Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
-
Upload
norman-oder -
Category
Documents
-
view
217 -
download
0
Transcript of Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
1/12
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
2/12
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
3/12
STV Construction, Inc.
Project Date 4/14/2014Location Weekday Monday
Client Report # 294
Contract # Weather
Project # Temp. L/H 62/76
STV Representative: Bill King Wind Speed
Work hours 8:30-6:45 Precip
117 88 1.3
930 0.126
Additional New Observations: Demo of 215 Dean St. continued today with semi-length dumptruck after dumptruck (A. Russo company),being filled and hauling away demolished material. No problems coordinating truck deliveries with B2.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Other - Hoist sidewalk shed extension over crosswa k at northeast corner completed.
New Information received:
Eastern-most mods on Dean St. transfer beam have windows facing east.
Module Transportation - 4 mods delivered to site overnight; during the day = 6 total.
Module Installation - 6 new mods installed, all on the Dean St. transfer beam, which completes the 5th floor. Mod completion at 12.6%,
117 of 930 installed. Installation Rate = 117 in 88 work days = 1.3 mods per day so far.
Module Fabrication - Ongoing at Navy Yard, still working on 6th floor mods with 142-man workforce. Draft 2-week look-ahead by FCRstates that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state of
completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Bright, Sunny, Warm, Breezy
2114659
Summary of Construction Activities
20 mph gusting to 39 mph late (after mods)
0"
Tower Crane - Active
Foundation-related - Civetta on site but knockout panel areas continue to be dormant. Work unfinished.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. TCO
date now projected for March, 2015, a 2-month slip.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week look-
ahead. Must watch out that work areas contain dust from affecting other workers/the public.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
1/20/14 - Emailed Skanska's Bill Carson stating that SOFP cloud must be contained when spraying the rest of the ground floor, for protection
of other workers as well as of the public passing by. No response. Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.
New Information requested:
Special instruction(s) given:
Information previously requested: 2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response.(Note: on 4/4, Skanska still discussing internally.)
1 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
4/12
STV Construction, Inc.
Manpower on Site 20-30
Navillus
Civetta 0
Stearns 10
J SuporTrucking 4
MEP trades
Other 8-10
William Kin 4/14/2014 Date
Potain Tower Crane
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Prepared by Bill King
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
2 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
5/12
STV Construction, Inc.
Project Date 4/15/2014Location Weekday Tuesday
Client Report # 295
Contract # Weather
Project # Temp. L/H 35/63
STV Representative: Bill King Wind Speed
Work hours 9:00-5:30 Precip
117 89 1.3
930 0.126
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 89 work
days = 1.3 mods per day so far. No more mods expected until May 2014.
Module Fabrication - Ongoing at Navy Yard, still working on 6th floor mods with 142-man workforce. Draft 2-week look-ahead by FCRstates that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state of
completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Rainy, Windy
2114659
Summary of Construction Activities
19 mph gusting to 39 mph
.7" rain/.8" snow
Tower Crane - Inactive
Foundation-related - Civetta on site waterproofing back basement wall prior to backfilling on 4/16. Knockout panel areas done - remain tobe fitted by others.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Other - Hoist sidewalk shed extension over crosswa k at northeast corner completed.
New Information received:
Leaking in 2 spots on 5th floor - one in corridor with barrel, the other in unit along window (bucket)
Additional New Observations: Demo of 215 Dean St. continued with gravel deposited in basement area.
Information previously requested: 2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response.(Note: on 4/4, Skanska still discussing internally.)
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
1/20/14 - Emailed Skanska's Bill Carson stating that SOFP cloud must be contained when spraying the rest of the ground floor, for protection
of other workers as well as of the public passing by. No response. Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.
New Information requested:
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. TCO
date now projected for March, 2015, a 2-month slip.
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week look-
ahead. Must watch out that work areas contain dust from affecting other workers/the public.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues.
1 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
6/12
STV Construction, Inc.
Manpower on Site 10-15
NavillusCivetta 4-6
Stearns 0
J SuporTrucking 0
MEP trades
Other 8-10
William King 4/15/2014 Date
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by Bill King
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
2 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
7/12
STV Construction, Inc.
Project Date 4/16/2014Location Weekday Wednesday
Client Report # 296
Contract # Weather
Project # Temp. L/H 32/48
STV Representative: Bill King Wind Speed
Work hours 8:00-5:00 Precip
117 90 1.3
930 0.126
Additional New Observations: Tally of Apts with Signif Water Damage: 2nd flr- 9 mods (all); 3rd flr - 4 mods; 4th flr - 3 mods; 5th flr - 3mods (could not get into 1-2 units on each of floors 3-4); total apts with damage = 9+4+3+3=19 out of 39 total = nearly 50%.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Other - Hoist sidewalk shed extension over crosswa k at northeast corner completed.
Additonal ripped out ceiling holes noted in a new apt. as well as in the corridor.
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 90 workdays = 1.3 mods per day so far. No more mods expected until May 2014.
