1 Minor Mineral Ordinary Soil Mine (Proposed Project) Village : Jambusar, Ta : Jambusar, Dist : Bharuch (Gujarat) Production Capacity : 1,00,000TPA Area : 05-99-12 Ha. Proposal For Environmental Clearance As per the EIA Notification 15th January 2016 Proponent Sh Indravadan Rana, S/O Sh Girishbhai Rana At : Jambusar, Sr. No. 1824/A Paiky, Taluka : Jambusar, Dist : Bharuch Mo :- +91 9824218590

Transcript of As per the EIA Notification 15th January 2016...

1

Minor Mineral Ordinary Soil Mine

(Proposed Project)

Village : Jambusar, Ta : Jambusar, Dist : Bharuch (Gujarat)

Production Capacity : 1,00,000TPA

Area : 05-99-12 Ha.

Proposal

ForEnvironmental Clearance

As per the EIA Notification 15th January 2016

Proponent

Sh Indravadan Rana,S/O Sh Girishbhai Rana

At : Jambusar, Sr. No. 1824/A Paiky,

Taluka : Jambusar, Dist : Bharuch

Mo :- +91 9824218590

2

Sh Indravadan Rana, S/O Sh Girishbhai Rana

“Link bungalows, Link Road,

Bharuch

Date 2-9-2016

To,

Assistant Geologist,

Geology and Mining Dept.,

Collector Offices,

Bharuch

Sub :- Application for Environmental Clearance Certificate (Ec.)

Respected Sir,

As per the EIA Notification 15th January 2016 it is compulsory to get Ec. to domining activities of minor mineral. I the applicant Sh Indravadan Rana, S/O ShGirishbhai Rana applied of mineral Ordinary Soil of area 05-99-12 Ha. at Village :Jambusar, Taluka : Jambusar, Dist. Bharuch from collector Bharuch. I amsubmitting the application for Ec. in prescribe form and format.

Your Thanking

Sh Indravadan Rana, S/O Sh Girishbhai Rana

Submissions :-

(A) Form - 1 M

(B) Form - 1

(C) Pre-feasibility Report

3

(A)

FROM - 1 M

APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY "B2"FOR LESS THAN AND EQUAL TO FIVE HECTARE

Basic Information:-

(viii) Name of the Mining Lease site Sh Indravadan Rana, S/O ShGirishbhai Rana

(ix) Location / site (GPS Co-ordinates) Jambusar/22° 0'49.77"N 72°47'18.67"E

(x) Size of the Mining Lease (Hectare) 05-99-12 Hectare(xi) Capacity of Mining Lease (TPA) 1,00,000TPA(xii) Period of Mining Lease Approximately 5 Years(xiii) Expected cost of the Project Approximately 10.00 Lacs.(xiv) Contact Information 98242 18590

Environmental Sensitivity:-

Sr.No.

Area Distance inKilometer/Details

1. Distance of project site from nearest rail or roadbridge over the concerned River, Rivulet, Nallahetc,

Distance from thenearest bridge over theRiver is about 7.39 Km

2. Distance from infrastructural facilitiesRailway line 4.41 KmNational Highway 4.52 Km N.H. No. 228State Highway 4.52 Km S.H. No. 6Major District Road 4.52 Km N.H. No. 228Any Other Road Jambusar 0.09 Km

Gramya Marg.Electric Transmission Line pole or tower Electric Pole is 3.72 Km

away from leaseboundary.

Canal or check dam or reservoirs or lake orponds

Check dam 4.09 km awayfrom lease boundary.

In-take for drinking water pump house Drinking water tankJambusar.

Intake for Irrigation canal pumps None3. Areas protected under international

conventions, national or local legislation for theirecological, landscape, cultural or other relatedvalue

None

4. Areas which are important or sensitive forecological reasons - Wetlands, watercourses orother water bodies, coastal zone, biospheres,

None

4

mountains, forests5. Areas used by protected, important or sensitive

species of flora or fauna for breeding, nesting,foraging, resting, over wintering, migration

None

6. Inland, coastal, marine or underground waters Underground water levelis below 200 Mtr.

7. State, National boundaries None8. Routes or facilities used by the public for access

to recreation or other tourist, pilgrim areasNone

9. Defence installations None10. Densely populated or built-up area, distance

from nearest human habitationJambusar is about 3.72Km away from leaseboundary.

