Artificial Recharge & Storm Water Management In Hero Honda...

10
Artificial Recharge & Storm Water Management In Hero Honda Motors Ltd For Haridwar & Dharuhera Plants, Haryana State, India Dr. S. K. Jain 1 & Dilip Singh Chundawat 2 1 President, Institute of Water Conservation, Jal Niketan, 5-Jha-2, Jawahar Nagar, Jaipur-302004 (Raj.) India 2 Dy GM (Projects), GWMICC P Ltd., Jal Niketan, 5-Jha-2, Jawahar Nagar Jaipur – 302004 (Raj.) India Mo: +91-9829067474, +91-9414070292 E-mail: [email protected] www.groundwaterindia.com ABSTRACT Artificial recharge is the process by which rainwater is infiltered into groundwater system and ground water resources are augmented by altering natural conditions of replenishment. The storm water generated in industries with large catchment can be diverted to scientifically designed artificial recharge system based on runoff generated at peak rainfall intensity and recharge rate of sub-surface strata. There are several methods for artificial recharge depending upon the feasibility in different regions. In case of higher infiltration capacity of vadose & saturated zone, percolation pits with recharge shaft in the reservoir can be planned for increased surface water storage assimilation in to the aquifer. This serves as significant tool in storm water management and improvement of ground water regime through artificial recharge reservoir. Similarly, for recharging deep aquifer, injection wells can be planned through filtration chamber (2). Hero Honda Motors had been facing problem due to storm water generation within the plant premises at Dharuhera, Haryana and Haridwar, Uttranchal due to improper drainage system & absence of any artificial recharge measure. The detailed studies were carried out by M/s GWMICC P Ltd., Jaipur in both the plants regarding the existing drainage system, hydrogeological conditions, climatic conditions & scope of implementation of recharge measures. An outcome of these studies, recommendations were given for drain design, new rainwater harvesting structures & artificial reservoirs. As a follow up, the Hero Honda Motors Ltd. had sincerely implemented the recommendations through M/s Jain Earth Matters, Jaipur for proper storm water management in their premises. After implementations, in last two rainy seasons, all the structures are working efficiently even at more than average rainfall of last five years and the problem due to storm water within the premises is completely solved. Key-Words: - Artificial Recharge, Groundwater, Storm water, Runoff, Vadose zone, Saturated zone 1. Introduction The storm water during rainy season causes drainage problem and often paved areas of industries are damaged by rainfall runoff. Without proper drainage, the water on paved area during rains remains stagnant for hours together and poor storm water management results into erosion of roads. In our country, industries are facing water crises due to over exploitation of under ground water and no provision for recharge of aquifers. Declining water levels are also consuming more energy in lifting the water and reduction in green coverage. Solution of managing storm water in industrial premises from paved areas is channilizing the same to ground water system through artificial recharge reservoir in hygienic manner. This method not only helps in controlling the devastating effects of storm water, but would improve ground water regime both in terms of rising of water levels and increase in ground water availability. The technique will also increase life of roads/paved areas of industrial premises and reduce cost on maintenance and repairs. Besides, better plant growth is envisaged with less water requirement due to moist condition of surface soil through percolation structures. Considerable research efforts have been invested in developing alternative approaches to conventional stormwater management focusing on rainwater management, infiltration of rainfall on site, and detention of runoff during large storm events (11,12,13). Examples of innovations include harvesting roof runoff and reusing water, managing rainwater by infiltration into soils in bioretention areas, minimizing impervious surfaces, and using pervious pavement (10). Recent Researches in Hydrology, Geology and Continuum Mechanics ISBN: 978-960-474-275-2 79

Transcript of Artificial Recharge & Storm Water Management In Hero Honda...

  • Artificial Recharge & Storm Water Management In Hero Honda

    Motors Ltd For Haridwar & Dharuhera Plants, Haryana State,

    India

    Dr. S. K. Jain1 & Dilip Singh Chundawat

    2

    1President, Institute of Water Conservation, Jal Niketan, 5-Jha-2, Jawahar Nagar, Jaipur-302004

    (Raj.) India

    2Dy GM (Projects), GWMICC P Ltd., Jal Niketan, 5-Jha-2, Jawahar Nagar Jaipur – 302004

