ATTACHMENT 5 TO ITEM 10 - cambridge.wa.gov.au
Transcript of ATTACHMENT 5 TO ITEM 10 - cambridge.wa.gov.au
COUNCIL MEETING
28 SEPTEMBER 2021
ATTACHMENT 5 TO ITEM 10.2
DIRECTOR OF INFRASTRUCTURE & WORKS REGISTER OF CURRENT PROJECTS
INFRASTRUCTURE AND WORKS
The Infrastructure and Works Division is responsible for maintaining and improving the Town’s assets such as parks, roads, footpaths, buildings, and trees. This also includes the operation of the kerbside waste collection service, verge bulk waste programs, illegal dumping investigations, coordination of the mattress collections and coordination of the various community waste education programs. SERVICE STANDARD The Infrastructure and Works administration team takes a large number of service requests each year and occasionally receive both positive and negative feedback. The graph below represents a summary of various complaints and compliments received. In future, data collection will be broadened to assist the team define service standards and performance targets.
0123456789
November December January February March April June July August
Service Compliments & Complaints 2021
Complaint Compliment
CAPITAL WORKS PROGRAM 20/21
The Town's capital works projects are defined as building and engineering works that create an asset, as well as constructing or installing facilities and fixtures associated with, and forming an integral part of those works. This definition focuses on works where construction activity is required in order to create an asset. Such works would typically include constructing buildings and roads, structures or mechanical installations, upgrading or extending existing buildings, and major road works to upgrade existing roads.
PROJECT NAME RISK SCHEDULED START
SCHEDULED FINISH
OVERALL STATUS
ASSETS/BUILDING
Lake Monger Community Shed Internal Fit Out June 21 November 21 Scheduled
Admin Building - Furniture Upgrade July 21 May 22 Scheduled
City Beach Oval Pavilion - Painting March 22 April 22 Scheduled Alderbury Sportsground Pavilion - Replace Toilets
and Change 3 - Medium May 21 February 22 Works in Progress
DAIP Program 3 - Medium July 21 June 22 Design Sydney Cheek Pavilion - Upgrade Toilets & Change
rooms 3 - Medium July 21 June 22 Design
Sydney Cheek Pavilion - Upgrade Toilets & Change rooms 3 - Medium July 21 June 22 Design
City Beach Civic Centre - Treat corrosion of roof trusses January 22 February 22 Scheduled
McLean Park Toilets & Change room - Painting January 22 February 22 Scheduled
Perry Lakes Reserve Toilets - Steel framing January 22 February 22 Scheduled
Wembley Sports Park - Main change room floor September 21 October 21 Scheduled
Cambridge Bowling Club - Repair stair February 22 May 22 Scheduled McLean Park Toilets & Change room - Window
security grill January 22 February 22 Scheduled
City Beach Precinct - Roof repairs March 22 May 22 Scheduled
PARKS
Walking Trail Strategy - Supporting Infrastructure 4 - Low July 21 November 21 Works in Progress Perth Netball Association-Conversion of court install
light 4 - Low July 21 November 21 Works in Progress
Contingency Emergency Bore, Pump & Retic 4 - Low July 21 October 21 Works in Progress
City Beach to Floreat Beach boardwalk 4 - Low August 21 September 21 Works in Progress
Treescape Plan - Precinct Streets Planting Program 4 - Low July 21 June 22 Works In Progress
Various Parks – Ground Water Monitoring 4 - Low July 21 June 22 Works in Progress
Beaches & Dunes - Floreat Beach Dune Restoration 4 - Low October 21 April 22 Works in Progress Lake Monger Reserve - Management of
Rehabilitation Zones 4 - Low July 21 June 22 Works in Progress
Various Parks - Upgrade Garden Beds 4 - Low July 21 September 21 Works in Progress
Various Reserves - Upgrade Garden Beds 4 - Low July 21 September 21 Works in Progress
City Beach Park - furniture replacement 4 - Low August 21 November 21 Works in Progress
Lake Monger Reserve - Environmental Monitoring 4 - Low October 21 April 22 Works In Progress
City Beach Park - CCTV Fixed Cameras 4 - Low July 21 November 21 Works in Progress
Various Parks - SDS Controllers 4 - Low July 21 October 21 Works in Progress
Various Sportsgrounds - SDS Controller 4 - Low July 21 October 21 Works in Progress
Floreat Beach Park - SDS Controller 4 - Low July 21 August 21 Works in Progress
Various Road Reserves - SDS Controllers 4 - Low July 21 October 21 Works in Progress
Wembley Sports Park - Concrete Path 4 - Low July 21 November 21 Works in Progress Coastal Hazard Risk Management and Adaptation
Plan 2 - High July 21 November 22 Works in Progress
Henderson Park - Bollard Upgrade 4 - Low August 21 October 21 Works in Progress
Various Sportsgrounds - Bore, Pump and Cubicles 4 - Low July 21 October 21 Works in Progress
Maloney Park - Fencing Replacement 4 - Low August 21 November 21 Works in Progress
Town of Cambridge - Bus Shelters 4 - Low October 21 December 21 Scheduled
Vincent St West (Northwood - Barrington) 2 - High August 21 September 21 Complete
Cambridge St (Joseph - McCourt) 2 - High October 21 November 21 Scheduled
Drainage Pit Rehabilitation 3 - Medium August 21 June 22 Works in Progress
Kerb replacement for road surfacing program 3 - Medium August 21 June 22 Works in Progress
Kimberley St / Lake Monger Dr Intersection 3 - Medium September 21 October 21 Scheduled
Selby St Shared Path 3 - Medium August 21 September 21 Works in Progress
Replacement of cracked section of concrete paths 4 - Low August 21 June 22 Scheduled
Cambridge St (Joseph - Station) Tram track repairs 2 - High October 21 November 21 Scheduled
Northwood St - (Cambridge - Railway Pde) 3 - Medium September 21 November 21 Design
Cambridge St (McCourt - Joseph) Tram track repairs 2 - High October 21 November 21 Scheduled Cambridge St (Jersey - Alexander) Tram track