11. Areas occupied by sensitive man-made landuses (Hospitals, Schools, Places of worship,community facilities)

Jambusar is about 3.72Km away from leaseboundary.

12. Areas containing important, high quality orscarce resources (ground water resources,surface resources, forestry, agriculture,fisheries, tourism, minerals)

None

13 Areas already subjected to pollution orenvironmental damage. (those where existinglegal environmental standards are exceeded)

No critically polluted areain the periphery of 10.00Km from lease boundary.

14. Areas susceptible to natural hazard which couldcause the project to present environmentalproblems (earthquakes, subsidence, landslides,erosion, flooding or extreme or adverse climaticconditions)

None

15. Is proposed mining site located over or nearfissure / fracture for ground water recharge

No, Proposed miningproject will not affectground water rechargesystem.

16. Whether the proposal involves approval orclearance under the following Regulations orActs, namely :

None

(a) The Forest (Conservation) Act, 1980 None(b) The Wildlife (Protection) Act, 1972 None(c) The Coastal Regulation Zone Notification,

2011.None

If yes, details of the same and their status to begiven.

17. Forest land involved (hectares) None.18. Whether there is any litigation pending against

the project and/or land in which the project ispropose to be set up ?

No Litigation is pendingagainst the lease area /applicant of this leasearea in not any court oflaw as per our bestknowledge.

(a) Name of the Court -

5

(b) Case No. -(c) Orders or directions of the Court, if any,

and its relevance with the proposedproject.

-

(Signature of ProjectProponent)

Sh Indravadan Rana, S/O ShGirishbhai Rana

At:Jambusar

Ta: Jambusar

Dist: Bharuch

6

(B)FROM 1 (Application for Environment Clearance Certificate)

Sr.No.

Item Details

1 Name of the Project Ordinary Clay Mining Project ofSh Indravadan Rana, S/O Sh Girishbhai

RanaAt village :Jambusar,Ta:JambusarDis.Bharuch.

2 S. No in schedule As per Gazette Notification dated 15thJanuary 2016.

3 Proposedcapacity/area/length/tonnage tobe handled/commandarea/lease area/number of wellto be drilled

S.No. Proposed Capacity Area1. 1,00,000TPA 05-99-12

Ha.

4 New/expansion/modernization It is a Proposed Project.5 Proposed capacity/area etc. The Proposed Capacity is nil and lease area

is05-99-12 Ha.

6 Category of project i.e. “A” or“B”

" B-Category as per EIA Notification 2016

7 Does it attract the generalcondition? If yes please specify

No, it does not attract the general Condition.

8 Does it attract the specificcondition? If yes please specify

No, it does not attract the Specific Condition.

9 Location The lease area of Ordinary Soil situated nearvillage: Jambusar., Ta : Jambusar, Dist :Bharuch (Gujarat) The geographical locationof the mine is as under :-Latitude (N) Longitude (E)22° 0'49.77"N 72°47'18.67"E

Plot/Survey/Khasra No Govt. sr. no. 1824/A Paiky.Village JambusarTehsil JambusarDistrict BharuchState Gujarat

10 Nearest railway station/airportalong with distance in Kms.

S.No.

Particulars Name Distance(FromLeaseboundaryin km.)

1 Nearestrailwaystation

Jambusar 4.07 km.

2 Nearest Rajkot 57.51 km

7

Airport11 Nearest town, city, district

headquarter along withdistance in Kms.

S.No.

Particulars Name Distance(FromLeaseboundary)

1 NearestVillage

Jambusar 3.72 km

2 Nearest City Jambusar 3.72 km3 Nearest

DistrictHeadquarter

Bharuch 36.84 km

12 Village Panchayat, ZilaParishad, MunicipalCorporation, local body(Complete postal address withtelephone nos to be given)

VillagePanchayat

Jambusarvillagepanchayat.

