Excellence in Execution S c h l u m b e r g e r - P r i v a t e Project : Assembly Fixture control and conventional naming Team Leader: Valeria Cabriales Team Members: Carlos Aragon. Adrian Sanchez de la Cerda Sergio Torres Alvarado Managers: John Tufts - MSS-CA PLM Ramiro Baez – Technology Manager Quality: Omar Sangabriel – QMS Coordina Esau Garcia - Quality Plan Con Angel Ramón Medellin López Finance Controller : Lupita Jesus LSS Support : Juan Angel Lopez Franco Project finish date :

Transcript of Assembly fixture inventory Report presentation

Page 1: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Project : Assembly Fixture control and conventional naming Team Leader: Valeria Cabriales

Team Members:Carlos Aragon.Adrian Sanchez de la CerdaSergio Torres Alvarado

Managers:John Tufts - MSS-CA PLMRamiro Baez – Technology Manager

Quality: Omar Sangabriel – QMS CoordinatorEsau Garcia - Quality Plan Control EngineerAngel Ramón Medellin López

Finance Controller : Lupita Jesus

LSS Support : Juan Angel Lopez Franco

Project finish date :

Page 2: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Personal Introduction

2

Valeria Marisol Cabriales Garza.

Mechatronic engineer student at,Facultad de Ingeniería Mecánica y Eléctrica (UANL)

Academic experience: Academical exchange: Dresden, Germany (July 2014- July 2015).

Professional experience:OSRAM Regensburg Germany (January 2014- July 2014)Optosemiconductors industry

LabView programmer Intern (testing and projects development).

Preh de México (August 2014-December 2014)Plastic injection for automobile industryMaintenance Intern.

Schlumberger CMPU (January 2015 – actual )Completions accessories Manufacturing Intern, Multistage.

Page 3: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Project Background An assembly fixture is a tool to perform an acceptance test. There are many different types and designs. They can be stated on GEMs.

D

M

A

I

C

Page 4: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Project BackgroundCribmaster is an inventory database.

Kits (relation between the part number and its corresponding fixtures)

D

M

A

I

C

Page 5: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Project Background 1,577 folders of fixtures drawings on the local server, “PJF####”. Fixtures for machining and assembly are mixed in the same server file.

D

M

A

I

C

Page 6: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

DefinitionD

M

A

I

C

Business Objectives:― On Time Shipment― HSE ― Quality

KPIs to measure impact:― OTS― Fixture Inventory

SCOPE: ― Assembly

MMS-CA

HSE

Quality

On time shipment

Inventory

Page 7: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Process Map of a fixtureD

M

A

I

C

Customer Demand

Part Number

ME’s

Planning

Search inventory of fixture

New Fixture design Production Quality

Assembly and

functional test

Pressure test

Assembly

Next Operation…

Page 8: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Problem /Opportunity Fixture’s nomenclature and control process are not standardize. It is not stated which fixture to use for a particular assembly

therefore time wasted during the search of fixtures. Non unified process between SC, MSS and LH Duplicated fixtures on inventory. Lack of fixture at the moment of the acceptance test

D

M

A

I

C

Page 9: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Measure – Process Map

Adexa Assembly demand

Design or buy

new fixture

Perform the

acceptance test

In-house or vendor fabrication

Process map before Project implementation.

D

M

A

I

C

Planning

EM’sYES

NO

YES

Does a Fixture is required?

Fixture on

GEMS?Cribmaster

NOSearch

adequate fixture

NO

No action required

YES

Page 10: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Measure – Process Map

Adexa Assembly demand

Design or buy

new fixture

Perform the

acceptance test

In-house or vendor fabrication

D

M

A

I

C

Planning

EM’sYES

NO

YES

Does a Fixture is required?

Fixture on

GEMS?

Search on Cribmaster Inventory

NOSearch

adequate fixture

NO

No action required

YES

Page 11: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Measure - Quantity of Fixtures per type

Drift Bar (OD /ID)

26%

Rod Bar2%

Test Sleeve3%

Test plug24%

Test cap15%

Bore seal18%

Expander (hp body)

1%

Landing Nipple 6%

Spacer4% Nut

1%

Drift Bar (OD /ID)Rod BarTest SleeveTest plugTest capBore sealExpander (hp body) Landing Nipple SpacerNut

M

D

A

I

C

Types of fixtures

Page 12: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Analyze

A

D

M

I

C

Lack of fixtures at

the moment of

the test.

Page 13: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Analyze

A

D

M

I

C

Problems/Root Causes SolutionNo ownership of fixtures assignation process.

Implementation for assembly fixture control procedureIndividual method to assign fixtures

No standardized procedure to register fixture on data base

No accurate information that describe the fixture

No restrictions for duplicated fixture

Fixture inventory reportTime wasted while searching the corresponding fixture

Inventory status is not complete reliableFixtures failure Validation of fixtures

Page 14: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

New Assembly and test fixtures control procedure DMS#101895158.

