Assignment 2010 Rev B

download Assignment 2010 Rev B

of 14

Transcript of Assignment 2010 Rev B

  • 8/8/2019 Assignment 2010 Rev B

    1/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 1 of 14

    Setonix

    BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT

    Rev Description By Check PE PM Date

    A Issued for Engineering Check K Mullen 28 July 2010

    B Issued for Use K Mullen 7 September 2010

    1 Revised as Noted K Mullen

    Revised and Updated

  • 8/8/2019 Assignment 2010 Rev B

    2/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 2 of 14

    CONTENTS

    1. INTRODUCTION.................................................................................................... 31.1 General ................................................................................................................ 31.2 Seabed Topography ............................................................................................ 31.3 Field Location....................................................................................................... 41.4 Development Drilling............................................................................................ 41.5 Subsurface Challenges........................................................................................ 41.6 Design Intent........................................................................................................ 5

    2. FIELD DESIGN PARAMETERS............................................................................ 62.1 Design Life ........................................................................................................... 62.2 Availability ............................................................................................................ 62.3 Hydrate Prevention and Remediation.................................................................. 62.4 Corrosion Inhibition .............................................................................................. 62.5 Gas Disposal........................................................................................................ 62.6 Well Test .............................................................................................................. 6

    3. SUBSURFACE AND WELLS................................................................................ 73.1 Reservoir Data ..................................................................................................... 73.2 Well Productivity .................................................................................................. 73.3 Xmas Trees.......................................................................................................... 73.4 Drilling and Type of Wells .................................................................................... 7

    4. FLUID PROPERTIES ............................................................................................ 94.1 Well Test Data ..................................................................................................... 94.2 Produced Oil Properties....................................................................................... 94.3 Produced Water ................................................................................................... 94.4 Crude Viscosities ................................................................................................. 9

    5. METOCEAN AND ENVIRONMENTAL............................................................... 115.1 Water Depth....................................................................................................... 115.2 Metocean Conditions ......................................................................................... 115.3 Variation of Water Temperature with Depth ...................................................... 115.4 Soil Conditions ................................................................................................... 115.5 Environmental .................................................................................................... 11

    6. COSTING AND SCHEDULE............................................................................... 116.1 Costing ............................................................................................................... 116.2 Schedule ............................................................................................................ 11

    7. APPENDIX - CONVERSION FACTORS............................................................. 12

    8. APPENDIX - COST DATABASE / RELIABILITY DATA.................................... 14

  • 8/8/2019 Assignment 2010 Rev B

    3/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 3 of 14

    1. INTRODUCTION

    1.1 General

    Setonix Oil Company (SOC) wishes to invite bidders to submit a tender for

    the development of the Perth Canyon oil field.

    The Perth Canyon oil field is located in a water depth of approximately1600 m. The Perth Canyon oil is a medium-light crude with anapproximate gravity of 47.2API containing a small amount of associatedgas, primarily methane, and increasing amounts of produced water. It isplanned to develop the field through subsea wells. Tenderers are torecommend development and export options for the field architecture.

    The Perth Canyon oil field comprises a single reservoir with recoverablereserves of 80 million barrels.

    1.2 Seabed Topography

    The Perth Canyon is a relict of the Swan River drainage system, cuttinginto the shelf west of Perth and Rottnest Island. At the canyon head thedepth plunges from 200 m to 1000 m. The canyon mouth opens onto theabyssal plain at 4000 m. In between, the canyon curves sinuously over100 km, with a sharp bend halfway referred to as the dogleg, as shown inFigure 1. Two small branches are present on the south rim near thedogleg.

    Figure 1 Perth Canyon

  • 8/8/2019 Assignment 2010 Rev B

    4/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 4 of 14

    1.3 Field Location

    The layout of the Perth Canyon field is indicated in Figure 2 below.

    Rottnest

    Island

    Rottnest

    Island

    Figure 2 Perth Canyon Reservoir

    Reservoir dimensions: ~13 km x 4 km.Reservoir water depth: 1600 m.