3.72 km

ZillaPanchayat

BharuchDistrictPanchayat

36.84 km

Nagarpalika JambusarNagarpalika

3.72 km

PostalAddresswithtelephoneNo.

Sh Indravadan Rana, S/OSh Girishbhai Rana“Link bungalows,Link road,Bharuch

13 Name of the applicant Sh Indravadan Rana, S/O Sh GirishbhaiRana

Link bungalows,Link road ,Bharuch ,

14 Registered address Sh Indravadan Rana, S/O Sh GirishbhaiRanaLink bungalows,Link road ,Bharuch

15 Address for correspondence Sh Indravadan Rana, S/O Sh GirishbhaiRana

Link bungalows,Link roadBharuch ,

Name Sh Indravadan Rana, S/O Sh GirishbhaiRanaLink bungalows,Link road ,Bharuch ,

Designation OwnerAddress Sh Indravadan Rana, S/O Sh Girishbhai

RanaLink bungalows,Link road ,Bharuch

Pin code

8

E-mail [email protected] 09824218590Fax No --

16 Details of alternative sitesexamined, if any. Location ofthese sites should be shown ona topo sheet

No. Mineral Ordinary Soil is naturallyoccurring resource and this is a site specificproject. Hence no alternative can be chosen.

17 Interlinked Project N.A.18 Whether separate application

for interlinked project has beensubmitted?

N.A.

19 If yes date of submission N.A.20 If no reason N.A.21 Whether the proposal involves

approval/ clearance under: ifyes, details of the same andtheir status to be given.

No

The Forest (Conservation) Act,1980?

There is no reserve orprotected forest within 10.00km periphery of lease area.

N.A

The Wildlife (Protection) Act,1972?

There is no Wildlife sanctuarywithin 10.00 km periphery oflease area

N.A

Eco-Sensitivity zone within10.00 km periphery of leasearea

N.A

The C.R.Z. Notification, 1991? There is no C.R.Z. within 10.00 km peripheryof lease area.

22 Whether there is anyGovernment order/policyrelevant/ relating to site

N.A.

23 Forest Land involved? N.A.24 Whether there is any litigation

pending against the projectand / or land in which theproject is propose to be set upName of courtCase noOrder/directions of the court,

No other litigation is pending in the any courtof law as per our best knowledge.

9

1. Construction, operation or decommissioning of the project involving actions, which willcause physical changes in the locality (topography, land use, changes in water bodies,etc)

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details there of with approximatequantity/rate wherever possiblewith source of information of data

1.1 Permanent or temporarychange in land use, landcover or topographyincluding increase inintensity of land use (withrespect to local land useplan)

No Land will be used for collection ofOrdinary Soil for filling purpose ininfrastructures; it does not involveany permanent change in thetopography of the permit hold area.

1.2 Clearance of Proposed land,vegetation and buildings?

No There is no tree or Proposedstructure on the proposed site.Hence no clearance is required.

1.3 Creation of new land uses? No N.A.1.4 Pre-construction

investigations e.g. boreholes, Clay testing?

No Not Applicable

1.5 Construction works? No Not Applicable1.6 Demolition works? No Not Applicable1.7 Temporary sites used for

construction works orhousing of constructionworkers?

No Workers are hired from nearbyvillages so no housing facility isrequired. However, temporary restshelters will be provided at the site.

1.8 Above ground buildings,structures or earthworksincluding linear structures,cut and fill or excavations

No Not Applicable

1.9 Underground works includingmining or tunneling?

No Not Applicable

1.10 Reclamation works? No No reclamation work will be done1.11 Dredging? No Ordinary Soil mining will be done.

1.12 Offshore Structures? No There will be no off shore structures.

1.13 Production andmanufacturingprocesses?

No Nil

if any and its relevance withthe Proposed project.

25 Expected cost of the project Rs.2,00,000 /-

10

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details there of with approximatequantity/rate wherever possiblewith source of information of data

1.14 Facilities for storage ofgoods or materials?

yes Not required.

1.15 Facilities for treatment ordisposal of solid waste orliquid effluents?

No No need for treatment or disposal ofsolid waste and liquid effluents.

