by 19%.
Receivables
Position of trade debts during four years was as under: (Rs.in million)
2000-01 2001-02 2002-03 2003-04
3,733 3,042 2,695 2,960 Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
Out of the total amount of Rs.2,960 million, Rs.829 million were placed under doubtful
debts, which was 28% of receivables. It was very high and needs justification. Main reason
for receivables was non-recovery from private sector and permanently disconnected
consumers.
Distribution Losses
Distribution losses of IESCO during the year 2003-04 were as under:
Units Received 5,841 million
Units Billed 5,205 million
Units Lost 636 million
Percentage losses during the year 10.9%
Target for the year 10%
Losses above the target 0.9%
Monetary loss (5,841 x 0.9 / 100) x 3.73 Rs.196 million
The distribution losses marginally decreased from 10.95% in 2002-03 to 10.9% in 2003-
04 but remained above the target.
12.2 Expenditure of Rs.133.067 million on incomplete works started under
OECF/IBRD loans
The works under IBRD/OECF loans were to be completed with in the stipulated time as
given in work orders. Moreover, the installation charges were not to exceed 26% of
material cost as envisaged in Authority’s circular No. 905-22/GMO/BS/B-1
dated 21st June, 1989.
In IESCO, Islamabad an expenditure of Rs.133.067 million was incurred on IBRD/OECF
funded works during 1993-94 to 1997-98 but the same were appearing as works
in progress in the accounts for the year 2001-02. Due to non-completion of works,
investment of Rs.133.067 million had been blocked. This amount included Rs.45.079
million incurred on account of installation charges which was Rs.22.202 million more
than the prescribed limit of 26% of cost of material.
The matter was reported to management in August, 2003. It was replied that said works
were executed departmentally after close of IBRD/OECF loans and installation charges
exceeded the prescribed limit due to payment of consultancy charges. Documentary
evidence regarding completion of these works was not produced. The matter was brought
to the notice of Principal Accounting Officer (PAO) in December, 2003 followed by
reminders in January, April & July, 2004. It was also discussed in DAC meeting held on
19th March, 2005 wherein management promised to submit detailed reply alongwith
proof of energization/completion of works. The DAC directed to get the record alongwith
the completion records verified from Audit upto 30th March, 2005, but no detailed reply
and record was produced.
12.3 Blockage of Rs.2.409 million due to non-energization of 11 KV feeder and
loss of Rs.0.360 million due to theft of material
As per work order, 11 KV Soni Feeder valuing Rs2.409 million was to be constructed
and energized in 1995 to facilitate suburbs of Pindi Gheb. The feeder was completed in
1995 but could not be energized, as a result, not only the envisaged benefits were denied to
public but material worth Rs.0.360 million was also stolen from the site.
The matter was reported to the Company in December, 2003 and discussion was held
on 12th April, 2004 wherein enquiry report regarding stolen material was produced which
was not found satisfactory. The draft para was issued to the Ministry in June, 2004. It was
stated by the management that as per earlier inquiry, material valuing Rs.0.360 million was
actually stolen and the Sub Divisional Officer found involved in non-energizing the feeder,
was compulsorily retired. The DAC asked IESCO to certify actual energization and submit
self contained reply alongwith copy of findings of the committee apart from regularization of
loss from the competent authority. These directives have not been complied with by the
management.
12.4 Shortage of material valuing Rs.1.301 million
As per Audit Manual of WAPDA, Chapter 4, item 12.6.1, heavy shortages/excess should
be reported to Chief Engineer concerned for prompt investigation.
In Islamabad Electric Supply Company, shortage of material amounting to
Rs1.301 million was pointed out by the stock verifier during the year 2002-03 but no
progress towards investigation/recovery was intimated.
The matter was reported to the management in April, 2004. It was replied that a
Joint Examination Committee was being constituted which would sort out
exact shortage/surplus and further action would be taken in the light of report of
the Committee. No progress in this regard was intimated to audit. The draft para was
issued to the Ministry in July, 2004. It was discussed on 19th March, 2005 in DAC
meeting. The DAC directed the management that report of the Committee regarding
shortage and surplus of store be provided and amount recovered be got verified from
Audit in a week’s time. No record in this regard was produced to Audit till the
finalization of the report.
13. LAHORE ELECTRIC SUPPLY COMPANY
Lahore Electric Supply Company (LESCO) started its commercial operations as a Public
Limited Company in July, 1998. Its objectives are to purchase electricity from NTDC and
to sell it to the consumers, to plan and execute new works and to maintain distribution
system & power grid stations under its jurisdiction. All the properties, rights, assets,
obligations and liabilities of Lahore Area Electricity Board, were transferred to LESCO.
13.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity purchased during the year 2003-04 was invoiced by the NTDC at the
provisional rate of Rs.3.379/kWh (2003: Rs.3.317/kWh). Adjustment, if any, is to be
made on finalization of rate and reflected in the accounts for the year in which the rate is
finalized. As transfer price of electricity from NTDC to DISCOs, has not been
determined by NEPRA, the financial statements prepared on the basis of provisional
transfer price determined by WAPDA did not present true picture of the Company’s
financial performance.
An overview of the financial statements of the Company in tabulated form is
given below:
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 33,970 36,899 41,503 47,328
Total Operating Cost 34,801 37,944 42,729 47,311
Operating Profit/(Loss) (831) (1,045) (1,226) 18
Other Income 977 681 1,164 931
Financial Charges 1,026 484 731 467
Net Profit/(Loss) (880) (848) (793) 482
Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
The Company was sustaining loss since the financial year 2000-01 but earned a net profit
of Rs.482 million during the financial year 2003-04. The main reasons for conversion of
loss into profit during the financial year were as under:
i) Increase in sale revenue by 39% due to increase in consumption.
ii) Decrease in financial charges by 54% due to repayment of loans.
iii) Decrease in distribution losses from 14.7% to 14.1%.
Receivables
Position of trade debts during four years was as under: (Rs.in million)
2000-01 2001-02 2002-03 2003-04
5,535 5,676 6,208 5,896 Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
The reason for these receivables is non-recovery from private sector and permanently
disconnected consumers.
Out of the total amount of Rs.5,896 million, Rs.1,688 million was placed under doubtful
debts. This provision was 28.62% of receivables which was very high.
Evaluation of Assets
As per Chartered Accountant’s (M/s Ford Rhodes Sidat Hyder & Co) report on the
accounts pertaining to the year 2003-04 no reliable record was available with the
Company from which the Auditors could verify/check the value of Company’s fixed
assets and capital work-in-progress.
Distribution Losses
Distribution losses of LESCO during the year 2003-04 were as under:
Units Received 1,2921.88 million
Units Billed 11,100.92 million
Units Lost 1,820.96 million
Percentage losses during the year 14.1%
Target for the year 13.2%
Losses above the target 0.9%
Monetary loss (12921.88 x 0.9 / 100) x 3.73 433.78 million
The distribution losses decreased from 14.7% in 2002-03 to 14.1 % in 2003-04 but
remained above the target.