Module Fabrication - Ongoing at Navy Yard, still working on 6th floor mods with 142-man workforce. Draft 2-week look-ahead by FCRstates that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state of
completeness. Were supposed to start installation today, 4/16/14, per latest (3/14/14) schedule. Only a half dozen completed mods
observed sitting outside Bldg 293 at the Navy Yard.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Sunny, Cold, Warming, Windy
2114659
Summary of Construction Activities
19 mph gusting to 30 mph
0"
Tower Crane - Inactive for 2nd day in a row
Foundation-related - Civetta backfilled half of
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
8/12
STV Construction, Inc.
Manpower on Site 20-30
Navillus
Civetta 4-6
Stearns 6
J SuporTrucking 0
MEP trades
Other 8-10
William King 4/16/2014 Date
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
5 Cement Mixers for gravel backfill
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by Bill King
Gravel backfill
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
2 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
9/12
STV Construction, Inc.
Project Date 4/17/2014Location Weekday Thursday
Client Report # 297
Contract # Weather
Project # Temp. L/H 36/48
STV Representative: Bill King Wind Speed
Work hours 8:45-4:45 Precip
117 92 1.3
930 0.126
Additional New Observations:
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Other - Hoist sidewalk shed extension over crosswa k at northeast corner completed.
New Information received:
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 92 workdays = 1.3 mods per day so far. No more mods expected until May 2014.
Module Fabrication - Ongoing at Navy Yard, presumably, still working on 6th floor mods with 142-man workforce. Draft 2-week look-ahead by FCR stated that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state
of completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule. Only a half dozen completed mods were
observed sitting outside Bldg 293 at the Navy Yard on 4/16.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Mix of Clouds & Sun, Cool
2114659
Summary of Construction Activities
15 mph gusting to 27 mph
0"
Tower Crane - Inactive for 3rd day in a row
Foundation-related - Civetta received more gravel for backfill (3 cement trucks full) but did not place it - still waiting for walls to dry to apply
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week look-ahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
1/20/14 - Emailed Skanska's Bill Carson stating that SOFP cloud must be contained when spraying the rest of the ground floor, for protection
of other workers as well as of the public passing by. No response. Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.
ew n orma on reques e :
Information previously requested: 4/16/14 - Via email requested from Skanska's John Dolan and Bill Carson explanation for delay to6th floor mods - no response.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response. (Note: on 4/4, Skanska still discussing
internally.)
1 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
10/12
STV Construction, Inc.
Manpower on Site 15-20
Navillus
Civetta 4-6
Stearns 6
J SuporTrucking 0
MEP trades
Other 8-10
William King 4/18/2014 Date
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by Bill King
More gravel
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
2 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
11/12
STV Construction, Inc.
Project Date 4/18/2014Location Weekday Friday
Client Report # 298
Contract # Weather
Project # Temp. L/H 36/50
STV Representative: Bill King Wind Speed
Work hours 8:45-4:45 Precip
117 92 1.3
930 0.126
Additional New Observations: 8 holes cut in ceilings near façade walls of 3 Flatbush-facing apts on 5th floor. Similar holes cut in 3rdfloor ceilings. Most of fallen/torn down ceiling on 3rd floor removed. One more storage room to go on 2nd floor.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Other - Hoist sidewalk shed extension over crosswa k at northeast corner completed.
Workers taking down temporary aluminum bracing etc. in eastern-most units on 5th floor.
Both Skanska's John Dolan and Bill Carson not seen on site Wed-Fri.
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 92 workdays = 1.3 mods per day so far. No more mods expected until May 2014.
Module Fabrication - Ongoing at Navy Yard, presumably, still working on 6th floor mods with 142-man workforce. Draft 2-week look-ahead by FCR stated that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state
of completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule. Only a half dozen completed mods were
observed sitting outside Bldg 293 at the Navy Yard on 4/16.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Cold Start, High Overcast
2114659
Summary of Construction Activities
11 mph gusting to 20 mph
0"
Tower Crane - Inactive for 4th day in a row
Foundation-related - Civetta deposited more gravel backfill between arena and B2 foundations at eastern end. Gap < 5' wide.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week look-
ahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
1/20/14 - Emailed Skanska's Bill Carson stating that SOFP cloud must be contained when spraying the rest of the ground floor, for protection
of other workers as well as of the public passing by. No response. Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.
New Information received:
New Information requested:
Information previously requested: 4/16/14 - Via email requested from Skanska's John Dolan and Bill Carson explanation for delay to6th floor mods - no response.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response. (Note: on 4/4, Skanska still discussing
internally.)
1 of 2
-
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 4-18-14 - Proposed Redactions_Redacted
12/12
STV Construction, Inc.
Manpower on Site 15-20
Navillus
Civetta 4-6
Stearns 6
J SuporTrucking 0
MEP trades
Other 8-10
William King 4/18/2014 Date
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by Bill King
More gravel
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.