    Depth contours from the coast are [100, 200, 300, 500, 750, 1000, 1500, 2000, 2500,3000, 4000] m.

    1.4 Development Drilling

    From February 2008 to July 2009, SOC executed an exploration andappraisal program in the Perth Canyon resulting in the oil field discoveries.A total of nine wells were drilled over this period.

    The oil discovery was made in February 2009, when the PC-7 explorationwell encountered a gross oil column of 24 m in the reservoir.

    1.5 Subsurface Challenges

    Appraisal wells were drilled and a high-resolution seismic survey wasacquired over the field to assist in planning the production program.

  • 8/8/2019 Assignment 2010 Rev B

    5/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 5 of 14

    The reservoir lies in the Perth Canyon which is an ancient river outfall. TheMiocene submarine fan / channel reservoir is located 1,700m below thebottom of the ravine, in a water depth of approximately 1600 m.

    Subsurface presents extreme challenges for drilling due to debris flow and

    fluvial deposits comprising boulder beds, sandstone, clay, marl, withblocky landslide material.

    1.6 Design Intent

    Tenderer shall:

    Design a subsea system to produce oil from the Perth Canyon field.

    Set production rates to optimise return on investment.

    Determine an optimised subsea architecture, and justify equipmentsizing and field life.

    Design equipment and provide an operating philosophy to permit

    production from the field. Review economics of the field and design the production system togive the best return on investment.

    Where it is felt that essential development information is missing, Tendereris invited to use reasonable engineering judgement and makeassumptions (These should be stated and justified). Process analysis isnot required.

    Tenderer shall provide a description and justification for the following:

    Well design ( vertical vs. deviated)

    Horizontal or vertical trees

    Initial number of wells, and any subsequent phases of drilling newwells, if needed

    Number of manifolds, and location

    Flowline jumper routing, and manifold valving arrangements

    Well testing and monitoring facilities

    Annulus monitoring and venting

    Wax, hydrate and corrosion control

    Location and size of production facility

    Risers

    Technology for operation and control of the field

    Flowline route and materials

    Flowline sizing1

    Pigging and inspection philosophy

    Outline Environmental Impact Assessment

    Schedule, and time to First Oil

    Production rate, and life of field

    Use or disposal of associated gas and produced water

    1http://www.freefuelforever.com/Pressure%20Drop%20Calculator.exe

  • 8/8/2019 Assignment 2010 Rev B

    6/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 6 of 14

    2. FIELD DESIGN PARAMETERS

    2.1 Design Life

    Facilities shall be designed for a life of 20 years.

    2.2 Availability

    Overall development availability shall be in excess of 95%.

    Tenderer is to demonstrate how this availability will be achieved2.

    The facilities shall be designed for operating flexibility in terms of beingable to continue production whilst equipment has failed or is degradedawaiting repair (e.g. through provision of bypasses, redundancy, etc.).

    2.3 Hydrate Prevention and Remediation

    For the anticipated operating, shut-in, start-up and ambient conditions ofthe subsea production and lift/injection gas systems, hydrate mitigationtechniques may be required to avoid operation inside the hydrate region.

    Tenderer shall recommend whether hydrate inhibitor injection shall bemade only at start-up and shutdown, or on a permanent basis.

    Tenderer shall make provision for clearing flowlines of a complete hydrateblockage by relieving pressure from both sides of the blockage for safedisposal.

    2.4 Corrosion Inhibition

    Tenderer shall make provision for the injection of corrosion inhibitor intoflowlines and subsea facilities where necessary.

    2.5 Gas and Water Disposal

    Gas and produced water disposal methods should be reviewed andconsidered by Tenderer.

    2.6 Well Test

    Production wells are to be individually tested at least once a month for 12to 24 hours.

    2 By means of reliability modelling.

    A useful tool is RAPTOR Version 4.0S available from http://www.barringer1.com/raptor.htm

  • 8/8/2019 Assignment 2010 Rev B

    7/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 7 of 14

    3. SUBSURFACE AND WELLS

    3.1 Reservoir Data

    Reservoir data is provided in the following table.