13.2 Blockage of Rs.30.238 million due to non-completion of works
The works under IBRD/OECF loans were to be completed within the stipulated time as
given in work orders. LESCO incurred an expenditure of Rs.30.238 million on various
works, out of OECF and IBRD loans. These loan accounts were closed in June, 1998 and
1999 respectively but the works remained incomplete. No efforts were made to complete
the pending works during last five years and thus the investment of Rs.30.238 million
was blocked and the planned benefits were also delayed.
The matter was reported and discussed with LESCO management in April, 2004. It was
replied that the case would be probed into and reply submitted within one month. No
response was received; therefore, the draft para was issued to the Ministry in
July, 2004. It was replied by the management in February, 2005 that material booked
against these works had physically been installed at site and most of the works had been
completed. No documentary evidence in respect of completion of the works and
energization was produced. The DAC, in its meeting on 19th March, 2005, directed the
management that completion reports drawn may be submitted to Audit by 30th March,
2005 but the same were not provided till the finalization of this report.
13.3 Accumulation of arrears of Rs.25.120 million against temporary connections
due to violation of rules
According to conditions of Schedule of Tariff “E”, the LESCO was required to supply
power after obtaining security equal to the anticipated supply and other miscellaneous
charges for the period of temporary connections which is a guarantee against loss. Due to
non-adherence to the conditions of schedule of tariff, the consumers used energy and left
the sites without paying the energy charges of Rs.25.120 million.
The matter was reported to the LESCO management in June, 2004 and discussed in
August, 2004. No satisfactory reply was given. The draft para was issued to the Ministry in
November, 2004 and was discussed in DAC meeting held on 19th March, 2005. It was
replied by the management that arrears against temporary connections had been reduced to
Rs.20.499 million after some recovery but original record in support of this small
percentage of recovery was not produced. DAC directed the management to get the
available record verified from Audit by 30th March, 2005 and make efforts to recover
the outstanding dues.
13.4 Loss of Rs.16.34 million due to theft of WAPDA material and its utilization in
Private Housing Schemes
The committees constituted in November, 1998, December, 1999, May & September,
2000 by WAPDA to conduct physical inspection of the electrification works carried out
by private housing schemes, detected that Authority’s stolen material of Rs16.34 million
was installed in four private housing schemes. Action was required to be taken against
the responsible persons as well as to make good the loss. No steps were taken despite
lapse of 3-6 years.
The matter was reported and discussed with the management in April, 2004. It was
responded that legal action was underway. The draft para was issued to the Ministry in
July, 2004. The management stated that the material installed in these housing schemes
was not WAPDA property and the same was purchased by the housing schemes from the
market. In DAC meeting held on 19th March, 2005 the management was directed to
produce documentary evidence in support of reply by 30th March, 2005 which was not
produced till the finalization of the report.
13.5 Non-recovery of Rs.14.614 million from Cable TV Network Operators
As per Authority’s instructions circulated vide No. 38271-304 dated 13th November 2002
rent @ Rs.40/pole/month was required to be recovered from T.V. Network companies.
In LESCO Lahore, 3 major companies as well as other Cable T.V. network operators were
using WAPDA poles/structures without paying rent. As per Authority’s instructions, rent
@ Rs.40/pole/month was required to be recovered from these companies which was not
recovered. Thus the Company sustained a loss of Rs.15.961 million.
In preliminary reply it was stated that necessary recovery in respect of three major
Companies had been affected. In case of remaining operators, recovery position would be
intimated to Audit later on. Recovery of Rs.1.282 million had been verified leaving a
balance of Rs.14.679 million.
The matter was reported to the Company’s management in July and August, 2003.
Reminders were issued in April and July, 2004 but no reply was received.
A draft para was issued to the PAO and was discussed in DAC meeting held on
19th March, 2005. DAC directed the management to get the record of the recovered
amount verified from Audit by 30th March, 2005 and make efforts to recover the balance
amount. Further recovery of Rs.64,800 was verified by Audit, leaving balance of
Rs.14.614 million.
13.6 Loss of Rs.14.535 million due to shortage of electrical material
Para 94 of WAPDA Accounting Manual provides that loss due to shortage of
material/equipment is required to be recovered from the responsible.
In LESCO Lahore, a physical survey of HT/LT lines was conducted by management and
it was found that electrical material valuing Rs.17.66 million was missing from various
locations. The matter was required to be investigated to fix responsibility and make good
the loss in the light of item No.13 of minutes of review meeting held on 19th April, 2003
under the chairmanship of Chief Executive Officer LESCO.
The matter was reported and discussed with LESCO management in April, 2004. It was
replied that action would be taken within one month. No action was intimated to audit
thus draft para was issued to the Ministry in July, 2004. The management replied in
March, 2005 that disciplinary action has been taken against the officials concerned and
accountal of missing material may be verified. DAC on 19th March, 2005 directed the
management to get the record verified. Record relating to recovery of Rs.3.125 million
was produced and verified leaving a balance of Rs.14.535 million.
13.7 Non-return of sub-station equipment and other material valuing
Rs.8.550 million
As per Abridged Condition No. 14, on disconnection of electric supply to a consumer all
electrical equipment and apparatus is required to be removed and returned to store.
In LESCO Lahore, 606 SCARP Tube-wells were permanently disconnected/denotified
by the Irrigation and Power Department. Twenty-four tubewells out of 606 were
reconnected and handed over to private consumers. The electrical equipment of 161
tube-wells was returned to store. Equipment of the remaining 421 tube-wells valuing
Rs.21.05 million was not returned to store/accounted for.
The matter was reported to the management in July, 2003. It was replied that final reply
will be given after verification of record. Draft para was issued to the Ministry in
October, 2003. Return of material relating to 86 tube wells amounting to Rs.4.300 million
was verified by Audit in September, 2004. The para was discussed in DAC meeting held
on 19th March, 2005 wherein DAC directed the management to get the remaining record
verified from Audit by 30th March, 2005. Record relating to 164 (47 + 117) tubewells
valuing Rs.8.200 million (Rs.2.35 million + Rs.5.85 million) was verified by Audit
but the record for the remaining amount of Rs.8.550 million was not produced
for verification.
13.8 Loss of Rs.4.517 million on account of missing material
Para 94 of WAPDA Accounting Manual provides that loss due to shortage of
material/equipment is required to be recovered from the responsible.
In LESCO, twenty 100 KVA and four 200 KVA sub-stations were drawn from store in
April and May, 2003 to be installed at the sites from where the sub-stations were reported
missing. Accordingly an enquiry was conducted and recovery of Rs3.479 million was
imposed upon Mr. Zahid Munir, Line Superintendent out of which an amount of
Rs.32,832 was recovered. The remaining sub-stations valuing Rs.1.071 million were to
be returned to store besides disciplinary action against the other responsible persons but
the same was not done.
