  • 1. City of Hudson Atterbury Boulevard Bridge Replacement Project

2. City of HudsonAtterbury Boulevard Bridge Replacement Project

      • Project Team:
    • GPD Group - Design Engineer
      • Mark Grossman, PE Project Manager
    • City of Hudson Owner
      • Chris Papp, PE Project Manager
    • QCI Project Representation
      • Courtney Norris, PE - Project Manager
    • Campbell Construction Contractor
      • Mark Streb Project Manager
      • Monte King - Superintendant
        • Barbicas (Asphalt) DBE (6%)

3. Atterbury Boulevard Bridge Replacement Project

  • Ohio Map:

4. City of HudsonAtterbury Boulevard Bridge Replacement Project

  • City Map:

5. City of HudsonAtterbury Boulevard Bridge Replacement Project

  • Aerial of Site:

6. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Project History:
  • Existing bridge experienced substantial settlement of the south abutment 2004
  • Interim repairs to foundations were completed in 2004
  • Municipal Bridge Funds awarded in late 2005
  • GPD Group selected as Design Consultant in mid 2007
  • Project Bid in May 2009
  • Project Complete in November 2009

7. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Non-Traditional LPA Project
  • Bridge Replacement
    • H-pile Foundation
    • Precast Reinforced Concrete Arch
    • Form Liners
    • Decorative Railing
  • Roadway Reconstruction Approach Work
  • Waterline & Utility Relocation
  • Pavement Drainage and Storm Sewer Work

Project Description 8. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Bridge Site Plan View:

9. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • BEFORE IMPROVEMENT:

10. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • AFTER IMPROVEMENT:

11. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • H-Pile Foundation:

12. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Precast Reinforced Concrete Arch

13. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Decorative Railing

14. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Construction Schedule:
    • Started - July 2009
    • Completed - November 2009

15. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Construction Photos

16. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Construction Photos

17. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Construction Photos

18. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • Project Construction Costs:
    • Construction Est. $ 691,000
    • Project Bid $ 607,661
    • Change Orders $5,281(0.9%)
    • Final Const. Cost $ 600,036
    • Total Project Cost $ 786,832
  • Funding Break Down
    • ODOT Bridge Funds $ 433,000 (55.0%)
    • OPWC Loan $ 143,714 (18.3%)
    • City Funds $ 210,118 (26.7%)

19. City of Hudson Atterbury Boulevard Bridge Replacement Project

  • On behalf of the City of Hudson