    Parameter DesignOil In Place (MMbbl) 270Recoverable reserves (MMbbl) 80

    FWHP -SIWHP -FWHT -Reservoir Initial Pressure (bara) 260 baraReservoir Temperature 120 C

    The reservoir is located 1700 m below the canyon floor in a water depth of1600 m. The reservoir (shown in Figure 2) measures 4 km x 13 km,oriented in an east-west direction.

    3.2 Well Productivity

    Well characteristics are given in the table below:

    Parameter DesignMaximum well production rate (per well)at start of field life

    15,000 bbl per day

    As oil is drawn from the reservoir, the maximum flow rate from each well

    declines in proportion to the remaining recoverable reserves3

    .

    3.3 Xmas Trees

    Tenderer shall determine whether horizontal or vertical trees are preferred.

    3.4 Drilling and Type of Wells

    Wells shall have 5" tubing.

    Tenderer shall determine whether vertical or deviated wells are preferred(see Figure 3). Due to the difficult subsurface conditions, the maximum

    deviation permitted by Drilling is 1.0 km.

    3 For example, after three quarters of the oil has been extracted, and 20 MMbbl recoverable reserves remain in

    the reservoir, the maximum flow rate of each well falls to (20/80)*15,000 = 3,750 bbl per day.

  • 8/8/2019 Assignment 2010 Rev B

    8/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 8 of 14

    1.25 km

    1.7 km

    0.9 km

    0.8 km

    1 km

    1.25 km

    Vertical Completion Deviated Completion

    Figure 3 Vertical vs. Deviated Wells

    Bottom hole locations shall not be closer together than 2.5 km, as wellsany closer than this would unduly interfere with one another. This placeslimitations on the top hole locations, as shown in Figure 4 below.

    1.25 km

    2.5 km

    1.25 km1.25 km

    1.25 km

    2.5 km

    500 metres

    Figure 4 Distance between Bottom-Hole Locations

  • 8/8/2019 Assignment 2010 Rev B

    9/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 9 of 14

    4. FLUID PROPERTIES

    4.1 Well Test Data

    A well test report for the PC-7 exploration well has been produced. This

    has included preliminary characterisation of the wellstream composition.Key results are presented in Table 4.1.

    Table 4.1

    Well Test Data

    PC-7 exploration well

    Date 9 Feb 09

    Oil Gravity 47.2 API

    Solution GOR 65 scf/bbl

    Pour Point 1.6C (35F)

    4.2 Produced Oil Properties

    The Perth Canyon crude oil is medium-light with an approximate gravity of47.2API and a low gas oil ratio GOR.

    4.3 Produced Water

    Initial water cut (percentage of water in the oil) will be zero, with water cutincreasing through field life, to 100% when all reserves have beenextracted: i.e.

    Zero water cut at start of field life. 25% water cut when 60 million barrels of oil remain in the reservoir.

    50% water cut when 40 million barrels of oil remain in the reservoiretc.

    Note that the increasing water cut will also have an effect on the viscosityof the well fluids.

    4.4 Crude Viscosities

    PC-7 viscosity data4 is only available for the dead crude. The results aresummarised in Table 4.2 below.

    Table 4.2

    PC-7 Dead Crude Viscosities

    Temperature Viscosity(cP)

    40C (104F) 2.46

    50C (122F) 1.80

    4Viscosity is based on Beggs and Robinson equation.

  • 8/8/2019 Assignment 2010 Rev B

    10/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 10 of 14

    4.5 Hydrate Properties

    The hydrate curve for the Perth Canyon crude with various inhibitors isshown in Figure 5.