The matter was reported and discussed with Company’s management in March, 2004.
It was replied that action would be taken within 4 weeks. No response was received
uptill 30th June, 2004. The draft para was issued to the Ministry in July, 2004.
In February, 2005, it was replied that recovery to the tune of Rs.0.896 million
had been imposed on the officials but no record was produced in support of reply
and recovery. DAC in its meeting on 19th March, 2005 directed the management to
get the recovery verified from Audit, but management remained unresponsive till
the finalization of this report.
13.9 Non-accountal of electrical material valuing Rs.3.369 million
According to Abridged Condition No. 14, on disconnection of electric supply to
a consumer all electrical equipment and apparatus is required to be removed and
returned to store.
In LESCO, twenty-three industrial connections were permanently disconnected on non-
payment of electricity charges. The sub-stations installed at these locations were required
to be returned to store after removal from sites as per procedure mentioned above. There
was no evidence on record to show that these materials costing Rs.3.369 million were
returned to store.
The matter was reported and discussed with Company’s management in December, 2003.
It was promised that detailed reply would be given within a fortnight but no progress
was intimated upto 30th June, 2004. The draft para was issued to the Ministry in
July, 2004 and was also discussed in DAC meeting held on 19th March, 2005 wherein
management explained their view point. The DAC directed the management to get
the recovery verified from Audit by 30th March, 2005 but no record was produced
till finalization of the report.
13.10 Undue benefit of Rs.3.124 million to the consumer on account of capital cost
In the light of General Manager (CS) WAPDA’s circular No. 863-80/DD(R&CP)/55716
dated 25th August, 2000, all categories of connections having applied load above 2,500 KW
but not exceeding 5,000 KW will be given through independent feeders drawn directly from
Grid Stations and consumers having applied load less than 2,500 KW can be grouped on
exclusive industrial feeder subject to the condition that technical parameters remain within
permissible limits.
In LESCO, three industrial units namely; M/s Sheikh Spinning, M/s Hira (Sharif) and
M/s Millac Food with sanctioned loads of 2,400 KW, 2,626 KW & 1,500 KW,
respectively were running on 11 KV Hira Feeder.
In September, 2002 M/s Sheikh Spinning applied for extension of load from 2,400 KW to
3,200 KW. Technically, extension in load was not possible from the existing feeder. The
sanction was granted in February, 2003 with the condition that the extension would be
accommodated on existing 11 KV Hira Feeder after shifting 2,626 KW load of M/s Hira
(Sharif) on separate new feeder. The cost of new feeder i.e. Rs.3.124 million was to be
paid by M/s Sheikh Spinning. Despite disagreement of Director Technical, a modification
was issued stating that extension of load should be accommodated on existing feeder
temporarily till such time M/s Millac Food uses full sanctioned load. Resultantly
Rs.3.124 million was not recovered from M/s Sheikh Spinning.
The matter was reported to LESCO management in June, 2004 and discussed in
August, 2004. It was replied that a committee had been constituted to see the matter
regarding contents of audit para. The draft para was reported to the Ministry in October,
2004. In February, 2005, the management reiterated its above reply. The para was
discussed in DAC meeting held on 19th March, 2005 wherein management stated that
demand notice had been issued to the consumer. No recovery was, however, affected.
13.11 Non-recovery of Rs.2.566 million from Cable T.V. network operator
As per Authority’s instructions circulated vide No. 38271-304 dated 13th November, 2002
rent @ Rs.40/pole/month was required to be recovered from T.V. Network companies.
In LESCO, it was noticed that M/s World Call (Pvt.) extended cable television network.
For this extension 4,583 poles were used without any agreement and sanction.
No recovery from October, 2002 to November, 2003 to the extent of Rs.2.566 million
(14 months x Rs.40 x 4583) was made.
The matter was reported to management on 25th March, 2004 and discussed on
27th April, 2004. It was stated that a comprehensive reply would be given within a
fortnight. No reply was furnished upto 30th June, 2004. The draft para was issued to the
Ministry in July, 2004 and the same was discussed in DAC meeting held on 19th March,
2005 wherein management stated that inquiry was at its final stage. The DAC directed to
finalize the inquiry at the earliest under intimation to audit. Report of inquiry committee
was not made available to audit till finalization of this report.
13.12 Undue benefit of Rs.1.718 million to the consumer on account of capital cost
According to Re-Connection Order policy issued vide No. 1357-74/59026 dated
11th October, 1999 if a disconnected consumer applies for reconnection after expiry of 3
years form the date of disconnection, no credit of the cost of removed material will be
afforded even if he had paid the cost of material at the time of obtaining connection. In such
cases the capital cost will be recovered treating Re-Connection Order as new connection.
Moreover, the consumer who switch over to private generation has no right for any relaxation
after expiry of five years on resorting to WAPDA system.
In LESCO load of M/s Mian Textile Mill Ltd. was extended from 650 KW to 2,340 KW in
June, 1991 through an existing 11 KV Manga-II feeder. The consumer deposited Rs.2.371
million on account of “cost of rehabilitation of Manga-II feeder”. In January, 1997 the
connection was disconnected due to shifting of the consumer from WAPDA system to
private generation.
After lapse of 5 years, the consumer applied for reconnection on WAPDA system.
Reconnection was allowed in May, 2002 and consumer was asked to pay Rs1.718 million
as capital cost for construction of new 11 KV Ravi Imran feeder. Later on the connection
was energized in lieu of deposit made for rehabilitation of Manga-II feeder in 1991. Thus,
company sustained a loss of Rs.1.718 million on account of non-recovery of capital cost.
The matter was reported and discussed with the Authority in August 2004. It was replied
that capital cost was waived off under the incentive package for CPPs (Captive Power
Producers) consumers. Reply was not acceptable as the incentive package for CPPs
consumers was announced on 18th June, 2002 whereas the said consumer was given
benefit of non-payment of capital cost on 13th June, 2002. The draft para was issued
to the Ministry in October, 2004. It was discussed in DAC meeting held on
19th March, 2005 wherein management stated that case for ex-post facto sanction from
Member (Power) was in process. The DAC pended the para with direction to get the
same at the earliest. The management could not produce ex-post facto sanction from the
competent authority till the finalization of this report.
14. MULTAN ELECTRIC POWER COMPANY
Multan Electric Power Company (MEPCO) started its commercial operations as a Public
Limited Company in July, 1998. Its objectives are to purchase electricity from NTDC and
to sell it to the consumers, to plan and execute new works and to maintain distribution
system and power grid stations under its jurisdiction. All the properties, rights, assets,
obligations and liabilities of Multan Area Electricity Board, were transferred to MEPCO.