    (Raj.) India

    Mo: +91-9829067474, +91-9414070292 E-mail: [email protected]

    www.groundwaterindia.com

    ABSTRACT

    Artificial recharge is the process by which rainwater is infiltered into groundwater system and ground

    water resources are augmented by altering natural conditions of replenishment. The storm water generated

    in industries with large catchment can be diverted to scientifically designed artificial recharge system

    based on runoff generated at peak rainfall intensity and recharge rate of sub-surface strata. There are

    several methods for artificial recharge depending upon the feasibility in different regions. In case of

    higher infiltration capacity of vadose & saturated zone, percolation pits with recharge shaft in the

    reservoir can be planned for increased surface water storage assimilation in to the aquifer. This serves as

    significant tool in storm water management and improvement of ground water regime through artificial

    recharge reservoir. Similarly, for recharging deep aquifer, injection wells can be planned through

    filtration chamber (2). Hero Honda Motors had been facing problem due to storm water generation within

    the plant premises at Dharuhera, Haryana and Haridwar, Uttranchal due to improper drainage system &

    absence of any artificial recharge measure. The detailed studies were carried out by M/s GWMICC P

    Ltd., Jaipur in both the plants regarding the existing drainage system, hydrogeological conditions,

    climatic conditions & scope of implementation of recharge measures. An outcome of these studies,

    recommendations were given for drain design, new rainwater harvesting structures & artificial reservoirs.

    As a follow up, the Hero Honda Motors Ltd. had sincerely implemented the recommendations through

    M/s Jain Earth Matters, Jaipur for proper storm water management in their premises. After

    implementations, in last two rainy seasons, all the structures are working efficiently even at more than

    average rainfall of last five years and the problem due to storm water within the premises is completely

    solved.

    Key-Words: - Artificial Recharge, Groundwater, Storm water, Runoff, Vadose zone, Saturated zone

    1. Introduction The storm water during rainy season causes

    drainage problem and often paved areas of

    industries are damaged by rainfall runoff. Without

    proper drainage, the water on paved area during

    rains remains stagnant for hours together and poor

    storm water management results into erosion of

    roads. In our country, industries are facing water

    crises due to over exploitation of under ground

    water and no provision for recharge of aquifers.

    Declining water levels are also consuming more

    energy in lifting the water and reduction in green

    coverage. Solution of managing storm water in

    industrial premises from paved areas is

    channilizing the same to ground water system

    through artificial recharge reservoir in hygienic

    manner. This method not only helps in controlling

    the devastating effects of storm water, but would

    improve ground water regime both in terms of

    rising of water levels and increase in ground water

    availability. The technique will also increase life

    of roads/paved areas of industrial premises and

    reduce cost on maintenance and repairs. Besides,

    better plant growth is envisaged with less water

    requirement due to moist condition of surface soil

    through percolation structures. Considerable

    research efforts have been invested in developing

    alternative approaches to conventional stormwater

    management focusing on rainwater management,

    infiltration of rainfall on site, and detention of

    runoff during large storm events (11,12,13).

    Examples of innovations include harvesting roof

    runoff and reusing water, managing rainwater by

    infiltration into soils in bioretention areas,

    minimizing impervious surfaces, and using

    pervious pavement (10).

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 79

  • 2. Methodology In designing Artificial recharge reservoir,

    capturing storm water runoff from the roads/paved

    areas and creating artificial connectivity to sub

    surface water in the hygienic manner through

    storage & filtration of storm water is the key

    concept. The effectiveness of the concept lies in

    reasonable cost, coverage of large areas and

    immediate implementation and immense benefits

    in terms of additional water availability,

    improvement in water quality, increased

    plantation, maintaining eco-balance, reducing the

    cost on maintenance and repairs of roads and

    many fold increase in life of the roads/paved areas.

    Storm water harvesting from industrial premises

    can be achieved by creating storage of rain fall

    runoff and recharging ground water through

    filtration chambers having inverted filter of sand,

    gravel & pebbles. Such Artificial recharge

    reservoir would not only control storm water

    hazards in industries, but will enhance ground

    water availability 8 to 10 times compared to

    natural process of rainfall infiltration. The location

    and design of sustainable storm water harvesting

    system require hydro geological study of the area

    as well as sub surface information of most

    permeable zone. Besides, average rainfall and

    rainfall intensity need to be analyzed as per

    climatic zones. Based on normal rainfall and peak

    rain fall intensity, the storm water harvesting

    system through reservoir is designed in such a way

    that 70-80 % of storm water is sent back to ground

    water regime after natural filtration process based

    on rate of Recharge after Recharge Test on

    existing wells/pits (8 ).

    3. Case study–1: Road/paved area

    storm water recharge through

    artificial recharge reservoir in

    industrial premises of Hero Honda

    Motors limited, Sidcul, Haridwar,

    Uttranchal. The total road/paved areas of the factory

    premises is 115080 m2, which would generate

    129465 m3 volume of storm water runoff for

    recharge to the ground water at average

    rainfall of 1520 mm per annum. The location

    of the reservoir for the Storm Water

    Harvesting is given in Fig. 1and the detailed

    lay out plan of reservoir with the location of

    percolation structures is shown in Fig. 2. The

    designs of percolation structures in the

    reservoir are given in Fig. 3 based on peak

    rainfall intensity for 15 minutes. The storm

    water drains as shown meets reservoir at the

    inlets (I1 and I2). For extreme events of

    rainfall, two spillways are designed for

    overflow of water towards main road as

    shown in Fig. 4. To prevent sand, two

    desilting tanks are recommended at the inlets

    to the reservoirs as shown in Fig. 5 .All design

    parameters are explained clearly in diagram

    (5, 7). The runoff generated at 200 mm

    rainfall on 10 th/11th Sep.,09 and on 28th/29th

    Aug. 10 continuously for two days was

    completely recharged to ground water without

    any over flow and the system functioned very

    well.