    Figure 5 Hydrate Curves for Perth Canyon Crude5

    5 Ref. OTC 11963 The Physical Chemistry of Wax, Hydrates, and Asphaltene

    http://www.stonefieldsheep.com/images/OTC%2011963.pdf

    StableHydrate

    Region HydrateFree

    Region

  • 8/8/2019 Assignment 2010 Rev B

    11/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 11 of 14

    5. METOCEAN AND ENVIRONMENTAL

    5.1 Water Depth

    The Perth Canyon field is located in a water depth of 1600 m.

    5.2 Metocean Conditions

    Tenderer is to determine metocean conditions.

    5.3 Variation of Water Temperature with Depth

    Tenderer is to determine variation of water temperature with depth.

    5.4 Soil Conditions

    Tenderer is to determine soil conditions.

    5.5 Environmental

    Terms of the operating license are expected to be extremely strict:

    Flaring not permitted except under emergency conditions.

    Loss of hydrocarbons to the environment not permitted (severepenalties will be imposed)

    Disposal of waste materials to the environment not permitted

    Produced water disposed of overboard to contain less than 25 ppmoil

    Interference with marine life is not permitted

    6. COSTING AND SCHEDULE

    6.1 Costing

    A one page costing for equipment and vessels is to be prepared.

    6.2 Schedule

    Tenderer is to provide a one page schedule for the project.

  • 8/8/2019 Assignment 2010 Rev B

    12/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 12 of 14

    7. APPENDIX - CONVERSION FACTORS

    Mass 1 tonne 0.9842 UK ton

    Mass 1 kg 2.2046 lb

    Force 1 N 0.10197 kgf 0.22481 lbfForce 1 kgf 9.80665 N

    Force 1 lbf 4.448222 N

    Impact Energy 1 ft-lb 1.355818 J

    Torque 1 ft-lb 1.355818 Nm

    Volume 1 bbl 0.1589873 m3 158.9873 litre

    Volume 1 US gallon 3.785412 m3

    Speed 1 knot 0.5144444 m/s

    Power 1 hp 0.746043 kW

    Length 1 mile 1.609344 km

    Length 1 ft 0.3048 m

    Pressure 1 bar 100 kPa 0.100 MPa 14.504 psi

    Pressure 207 bar 20700 kPa 20.7 MPa 3000 psi

    Pressure 1psi 6.894757 kPa 0.006894757 MPa

    Pressure 1MPa 1N/mm2

    US Customary Units Metric

    1 trillion (T) 10^12 1 Terajoule (TJ) 10^12

    1 billion (B) 10^9 1 Gigajoule (GJ) 10^9

    1 million (MM) 10^6 1 Megajoule (MJ) 10^6

    Heating value

    1 cubic metre of natural gas

    (North West Shelf)

    between 37.3 to 41

    Megajoules

    1 British Thermal Unit BTU 1055 joules

    Volume

    1 standard cubic metre of

    natural gas

    35.3147 cubic feet of

    natural gas

    1 billion cubic metres of

    natural gas

    750,000 tonnes of LNG

    1 trillion cubic feet of natural

    gas

    28.3168 billion cubic

    metres of natural gas1 terajoule per day 26,300 cubic metres of

    natural gas per day0.929 million cubic feet ofnatural gas per day

    1 barrel of oil 158.987 litres of oil

    1 barrel of oil equivalent 0.1024 tonnes of LNG

    1 tonne of crude oil 7.8616 barrels of oil

    Mass

    1 metric tonne 0.984207 long tons 1000 kilogram

    LNG

    1 metric tonne of LNG 52.9 million British

    Thermal units

    1333 cubic metres of natural

    gas at 0C

    1.242 tonnes of oil

    equivalent

    1 million tonnes of LNG peryear (1 mtpa)

    1.333 billion cubic metresper year

    3.65 million cubic metres ofnatural gas per day

    1 barrel of oil 0.158987 kilolitres of oil

    1 kilolitre of oil 6.29 barrels of oil1 standard cubic metre of natural gas 35.3147 cubic feet of natural gas

    1 billion cubic metres of natural gas 730,000 tonnes of LNG

    1 terajoule 26,300 cubic metres of natural gas 0.929 million cubic feet of natural gas

    Pressure bara Temp C

    Metric standard conditions 1.01325 15

    Normal conditions 1.01325 0

    Metric standard conditions should normally be used.