14.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity purchased during the year i.e. 2003-04 was invoiced by the NTDC at the
provisional rate of Rs.2.891/kWh (2003: Rs.2.875/kWh). Adjustment, if any, is to be
made on finalization of rate and reflected in the accounts for the year in which the rate is
finalized. As transfer price of electricity from NTDC to DISCOs has not been determined
by NEPRA, the financial statements prepared on the basis of provisional transfer price
determined by WAPDA did not present true affairs of the Company.
An overview of the financial statements of the Company in tabulated form is
given below:
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 19,812 23,029 26,092 28,716
Total Operating Cost 20,026 23,677 26,028 28,620
Operating Profit/(Loss) (214) (648) 64 96
Other Income 649 445 492 572
Financial Charges 1,100 701 691 687
Net Profit/(Loss) (665) (904) (135) (19)
Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
The Company sustained a loss of Rs.19 million in the financial year 2003-04. It was
Rs.135 million during the financial year 2002-03 which was Rs.116 million less than the
previous year. The main reasons of decrease in loss were as under:
i) Total revenue increased by 10% as compared to the previous year, due to increase
in consumption and decrease in distribution losses (17.5%:2003 to 16.96%:
2004).
ii) Other income increased by 16.26% from Rs.492 million in 2002-03 to
Rs.572 million in 2003-04 due to increase in revenue from sale of scrap, profit on
bank deposits and other miscellaneous income.
Distribution Losses
Distribution losses of MEPCO during the year 2003-04 were as under:
Units Received 8,727.38 million
Units Billed 7,247.64 million
Units Lost 1,479.74 million
Percentage losses during the year 16.96%
Target for the year 16%
Losses above the target 0.92%
Monetary loss (8727.38 x 0.96 / 100) x 3.73 312.5 million
The distribution losses decreased considerably from 17.5% in 2002-03 to 16.96% in
2003-04 but remained above the target.
Receivables
Position of trade debts during the last four years was as under:
(Rs.in million)
2000-01 2001-02 2002-03 2003-04
1,952 3,289 3,700 3,675 Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
The reason for these receivables was slow pace of recovery from private sector and
permanently disconnected consumers. Efforts should be made to expedite recovery.
During 2003-04 an amount of Rs.1,211 million was placed under doubtful debts i.e. 33%
of receivables which was very high.
Evaluation of Assets
As per Chartered Accountant’s (M/s Riaz Ahmed & Co.) report on the accounts
pertaining to the year 2003-04 stipulation of Business Transfer Agreement (BTA) and
Supplementary Business Transfer Agreement (SBTA) regarding transfer of legal title of
the operating fixed assets to the company have not been complied with and consequently
the company has not issued shares in favour of WAPDA against purchase consideration.
Further the loan agreements have not been finalized with WAPDA, Government of
Pakistan and direct lenders in accordance with clause 10-A of SBTA, which are pre-
requisites for the effectiveness of SBTA.
14.2 Loss of Rs.45.978 million due to undue favour extended to Industrial
Consumer
In the light of General Manager (CS) WAPDA circular No.6511-6742/GMCS/DG
(R&CP)/55716 dated 31st August, 1994, industrial consumer with load over 5,000 KW
will provide his own grid station.
In Multan Electric Power Company Ltd., M/s Hashir Group of Industries established
three textile units in Muzaffargarh. Two units were being fed from independent 11 KV
feeders while third one was operated through self power generation. In March, 2001 a
third independent feeder for third unit was constructed to cater for the sanctioned load of
3,500 KW but it could not be energized. In February, 2002 the consumer put the load of
Unit-III on Feeder Hashir-I un-authorizedly, due to which technical line losses increased
causing a loss of Rs0.689 million as assessed by MEPCO for March and April, 2002.
The combined load of these three independent connections exceeded 5,000 KW and as
per prevailing tariff, power was to be supplied at consumer’s premises through
independent grid station to be constructed by the consumer. The consumer was favoured
as neither grid station was constructed by the consumer nor its cost i.e. Rs.31.578 million
was recovered from him.
The consumer purchased Mohib Textile Mills in October, 2000. The said premises was
defaulter for Rs.13.711 million. In terms of commitment and affidavit dated 11th January,
2001 and clarification given vide General Manager (CS) letter dated 11th December, 2002
all outstanding dues were recoverable from M/s Hashir Group, but the consumer failed to
deposit the outstanding dues. In this way the consumer was unduly benefited by
not recovering Rs.45.978 million.
The matter was reported to executive authorities in June, 2003 but no satisfactory response
was received. The draft para was issued to the Ministry in October, 2003. It was discussed in
DAC meeting held on 19th March, 2005 wherein Chief Executive Officer briefed the position
in detail. The DAC directed that revised reply with record be provided to Audit for
verification. The record produced by management showed an adjustment note dated
10th March, 2005 amounting to only Rs.0.349 million. No progress towards recovery of rest
of the amount was intimated.
14.3 Loss of Rs.29.325 million due to purchase of defective energy meters
In the light of para 5 of Purchase Order No. 5370/C.E/(PAD)/DPE-1/T-2728/3074
dated 10th December, 2002, inspection of the material was to be carried out at the site
of Factory by CE (MI), WAPDA. In MEPCO Multan, a Purchase Order dated 10th
December, 2002 valuing Rs.195.500 million was placed on M/s ESCORTS Pakistan Ltd.,
Lahore for the supply of 200,000 single phase energy meters, out of which 30,000 meters
were allocated to the Regional Store MEPCO, Multan. At the time of installation these
energy meters were reportedly found defective. On receipt of complaints of defective meters
from various corners the same were got tested at M&T Division which declared them
defective. The Chief Executive Officer ordered to return the whole lot to the manufacturer for
its replacement which was not done by the Manager Material Management MEPCO, Multan.
Resultantly, the Authority sustained a loss of Rs.29.325 million.
The case was reported to the Authority in April, 2004. It was replied that the matter was
under investigation at Authority level and progress would be intimated to audit but no
reply was received. The draft para was issued to the Ministry in June, 2004. It was replied
in February, 2005 that only 4,221 meters had been received after rectification. The para
was also discussed in the DAC held on 19th March, 2005. In view of explanation given by
the management, the DAC directed that record be provided to Audit for verification
regarding number of meters received, found defective, repaired and in balance but no
record was produced till the finalization of this report.
14.4 Blockage of funds to the tune of Rs.23.653 million
Para 5(a) of memorandum issued by WAPDA vide No. C/78/13384-584 dated 17th & 19th
January, 1978 denotes that purchases should be made only of such items and in such
quantities as are required for a specific work. In no case should these purchases be made
for storing an item for indefinite period. In MEPCO, material valuing Rs.23.653 million
was lying un-utilized/ un-issued since 1995-2002. Non-utilization of material for such a
long period clearly indicated that the procurement of material was made without
assessing the actual requirements of field formations which resulted in blockage of
Company’s funds.
The matter was reported to the management in September, 2003. It was replied that
Manager Material Management had already been requested for early allocation of
material to the needy formations and it would be pursued on top priority. Reply was not
accepted in the absence of documentary proof.