    4. Case study –II: Storm water

    recharge through artificial recharge

    technique in industrial premises of

    Hero Honda Motors limited,

    Dharuhera, Rewari, Haryana. In Dharuhera plant premises, total area of the

    roads is 7581.5 m2, which would generate 85.29

    m3 volume of storm water runoff for recharge to

    the ground water at an average rainfall of 726 mm,

    considering peak rainfall intensity of 60 mm/hour

    and 0.75 as the catchment factor. The locations of

    the Rainwater harvesting structures for the road

    runoff are given in Fig. 6. The storm water is

    initially collected in Desilting chamber through

    covered drains from different road/paved area of

    the premises as shown in Fig. 7. After siltation, the

    overflow is passed to filtration chambers through

    8’’ dia pipe line where the storm water get treated

    with different filter media & ultimately through

    injection well of 60 m (Fig. 8), recharged to deep

    aquifer (6,9). The rainwater harvesting system is

    working efficiently in last two monsoon seasons

    even on more than average rainfall.

    5. Removal of pollutants The percolation structures have been designed

    with sufficient vadose zone of 30 m acting as

    natural filter that removes pollutants and other

    impurities from the water as it moves down to the

    ground water through natural filtration media

    consisting of pebbles , gravels, coarse sand,

    charcoal and potassium permanganate layers.

    Quality improvement through proper infiltration

    management is expected to be achieved as given in

    Table-1 (3).

    Table-1: Water quality Improvement Parameter Pollutant removal

    Suspended

    Solids

    Essentially complete removal

    Dissolved

    Solids

    No removal

    Biodegradable

    organic

    Essentially complete removal

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 80

  • compounds

    (BOD)

    Synthetic

    organic

    compounds

    Some are almost completely

    removed, some significantly and

    some very little

    Bacteria and

    viruses

    Essentially complete removal due

    to zone of deariation. However,

    as precautionary measure,

    potassium permanganate layer

    has been also provided in the

    system.

    Nitrogen Significant removal

    Phosphorus Significant removal

    Fluoride Significant removal

    Heavy metals Significant to essential removal

    Boron No removal

    Oil & grease

    & other

    hydrocarbons

    79% to 98% removal. (For

    complete removal, charcoal layer

    has been provided as it acts as a

    good absorbent of oil & grease)

    The above table clearly indicates that Rapid-

    infiltration soil-treatment systems are capable of

    removing essentially all biodegradable organics,

    suspended solids, and bacteria and viruses from

    the wastewater. They can also remove almost all

    the phosphorous and significantly reduce

    concentrations of nitrogen and heavy metals. Most

    of the quality improvement of the wastewater

    takes place in the top 1 m of the soil beneath the

    infiltration structures. Considerable additional

    movement in vadose zone and aquifer is needed

    for quality improvement in long term & to avoid

    concentration of pollutants in the upper top 10 m.

    However, to complete the renovation process

    (dieoff of bacteria and viruses, phosphate

    precipitation, decomposition of organics, taste and

    odor removal etc.), a rule of thumb is to allow at

    least 100 m distance of underground travel and an

    underground detention time of at least one

    month(1).

    6. Advantages 1. Reduction in runoff which chokes storm drains. 2. No flooding of Industrial premises.

    3. Augmentation of ground water storage and

    control of decline of water levels.

    4. Improvement of quality of ground water.

    5. Reduced stagnant water on road will improve

    life of road & avoid frequent repairs &

    maintenance.

    6. Surviving water requirement during summer,

    drought etc. in cities and industrial premises.

    7. Better plant growth all around the reservoir.

    7. Conclusion The technique of artificial recharge measures

    which may be through artificial reservoir with

    recharge shaft or rainwater harvesting system with

    injection well presented will be helpful in

    controlling storm water hazards in many industrial

    areas with improvement in ground water recharge

    by utilizing rainfall runoff. The innovatively

    designed structures are simple, easy to construct,

    operate and maintain. The implementation taken

    up as shown in the case study has shown positive

    results of rise in water level with in short time.