  • 8/8/2019 Assignment 2010 Rev B

    13/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    Assignment 2010 rev B.doc 7 September 2010 page 13 of 14

    Approximate Conversion Factors from BP website

    Crude oil*

    To

    Tonnes (metric) kilolitres barrels US gallons tonnes/year

    From Multiply by

    Tonnes (metric) 1 1.165 7.33 308 Kilolitres 0.858 1 6.2898 264

    Barrels 0.136 0.159 1 42

    US gallons 0.00325 0.0038 0.0238 1

    Barrels/day 49.8

    *Based on worldwide average gravity.

    Products

    To convert

    Barrels to tonnes tonnes to barrels kilolitres to tonnes tonnes to kilolitres

    Multiply by

    LPG 0.086 11.6 0.542 1.844

    Gasoline 0.118 8.5 0.740 1.351

    Kerosine 0.128 7.8 0.806 1.240

    Gas oil/diesel 0.133 7.5 0.839 1.192

    Fuel oil 0.149 6.7 0.939 1.065

    Natural gas and LNG

    To

    billion cubic

    metres NG

    billion

    cubic feet

    NG

    million

    tonnes oil

    equivalent

    million

    tonnes

    LNG

    trillion

    British

    thermalunits

    million

    barrels oil

    equivalent

    From Multiply by

    1 billion cubic metres NG 1 35.3 0.90 0.73 36 6.29

    1 billion cubic feet NG 0.028 1 0.026 0.021 1.03 0.18

    1 million tonnes oilequivalent

    1.111 39.2 1 0.805 40.4 7.33

    1 million tonnes LNG 1.38 48.7 1.23 1 52.0 8.68

    1 trillion British thermalunits

    0.028 0.98 0.025 0.02 1 0.17

    1 million barrels oil

    equivalent

    0.16 5.61 0.14 0.12 5.8 1

    Units and conversion factors from BP website

    1 metric tonne = 2204.62 lb.

    1 kilolitre = 6.2898 barrels

    1 kilocalorie (kcal) = 4.187 kJ = 3.968 Btu1 kilojoule (kJ) = 0.239 kcal = 0.948 Btu

    1 British thermal unit (Btu) = 0.252 kcal = 1.055 kJ

    1 kilowatt-hour (kWh) = 860 kcal = 3600 kJ = 3412 Btu

    Calorific equivalents

    One tonne of oil equivalent equals approximately:

    Heat units 10 million kilocalories

    42 gigajoules

    40 million BtuSolid fuels 1.5 tonnes of hard coal

    3 tonnes of lignite

    Gaseous fuels See Natural gas and LNG table

    Electricity 12 megawatt-hours

    One million tonnes of oil produces about 4000 gigawatt-hours of electricity in a modern power station.

    Convert.exe http://joshmadison.com/article/convert-for-windows

  • 8/8/2019 Assignment 2010 Rev B

    14/14

    SETONIX OIL COMPANY BASIS OF DESIGN

    PERTH CANYON DEVELOPMENT Doc No. 0902-84 Rev B

    MASTER OF OIL AND GAS ENGINEERING SUBSEA TECHNOLOGY MODULE OENA 8554

    8. APPENDIX - COST DATABASE / RELIABILITY DATA

    The following budgetary cost database is provided for high level costing of options to aid in theselection process for this assignment and to calculate budgetary field development CAPEX and OPEX.More detailed cost information may be provided by some lecturers. Note that this is not a

    comprehensive component list and students should not feel obliged to use only those componentslisted below. Cost and failure for other equipment may be derived from the data below.