1.16 Facilities for long termhousing of operationalworkers?

No Not Applicable

1.17 New road, rail or sea trafficduring construction oroperation?

No Not Applicable

1.18 New road, rail, airwaterborne or other transportinfrastructure including newor altered routes andstations, ports, airports etc?

No Not Applicable

1.19 Closure or diversion ofProposed transport routes orinfrastructure leading tochanges in trafficmovements?

No Not applicable

1.20 New or diverted transmissionlines or pipelines?

No N.A.

1.21 Impoundment, damming,culverting, realignment orother changes to thehydrology of watercourses oraquifers?

No N.A.

1.22 Stream crossings? No N.A.1.23 Abstraction or transfers of

water form ground or surfacewaters?

No Not Required

1.24 Changes in water bodies orthe land surface affectingdrainage or run-off?

No The mining will be up to 1.5 mtrsonly which will not intersect theground water level or water. bodies.

1.25 Transport of personnel ormaterials for construction,operation ordecommissioning?

No In the operation phase Ordinary Soilwill be excavated by manual only.

1.26 Long-term dismantling ordecommissioning orrestoration works?

No Not Applicable

11

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details there of with approximatequantity/rate wherever possiblewith source of information of data

1.27 Ongoing activity duringdecommissioning whichcould have an impact on theenvironment?

No N.A.

1.28 Influx of people to an areaeither temporarily orpermanently?

No Mostly local people are deployedto carry out the extraction. Sono influx of people will be seen.

1.29 Introduction of alien species? No Not Applicable1.30 Loss of native species or

genetic diversity?No Not Applicable

1.31 Any other actions? No Not applicable2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

Sr.No

Information/Checklistconfirmation

Yes/No?

Details there of with approximatequantity/rate , wherever possiblewith source of information data

2.1 Land especially undeveloped oragricultural land (ha)

No The activity will be done in theproposed Ordinar clay minePermit area which is a Talav landwhich is govt. Land. No agriculturalland is involved.

2.2 Water (expected source &competing users) unit: KLD

Yes Total water requirement is about1.0 KLD. This water will be metfrom nearby Borewel.

2.3 Minerals (MT) No -2.4 Construction material - stone,

aggregates, Clay / Clay (expectedsource, MT)

No No Construction material isrequired.

2.5 Forests and timber (source, MT) No Not applicable2.6 Energy including electricity and

fuels (source, competing users)unit: fuel (MT), energy (MW)

No Not applicable

2.7 Any other natural resources (useappropriate standard units)

No Not envisaged.

3. Use, storage, transport, handling or production of substances or materials, which could beharmful to human health or the environment or raise concerns about actual or perceivedrisks to human health.

Sr.No.

Information / Checklistconfirmation

Yes/No?

Details are there of withapproximate quantity/ratewherever possible with sourceof information of data

12

3.1 Use of substances or materials,which are hazardous (as perMSIHC rules) to human healthor the environment (flora, fauna,and water supplies)

- Not Applicable

3.2 Changes in occurrence ofdisease or affect diseasevectors (e.g. insect or waterborne diseases)

- Not Applicable

3.3 Affect the welfare of people e.g.by changing living conditions?

No This project will not affectthewelfare of people. However it willprovide livelihood to theworkforce during the operationwhich will rather help inimproving their living conditions.

3.4 Vulnerable groups of peoplewho could be affected by theproject e.g. hospital patients,children, the elderly etc.,

No This project will not affectthevulnerable groups of people.

3.5 Any other causes Yes Transportation is one of themajoractivities in the project. Accidentsmay occur, which may beavoided by taking due care &precautions.

4. Production of solid wastes during construction or operation or decommissioning(MT/month)

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there of withapproximate quantity/ratewherever applicable with sourceof information of data

4.1 Clay, overburden or minewastes

No. It is to make water reservoir deeperso there will not be any O.B. orMine waiste..

4.2 Municipal waste (domestic andor commercial wastes)

No No domestic or commercial wastes.

4.3 Hazardous wastes (as perHazardous Waste ManagementRules)

No N.A.

