ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06
description
Transcript of ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06
ATLAS Muon SystemWBS 3.5
DoE/NSF M&O Evaluation Group ReviewBNL
19-Jan-06
Frank TaylorMIT
V1.3
ATLAS Muons MEG Review BNL 19-Jan-062 F.E. Taylor
Goal: Install & commission U.S. deliverables
240 MDT chambers on-chamber readout
electronics alignment
32 CSC chambers Complete electronics
– on-chamber
– off-chamber
– LV & HV and cabling
Endcap Global alignment system
Alignment bars BCAMs Proximity cameras, etc.
Phase I – B184 Certify Chambers RFI
MDT Complete 240/240 CSC partially complete @ BNL
Phase II – B180 & B191 Certify Chambers after
installation on Structures EIL4 2/16 Complete BW 4/32 Complete
Phase III – UX15 Integrate wheels & EIL4 stations
following installation in Pit Connect to & commission with
RODs in USA15 Commission wheels with
Cosmics
M&O Plan WBS 3.5
ATLAS Muons MEG Review BNL 19-Jan-063 F.E. Taylor
Small & Big Wheels
JD/SW
Big Wheels
ECT
32 sectors assembled into 2 MDT Big Wheels
2 Small Wheels
16 EIL4 on frames
64 alignment bars mounted in BW-L sectors & EIL4 frames
ATLAS Muons MEG Review BNL 19-Jan-064 F.E. Taylor
M&O-Installation Locations & Phases
MDT Test StationBMC, UM, UW
CERN - Bld 184
CSC Test StationBNL - 832
Alignment SystemTest Station
CERN - Bld 180
CommissionBig Wheel [BW]Sectors & EIL4 CERN - Bld 180
Commission Small Wheel [SW]
CERN - Bld 191
Phase IICY 05 - 06
Phase ICY 04 - 06
Phase IIICY 06 - 07
ATLAS
UX15
Beam On - CY-07
Installation on Support Structures
Complete
Partially Complete
Started
CSC B184 CERN
Sta
tus
Jan
06
ATLAS Muons MEG Review BNL 19-Jan-065 F.E. Taylor
Work Stations in B180 @ CERN
BW-Large construction area Construction of Al frames & Installation of Chamber Services
Tilt Table - Large Installation of chambers & Phase II commissioning
A-frame Large & Storage Service connections – gas, LV, HV Mini-DAQ test station
BW-Small construction area Construction of Al frames & Installation of Chamber Services
Tilt Table - Small Installation of chambers & Phase II commissioning
A-frame Small & Storage Service connections – gas, LV, HV Mini-DAQ test station
EIL4 construction area Installation of chambers on frames Phase II commissioning & storage
Service connections – gas, LV, HV Mini-DAQ test station
Alignment testing room & 8-Sector test station Verify alignment parts (bars, BCAMS, etc,) are ‘RFI’ & Mech Engineering
Barracks for offices & cable preparations
CommentsTilt tables & A-frames from Pakistan & assembled by them @ CERN
Storage tooling designed by CERN & fabricated locally
Overall engineering responsibility CERN
ATLAS Muons MEG Review BNL 19-Jan-066 F.E. Taylor
Phase II - B180 & B191
EML5 C03 being installed
EIL4s mounted on Frames, Phase II commissioned,
mated with TGC Frame & Stored as
‘RFI’.
16 assemblies to make and to finish in
Spring 06
Installation plan in UX15 being
reassessed in light of interference with barrel chamber
installations
B180 BW-L & S Sector Construction & Commissioning & Storage
SW & JD Disk to be in B191
Start Spring 06
ATLAS Muons MEG Review BNL 19-Jan-067 F.E. Taylor
Phase III – UX15 In Planning Stage
Installation of Sectors/SWs/EIL4s in UX15 CERN Responsible with US involvement
In UX15 Services around periphery connected
Gas lines, LV, HV, fiber optical cables, DCS Gas system commissioned All chambers connected & tight & correct
flow rate Alignment system connected
All monitors tested to be operational Connections to Services USA15 & UX15
LV system commissioned HV system commissioned DAQ system commissioned
Integration & Commissioning as System Alignment system optically connected &
functional Cosmics, random trigger, etc.