I

D

M

A

C

RELEASED

Page 15: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve - Procedure content

I

D

M

A

C

Assembly fixtures

Funcitonal test

Landing Nipple

Pressure test

Test plug/cap

Test cap (premium thread)

Test plug A

Test plug B

Bore seal plug A

Bore seal plug B

Rod bar Nut HP body (expander) Test sleeve

Drift test

Drift bar

OD Drift bar (external diameter)

ID Drift bar (Internal

diameter)

Fixture categorization.

Page 16: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve - Procedure content

I

D

M

A

C

Fixture example nomenclature.

Page 17: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

Example of a faster search:

Thread type : 1.750-4 stub acme

I

D

M

A

C

Page 18: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve – Assembly fixtures process map

I

D

M

A

C

- Define if a fixture is required- Search adequate Fixture

Page 19: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve – Assembly fixtures process map

I

D

M

A

C

- Compatible fixture or new design- Sustaining validation

Page 20: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve – Assembly fixtures process map

I

D

M

A

C

- Add fixture information to cribmaster

Page 21: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve – Assembly fixtures process map

I

D

M

A

C

- Verify fixture inspection

Page 22: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve – Assembly fixtures process map

I

D

M

A

C

- Purchase or machine a fixture

Page 23: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

Standard work instructions (SWI) :―Register a new fixture in cribmaster (AT-49).―Register a kit of fixtures in cribmaster (AT-50).

I

D

M

A

C

AT-49 AT-50RELEASED

RELEASED

Page 24: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

I

D

M

A

C

Page 25: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

I

D

M

A

C

Page 26: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

I

D

M

A

C

Page 27: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

I

D

M

A

C

Page 28: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

I

D

M

A

C

Page 29: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Improve

I

D

M

A

C

Page 30: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Actual status of fixtures on cribmaster

Drift Bar (OD /ID)

26%

Rod Bar2%

Test Sleeve3%

Test plug24%

Test cap15%

Bore seal18%

Expander (hp body)

1%

Landing Nipple 6%

Spacer4% Nut

1%

Drift Bar (OD /ID)

Rod Bar

Test Sleeve

Test plug

Test cap

Bore seal

Expander (hp body)

Landing Nipple

Spacer

NutI

D

A

M

C

Page 31: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Control

Assembly and Test Fixture Control procedure Standard work instructions Assembly fixture report Meeting and indoctrination sessions

C

D

M

A

I

Page 32: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Project CostsCost and benefits calculations

Project: "Assembly Fixtures control and conventional naming"

Savings calculations (time saving)

Time searching (before)Time searching (after

improvement)New kits registered on

2015 Fixtures average per kit ME's hour cost Subtotal saving

1:00:00 0:10:00 81 2 $ 22.50 $ 2,187.00

Cost calculations

Hours Hour cost Subtotal cost

40 22.5 $ 900.00

Total calculations

Subtotal saving (time searching) Total project cost TOTAL

$ 2,187.00 $ 900.00 $ 1,287.00

Page 33: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Project Benefits:

― Faster search of fixtures― Avoid any extra inventory ― Accurate information about fixture characteristics ― Planning activities are done before production dates ― Improve 16% of lack of fixture― Improve 66% fixture process flow for CA― Creation of 92 kits until today.― Could be used by the 3 PL.

Page 34: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Next Steps

― Continuous improvement of the inventory report― Migrate fixtures to Gems― Reduce the variety of fixture designs

Page 35: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Knowledge gained…– Drawings interpretation.– SWI, visual aid, process map, procedures development. – Machining, testing and Assembly process– Time management– CI projects development

Page 36: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Question and answer section

?

Page 37: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Thank you!

Page 38: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Measure Total number of kits of MSS part numbers until 2014: 233 kit’s Average per year: 38 kitsM

D

A

I

C2009 2010 2011 2012 2013 2014

9

30

55 53

22

64

Number of Kits per yearNumber of Kits per year

Page 39: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Definition Catalog of fixtures has very varied options.

D

M

A

I

C

Test plug B Test plug BRod Bar

Test plug B

Bore seal plug B

NutSpacer

Test plug B Bore Seal plug B

Test plug B Configuration

Mixed Bore Seal Plug B/Test Plug B configuration

Bore Seal Plug B configurationBore Seal plug BBore Seal plug B

Rod Bar

SpacerNut Nut

Page 40: Assembly fixture inventory Report presentation

Excellence in Execution

Schlumberger-Private

Project BackgroundThe (F.A.T.) factory acceptance test:- Drift test - Functional test - Pressure test