repairs 2 - High October 21 November 21 Scheduled
Durston Rd (The Boulevard - Malton) 2 - High September 21 October 21 Scheduled
Kalinda Drive (The Boulevard - Oceanic) 2 - High September 21 October 21 Scheduled
Cambridge St (Station - Gregory) Tram track repairs 2 - High October 21 November 21 Scheduled
Cambridge St (Marlow - Simper) 2 - High September 21 September 21 Works in Progress
Chipping Rd (The Boulevard - Belford) 2 - High October 21 October 21 Scheduled
Rochdale Rd (West Coast Hwy - 250m South) 2 - High September 21 September 21 Scheduled
Cambridge St EB (Station - Joseph) 2 - High October 21 October 21 Scheduled
Challenger Pde Disability access 3 - Medium September 21 September 21 Scheduled
Jersey St (Herdsman - Salvado) 3 - Medium October 21 October 21 Design
Cambridge S WB (Station - Joseph) 2 - High October 21 November 21 Scheduled Quarry Amphitheatre - New access road to western
carpark 4 - Medium October 21 October 21 Design
ENGINEERING
Duration (Days), 487
Duration (Days), 0
Duration (Days), 243
Duration (Days), 181
Duration (Days), 212
Duration (Days), 245
Duration (Days), 214
Lake Monger Community Shed
Wembley Golf Course - Machinery Shed
Perth Netball Association-Conversion of court install light
Lake Monger Drive South East - Relocate Public toilet
Reabold Tennis Club - embankment retaining and landscaping
Alderbury Sportsground Pavilion - Replace Toilets and Change
Admin Building - Furniture Upgrade
Asset Services
Parks Services
July 21
July 21
July 21
August 21
July 21
July 21
October 21
July 21
July 21
July 21
August 21
October 21
July 21
July 21
July 21
July 21
July 21
July 21
July 21
June 21 July 21 August 21 September 21 November 21 December 21 January 22 March 22 April 22 May 22
Walking Trail Strategy - Supporting Infrastructure
Perth Netball Association-Conversion of court install light
Contingency Emergency Bore, Pump & Retic
City Beach to Floreat Beach boardwalk
Treescape Plan - Precinct Streets Planting Program
Various Parks – Ground Water Monitoring
Beaches & Dunes - Floreat Beach Dune Restoration
Lake Monger Reserve - Management of Rehabilitation Zones
Various Parks - Upgrade Garden Beds
Various Reserves - Upgrade Garden Beds
City Beach Park - furniture replacement
Lake Monger Reserve - Environmental Monitoring
City Beach Park - CCTV Fixed Cameras
Various Parks - SDS Controllers
Various Sportsgrounds - SDS Controller
Floreat Beach Park - SDS Controller
Various Road Reserves - SDS Controllers
Wembley Sports Park - Concrete Path
Coastal Hazard Risk Management and Adaptation Plan
Aug-21
Aug-21
Aug-21
Sep-21
August 21
August 21
September 21
September 21
September 21
September 21
September 21
September 21
September 21
September 21
June 21 July 21 August 21 October 21 November 21 December 21 January 22 March 22 April 22 May 22 July 22
Denton St - widen road to provide parking
Vincent St West (Northwood - Barrington)
Drainage Pit Rehabilitation
Kerb replacement for road surfacing program
Kimberley St / Lake Monger Dr Intersection
Selby St Shared Path
City Beach Car Park design upgrades
Replacement of cracked section of concrete paths
Marlow St (Cambridge - Ruislip) widening
Cambridge St - (Connolly - McCourt) Puffin Crossing
Northwood St - (Cambridge - Railway Pde)
Moray Avenue - Traffic Calming
Cambridge St (Jersey - Alexander) Tram track repairs
Durston Rd (The Boulevard - Malton)
Kalinda Drive (The Boulevard - Oceanic)
Cambridge St (Marlow - Simper)
Rochdale Rd (West Coast Hwy - 250m South)
Challenger Pde Disability access
Engineering Services
PARKS AND NATURAL ENVIRONMENT TOTAL PROJECTS COMPLETED YEAR TO DATE
Completed Outstanding
16 50 CURRENT PROJECT UPDATE
Project Title Dunblane Park Upgrade
Summary Upgrading the park with new irrigation, path, trees and landscaping
Commencement Date October 20 Estimated Completion Date July 21
Total Budget $200,000 Actual Cost to date $189,874
Risk 1 - High Updated Estimated Total Budget $200,000
Construction has now been completed and the upgraded park is being very well received by the local community.
Seating Nodes and New Turf Tree Planting and New Pathway
Project Title Lake Monger Reserve - South East Park Improvements
Summary New playground, furniture, pathways, basketball court and fitness equipment to Lake Monger SE foreshore
Commencement Date March 2021 Estimated Completion Date September 2021
Total Budget $62,000 Actual Cost to date $3,261
Risk Low Updated Estimated Total Budget $240,000
New park amenities including playground, furniture, pathways, basketball court and fitness equipment at the Lake Monger South East foreshore are completed and now open to public.
Fitness Equipment Basketball Court
Fitness Equipment Playground & Furniture
Project Title West Coast Highway (Peasholm - Boulevard)
Summary New landscaping and irrigation works to West Coast Highway median island between Peasholm and The Boulevard.
Commencement Date June 2021 Estimated Completion Date September 2021
Total Budget $325,500 Actual Cost to date $148,151
Risk Medium Updated Estimated Total Budget $400,000
Project completion aimed for this week with tree planting, mulching and garden planting finishing up on Friday 3rd September.
New West Coast Highway Landscaping
Project Title Lake Monger Drive South East - Relocate Public toilet
Summary New universal access three cubicle toilet block next to new carpark
Commencement Date January 21 Estimated Completion Date September 21
Total Budget $250,000 Actual Cost to date $170,949
Risk 3 - Medium Updated Estimated Total Budget $250,000
The building has been installed and the fit out is nearing completion. The stone cladding and texture painting is expected to be complete in the next few days of dry weather. Works are expected to be completed by late September.