    Equipment Cost (A$) Mean Time to Failure MTTF (yrs)Subsea Wellhead 300,000 200

    Xmas Tree - Diver Installed 2,000,000 50

    Xmas Tree - Diverless 3,000,000 50

    4 Slot Manifold, mudmat foundation, clusterarrangement, no pigging loop, diver installed.Not including choke, control pod orflowmeter

    4,000,000 Assume only critical failures are leakage from valves inproduction flowpath - 1200 yrs each, and diver made-upflanged connections - 1000 yrs each.

    6 Slot Manifold, mudmat foundation, clusterarrangement, no pigging loop, diver installed.Not including choke, control pod orflowmeter.

    5,500,000 Assume only critical failures are leakage from valves inproduction flowpath - 1200 yrs each, and diver made-upflanged connections - 1000 yrs each.

    Subsea Heat Exchanger - for 1 well 600,000 Critical failures is limited to leakage from isolation valves in theproduction flowpath and end connections as per manifolds

    Incremental cost for diverless installation ofmanifold / heat exchanger etc. - remoteconnections and isolation valves required

    1,000,000 Note that diverless connections have a MTTF of 250 years

    Choke Valve - Diver Retrievable 200,000 Assume 25% of chokes are repaired during field life.

    Control Pod - Diver Retrievable 600,000 15 yearsIncremental cost for ROT for choke andcontrol pod

    250,000 N/A

    Multiphase Flowmeter - Diver Retrievable 250,000 10 yearsMultiphase Flowmeter - ROT Retrievable 550,000 10 years

    High Integrity Pipeline Protection System(HIPPS) for 6 wells (downstream of manifold) -ROT retrievable

    5 - 7,000,000 -limited data

    3 years. Failure results in loss of production. Repair by retrievalof HIPPS module using vessel with >30 tonnes cranage

    Subsea Separation System for 1 well - diverlessinstalled

    3,000,000 3 - 6 years. (Little data available)

    Subsea Separation System for 6 wells 10,000,000 3 - 6 years. (Little data available)Direct Hydraulic Control Umbilical - 6 wells 2,000 / metre 15 years

    Electrohydraulic Control Umbilical - 6 wells 500 / metre 15 yearsIncremental cost increase for chemicalinjection line in umbilical

    100 / metre N/A

    Cost for CRA flowlines(Corrosion Resistant Alloy)

    6,210 / tonne Flowlines are unlikely to fail (MTTF >> 1000 years). Connectionsfailure MTTFs as per manifold data above.

    Cost to lay CRA line 280,000 / kmCost for Carbon Steel flowlines 883 / tonne As above

    Cost to S-lay Carbon Steel line 150,000 / kmCost to J-lay Carbon Steel line 270,000 / km

    Flexible flowlines - 6 X 50m 4,000 / metre As above

    Flexible flowlines - 6 X >1 km 1,700 / metre As aboveFlexible flowlines - 12 X 50m 5,500 / metre As aboveFlexible flowlines - 12 X >1km 3,500 / metre As above

    Flowline Bundle Cost +10% Assume cost of individual components of bundle plus 10%.Assumes availability of fabrication/launch site.

    Vessels/Buoys Cost Notes3

    rd

    Semi submersible drilling rig spread rateDP deepwater drillship spread rate[Spread rate is about double the day rate]

    350,000 / day400,000 / day Mobilisation cost is $25,000,000. Wait time of up to 6 months.Vertical wells take 30 days to drill.Offset/horizontal wells take 45 days to drill

    Diving Support Vessel (includes sat divingspread and 50 tonne cranage)

    138,000 / day Mobilisation cost is $ 2,250,000. Wait time up to 3 months.

    Diving Support Vessel ( includes 300 tonnecranage but no sat diving spread)

    320,000 / day Mobilisation cost is $ 2,250,000. Extra for sat diving spread is$25,000 / day. Wait time up to 6 months

    ROV Support Vessel (includes 15 tonnecranage)

    35,000 / day Mobilisation is $1,500,000. Wait time up to 2 weeks

    FPSO (Floating Production, Storage andOfftake Vessel)

    700,000,000 Rental: 70,000,000 p.a.

    East Spar - type buoy 30,000,000