4.4 Other industrial process wastes No Not applicable4.5 Surplus product No No surplus product generates.4.6 Sewage sludge or other sludge

from effluent treatmentNo N.A.

4.7 Construction or demolitionwastes

No Not Applicable

4.8 Redundant machinery orequipment

No N.A.

4.9 Contaminated Clays or other No Not Applicable

13

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there of withapproximate quantity/ratewherever applicable with sourceof information of data

materials4.10 Agricultural wastes? No Not Applicable4.11 Other solid wastes? No N.A.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details there of withapproximate quantity/ratewherever applicable withsource of information of data

5.1 Emissions from combustion offossil fuels from stationary ormobile sources

Yes There will be emissions duetotransportation of material fromsite to the end user. But theaverage number oftruck/tractor to be loaded perhour is not more than one.

5.2 Emissions from productionprocesses

Yes There will be small amount ofdust emission during theexcavation process

5.3 Emissions from materialshandling including storage ortransport

Yes There will be emission ofdust during the transportationof Ordinary Soil from Permitarea to the Filling site area.

5.4 Emissions from constructionactivities including plant andequipment

No _

5.5 Dust or odours from handling ofmaterials including constructionmaterials, sewage and waste

No _

5.6 Emissions from incineration ofwaste

No _

5.7 Emissions from burning of wastein open air (e.g. slash materials,construction debris)

No _

5.8 Emissions from any other sources No _

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there of withapproximate quantity/rate whereverapplicable with source ofinformation of data

14

6.1 From operation ofequipment e.g. engines,ventilation plant, crushers

- Not Applicable

6.2 From industrial or similarprocesses

- Not Applicable

6.3 From construction ordemolition

- Not Applicable

6.4 From blasting or piling - Not Applicable6.5 From construction or

operational traffic- Not Applicable

6.6 From lighting or coolingsystems

- Not Applicable

6.7 From any other sources - Not Applicable7. Risks of contamination of land or water from releases of pollutants into the

ground or into sewers, surface waters, groundwater, coastal waters or thesea

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there of withapproximate quantity/ratewherever applicable with sourceof information of data

7.1 From handling, storage, useor spillage of hazardousmaterials

- Not Applicable

7.2 From discharge of sewage orother effluents to water or theland (expected mode andplace of discharge)

- Not Applicable

7.3 By deposition of pollutantsemitted to air into the land orinto water

Yes Only dust emission is expectedinto air due to movement ofvehicles. However dust suppressionwill be done by sprinkling water.

7.4 From any other sources No -7.5 Is there a risk of long term

build up of pollutants in theenvironment from thesesources?

No -

8. Risk of accidents during construction or operation of the Project, whichcould affect human health or the environment

Sr.No.

Information/Checklistconfirmation

Yes/No? Details are there of withapproximate quantity/ratewherever applicable withsource of information of data

8.1 From explosions, spillages, firesetc from storage, handling, useor production of hazardoussubstances

No No such activity is envisaged.

8.2 From any other causes Yes Risk of accidents is expected

15

Sr.No.

Information/Checklistconfirmation

Yes/No? Details are there of withapproximate quantity/ratewherever applicable withsource of information of dataduring transportation and duringloading of minerals intotrucks/tractors.

8.3 Could the project be affected bynatural disasters causingenvironmental damage e.g.floods, earthquakes, landslides,cloudburst etc)?

Yes The mine lease area lies inSeismicZone III which is prone toearthquakes. However there areno built in structures at the sitewhich would affect the mining.

9. Factors which should be considered (such as consequential development)which could lead to environmental effects or the potential for cumulativeimpacts with other Proposed or planned activities in the locality

Sr.No.