Toilet Building
Project Title Perry Lakes Reserve - Lake Water Quality Monitoring
Summary Water quality and sediment monitoring to provide a baseline picture of water quality and wetland health
Commencement Date July 20 Estimated Completion Date February 22
Total Budget $30,000 Actual Cost to date $422
Risk 3 - Medium Updated Estimated Total Budget $30,000
Water quality sampling was undertaken at Perry Lakes in May following the first major rainfall of the season. Results from sampling assist in providing a trend of water quality and wetland health. Baseline results can be compared with future sampling following interventions such as storm water diversion to Perry Lakes and revegetation project to ascertain the improvements in water quality and wetland health. A report is expected following analysis of the samples.
Project Title Reabold Tennis Club – embankment retaining and landscaping
Summary New retaining walls and landscaping to Reabold Tennis Club embankment
Commencement Date January 21 Estimated Completion Date October 21
Total Budget $80,000 Actual Cost to date $90,874
Risk Low Updated Estimated Total Budget $100,000
Construction of walls is nearing completion. Retic and Landscaping will follow in the coming weeks. Works are expected to be complete in early October.
Wall construction underway
Project Title Ruislip Park - Upgrade
Summary Park upgrade works to Ruislip Park in West Leederville
Commencement Date March 22 Estimated Completion Date May 22
Total Budget $250,000 Actual Cost to date $2,625
Risk 4 - Low Updated Estimated Total Budget $250,000
Over 80 responses have been received in the last 2 weeks for the Ruislip Park upgrade survey. Respondents have been asked to provide input on retaining walls, playground options and removal of trees. Ruislip Park Layout Design
Project Title Woolwich Park - Upgrade
Summary Park upgrade works to Woolwich Park in West Leederville
Commencement Date March 22 Estimated Completion Date May 22
Total Budget $140,000 Actual Cost to date $0
Risk 4 - Low Updated Estimated Total Budget $140,000
A public survey is now open for Woolwich Park upgrade. Respondents will be able to comment on potential park upgrade features such as improved turf area, improved sight lines and potential additional park amenity such as furniture and play opportunities.
Aerial Park Layout Design
Project Title Lake Monger Reserve - Environmental Monitoring
Summary Water quality and sediment monitoring to provide a baseline picture of water quality and wetland health
Commencement Date July 20 Estimated Completion Date February 22
Total Budget $10,000 Actual Cost to date $1,600
Risk 3 - Medium Updated Estimated Total Budget $10,000 Water quality sampling was undertaken at Lake Monger in May following the first major rainfall of the season. Results from sampling assist in providing a trend of water quality and wetland health. Baseline results can be compared with future sampling following interventions such as refurbishment of the nutrient stripping zone to ascertain any improvements in water quality and wetland health resulting from the works.
Project Title Beaches and Dunes - Floreat Beach Dune Restoration
Summary Restoration of the dunes at Floreat Beach including installation of protective infrastructure and revegetation
Commencement Date February 21 Estimated Completion Date August 21
Total Budget $20,000 Actual Cost to date $590
Risk 2 - High Updated Estimated Total Budget $20,000
A new path was constructed in the southwest corner of the helipad car park at Floreat. Previously the nearest access to the beach was located at the north western end of the carpark resulting in frustration of those parking at the southern end. The new path will reduce uncontrolled access through the steep dunes in front of the car park by the public and increase likelihood of revegetation survival.
ENGINEERING
TOTAL PROJECTS COMPLETED YEAR TO DATE
Completed Outstanding
54 23
CURRENT PROJECT UPDATE
Project Title Vincent St West (Northwood - Barrington) Summary Kerb replacement and resurfacing works
Commencement Date August 21 Estimated Completion Date September 21
Total Budget $164,700 Actual Cost to date $89,718 Risk 2 - High Updated Estimated Total Budget $90,000
Vincent Street West Vincent Street West
The Kerbing and resurfacing works have now been completed. The line marking component of the works is to be undertaken by Main Roads WA. The Town is waiting on confirmation of when this will be completed.
Project Title Selby St Shared Path
Summary 3 metre -wide asphalt shared path along the western side of Selby Street from The Boulevard to Grantham Street
Commencement Date August 21 Estimated Completion Date September 21
Total Budget $198,200 Actual Cost to date $100,944
Risk 3 - Medium Updated Estimated Total Budget $200,000
Construction commenced in June 2021, and has now been completed. Line marking, tactile ground surface indicators and reticulation repairs are outstanding. This work is anticipated to be completed by the end of September 2021, once the asphalt has had time to oxidise. The path opening activation event which is a requirement of DoT funding, has yet to be organised.
Shared Path Complete Shared Path Complete
Shared Path Complete Shared Path Complete
Project Title Kimberley St / Lake Monger Dr Intersection
Summary Intersection efficiency improvement, creating a more streamline approach of vehicles turning left and right from Kimberley Street which will aid in lower congestion at the intersection.
Commencement Date September 21 Estimated Completion Date October 21
Total Budget $90,600 Actual Cost to date $6,268
Risk 3 - Medium Updated Estimated Total Budget $90,000
The RFQ advertisement period closed on 21 July. A contractor has now been engaged to carry out the work and a start-up meeting has been held. It is anticipated that construction should commence in early November 2021 and will take approximately six weeks to complete. The contractor has commenced traffic management and stakeholder engagement processes.
Project Title The Boulevard (Selby - Floreat) Summary Resurfacing Works Commencement Date August 22 Estimated Completion Date September 22
Total Budget $485,500 Actual Cost to date $247,722
Risk 2 - High Updated Estimated Total Budget $250,000
Resurfacing works commenced in May but due to weather, works were put on hold. They required works have now been completed. It is anticipated that Main Roads WA will undertake the line marking works by the end of September 2021.
Resurfacing Works Complete Resurfacing Works Complete
STORM DAMAGE UPDATE The Town’s Engineering Team has engaged with Cardno to review the flooding areas from July’s storm events. The table below is a list of all reported and identified flooding areas throughout the Town which will be investigated by Cardno. The Table is prioritised as: 1. Red – High Priority 2. Amber – Priority 3. Green – Potential issue 4. Blue – Unlikely an issue
Street Name Reported Water in property
Details Priority Code Rating Action undertaken
Joseph Street Yes Flooding to front door from two blocked drains on the street. Green Educted
*unknown location as yet Yes Waist-deep water at property. SES has been called. He will email in with pictures following clean up to initiate a review of drainage in the area.
