ARUP_Presentation_Tunnel Geoheat Source UK 21 02 11

download ARUP_Presentation_Tunnel Geoheat Source UK 21 02 11

of 42

description

Tunnel Geothermal Linings- Principles, Benefits, and Potential IssuesDuncan Nicholson15/02/2011Presented at Geothermal Tunnel Lining Workshop

Transcript of ARUP_Presentation_Tunnel Geoheat Source UK 21 02 11

  • Geothermal Tunnel Linings - WorkshopAgenda 08.30 Registration & Coffee, Breakfast

    09.00 Introduction & Welcome

    09.15 Principles & Benefits of tunnel geothermal energy Duncan Nicholson, Director ARUP Geotechnics

    1

    09.45 Installing geothermal pipe in Tunnel linings Ralf Winterling, Technical Director REHAU Ltd

    10.15 Energy lining segment design and construction Case History Dr. Jan-Niklas Franzius, Zblin AG

    10.45 Discussion and questions

  • Tunnel Geothermal Linings- Principles, Benefits, and Potential Issues

    Duncan Nicholson 15/02/2011 Presented at Geothermal Tunnel Lining Workshop

  • Contents

    Background Geothermal tunnels

    cold tunnels and hot tunnels Connecting tunnels to buildings Impaction of ground conditions Market and distribution

    3

    Benefits Potential issues

    below surface: pipework connections, fire safety and structural integrity

    above surface:- access installation:- impact on tunnel construction programme

  • Background Ground Sourced Heat Energy

    Open Systems Water wells Extract water 500kW / hole

    Closed Systems Vertical or horizontal loops Extract heat 3.5kW / hole

    Source: Commercial Earth Energy Systems (Canada Natural Resources)

  • Geothermal Piles and Sprayed Lining

    5

    Geothermal Piles at

    One New Change,

    Arup (2009)

    Austrian Sprayed concrete lining at Lainzer Tunnel,

    After Brandl (2006)

  • Other Infrastructure Projects Loops are used in;-

    Diaphragm walls Base slabs Linings of the station tunnels, eg metro NATM tunnel lining, Channel Tunnel heat-exchange pipes

    Crossrail

    6

    Diaphragm wall, Brandl (2006)

    Crossrail Redevelopment above stations: Thermal diaphragm walls Thermal piles

  • Geothermal Tunnel Concept

    7

    Access points at 500m centres for each tunnel

  • Position of pipes inside tunnel segment

    Thermal Loops Inside Segment

    Box out section for the pipe connections.

  • Hot TunnelsHot Tunnels:

    Tunnel air temperature higher than ground Heat Energy mostly from tunnel

    Mainly for building heating helps to cool the tunnel Not efficient for cooling building Tunnel

    9

    Hot tunnel locations :- cable tunnels, foul sewers, Deep/long rail and road tunnels

    Not efficient for cooling building Tunnel Heat source

    Ground Heat source

  • Cold tunnelsCold Tunnels:

    No tunnel heat source Tunnel air temperature low Provides building heating and cooling Heat energy mostly from soil mass not tunnel

    No tunnel

    10

    Cold Tunnel locations Short road and rail tunnels Cold climates Good natural air ventilation

    No tunnelheat source

    Ground Heat source

  • Cold Tunnel Example Janbech Tunnel

    11

    Details to be given by Dr Franzius from Zblin

  • Linking Header pipes to surface

    12

    Existing access points

    Shafts, stations, entrances,

    Dedicated access points

    Boreholes

  • Vertical Drilling Connect cross passage or tunnel

    202 casing with 110mm pipeVerticality tolerance

    1 in 200 (+/-100mm at 20m depth)

    2 boreholes per access point for header and return~ 40K for a pair~ 40K for a pair

  • Inclined Drilling14m

    Connect to cross passage /tunnel

    225 liner with 2 x 110mm pipe inside .

    1 borehole per access point

    Verticality tolerance 1 in 200 +/-100mm at 20m depth Up to 35o from vertical

    Cost 33K

  • Directional Drilling Connection surface site 50-100m from tunnel 300mm liner with 2 x 110mm pipes Magnetic guidance system

    Accuracy +/-0.1o

    49K for 100m

    15

  • Impact of Ground Conditions

    Tunnels in Clay: Heat stays, - local conduction Access boreholes - easy to construct

    Heat conduction

    16

    Tunnels in Sand: Heat dissipates with ground water

    flow Access borehole are difficult to

    construct water bearing sand. Grouting required

    Ground water flow

  • Thermal transfer Heat transfer mainly from hot air inside tunnel to

    heat buildings.

    Heat transfer from plastic pipe 30w/m2

    Assume pipe loops at 0.5m centres in rings

    17

    Assume pipe loops at 0.5m centres in rings Power out put is 15 x 40m = 0.6KW/m of tunnel.

    For 6m dia tunnel 1000m long = 600kW.

  • Thermal Transfer Modelling - SetupOuter radius: temperature fixed at 15C

    18

    Heat extracted from pipes at rate equivalent to 30W/m2 of tunnel surface

    Inner surface: receives heat from tunnel air q = (Tair Tseg).

  • Heat Transfer - Hot Tunnels

    Heat extraction rate = 30W/m2(Constant)

    Tunnel air temperature = 25oC

    Pipe temperature = 17.6oC

    All heat extraction comes from

    19

    All heat extraction comes from the tunnel

    For pipe flow rate of fluid = 0.27l/s

    Flow temp = 14.6C approxReturn temp = 20.6C approx

  • Market for Tunnel Geothermal Low grade energy source use locally

    Residential buildings heating demand Office blocks cooling and heating demands

    20

    Old buildings - refurbishment New buildings - renewable source requirement

    Helps at Planning Stage with Part L

    Cools tubes / ground reduces ventilation costs

  • Typical London Residential Building

    Typical 5 Storey refurbished buildings heating needs 40-50W/m2 of floor.