ATLAS Muons MEG Review BNL 19-Jan-068 F.E. Taylor
Master Schedule V7.09
PA
P J
an-0
5 th
is
date
was
11/
16/0
5
ATLAS Muons MEG Review BNL 19-Jan-069 F.E. Taylor
FY06-07 Milestones
Phase II
Phase III
ATLAS Muons MEG Review BNL 19-Jan-0610 F.E. Taylor
3.5 Budget Profile - Labor & Materials
Ant
icip
ate
that
res
ourc
es f
or
FY
07 w
ill n
eed
to b
e ab
out
the
sam
e as
in F
Y06
ATLAS Muons MEG Review BNL 19-Jan-0611 F.E. Taylor
3.5 Budget Profile – Labor | MaterialsLa
bor
- P
roje
ctM
ater
ials
- P
roje
ct
ATLAS Muons MEG Review BNL 19-Jan-0612 F.E. Taylor
3.5 Labor Plans MANPOWER ESTIMATE SUMMARY IN FTEs per year
WBSNo: 3.5 Funding Type: Research Program 1/16/2006 6:02:54 PM
Description: Muon - Endcap Institutions: All Funding Source All
FY06 FY07 FY08 FY09 FY10 FY11 Faculty .0 Sr Research Scientist .0 .0 Term Scientist .0 .0 Post Doc .0 .0 Grad Student .0 .0 Mechanical 3.6 .2 Electrical Engineer 1.8 1.9 .8 .2 .2 .2 Technician 6.0 2.2 2.4 1.9 1.9 1.9 Computer 2.1 1.0 1.8 1.0 1.0 1.0 Designer .0 .0 Administrator .0 .0 General Labor 7.6 3.2 .3 .1 .1 .1 TOTAL LABOR 21.1 8.6 5.2 3.2 3.2 3.2
1760 Hours per FTE year
Anticipate that resources for FY07
will need to be about the same as in FY06
MR
ATLAS Muons MEG Review BNL 19-Jan-0613 F.E. Taylor
Impact of Not Funding MR FY06 & FY07
FY06 – $276k Engineering & Technical support cut - Schedule Slippage
$40k Pre-Ops MDT Chambers (UoM & UoW) (WBS 3.5.1.1.3) $225k Pre-Ops CSCs Phase II (BNL) (WBS 3.5.2.1.3) $11k Tech Support for Monitor & Calib Center (UoM) (WBS 3.5.5.1.1.1)
FY07 - $1365k Deep cuts in personnel - Meeting BW, SW RFI Dates
Untenable $160k MDT Phase II (WBS 3.5.1.1.3) $513k MDT Phase III (WBS 3.5.1.1.4) $92k MDT Operations – Beam On (WBS 3.5.1.2) $263k CSC Pre-Operations Phases II & III (WBS 3.5.2) $136k Alignment Pre-Operations (WBS 3.5.3) $202k Monitoring & Calibration (WBS 3.5.5)
ATLAS Muons MEG Review BNL 19-Jan-0614 F.E. Taylor
Safety General Safety Training
All US persons upon arrival @ CERN have to take CERN General Safety Course
Rigging After rigging accident in B180 new procedures put in place,
documented and riggers trained Scissor Lift Certification
3 US persons have been trained & ~ 6 more are scheduled for training
Crane School 1 person trained & more scheduled
Work @ Height – Harness Training 3 persons trained & more to be scheduled
Procedures in B180 A CERN person now designated in charge
Authorized to stop unsafe operations Enforces wearing Hardhats & Safety Shoes
Protocols distributed by paper to US work crews & will be posted on web by ATLAS GLIMOS
Written in English, French and Russian Procedures in UX15 posted on ATLAS page
Enforced by ATLAS GLIMOS
ATLAS Muons MEG Review BNL 19-Jan-0615 F.E. Taylor
Conclusions
US Manpower and Operations moved to CERN Tasks defined and organization in place and coherent with CERN
Key engineering & technical personnel are @ CERN– Several physicists & engineers with line responsibilities are commuting
Delays have accumulated BW Chamber Installation & Commissioning
B180 occupancy delayed and slow delivery of BW frames & tooling Tooling is now complete but more Pakistanis/Russians needed
SW Chamber Installation & Commissioning B191 occupancy delayed by ECT
Installation in UX15 date ~ fixed - more work to be done in parallel EIL4, BW and SW installation work will overlap in CY06
5 ‘Operations’ simultaneously conducted Share manpower, share tooling, logistical overhead
M&O resources will have to support this compressed schedule Sustained funding anticipated in FY07 at ~ FY05/FY06 Level
Installation & Commissioning of Wheels and chambers in UX15