Alderbury Street Yes Sump at 50 Alderbury Street full overflowing into property Blue
Alexander Street Underpass No Underpass flooded 15-20cm Amber
Arbordale and Alderbury Street intersection no Localised flooding at intersection Blue
Bent Street, Brompton Road, Chipping Road, WCH No Reports of ~80cm flooding. Blue
Boronia Crescent Yes Claims of flooding due to lack of kerb height adjacent to property. This is a building site. Green
Boronia Crescent Yes
The next door neighbours (top, north side) have a driveway which does not have a reasonable lip. When it rains, the water rushes down the street, into their driveway, over the pedestrian refuge in front of my letterbox and into my driveway. It is like a river going down my drive and into my carport (10 to 20 cm deep) an along my front verandah, right across to my southern neighbours dividing fence and lapping my front door. The water has formed a lake in my front yard. Interestingly, my driveway is also sloping down, but the water runs down the street and not into my yard. My double driveway (also brick paved) must have the correct configuration of slope and curb onto the road. This never happened for the 1st 20 years with my previous neighbours and their old house and driveway. The current house and its driveway configuration is a constant problem and quite dangerous when torrential rain occurs. I have taken photos and a video of the lake outside my door, in my yard and in my carport. I cannot make them small enough to attach so will show the officer once he or she arrives at my home.
Green
Brompton Rd no Called in to report flooding at the carpark of the Church. Green
Cambridge Street yes Blocked drainage, water going into shop, resident said no need to call. Green
Cambridge Street no Blocked drainage, water going into shop. Amber
Cambridge Street no Flooding has subsided but drains were fully blocked up and now there is plants and debris everywhere. Amber
Cambridge Street (Sump and intersection with Selby) Yes Sump filled and minor inundation at 417 Cambridge Street Major intrusion into
442b Cambridge St reported at front counter request to excavate sump more Blue
Champion Crescent No Street flooded. Amber
Champion Crescent No
I would like to report an issue with storm water backing up at 5 & 7 Champion Crescent Floreat. During the recent heavy rains the storm water was not adequately draining and was pooling significantly over the verges. More concerning was the storm water could not escape from our property at 7 Champion Crescent and caused flooding in our garage. Can the council please investigate the cause of the poor street drainage and rectify
Amber
Chipping Road No Localised flooding at low point Green
Connolly Street No South of Ruislip Street intersection adjacent to 55 Connolly Street. No ingress into property but water holding in road causing localised flooding Green Educted
Crosby Street Yes
Grated Pit on Crosby Street (North of the property) is overflowing during heavy rainfall event. That runoff on Crosby Street was causing flooding issues in front of the property and driveway. The resident has put sand bag as a measure at his own cost. Will be sending photos of the affected areas.
Blue
Elphin St Yes Drain at the front of 28 Elphin St is blocked due to construction waste, which is resulting in flooding, my garage flooded as a result of the build-up. Property at 30 Elphin St subject to flooding
Green
Floreat Beach Car Park No Send Snap Solve Water always builds up here when it rains. There is no drain. Can this be considered for improvement, please. Blue
Glengarriff Drive Yes
He said he witnessed the Town resurface Glengarriff and bitumen straight over the existing drains – apparently when he asked the worker what he was dong covering the drains he just shrugged. Now his property is underwater “almost to the power-points” He said he will be holding the Town personally liable for all damage to his house and will pursue insurance claims. As an aside, he was told by a depot staff member to go to the depot to collect free sandbags and when he got there at ten to 4 today it was closed and no sandbags there. Just letting you know as we can expect this one to escalate.
Blue
Gregory St No The drain at front was so inundated with water it didn’t drain away and we had a flooded front yard which nearly came in our front door - I have a photo of water up to outside of drain and not drains away at all!!
Blue
Harborne Street Resident reported flooding and drain blockage. Backyard of the property was flooding from Logan Lane due to the Friday storm event. Do not have any photos of the situation but accusing the soak well on the Lane way was overflowing and creating water logging on all over the lane.
Green
Harrogate Street Yes Eloise, from Oakwood Pty Ltd rang to say that due to flooding from the road, their basement is now flooded. Blue Educted pits
Herdsman Parade No Minor flooding at low point Green
Howtree Place Yes
Adjacent to Reabold Tennis Club. Pit failure likely to inundation and debris over gully grate (double pit with Side Entry) causing water to flow over kerb and footpath. Significant scour and washout down tiered embankment into Reabold and underneath path (turbulence effect). Will require box out and reconstruction. Hazard management is in place for the meantime until works commence 12/13 July.
Red Site has been made safe and works to repair will commence 16 July 2021
Joseph Street Yes Their neighbour and footpath are flooded due to the drain overflowing. Green Educted pits
Lake Monger Drive No Flooding at the corner of Kimberly and Lake Monger Drive. Blue
Lake Monger Drive No St Vincent's Avenue to Gregory Street both directions under 100mm (Roadway retention). Holding more in outside lanes; centre island was free of water. Cleared up after 30 minutes
Blue
MacEwan Street Yes Flooding due to drain failure/blockage Green Educted 1 Pit other pits parked on unable to access
Marlow Street Yes Flooding due to speed hump outside his house -- has used sandbags to prevent water coming into house, but side and back yard flooded. Green
McCourt Street Park Sump Yes Runoff from surroundings flooding park and detention basin - As soon as road pits failed through inundation the park completely filled within 5 minutes Red Review by contractor who undertook the work
Moray Ave
Rebecca recently experienced flooding due to drainage problems at 20 Moray Avenue Floreat. She was home at the time and able to mitigate the excess rain, however she says if she wasn’t, her house would have been flooded. She would like to talk with a technical officer / engineer about the Moray Avenue Drainage Plan and what is being done to address the problems with the drains in the future.
Blue
Moray Ave Yes
Send Snap Solve reported flooding around 70 Moray Ave Image provided; Historically, we have had issues with flooding at 70 Moray Ave, Floreat. Several years ago work was undertaken by council to address these problem, but I don't believe the significant works that we were promised at the time, have ever undertaken. With the downpour yesterday, we suffered significant flooding to our property. The street outside resembled a lake, as did our front yard, with 20cm of water in our garage. Could we urgently have sand bags delivered to protect our property come Monday's storms, please. Could we also have sand bags delivered to our 90 year old neighbour at 68 Moray Ave who also experiences flooding of her property, please.