The draft para was issued to the Ministry in June, 2004 and it was replied in
March, 2005 that material has been issued to field stores for its further consumption by
field formations. It was discussed in DAC meeting held on 19th March, 2005. In the light
of explanation given, the DAC directed that material used so far may be got verified
from audit and circular/letter be issued to other DISCOs and to its own formations
to inquire into their need. No progress in the utilization of the store was received till the
finalization of this report.
15. PESHAWAR ELECTRIC SUPPLY COMPANY
Peshawar Electric Supply Company (PESCO) started its commercial operations as a
Public Limited Company in July, 1998. Its objectives are to purchase electricity from
NTDC and to sell it to the consumers, to plan and execute new works and to maintain
distribution system & power grid stations under its jurisdiction. All the properties, rights,
assets, obligations and liabilities of Peshawar Area Electricity Board including FATA
were transferred to PESCO. However, in July, 2002 WAPDA decided to transfer the
business of FATA circle to Tribal Area Electric Supply Company Limited (TESCO)
which became effective in July, 2003.
15.1 OVERVIEW OF FINANCIAL STATEMENTS
The electricity purchased during the year 2003-04 has been invoiced by the NTDC at
the provisional rate of Rs.2.680/kWh (2003: Rs.2.899/kWh). Adjustment, if any, is to
be made on finalization of rate and reflected in the accounts for the year in which the rate
is finalized. As transfer price for electricity from NTDC to DISCOs, has not been
determined by NEPRA the financial statements prepared on the basis of provisional
transfer price determined by WAPDA did not present true financial position of
the Company.
An overview of the financial statements of the Company is given below:
(Rs.in million)
* 2000-01 * 2001-02 # 2002-03 2003-04
Total Revenue 24,133 28,272 19,178 21,871
Total Operating Cost 22,866 30,549 20,134 27,190
Operating Profit/(Loss) 1,267 (2,277) (956) (5,319)
Other Income 201 355 311 386
Financial Charges 1,961 652 513 518
Net Profit/(Loss) (493) (2,574) (1,158) (5,451) Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
* included revenue/cost relating to TESCO
# excluded revenue/cost relating to TESCO for comparison purpose
The Company sustained a loss of Rs.5,451 million in the year 2003-04 which was
Rs.4,293 million more than the previous year loss of Rs.1,158 million. The main reasons
of increase in loss were as under:
i) Provision of Rs.2,679 million for doubtful debts in profit & loss account due to
change in policy from arbitrary rate of gross billing to age analysis of trade debts.
ii) Increase in other operating cost by Rs.1,511 million due to change in policy
regarding employees’ retirement benefits and increase in depreciation.
Distribution Losses
Distribution losses of PESCO during the year 2003-04 were as under:
Units Received 7,741.840 million
Units Billed 5,310.150 million
Units Lost 2,431.690 million
Percentage losses during the year 31.41%
Target for the year 27.6%
Losses above the target 3.81%
Monetary loss (7741.84 x 3.81 / 100) x 3.73 Rs.1,100 million
Distribution losses slightly decreased from 32.03% in 2002-03 to 31.41% in 2003-04 but
remained above the target.
Receivables
Position of energy debts during the last four years was as under: (Rs.in million)
* 2000-01 * 2001-02 # 2002-03 # 2003-04
10,887 22,711 7,829 8,420 Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
* include receivables relating to FATA
# exclude receivables relating to TESCO for comparison
Main reason for these receivables was non-recovery from private & public sector and
permanently disconnected consumers.
Out of total amount of Rs.8,420 million, (excluding amount of FATA) Rs.3,508 million
were placed under doubtful debts i.e. 41.66% of receivables which was very high
percentage and needs justification.
Evaluation of Assets
As per Chartered Accountant’s (M/s M. Yousaf Adil Saleem & Co.) report on the
accounts pertaining to the year 2003-04 no reliable record was available with the
Company from which the Auditors could have verified/physically checked the value of
Company’s fixed assets and capital work-in-progress.
15.2 Non-completion of works-in-progress amounting to Rs.2385.282 million
The works under IBRD/OECF loans were to be completed within the stipulated time as
given in work orders. In PESCO Peshawar, Works-In-Progress (WIP) amounting to
Rs.4,675.282 million were appearing in the Financial Statements. The amount had
accumulated over the years since 1990-91 which also included abandoned works carried
under Tameer-e-Wattan and People Works Programmes. In the preliminary reply it was
stated that there were genuine reasons like non-availability of material, ban on Job
Transfer Note (where material of one work had already been utilized on other works),
termination of loans and other departmental difficulties.
The matter was reported to management in August, 2003. It was replied that committee
would be constituted to analyse the Works in Progress with reference to material drawn and
installed but no report in this regard was provided. On the issuance of Draft Para in
November, 2003 the record relating to capitalization of works amounting to Rs.2,290 million
was produced and verified by audit leaving a balance of Rs.2,385.282 million. The para was
discussed in the DAC meeting held on 19th March, 2005. The DAC directed the
management to produce documentary evidence regarding completion of remaining works, if
any, but no reply was received.
15.3 Recurring loss of Rs.251.137 million due to theft of electricity
Authority has devised a procedure for billing/regularization under code 888 for
unregistered consumers using direct hooks.
In PESCO, an amount of Rs.251.137 million was billed to such consumers in December,
2002 but neither recovery was effected nor the connections regularized, resulting in
recurring loss to the Company.
The issue was reported and discussed with management in August, 2003. It was stated
that information regarding number of consumers, FIRs lodged and recovery made on this
account was awaited from concerned circle offices. It was further replied in February,
2004 that the instructions and procedure were not applicable in Tribal Areas. However,
after allocating account numbers, the consumers were charged for recovery. No
information was given to audit about the recovery despite issuance of reminders in April
and July, 2004. The para was discussed in DAC meeting held on 19th March, 2005
wherein Chief Executive Officer explained the position in detail. Discussions in the DAC
meeting remained inconclusive and the Committee referred the matter to PAC for further
deliberation.
15.4 Non-disposal of material valuing Rs.12.12 million
In the light of Chapter-1 (Para 1.1 to 1.4.2) of WAPDA Purchase and Disposal Procedure
unserviceable material is required to be auctioned. In PESCO unserviceable
material/equipment worth Rs12.12 million was lying in various formations which was
required to be auctioned but the same was not done. Non-disposal of material resulted
into blockage of funds.
The matter was reported to PESCO in March, 2004. It was replied that the material worth
Rs1.299 million has been disposed off, record will be produced for verification and the
remaining material will be auctioned under intimation to audit. No progress in this regard
was intimated. The draft para was issued to Principal Accounting Officer in February,
2005. It was discussed in the DAC meeting held on 19th March, 2005. DAC directed the
management to submit a detailed reply and get it verified from Audit by 30th March, 2005
but the management did not respond.
