Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to...

6
Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. If you have any questions concerning these instructions, please call National Customer Service 800.482.1717. Assembly Instrucon Telephone 800.482.1717 Fax 812.482.8800 www.NationalOfficeFurniture.com Part # 2649287 Rev, B Printed in U.S.A © 2015 Kimball International, Inc. Package Contents 1 The base, worksurface, and TV mount that aach to the wall ship in separate boxes. The hardware used to aach the base to the wall ships with the base. Mio Wall 3 Figure B Aſter assembling the base, have at least one person stand the wall up while another person aaches the top and boom channels to wall using (8) 5/16”-18 x 1” bolts from base hardware kit. See Figure B. Note that there is a removable panel in the middle of the wall and on top of the boom channel. Removable Panel Hardware………………………………..Qty #8 x 1” panhead screws 0 to 16 16” L Brackets 0 to 2 5/16-18 x 1” panhead screws 4 to 8 HDW for Epicenter (optional) Qty 5/16-18 x 2.5” hex head bolts 2 to 3 Blinder HDW See Blinder AI Hardware from each base…...…..Qty #10 x 1” panhead screw 36 to 40 3” L brackets 6 5/16-18 x 1” panhead screws 8 Hardware from each TV Mount..Qty M8 x 70 Hex Head Lag Bolts 4 M8 Square Spacers 4 Component…………………..………….Qty Wall 1 Tools Required Drill (Phillips #2 and #3 bits) 3/16” drill bit Ratchet with 1/2” Socket Head Metric Socket Head #13 Level 2 If the Power Pole opon was selected ,remove the six (6) screws aaching the top plate to the wall. Flip the plates so the bent por- on is protruding upwards and replace 6 screws into the exisng holes. See Fig. A below. Figure A Removable Panel

Transcript of Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to...

Page 1: Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to shorter Length. 8 Slide pole over protruding metal flanges to connect pole to the top

Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. If you have any questions concerning these instructions, please call National Customer Service 800.482.1717.

Assembly Instruction

Telephone 800.482.1717 Fax 812.482.8800 www.NationalOfficeFurniture.com Part # 2649287 Rev, B Printed in U.S.A © 2015 Kimball International, Inc.

Package Contents

1 The base, worksurface, and TV mount that attach to the wall ship in separate boxes. The hardware used to attach the base to the wall ships with the base.

Mio Wall

3

Figure B

After assembling the base, have at least one person stand the wall up while another person attaches the top and bottom channels to wall using (8) 5/16”-18 x 1” bolts from base hardware kit. See Figure B. Note that there is a removable panel in the middle of the wall and on top of the bottom channel. Removable

Panel

Hardware………………………………..Qty

#8 x 1” panhead screws 0 to 16

16” L Brackets 0 to 2

5/16-18 x 1” panhead screws 4 to 8

HDW for Epicenter (optional) …Qty

5/16-18 x 2.5” hex head bolts 2 to 3

Blinder HDW See Blinder AI

Hardware from each base…...…..Qty

#10 x 1” panhead screw 36 to 40

3” L brackets 6

5/16-18 x 1” panhead screws 8

Hardware from each TV Mount..Qty

M8 x 70 Hex Head Lag Bolts 4

M8 Square Spacers 4

Component…………………..………….Qty

Wall 1

Tools Required

Drill (Phillips #2 and #3 bits)

3/16” drill bit

Ratchet with 1/2” Socket Head

Metric Socket Head #13

Level

2 If the Power Pole option was selected ,remove the six (6) screws attaching the top plate to the wall. Flip the plates so the bent por-tion is protruding upwards and replace 6 screws into the existing holes. See Fig. A below.

Figure A

Removable Panel

Page 2: Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to shorter Length. 8 Slide pole over protruding metal flanges to connect pole to the top

Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. If you have any questions concerning these instructions, please call National Customer Service 800.482.1717.

Assembly Instruction

Telephone 800.482.1717 Fax 812.482.8800 www.NationalOfficeFurniture.com Part # 2649287 Rev, A Printed in U.S.A © 2015 Kimball International, Inc.

Mio Wall

5

Figure F: Wall, base

vertical, and bottom

channel hidden for

better view.

Use #10 x 1” panhead screws from base

hardware kit here (4 per bracket)

Then attach worksurface to top channel brackets of base using #10 x 1” panhead screws from base hardware kit. See Figure F. Level the wall and base.

4 After unpacking the Mio worksurface, butt the back edge of the top against the wall. See Figures C and D. From base hardware, use (6) 3” L brackets spread out evenly underneath the worksurface and (24) #10 x 1” panhead screws to attach worksurface to wall. See Figure E. Note: Offset the L brackets 1/16” from the backedge of the work-surface before attaching brackets to Mio wall. This will help pull in any gaps.

Figure C Figure D

No Gap

L bracket 1”

from edge

Figure E

Offset L Brackets 1/16” from

edge

Page 3: Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to shorter Length. 8 Slide pole over protruding metal flanges to connect pole to the top

Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. If you have any questions concerning these instructions, please call National Customer Service 800.482.1717.

Assembly Instruction

Telephone 800.482.1717 Fax 812.482.8800 www.NationalOfficeFurniture.com Part # 2649287 Rev, A Printed in U.S.A © 2015 Kimball International, Inc.