Blue Educted pits
North Banff Road Yes In the past two significant rain events (9 July, 3 July) drains out the front of our house have not taken the water and our front yard and garage have flooded Blue
Oakdale and Alderbury Street No Localised flooding at intersection Green
Oceanic Dr intersections with Louth & Arbordale Street No Localised flooding minor inundation to 29 & 34 Arbordale Street Green
Pandora Drive No Runoff causing significant scouring down embankment between Pandora Drive and Durston Road. Will require reconstruction. Green
Perina Way No Woodchips have washed off a vacant block and clogged the drain so that water is rising up to the doors. Requested drain be cleared ASAP. Green
Perry Lakes Drive Oceanic intersection (Including South carriageway)
No Localised flooding with bubble up at parks filled (Westbound Lanes obstructed) Green
Railway Parade Yes Blocked drain out the front (on Southport side of property); flooded the inside of recently new fit out. Blue Works crew inspected area cleaned nearby pit
Reserve Street No Localised flooding at low point Green
Ruislip Street No Stormwater penetrating down footpaths of McCourt Street due to Catholic Education Centre runoff and lack of kerbing height and footpath ramp at intersection
Blue
Ruislip Street No Stormwater penetrating down footpaths of Tate Street due to runoff from lack of kerbing height and footpath ramp at intersection - western side Blue
Selby Street No
Claims of flooding due to Selby Street shared path works. Highly unlikely as picture given indicates water of approximately 25mm and evidence of water sheeting off of roof onto ground. Have sandbagged verge near driveway as measure to deal with resident.
Amber Water diverted back onto road
Tarongo Way Yes
On Friday July 9, 2021 our property at 41 Tarongo Way, City Beach, was flooded due to heavy rainfall. The storm water drain located in the road at the front of our property is inadequate and caused all the water from the rainfall to flow into our property which caused flood damage. Even with light/moderate rainfall this storm water drain does not do its job and we end up with flooding at the front of our property on every occasion.
Green
The Boulevard No Flooding in the street. Green
The Boulevard Yes
My garage gets flooded every time there is heavy rain like today and water floods down my driveway. Could you please look into this so that the water flows into the drain and not down my driveway.
Green
The Boulevard West of Perry Lakes Drive No Localised flooding Green
Weldon Street and Brompton Road intersection Yes Localised flooding had yet to subsided at 4:00pm Red Pits on intersection filled with debris cleaned
West Coast Highway No -31.911387, 115.758178 drains are blocked with grass and mud from council works on west coast highway around CMB4 path west coast highway near Hale Road
Green
Woolwich Street No Runoff from side streets and Woolwich from Blencowe Street to McCourt Street - Water sheeting within kerb channel and bypassing pits due to inundation failure
Blue
UPCOMING ROAD CLOSURES
Location Time Period Description
Cromarty Road (Crieff Street) 16/11/2020 – 01/09/2021
Jersey Street (Grantham Street – Ruislip Street) 16/11/2020 – 01/09/2021
Templetonia Crescent (Gunee Road – Dampier Avenue) 16/11/2020 – 01/09/2021 Construction Deliveries
Selby Street northbound (Grantham Street to The Boulevard) 23/06/2021 – 27/08/2021 (8am to 2pm) PSP construction
ASSETS/BUILDINGS TOTAL PROJECTS COMPLETED YEAR TO DATE
Completed Outstanding
32 10
CURRENT PROJECT UPDATE
Project Title South City Beach Kiosk (The Kiosk)
Summary Concept Design Options for the Kiosk Future
Commencement Date August 21 Estimated Completion Date May 22
Total Budget $50,000 Actual Cost to date $52
Risk 2 - High Updated Estimated Total Budget $50,000
The proposed South City Beach Kiosk redevelopment options were presented to the Town’s Design Review Panel (DRP) on 9 July 2021. The options were also sent to the Heritage Council of Western Australia (Heritage Council) seeking their feedback. The Town received feedback from the Heritage Council and DRP which are summarised below:
• None of the three concept design options were supported by the DRP and State Heritage. • The DRP suggested leasing the Kiosk, developing a businesses and keep it as an iconic asset in WA. They also
suggested developing a Conservation Management Plan for the Kiosk.
As per the Heritage Council suggestion the Town has engaged original architect, Mr Tony Brand, and revising the concept design options. The Town will submit a proposal for the Kiosk after the plan is revised. The Asset Services team is planning to prepare a business plan and Conservation Management Plan and will engage the Heritage Council when the plans are complete. If Council decides to progress with the project, a rigorous consultation process will be implemented to ensure the community is provided the opportunity to comment.
Project Title Lake Monger Community Shed
Summary Building the internal fit outs.
Commencement Date June 21 Estimated Completion Date November 21
Total Budget $200,000 Actual Cost to date $3,138
Risk Low Updated Estimated Total Budget $200,000
The approved internal fit out works for Lake Monger Community Shed have partially been carried out and the following items were completed in July 2021:
1. Compliant shelves were purchased and delivered. 2. The new security system was purchased, installed, commissioned and is now operational. 3. Fencing around the external bin store was installed. The new acoustic wall and woodworking area dust extraction, the new welding area wall, welding fume extraction, and the final electrical fit out were advertised as one package of works in form of Request for Quotation (RFQ) in July 2021. This RFQ was closed on Wednesday, 18 August 2021 at 2pm. The Town has reviewed the submissions and will provide recommendation for the award of the contract to Council in September 2021.
Project Title Alderbury Sportsground Pavilion - Replace Toilets and Change Rooms
Summary Demolish the existing facilities and replace with new toilets and change rooms.