15.5 Non-receipt of security deposits and cost of equipment due to
un-authorised extension in load - Rs.11.166 million
Under the provisions of Abridged Condition 6 for Connections, in case of any addition
or alteration made in the existing installation without approval of the competent authority, the
supply of such consumer was required to be disconnected without any prior notice.
In PESCO, 108 industries were consuming electricity load beyond sanctioned limit as
established in billing record, M&T reports/Surveillance reports in violation of the instructions
mentioned above. The field formations neither disconnected nor followed the proper
procedure for providing load extensions as a result of which the Company was deprived of
Rs.15.396 million on account of security deposit and cost of equipment that would have been
charged to consumers if the additional equipment was installed.
The matter was reported and discussed with management in August, 2003, it was stated
that notices would be issued to the consumers for regularization of illegal extension of
loads and the amount recovered would be got verified. No further response from the
management was received. The issue was reported to Principal Accounting Officer in
November, 2003. It was replied in February, 2004 that notices have been issued to the
consumers. The para was discussed in the DAC meeting held on 19th March, 2005 and
the management was asked to provide record for verification. Recovery of Rs.4.230
million was verified leaving a balance of Rs.11.166 million.
15.6 Less recovery of Rs.3.687 million from the cable network operators
As per Authority’s instructions circulated vide No. 38271-304 dated 13th November,
2002 rent @ Rs.40/pole/month was required to be recovered from T.V. Network
companies. In PESCO Peshawar, Surveillance Directorate pointed out that in a
sub-division, 6 Cable Network Companies had been charged pole rent for 491 poles
as per their declaration while 2,022 poles were actually in their use. Thus Rs.3.959 million
was less recovered.
The matter was reported and discussed with authorities in August, 2003. It was stated that
the field formations had been instructed to make the complete survey and recover the
amount, but no progress was made in this regard. Draft para was issued to the Ministry in
October, 2003. It was replied in January, 2004 that the recovery has been affected but
recoveries of Rs.0.272 million could only be verified. The para was discussed in DAC
meeting held on 19th March, 2005 wherein the management replied that a committee was
constituted to reconcile the figures of poles. DAC directed to supply a copy of Inquiry
Committee’s re-conciliation report regarding number of poles and get the original record
verified upto 30th March, 2005. The management failed to produce the original record till
the finalization of Report.
15.7 Non-existence of 11 KV feeder causing loss of Rs.2.549 million
After completion of construction work in accordance with the work order, the feeder was to
be handed over to Operation Wing for energization. In PESCO, bifurcation of 11 KV
Ismailia Feeder, with length of 6.77 KM was carried out at a cost of Rs.1.605 million. The
completion report was submitted in June, 1998 but it was not handed over to Operation
Wing. Audit could not find existence of conductor and other allied material at site
on physical verification. As such the expenditure of Rs.1.605 million shown to be incurred
on the construction of feeder was fictitious. Thus the Company was put to loss of
Rs.2.549 million (capital cost Rs.1.605 million + Rs.0.944 million envisaged benefits of
reduction in energy loss).
The matter was brought to the notice of management in August, 2003 followed by discussion
and it was decided that an enquiry committee would be constituted to investigate the matter
but no report was received. Ultimately the matter was referred to the Ministry in
November, 2003. It was discussed in DAC meeting held on 19th March, 2005. DAC directed
that a copy of inquiry report alongwith order of the competent authority and recovery
position/record be provided to Audit for verification by 30th March, 2005 but no response
was received.
15.8 Loss of Rs.1.26 million due to shortage of material
Para 94 of WAPDA Accounting Manual provides that loss due to shortage of
material/equipment is required to be recovered from the responsibles.
In PESCO, material valuing Rs.1.26 million was found short in various formations. The
shortage was required to be made good from the personnel held responsible but the same was
not done resulting into loss.
The matter was reported to the management in March and April, 2004 and discussed in
May, 2004 but no satisfactory reply was given. The draft para was issued to the Ministry in
September, 2004. It was replied that in one case matter would be investigated and in the
other, recovery position would be intimated to audit. DAC directed the management on 19th
March, 2005 to supply the findings of Enquiry Committee and get the recovery verified from
audit upto 30th March, 2005 but no record was produced.
16. QUETTA ELECTRIC SUPPLY COMPANY
Quetta Electric Supply Company (QESCO) started its commercial operations as a Public
Limited Company on July, 1998. Its objectives are to purchase electricity from NTDC
and to sell it to the consumers, to plan and execute new works and to maintain
distribution system & power grid stations under its jurisdiction. In addition, the Company
generates electricity through small thermal plants. All the properties, rights, assets,
obligations and liabilities of Quetta Area Electricity Board, were transferred to QESCO.
16.1 OVERVIEW OF FINANCIAL STATEMENTS
The Company purchases electricity from NTDC and Iran Power Generation and
Transmission Management Organization (IPGTMO). The rate applied for electricity
purchased during the year from IPGTMO was US $ 0.03 per unit and was valid for three
years. However, the purchase from NTDC during the year 2003-04 has been invoiced at
the provisional rate of Rs.1.68/kWh (2003: Rs.2.116/kWh). Adjustment is to be made on
finalization of rate and will be reflected in the accounts for the year in which the rate is
finalized. As transfer price of electricity from NTDC to DISCOs has not been determined
by NEPRA, the financial statements prepared on the basis of provisional transfer price
determined by WAPDA did not present true affairs of the Company.
An overview of the financial statements of the Company is given below: (Rs.in million)
2000-01 2001-02 2002-03 2003-04
Total Revenue 5,461 6,885 8,760 10,193
Total Operating Cost 5,929 8,314 11,668 11,197
OPERATING PROFIT/(LOSS) (468) (1,429) (2,908) (1,004)
Other Income 157 286 296 121
Financial Charges 1,002 245 235 231
NET PROFIT/(LOSS) (1,313) (1,388) (2,847) (1,114) Source: Financial Statements of the Company for the financial years 2000-01 to 2003-04
The net loss increased during the financial years from 2000-01 to 2002-03. However, the
Company sustained net loss of Rs.1,114 million in 2003-04 which was Rs.1,733 million
lesser than that of previous year. The main reasons of decrease in loss were as under:
i) Decrease in distribution losses from 18.1% in 2002-03 to 16% in 2003-04.
ii) Total revenue increased by 16.35% as compared to previous year due to increase
in power consumption.
iii) Cost of electricity decreased due to lesser tariff rate applied by NTDC.
iv) Due to increased purchase of electricity from IPGTMO Iran, self generation was
decreased from 65 million unit in 2002-03 to only 0.4 million units during
2003-04. This resulted in saving of Rs.646 million.
Distribution Losses
Distribution losses of QESCO during the year 2003-04 were as under:
Units Received 3885.33 million
Units Billed 3262.83 million
Units Lost 922.50 million
Actual losses during the year 16%
Target for the year 17%
Losses above the target Nil
Distribution losses of QESCO decreased during the year 2003-04 i.e 16.0% as compared
to 18.1% in the year 2002-03.