    Say 16 flats /building unit Space heating 40kW. Hot water 25kW.

    21

    Hot water 25kW.

    Similar to 50 to 100m long tunnel section.

  • Market for Tunnel Geothermal

    Building options: Existing buildings: residential housing dominated by space

    heating over the cold season, topped with DHW Existing building: office/retail complex, heating and cooling New buildings - heating and cooling

    Base Load and Peak Load

    22

    Base Load and Peak Load Combined GSHP and gas boiler

    GIS mapping of potential users along tunnel alignment

  • Buildings Identification Stage GIS

    23

  • Distribution of Tunnel Geothermal

    ESCO typeso Privately-owned ESCOs - More efficient at running district heating schemeso Private ownership - Only really works for large schemes (billing complexity)o Publicly-owned schemes - Difficulty growing (profit reinvestment constraint)

    Renewable Heat Incentiveo The indicative tariff is 1.5p/kWh for heat generated

    24

    o The indicative tariff is 1.5p/kWh for heat generated

    Main Heat Supply Optionso 1: Tunnel owner retains ownership of assets, identifies customers and sells heato 2: Tunnel owner becomes ESCO, - installs tunnel / access pipework and sells heat

    directlyo 3: Tunnel owner sells heat rights to an ESCO who installs access pipe work

  • Benefits of Tunnel Geothermal

  • Benefits

    Tunnel geothermal energy is renewable, low carbon, sustainable.

    Compatiable with Ground Source Heat Pumps Cheaper that vertical borhole loop options. Similar cost to thermal piles

    26

    Similar cost to thermal piles

    Payback time can be viable in many cases Provides an option for Cooling the Tube or

    adjacent tubes.

  • Cost Benefit Analysis Gas comparison

    1970s Council Block

    Central Boiler Room

    800kW Gas boiler

    Base Case

    400kW Gas boilerGSHP (cost of above ground works only)

    27

    400kW Gas boiler400kW Heat pump

    ground works only)

    GSHP (including cost of below ground works)

    400kW Gas boiler400kW Heat pump+ Ground Works

  • Cost Benefit AnalysisAnalysis of differential costs/revenues above the central gas boiler retrofit baseline

    Capital Costs Above Ground: Installed gas boilers/heat pump- 800kWth total thermal system

    size, 400kWth heat pump. Below Ground: hard dig trench & man hole; borehole connection; tunnel lining

    pipework installation.

    O&M Costs

    28

    O&M Costs Maintenance of building systems Sinking fund

    Fuel Costs

    Revenue RHI @ 1.5p/kWh heat generated CO2 @ 12/tonne. Approx saving of 80 tonnes CO2/yr

  • Key Financial Figures

    Basecase

    GSHP Excluding Below

    Ground Works

    GSHP Including below

    ground works

    CapEx () 80,400 144,200 269,000

    O&M Costs (/yr) 4,200 15,000 15,000

    29

    CO2 Sold at 12/tonne Sinking fund factored- 15years for Heat Pump, 25 years for boiler

    Fuel Costs (/yr) 26,800 22,000 22,000

    Revenue (/yr) 0 13,400 13,400

  • Added Benefit Cooling the Tube

    Extracted significant heat from tunnel Reduce cost on cooling/ventilation system

    30

  • Potential Issues and Risks

  • Pipe joint Rotation

    32

  • Joint rotation effects Max ring deformation = 1% of dia.

    Joint rotation is 1.45 degree

    Joint opening = 150mm tan 1.45

    = +/- 3.8mm

    Combined box out lengths = 0.3m

    33

    Combined box out lengths = 0.3m

  • Loss of lining area due to plastic pipes

    Lining thickness = 300mm Plastic pipe diameter = 20mm % reduction in Area = 20/300 = 6.7% Not significant

    34

    Not significant

  • Fire Safety Assessment

    R

    u

    n

    n

    i

    n

    g

    t

    u

    n

    n

    e

    l

    Single segment Single ring Small circuit

    Large circuit

    35

    Exposed pipework, eg header pipesNeed to satisfy fire / smoke requirements set out by rail operatorsMitigation measures to be assessed if needed

    Connected Building

    Access Point

    HP

    Heat pump

  • Structure Integrity - Fire

    Pipework inside segments could impact on the structure integrity of the linings

    Pipework performance under fire needs could be detrimental to linings

    36

  • Above Surface Access

    Restrict on drilling Drilling risks Connection inside tunnel

    37

  • Impacts on Tunnel Design and Construction

    Impact on segment erection Impact on space use inside tunnel Impact on construction cost Impact on tunnel maintenance

    38

    Impact on tunnel maintenance

  • Conclusions

    1. Thermal tunnels are an extension of GSHP systems2. Hot and cold tunnels effects heat outputs.3. Effect of ground conditions water4. Tunnel pipe work installed during construction5. Access from Shafts - Boreholes provide flexibility6. Consider Market surface building needs

    39

    7. Commercial case Cheaper than borehole loops 8. Detailed tunnel design issues

    - Concrete stresses- Joint rotation- Fire impacts- Surface connections- Seasonal heat load peak demands tunnel heat input

  • Thank you for your attention

    Any Questions?

    40

    Any Questions?

  • Buildings Indentification

    41

  • NPV

    42

    Upper Value: CO2 sold at 50/tonne; sinking fund not considered

    Lower Value: CO2 not tradable; sinking fund factored- 15years for Heat Pump, 25 years for boiler