Commencement Date May 21 Estimated Completion Date February 22
Total Budget $1,268,500 Actual Cost to date $123,872
Risk 2 - High Updated Estimated Total Budget $1,870,000.00
*This project received $400k external Community Sporting and Recreation Facilities (CSRF) fund which is not included in the estimated budget. The total budget will be revised during the mid-year budget review. The contract was awarded to Shelford Construction in March 2021. The external underground utility relocation works commenced in May 2021 and completed in June 2021. The external underground utility relocation works commenced in May 2021 and completed in June 2021. The demolition commenced on 18 June 2021 and is now complete. The earthworks and site works have begun and the first Progress Claim has been approved.
Alderbury Sportsground Pavilion - Photo of Demolition - 25 June 2021
The earthworks have now commenced and the concrete footing works were carried out in the last week of July 2021. The slab concrete pouring was completed on 16 August 2021.
Earth work preparation - July 2021 Concrete Reinforcement Preparation- July 2021
The concrete pouring for slab were carried out in August 2021 and steel works has been commenced in early September.
Concrete Pouring– Slab – August 2021 Start of Steel works – September 2021
WASTE
Participating Council Report: WMRC
Summary WMRC are to provide the Town of Cambridge with a regular report on the performance of its community recycling services.
Date of Report Period 1 September 2020 – 30 June 2021
The Memorandum of Understanding (MoU) between the Town of Cambridge and the Western Metropolitan Regional Council (WMRC) dated 2 September 2020, provides that the WMRC will provide the Participating Council with a regular report on the performance of its community recycling services including on: • numbers of residents calling at the [Recycling] Centre; • quantity of materials recycled; and • results of customer satisfaction survey.
Number of Cambridge residents calling at the WMRC Number of Cambridge visits (expressed in carloads) using free recycling drop off services including cardboard, scrap metal, polystyrene, e-waste, paint, sporting goods, gas bottles and other HHW:
Month Free service carloads September 2020 232 October 2020 394 November 2020 322 December 2020 403 January 2021 361 February 2021 326 March 2021 250 April 2021 201 May 2021 152 June 2021 73 TOTAL 2714
Paid service users for the period totalled: 2323 transactions including 11 bulk waste passes used. Quantity of materials recycled Green waste
• 314 transactions - 99.12 total tonnes Bulk waste
• 1222 transactions - 264 total tonnes
• 29 fridges degassed and recycled
• 76 mattresses and bases recycled
• 55 sheets of asbestos collected
• 32.15 tonnes of construction and demolition waste recycled
• 61 tyres recycled
Education Results of coordination through the Communications and Education team (provided at no charge to the Town)
Events held in the Town 1. Waste Watchers Workshop: 4 March 2021 – 9 residents 2. Compost, Worm Farm and Bokashi Workshop: 27 March 2021 - 7 residents Events held elsewhere 1. Waste Watchers Workshop (Peppermint Grove): – 0 residents 2. Secrets of Sustainable Shopping (Claremont): 11 March 2021 – 5 residents 3. Staff/Elected Member tour of West Metro RC: 10 March 2021 - 3 attendees 4. Community tour of SMRC RRRC: 18 March 2021 – 2 residents 5. Community tour of SMRC RRRC: 12 May 2021 – 2 residents 6. Community tour of West Metro RC: 2 residents WMRC and the Town of Cambridge co-promote community waste events through e-newsletters and social media. WMRC included the Town under their memberships of Plastic Free July and Recycle Right which entitled them to reduced membership rates. Cambridge Repair Lab: 18 September 2021 | 10:30am
– 12:30pm Repair Lab is a community initiative to help people fix their belongings, keep items in the system and reduce the burden on recycling, and ultimately save things going to landfill. Skilled volunteers will help you with repairs of clothing, textiles, bikes, furniture, jewellery, electronics and electrical, and general household items. If you're unsure, bring it down and we'll see what we can do! If you have skills – we would love to welcome you as one of our volunteers.
Pool Cover & Plastics Drop Off Day: 18 September 2021 | 10:00am – 2:00pm The Town of Cambridge is holding another Extended Plastics Drop-Off Day at the Admin Centre to collect a range of plastics. These items will be locally processed and used in the Australian manufacturing industry. A full list of accepted items can be requested from: [email protected]
Creating Wildlife Havens in Suburbia: 23 September 2021 | 6:30 – 8:30pm Wildlife havens serve a number of purposes including protecting wildlife and helping animal populations thrive. Wildlife gardens are designed to attract native animals like birds, frogs, lizards, bees, butterflies and other creatures. By creating a wildlife garden, you’re potentially providing a home, food, protection, or just a nice place to visit for our beautiful wildlife. This workshop focusses on suburban eco-systems, bird life, insects, and creating wildlife corridors and havens in our gardens. Attendance at this workshop qualifies you for a rebate against the purchase of a bird bath of your choice.
Charity Drop Off Day: 2 October 2021 | 9:00am – 3:00pm It is time to start thinking about our next Charity Day! The Town now holds Charity drop-off days three times a year to assist residents to maximise their Verge Valet space. We invite a range of charities to receive donation of those belongings which are too good to Verge Valet. Bring your unwanted household items including clothes and textiles and working electrical items (no white goods please!) to the Administration Centre. Simply drive up and our friendly staff will unload your car for you. Items must be clean and undamaged and presented in boxes or bags. Things you can donate at a Charity drop-off day:
• All types of clothing • Small furniture • Working electrical items - no white goods
please! • Accessories including jewellery, bags, hats,
belts • Manchester: Towels, tableware and tea towels • Bedding, linen and blankets • Shoes, boots and slippers • Homewares, including Games, Toys, DVD’s
CD's • Crockery, glassware
Kintsugi: The Art of Broken Pieces: 21 October 2021
| 6:30 – 8:30pm This is an age old way to minimise waste to landfill… Kintsugi is the Japanese art of putting broken ceramics back together with gold — built on the idea that in embracing flaws and imperfections, you can create an even stronger, more beautiful piece of art. Every break is unique and instead of repairing an item like new, the 400-year-old technique actually highlights the "scars" as a part of the design. This workshop includes a gold repair kit with all necessary equipment and tuition.