Receivables
Position of trade debts during four years was as under: (Rs.in million)
2000-01 2001-02 2002-03 2003-04
2,202 3,691 2,880 3,114 Source: Progress report of the office of G.M. Operation & Balance Sheet for the year 2003-04
Reasons for increase in the receivables was failure of Company to recover its dues from
public/private sectors and permanently disconnected consumers Against recoverables of
Rs.3,114 million provision for doubtful debts of Rs.1,372 million was made which is
very high i.e. 44% of the receivables and needs justification.
Evaluation of Assets
As per Chartered Accountant’s (M/s Taseer Hadi Khalid & Co.) report on the accounts
pertaining to the year 2003-04 no reliable record was available with the Company from
where the Auditors could verify/check the value of Company’s fixed assets and capital
work-in-progress.
16.2 Loss of Rs.22.323 million due to incorrect calculation of MDI reading
In QESCO two connections of B-2 category were charged less number of units due to
incorrect calculation of MDI reading, which resulted in a loss of Rs.22.323 million.
The matter was brought to the notice of management in January, 2004 and discussed in
May, 2004. It was informed that a committee had been constituted to check the MDI
meters. Findings of the committee were not provided to audit. The draft para was issued
to the Ministry in July, 2004. DAC, in its meeting held on 19th March, 2005, directed
the QESCO management to certify that reading formula was correct and also reconcile
the calculations with audit by 30th March, 2005. No response was received till the
finalization of this report.
16.3 Credit of Rs.19.078 million without adjusting the units
As laid down in CP-52 the adjustment of energy bills comprises of credit/debit of amount
and corresponding units. Accounts record of Chief Executive Officer, QESCO, Quetta for
the period July, 2002 to June, 2003 revealed that heavy amount of Rs.19.078 million, as
mentioned below, had been credited to the consumer accounts without adjusting units in
violation of the laid down commercial procedure.
Sr.
No.
Name of Circle Amount adjusted without
involving units
(Rs.in million)
1. Central Circle 6.090
2. Northern Circle 9.532
3 Southern Circle 3.456
Total 19.078
The matter was brought to the notice of management in April, 2004 and discussed in a
meeting held in June, 2004. It was promised that the latest position of the case would be
intimated, but no information was provided. The draft para was issued to the Ministry in
August, 2004. It was replied in February, 2005 that action was taken according to the
Authority’s instructions but no documentary evidence was provided in support of the
contention. The para was discussed in DAC meeting held on 19th March, 2005 wherein
Member (Power) explained the position in detail. The DAC directed the management that
a revised write up with relevant record be provided to Audit by 30th March, 2005, but the
directives were not complied with.
16.4 Blockage of funds to the tune of Rs.8.171 million due to non utilization
of material
Para 5(a) of memorandum issued by WAPDA vide No. C/78/13384-584 dated 17th & 19th
January, 1978 denotes that purchases should be made only of such items and in such
quantities as are required for a specific work. In no case should these purchases be made
for storing an item for indefinite period. Material valuing Rs.8.171 million was lying in
the regional store since 2002 resulting in blockage of funds in QESCO.
The matter was brought to the notice of management in April, 2004 and was discussed in
a meeting on 1st June, 2004. It was replied that latest status would be intimated within a
weeks time, but no reply was received and the draft para was issued to the Ministry in
July, 2004. The management replied in February, 2005 that some of the material had
been utilized and for the remaining material, other DISCOs had been asked to give their
requirements. The matter was discussed in DAC meeting held on 19th March, 2005
wherein Chief Executive Officer explained that material was still useable. The DAC
directed that the record regarding material issued and utilized be provided to Audit and
balance material be issued to other DISCOs. No progress in this regard was received till
the finalization of this report.
16.5 Non-removal of dismantled material worth Rs.2.97 million
As provided in Abridged Condition No. 14, the material of defaulting consumers, is required
to be removed as a result of execution of EROs for returning to store. In QESCO, electricity
of consumers was permanently disconnected but the electrical material valuing
Rs.2.97 million was not removed from their premises which led to theft of the material as
detailed below:
The matter was brought to the notice of the management in December, 2003 and was
discussed in May, 2004. It was replied that the formations concerned had been directed to
furnish a detailed/comprehensive reply within a week. When no response was received
from the management, draft para was issued to the Ministry in July, 2004. It was replied
in February, 2005 that due to non-payment of electricity bills, DCOs/EROs were issued
but no material was available on site as the people had migrated to other places due to
drought during previous years. Reply was not acceptable. Had the equipment been
removed in time, the loss would have been avoided. DAC, in its meeting held on
19th March, 2005, directed that report of Inquiry Committee already constituted for the
purpose be provided to Audit for verification by 30th March, 2005. DAC directives were
not complied with.
Sr.
No.
Advance
Para No.
Name of formation Material Quantity
No. of
Consumers
Amount
(Rs)
1. 18 &
18a,&
21(395)
i) XEN (E) Sibi
ii) XEN (E) Loralai
iii) SDO (E) Sibi
i) Single Phase meter
ii) P.V.C
iii) Meter Board
-do-
50 KVA Transformer
1 No.
20 Meters
1 No.
-do-
1 No.
588 Nos
107 Nos.
1 No.
Rs1,200/-
Rs400/-
Rs100/-
1700x588=0.999 (M)
1700x107=0.182 (M)
0.006x1 =0.006 (M)
2. 3(385) XEN (E) Sibi i) 25 KVA Transformer
ii) 50 KVA Transformer
iii) 36 Meters
29 Nos.
7 Nos.
36 Nos.
29 Nos.
7 Nos.
36 Nos.
42000 x29=1.218(M)
62000x7 = 0.434(M)
3650x36 = 0.131(M)
Total 2.97 (Million)
COMMENTS ON INTERNAL CONTROLS
Internal controls are all measures taken by an organization for the purpose of (1)
protecting its resources against waste, fraud, or inefficient use; (2) ensuring the reliability
of accounting data; (3) securing compliance with management’s policies; and (4)
evaluating the performance of all employees, managers and departments within the
organization.
Every large organization has an internal auditing system. The objectives of the internal
auditors are to monitor and improve the system of internal control. Internal auditors test
and evaluate both accounting and administrative controls in all areas of the organization
and prepare reports for the top management based on their findings and
recommendations.