Mio Wall

6 Remove the channel from the pole, set it and all other parts aside.

Steps 6-8 are used to attach the Power Pole. If the Power Pole option was not selected, skip to step 8.

7 With the Mio Unit in its desired location,

locate the power pole in the ceiling using

a plum bob or laser level. Mark the loca-

tion on the ceiling using the pole as a tem-

plate for the cut out. See figure G to right

Note: Varying ceiling materials will re-

quire various cutting processes and/or

tools. Consult with an Architect and/or

licensed contractor prior to making the

cut.

Note #2: It may be necessary to cut pole

to shorter Length.

8 Slide pole over protruding metal flanges to connect pole to the top

of the Mio Wall. It may be necessary to squeeze the flanges together

to create a press fit with the pole. See figure H below. Above the

ceiling tile, place the top ceiling plate over the power pole and align

the top and bottom plates. Fasten together using two (2) #8 x 1 1/2”

PanHead Phillips screws. See figure I below.

Figure G

Ceiling

Top Ceiling Plate

Bottom Ceiling Plate

Ceiling be-

tween plates

Figure H Figure I

Page 4: Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to shorter Length. 8 Slide pole over protruding metal flanges to connect pole to the top

Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. If you have any questions concerning these instructions, please call National Customer Service 800.482.1717.

Assembly Instruction

Telephone 800.482.1717 Fax 812.482.8800 www.NationalOfficeFurniture.com Part # 2649287 Rev, A Printed in U.S.A © 2015 Kimball International, Inc.

Mio Wall

11 Repeat steps 3 through 7 if wall is double sided.

9 For Single TV Mount: Attach horizontal AVTEQ TV mount rails to wall using (4) 5/16”-18 x 1” panhead screws. See figure J for correct orien-tation. Spread AVTEQ mount to desired width. To secure rails, use 3/16” drill bit through wall face to pre-bore holes for (4) M8 x 70 hex head lag screws and square spacers that come with TV Mount. Lag screws must be installed between 3” to 16” away from edge of wall. Then follow AVTEQ instruction sheet to complete TV mount installation. Note: Most TV mount hardware will be discarded.

Figure J: Correct

orientation of Sin-

gle TV Mount.

Note: Pre-bored holes in wall are offset. One screw

through top row, one through second row.

Double row of holes

Indicates top edge.

10 For Dual TV Mount: Attach horizontal AVTEQ TV mount rails to wall using (3) 5/16”-18 x 1” panhead screws. See figure K for correct ori-entation. To secure rails, use 3/16” drill bit through wall face to pre-bore holes for (8) M8 x 70 hex head lag screws and square spacers that come with TV Mount. Use lag screws into columns 1 and 10 from the right and columns 2 and 11 from the left, shown in figure G below. Then follow AVTEQ instruction sheet to complete TV mount installation. Note: Most TV mount hardware will be discard-ed.

Figure K: Correct

orientation of Dual

TV Mount.

Note: A single 5/16”-18 x 1” panhead screw is used

on top row with the lower most pre-bored hole (left),

two are used on bottom row. The upper right hole is

not used.

Double row of holes

Indicates top edge.

1 from right 10 from right 11 from left 2 from left

Page 5: Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to shorter Length. 8 Slide pole over protruding metal flanges to connect pole to the top

Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. If you have any questions concerning these instructions, please call National Customer Service 800.482.1717.

Assembly Instruction

Telephone 800.482.1717 Fax 812.482.8800 www.NationalOfficeFurniture.com Part # 2649287 Rev, A Printed in U.S.A © 2015 Kimball International, Inc.

Mio Wall

13 Depending on epicenter configuration, install each 16” L bracket(s) with (8) #8 x 1” panhead wood screws where worksurfaces will attach to back panel of Mio wall. See Figure N.

Figure N: Example of installing brackets on

one side of epicenter.

Worksurface

16” L bracket Epicenter

691mm or 27 3/16”

From bottom of panel to top of bracket

3” from end of worksurface to end of

bracket

Mio Wall

12 If an Epicenter configuration is selected, use 5/16-18 x 2.5” hex head shoulder bolts through epicenter frame to attach to threaded inserts on back of Mio Wall. See Figure L and M. Additional Blinder hardware are shipped when epicenters are used. See blinder instruction sheet for additional instructions.

Figure L: Upper Epicenter Figure M: Upper and Lower Epicenter

Page 6: Assembly Instruction - National Office Furniture · Note #2: It may be necessary to cut pole to shorter Length. 8 Slide pole over protruding metal flanges to connect pole to the top

Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. If you have any questions concerning these instructions, please call National Customer Service 800.482.1717.

Assembly Instruction

Telephone 800.482.1717 Fax 812.482.8800 www.NationalOfficeFurniture.com Part # 2649287 Rev, A Printed in U.S.A © 2015 Kimball International, Inc.

Mio Wall 14 Figures O and P show examples of the Mio setup with Epicenters. For

additional epicenter installation instructions see epicenter install sheet.

Figure O: Example of upper and lower

epicenter with worksurface on one side

Figure P: Example of upper and lower

epicenter with worksurface on both sides