Bike Day: 30 October 2021 | 9:00am – 3:00pm October is Bike Month and the Town is celebrating the event with a ‘Bring Your Bike’ day on 30 October to celebrate to celebrate Bike Month between 9am and 3pm at the Council Offices, 1 Bold Park Drive Floreat. Activities include recycling bicycles through the Dismantle Youth Development program and providing basic maintenance through the Bike Dr program. Workshops will be presented by the locally based Bike Smart program on road rules and how to, safely, make use of shared paths. Staying in line with the recycling theme, a ‘bike stuff swap’ station will allow people to bring second-hand bike clothes and associated equipment to swap. More information will be forthcoming in the next newsletter.
Bin Fairy: Ongoing program For those residents unsure about recycling, wanting to increase recycling, reduce waste to landfill and/or their dependence on plastics. This program is available for face to face sessions where residents can obtain advice on recycling and minimising their waste to landfill. These are flexible sessions, held in homes at residents’ convenience, and at times to suit them.
Green Waste bags: Ongoing program 75L green waste bags are now available for purchase – these are perfect to put out items for green waste Verge Valet bookings (they will be left by the team after emptying). They are $10 for 2 and available from the Admin Centre.
COUNCIL DECISIONS
MONTH – ITEM NO. REPORT TITLE DECISION SUMMARY COMMENTS (IF REQUIRED)
22/05/2018 – CR18.67 Infrastructure Traffic Study For West Leederville and Wembley
Work scope for RFQ – Traffic Study for Wembley West Leederville be approved and proceed to request for quotation. Amount of $80,000 be considered for inclusion in budget.
• A report was presented by Cardno at an Elected Members Forum on 3 December 2019. No clear direction was given but an additional Elected Member Forum date was proposed, date to be confirmed in the future; and
• A second forum to be arranged for 2021. 20/05/2019 - CR19.42 Pedestrian Crossings Study - Lake Monger Drive
That Council: 1. APPROVES the overall pedestrian
crossing improvement strategy along Lake Monger Drive;
2. APPROVES a new pedestrian crossing immediately west of Kimberley Street estimated at $130,000 for inclusion in the 2019-2020 budget, as shown in Attachment 1 Plan E 309 19 01;
3. LISTS FOR CONSIDERATION the following items for inclusion in the draft four year financial plan as future capital works: 3.1 2020-2021: Lake Monger Drive
pedestrian improvements - St Vincents Avenue Attachment 2 Plan E 309 19 06. project estimated at $85,000;
3.2 2021-2022: Lake Monger Drive pedestrian improvements – Northwood Street - eastern Lake Monger service road entrance as shown in Attachment 3 Plan E 309 19 02. Project estimated at $110,000;
3.3 2022-2023: Lake Monger Drive pedestrian improvements – east of Gregory Street as shown in Attachment 4 Plan E 309 19 07. Project estimated at $100,000;
4. NOTES that an underpass access under Lake Monger Drive is currently being investigated; and
5. REQUESTS the Underpass concept design options for the Lake Monger Drive/Gregory Street zone be PRESENTED at a Council Elected Members Forum by no later than September 2019.
• Presented and adopted by Council May 2019; • Consultation letter sent out to residents for the
Kimberley Street crossing 26 July 2019. Extending Consultation period to 4 weeks total;
• Concept design options to be presented at Elected Members Forum by February 2020;
• Council report September 2019 advising of petition about negative response to consultation letter sent to residents. Project deferred by Council;
• Letter sent out to all residents who participated in the consultation advising of Council decision; and
• Forum to Councillors to be conducted in 2021 by Cardno to present options.
22/09/20 – CR20.113 Town of Cambridge – Proposed Verge Valet Bulk Waste Collection Service
That Council: 1. APPROVES a Verge Valet bulk waste
collection service provided by the Western Metropolitan Regional Council for a trial period, commencing on 1 November 2020 to 30 June 2022; and
2. REQUESTS a report to be submitted to Council at the conclusion of the trial.
• In progress as per the Council decision.
25/05/2021 - CR21.50 South City Beach Kiosk – Progress Report
That Council:- 1. NOTES:-
1.1 the urgent concrete repair work to the South City Beach Kiosk has been completed;
1.2 the proposed concept designs that will improve the functionality of the asset by converting it to a pavilion style structure;
2. REQUESTS:- 2.1 the Town to seek comment from the
Design Review Panel prior to
• The concept design options were sent to the Design Review Panel.
• The Town will now explore options to activate the facility without modifying the building fabric.
progressing to public consultation on the proposed designs;
2.2 a further report to be presented to Council detailing the Design Review Panel’s feedback.
25/05/2021 - CR21.53 Churchlands Green Estate – City of Stirling Traffic Trials
That Council:- 1. RECEIVES the information relating to the
City of Stirling’s Traffic Management Trial within the Churchlands Green Estate, as shown in Attachment 1;
2. DOES NOT APPROVE the temporary six week closure of the right turn pocket on Empire Avenue in to University Avenue as the safest treatment; and
3. REQUESTS the Town to report back to Council on the results of the traffic counts and the possible impact to local roads at the completion of the trial.
• In progress as per the Council Decision.
25/05/2021 - CR21.54 Ocean Mia Estate - On-Street Parking
That Council:- 1. NOTES the four proposed options to
address the parking issues in Ocean Mia Estate;
2. APPROVES the Town to undertaken community consultation with effected residents; and
3. REQUESTS a further report to be presented to Council documenting the feedback received, following community consultation.
• Consultation to occur late June to July 2021. • Consultation has commenced with residents
of the estate. To close late August 2021.
22/06/2021 - CR21.65 Marlow Street, Cambridge to Ruislip Street, Road Modifications – Consultation Outcomes
That the item relating to Marlow Street, Cambridge to Ruislip Street, Wembley Road Modifications be REFERRED BACK to the Community and Resources Committee for further consideration. Procedural Motion put and CARRIED (6/2)
• The Town is reviewing alternate design options and meeting with community members to determine the best outcome.
27/07/2021 – CR21.74 Draft Perry Lakes Management Plan
That Council:-
1. APPROVES the Town to undertake community engagement on the: (a) Draft Perry Lakes Management Plan
2021-2031, as shown in Attachment 1; and
(b) Draft Perry Lakes Masterplan 2021-2031, as shown in Attachment 2;
2. AUTHORISES the Chief Executive Officer to determine and finalise the members of the Perry Lakes Management Plan Focus Group; and
3. REQUESTS a further report to be presented to Council documenting the feedback received, following the community engagement period.