WAPDA is responsible for the unified and coordinated development of water and power
resources of Pakistan and is one of the largest users of public funds. Its operations call for
a high degree of financial discipline to ensure regularity in its transactions. To safe-guard
the misuse of funds and eliminate the chances of financial irregularities, WAPDA has
introduced an internal control system as discussed below. Following internal checks are
being exercised by WAPDA/Corporate entities.
i) Policies/Plans
Formulation of all policies, rules and planning is being made at Authority level
for implementation in WAPDA and its corporate entities.
ii) Management Information System
Management Information System (MIS) exists in all the formations. However,
in certain areas the same is not adequate.
iii) Security and Maintenance of Assets
A system of custody, supervision & maintenance as well as security of assets is
available. An operating procedure for computerized inventory control system has
been implemented. Despite existence of an elaborate inventory and security
system a number of theft cases were noticed and had been reported.
iv) Monitoring and Surveillance
Monitoring and Surveillance teams at Authority/Company as well as circle level
are working for detecting technical and administrative faults/lapses resulting into
less generation of revenue. The performance of monitoring & surveillance teams
can play a vital role in enhancing the revenue.
WAPDA INTERNAL AUDIT
WAPDA & its corporate companies have their own set up of Internal Audit which
consists of a Chief Auditor assisted by five Deputy Chief Auditors at Head Quarter, eight
Regional Deputy Chief Auditors, thirty Senior Audit Officers and 40 Audit Officers.
Number of Audit Parties/Local Audit Parties exceeds 180. Following internal audit
system has been implemented by WAPDA/Corporate entities.
i) Divisional Accountant is the primary auditor who exercises pre-audit of 100%
financial transactions.
ii) The bill/invoice passed by the Divisional Accountant is further pre-audited by the
higher officers i.e. Budget & Accounts Officer (B&AO)/ Sr. B&AO/Director
Accounts etc. After scrutiny a claim becomes eligible for payment.
iii) Internal Audit is responsible to carry out an independent 100% review
of Consumer Accounts (100% billing except being charged under A-I which are
test audited) being maintained in XEN/RO to certify the correctness of electricity
billing. Remaining accounts of the formations are test audited.
iv) The projects at which Government Concurrent Audit Offices exist the accounts of
the same are not checked by the Internal Audit Wing of WAPDA.
The objective of Internal Controls is to obviate chances of financial irregularities.
Despite the presence of a large qualified set up of Account and Internal Audit in
WAPDA, following irregularities of common occurrence have been pointed out in this
Audit Report.
i) In WAPDA, system for custody, supervision, maintenance and security of assets
exists. In spite of this, cases of theft, misappropriation and mismanagement of
assets have been reported. It shows either there is some flaw in the existing
internal control system or system is not being implemented in an efficient manner
to protect and maintain the WAPDA assets.
ii) Contract management is yet another area which needs attention of the
management. Due to lack of proper implementation of financial controls,
important clauses of agreements are not enforced leading to financial loss to
the organization.
iii) Unsatisfactory financial performance of the companies, non-recovery of huge
amount of receivables from private consumers and violation of financial rules are
results of weak internal controls and lack of efficient financial management.
iv) The repetition of such type of irregularities can only be stopped if Internal Control
mechanism, already existing in WAPDA, is further strengthened and made more
effective.
Annexure-A
MESSENGER/UMS
,. ~.1(3)/2015-PAC-ll 24th
POINTS OF THE MEETING OF COMMITTEE-II loth PERTAINING TO M/O WATER
REPORTS/SPECIAL
loth FAarch,
M/o
M/o
99) PW
(INHAMUL S.O/Secretary
along
(CA&E), 3rd Secretary/Director (BI),
? -. - i . .
'.
S.O/Secretary
MOST IMMEDIATE BY SPECIAL
NATIONAL ASSEMBLY SECRETARIAT (Public Accounts Committee Wing)
Islamabad, the April, 2015
Subject: - ACTIONABLE ARISING OUT FROM DISCUSSION SUB-OF PAC HELD ON MARCH. 2015.
AND POWER ON THE APPROPRIATION ACCOUNTS, AUDIT AUDIT REPORTS FOR THE YEAR 2003-04.
Please find enclosed herewith Actionable Points arising out from discussion of the
Meeting of the Sub-Committee-ll of the Public Accounts Committee meeting held on
2015, in Committee Room No. 2, Parliament House, Islamabad pertaining to the Water and
Power for information and further necessary action please.
2. Kindly acknowledge the receipt.
The Secretary, Water and Power,
Government of Pakistan, Islamabad.
HAQKHAN) Sub-Committee-ll
Ph:9201781
2.
Copy with a copy of subiect Actionable Points is forwarded for information and necessary action to:-
1. The Deputy Auditor General (FAO), Audit House, Constitution Avenue, Islamabad. The Director General Audit (FG), Benevolent Fund Building, near Zero Point, Islamabad. The Director General Audit WAPDA, Sunny View Estate, Kashmir Road, Lahore.
4. The Director General Audit Floor, Audit complex Building, Edward Road, Lahore. 5. The Joint Finance Division, Islamabad. 6. The Section Officer (PAC imp), N.A. Secretariat, Islamabad.
.., . . . , .. . , . i .
I. . . . . . (INHAMUL HAQ KHAN)
Sub-Committee-ll
Draft Actionable Points
Q National Assemblv Secretariat
JPAC WING) -- C
t-
Actionable points arising from the discussion of meeting of PAC's Sub-Committee-ll held on loth March,
2015 while examining Appropriation Accounts/Audit Reports/Special Audit Reports for the year 2003-04
of Ministry of Water and Power are given below:
Audi t Report 2003-04 MINISTRY OF WATER AND POWER
DIRECTOR GENERAL AUDIT (FG), ISLAMABAD.
1. PARA-19.1(PAGE 421) AR 2003-04
i' 1 IRREGULAR EXPENDITURE ON ACCOUNT OF HOUSE RENT CEILING PAID TO OFFICERS/STAFF -RS 5.120 MILLION(Rs.3.781 million)
Audit pointed out that according t o part V of Pakistan Allocation Rules 1993, Government may
hire a private hoqse and allot it to a Government servant. The rental ceiling is paid to the owner of the
hired house. But IRSA, instead of requisitioning private houses and allotting those.ty.its officers/offidals,
paid an amount of Rs.5,123,040 as house rent ceiling to i t s officers/officials along with their salary without
concurrence of Finance Division and Housing and Works Division.
PA0 Informed the committee that IRSA was established under lndus River System Authority Act
1992 and the decision of the Authority t o pay the House acquisition ceiling as per entitlement of
officer/official as a part of monthly salary was justified under Section 12(2) read with section 22(1) of the
said Act.
ii) WRA-19.3(PAGE 422-423) AR 2003-04
IRSA-RS.2.020 MILLION
Audit briefed the Committee about the para and stated that according to Rule 12 of Rules of
Business, no Division can issue any orders which will directly or indirectly affect the finances of the
Federation without consultation with the Finance Division. But in contravention uf.t6is rule, 1 ~ ~ ~ ' a l l o h e d
to i t s employees, including members, medical allowance, conveyance allowance and IRSA allowance at
@20%, 15% and 20% of running basic pay respectively. Furthermore, in terms of Rule 4 of the lndus River
System Authority (Chairman and Members Conditions of Service) Rules, 2000 framed under Section 2 1 of