Information/Checklistconfirmation

Yes/No? Details are there of withapproximate quantity/ratewherever applicable withsource of information of data

9.1 Lead to development ofsupporting. Facilities , ancillarydevelopment or developmentstimulated by the project whichcould have impact on theenvironment e.g.: supportinginfrastructure (roads, powersupply, waste or waste watertreatment, etc.) housingdevelopment extractiveindustries supply industries,(other)

- Not Applicable

9.2 Lead to after-use of the site,which could have an impact onthe environment

- Not Applicable

9.3 Set a precedent for laterdevelopments

- Not Applicable

9.4 Have cumulative effects due toproximity to other Proposed orplanned projects with similareffects

- Not Applicable

10. Environmental SensitivitySr.No

Area Name /identity

Aerial distance (within 10 km) fromProposed location boundary

1 Areas protected under

international

Nil -

16

Sr.No

Area Name /identity

Aerial distance (within 10 km) fromProposed location boundary

conventions, national

or local legislation for

their ecological,

landscape, cultural or

other related value

2 Areas which are

important or sensitive

for ecological reasons -

Wetlands,

watercourses or other

water bodies, coastal

zone, biospheres,

mountains, forests

Nil -

3 Areas used by

protected, important or

sensitive species of

flora or fauna for

breeding, nesting,

foraging, resting, over

wintering, migration

Nil -

4 Inland, coastal, marine

or underground waters

No Not Applicable

5 State, National

boundary

No Not Applicable

6 Routes or facilities

used by the public for

access to recreation or

other tourist, pilgrim

areas

No Not Applicable

7 Defense installations No Not Applicable

8 Densely populated or Yes Nearest village Jambusar (Population

17

Sr.No

Area Name /identity

Aerial distance (within 10 km) fromProposed location boundary

built-up area 800) is about 3.72 km.

9 Areas occupied by

sensitive man-made

land uses (hospitals,

schools, places of

worship, community

facilities)

Yea All facilities available at city Bharuch

which is 36.84 km away from lease area.

10 Areas containing

important, high quality

or scarce resources

(ground water

resources, surface

resources, forestry,

agriculture, fisheries,

tourism, minerals)

Nil

-

11 Areas already

subjected to pollution

or environmental

damage. (those where

Proposed legal

environmental

standards are

exceeded)

Nil -

12 Areas susceptible to

natural hazard which

could cause the project

to present

environmental

problems

(earthquakes,

subsidence, landslides,

Yes The water level in river may fluctuate

depending on the rainfall intensity.

According to BMTPC Vulnerability Atlas

(earthquake), the study area falls in a

Zone-III.

There is no incidence of landslide but in

2001 a major incidence of earth quake

was there.

18

Sr.No

Area Name /identity

Aerial distance (within 10 km) fromProposed location boundary

erosion, flooding or

extreme or adverse

climatic conditions)

There is no date available flooding of the

area.

(IV).Proposed Terms of Reference for EIA studies

We request you to consider our project as B2 category project looking to tiny scale of ourproject and negligible potential of environmental impacts.

“I hereby given undertake that the data and information given in the application andenclosures are true to the best of my knowledge and belief and I am aware that if any part ofthe data and information submitted is found to be false or misleading at any stage, theproject will be rejected and clearance given, if any project will be revoked at our risk andcost.”

Date :- 2-09-2016Place :-Bharuch.

Signature of the applicant

Sh Indravadan Rana, S/O Sh Girishbhai RanaAt : Jambusar,

Taluka : Jambusar,Dist : Bharuch,

19

NOTE :

1. The projects involving clearance under Coastal Regulation Zone Notification.

1991 shall submit with the application a C.R.Z. map duly demarcated by one

of the authorized agencies. showing the project activates, w.r.t. C.R.Z. (at the

stage of TOR) and the recommendations of the State Coastal Zone

Management Authority (at the stage of EC). Simultaneous action shall also be

taken to obtain the requisite clearance under the provisions of the C.R.Z.

Notification, 1991 for the activities to be located in the CRZ.

2. The projects to be located within 10 km of national Parks. Sanctuaries.

Biosphere Reserves, Migratory Corridors of Wild Animals, the project

proponent shall submit the map duly authenticated by Chief Wildlife Warden

showing these features vis-à-vis the project location and the

recommendations or comments of the Chief Wildlife Warden thereon (at the

stage of EC)".

3. All correspondence with the Ministry of Environment & Forests including

submission of application for TOR/Environmental Clearance, subsequent

clarification, as may be required from time to time, participation in the EAC

Meeting on behalf of the project proponent shall be made by the authorized