• Consultation page with survey to be created W/E 20/8 and letter to surrounding residents ready to go when website is ready.
Report back to Council in October.
27/07/2021 – CR21.77 Moray Avenue Floreat Traffic Management Treatment – Consideration of Submissions
That Council:
1. RECEIVES the community engagement submissions for the installation of traffic management treatments on Moray Avenue between, Dumfries Road and Grantham Street in Floreat; and
2. REQUESTS the Administration to investigate alternative options and arrange a community forum to discuss options available.
• The Town will organise a community forum for residents of Moray Avenue to discuss ways to manage moving forward. Likely to occur after Churchlands Green Traffic Management trial.
COUNCIL MEETING
28 SEPTEMBER 2021
ATTACHMENT 6 TO ITEM 10.2
REGISTER OF PETITIONS OUTSTANDING MATTERS AS AT 22 JULY 2021
REGISTER OF PETITIONS - OUTSTANDING MATTERS 1 July 2018 Onwards - As At 16 September 2021No OCM Date Petition Convenor Petition Prayer No of
Signatures Resolution Vote Responsible Directorate Outcome
Complete /Not
Complete32 22.06.2021 Peter Plaisted A petition containing 45 signatures has been submitted by Peter Plaisted, 14A
Marlow Street, Wembley requesting that Council “reject the proposed road treatment for Marlow Street between Cambridge Street and Ruislip Street, Wembley. We wish for you to seriously consider the removal of the A.Costata trees and for no replacement trees to be planted intheir place and allow the verge trees to remain”.
45 That in accordance with Clause 3.5 of the Town of Cambridge Meeting Procedures Local Law 2019, the petitions be received and be referred to the Director Infrastructure and Works for investigation and further report to Council and also be considered at tonight’s Council meeting at Item CR21.65.
8/0 Director Infrastructure and Works
1. Elected Member’s comments during discussion on CR21.65 was a desire to maintain the trees.2. The Town will engage with the residents to seek a design that is acceptable by all.3. A report is due back in September to Council.4. The proposed road treatment was presented at 22 June 2021 Council Meeting and was not approved. Consideration of thetree removal has been completed.
Not Complete
36 27.07.2021 Fook Joo Chin and Hui Chuan Lau
petition containing 206 signatures has been submitted by Fook Joo Chin and Hui Lau, 23 Oceanic Drive, Floreat requesting that Council “obtains an independent traffic impact study on the Oceanic Drive/Brookdale Street intersection and surrounding streets and withdraw its approval of the closure of the Brookdale Street median strip”.
206 That in accordance with Clause 3.5 of the Town of Cambridge Meeting Procedures Local Law 2019, the petitions be received and be referred to the Director Infrastructure and Works for investigation and further report to Council.
5-Apr Director Infrastructure and Works
1. A report will be presented to Council at a future date addressing the petition’s request. Not Complete
COUNCIL MEETING
28 SEPTEMBER 2021
ATTACHMENT 7 TO ITEM 10.2
REGISTER OF NOTICES OF MOTION AS AT 22 JULY 2021
Page 5
Register of Notices of Motion - 2021 As at 16 September 2021
MeetinMeeting Date Item
/R
epor
t No
Title Notice of Motion Sumitted By Carried / Lost Vote For Against
Amended / Adopted as Presented
Council Resolution No %No Presented in 2021 8 150.00Adopted as Presented 3 37.50Adopted as Amended 0.00Motion Withdrawn 0.00Motion Lost 1 12.50Motion Deferred 0.00Motion Adjourned 1 33.33Yet to be Determined 0.00Lapsed 2 66.67Motion Ruled Out of Order 0.00
Notices of Motion by Elected Member No %Mayor Keri Shannon 5 62.50Cr Rod Bradley 0 0.00Cr Ian Everett 1 12.50Cr Alaine Haddon-Casey 2 25.00Cr Gary Mack 0 0.00Cr Kate McKerracher 0 0.00Cr Andres Timmermanis 0 0.00Total Notices of Motion 8 100.00
40 0 1 2 0 0 0 0
7
57
0 0
14
29
0 0 0 0
100
0
20
40
60
80
100
120
May
or K
eri S
hann
on
Cr K
ate
Barlo
w
Cr R
od B
radl
ey
Cr Ia
n Ev
eret
t
Cr A
lain
e Ha
ddon
-Cas
ey
Cr G
ary
Mac
k
Cr R
ob F
rede
ricks
Cr K
ate
McK
erra
cher
Cr A
ndre
s Tim
mer
man
is
Tota
l Not
ices
of M
otio
n
Notices of Motion by Elected Member (No and %)1 July 2021 -30 June 2022
No
%
3 2
74
26
24
67
29
48
32
21
7
0
10
20
30
40
50
60
70
80
2008 2010 2012 2014 2016 2018 2020 2022
Total Number of Notices of Motion 2009-2021
0
8
3
1 1
2
0
150.00
37.50
0.00 0.00
12.50
0.00
33.33
0.00
66.67
0.00 0
20
40
60
80
100
120
140
160
0
1
2
3
4
5
6
7
8
9
Coun
cil R
esol
utio
n
No
Pres
ente
d in
202
1
Adop
ted
as P
rese
nted
Adop
ted
as A
men
ded
Mot
ion
With
draw
n
Mot
ion
Lost
Mot
ion
Defe
rred
Mot
ion
Adjo
urne
d
Yet t
o be
Det
erm
ined
Laps
ed
Mot
ion
Rule
d O
ut o
f Ord
er
No of Notices of Motion 2021
Series1 Series3
COUNCIL MEETING
28 SEPTEMBER 2021
ATTACHMENT 8 TO ITEM 10.2
PUBLIC QUESTION TIME - RESPONSES TO QUESTIONS SUBMITTED TO COUNCIL BUT TREATED
AS CORRESPONDENCE
COUNCIL MEETING
28 SEPTEMBER 2021
ATTACHMENT 9 TO ITEM 10.2
CORRESPONDENCE TO CEO FROM MINISTER OF TOURISM