    Further effects on ground water regime are under

    monitoring. Such projects are expected to solve

    storm drainage problem of industries and improve

    ground water regime by recharge through rainfall

    runoff. At the same time, the system will also

    create hygienic conditions avoiding frequent

    maintenance and repairs of the paved areas/roads

    of most industrial premises & a step forward in

    solving storm water hazards inside the industrial

    premises.

    8. Acknowledgement Author expresses his gratitude to Hero Honda

    Motors Limited for implementation of the

    project. Author also wishes to thank Mr.

    Hanumant Sharma, Incharge, drilling and

    RWH, Jain Earth Matters, Jaipur for execution

    of the project successfully in both the

    premises.

    References: (1) Asano, Takashi, 1985. Overview : Artificial recharge of ground water, published by Butterworth

    Publishers, USA

    (2) CGWB (2000). Guide on Artificial recharge to ground water, Govt. of India Publication (3) Herman Bouwer (1985). Renovation of waste water with rapid infiltration Land treatment systems,

    Published in “Artificial recharge of ground water”, Butterworth Publishers, London.

    (4) Jain Dr. S. K.(2004) Innovative rainwater harvesting along road sides, paper published in the Book “Advances in Geosciences-Hydrological sciences Vol-4” by World Scientific Publishing Company

    (P) Ltd., Singapore.

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 81

  • (5) Jain Dr. S. K.(2006). Management of Storm water on roads and improvement of ground water regime. paper published in “Hydroinformatics Vol-I”, proceeding of 7th international conference on

    hydroinformatics, Nice, France.

    (6) Jain Dr. S. K.(2007). Artificial Recharge Studies through rainwater Harvesting at Dharuhera, Haryana. GWMICC (P) Ltd. Publication

    (7) Jain Dr. S. K.(2008). Artificial Recharge Studies through rainwater harvesting at Sidcul, Haridwar, Uttranchal. GWMICC (P) Ltd. Publication

    (8) Jain Dr. S. K.(2009). Efficient use of water through Storm water harvesting. paper published in workshop on “Efficient use & Management of water in Rajasthan”, CGWB, Western region, March

    2009.

    (9) Jain Dr. S. K.(2009). Groundwater recharge management through road storm water harvesting in industries & urban colonies, paper published in workshop on “issues related to Groundwater

    management in Gujarat” by West Central region, CGWB, March 2009.

    (10)Marsalek J and Schreier H (2010) Overview of the Theme Issue: Innovation in Stormwater

    Management in Canada: The way forward, Water quality research journal of Canada, pp. 5 – 10.

    (11) Stephens KA, Graham P, Reid D (2002) Stormwater planning: A guidebook for British Columbia.

    British Columbia Ministry of Water, Land and Air Protection, Victoria, B.C.

    (12) U.S.EPA. (2000) Low Impact Development (LID) : A literature review. Report EPA-841-B-00-005,

    Ofiice of water, Washington, D.C.

    (13) U.S. department of Defense (2004) Unified facilities criteria: Low impact Development. UFC, 3-

    210-10,25 October 2004. Available on-line at: htt://www.wbdge.org/ccb/

    DOD/UFC/ufc_3_210_10.pdf (Accessed: March 3, 2009).

    *****************************

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 82

  • Fig.-1: Location of Artificial Reservoir in Hero Honda Motors Premises, Haridwar

    ������� �����

    1 800 3200

    2400 2400

    D G FD V -2D G FDV -1

    WELD SHOP

    DOL PANEL

    M L DB

    VT PN DB

    CONN EC TING

    PASSAGE

    15000

    1 500

    22500

    15000

    18000

    RC C PADES TALS

    LPG PANEL

    WA.T. PANELCOMP. PANEL

    HWG PANEL

    ML DB

    VTPN DB

    V TPN DB

    PLATF ORM

    A A

    B

    B

    C C

    XR

    1

    3

    2 4

    � � �� �� �� �� �� �� ��

    ����������������

    �� �� �� �� �� �� ��� ���

    ������������������������

    ���� ����� ���� ����������� ���� ���� �� �� ��������� �

    ���� ����� ���� ����������� ���� ���� �� �� ����������

    ��������

    ������ !��! �!��� ��"������� ��#�����

    ������ !��! �!��� ��"������� ��#�����

    ������ !��! �!��� ��"������� ��#�����

    ������ !��! �!��� ��"������� ��#�����

    I N T E R L OC K IN G TILE S

    ��������

    ��������

    ������ !��!�!��� ��"���������#�����

    W1

    W1

    $

    ����

    ����

    ����

    ���� ����

    Scale 0 1 2 3 (In cm)

    0 44 88 132 (In mt.)

    NORTH

    EW

    S

    Investigated Siteboundary

    INDEX

    Drain

    RWH RechargeReservoir withten percolationstructures

    RWH

    structuresBuilding

    (6 Structures)B-1 buildings

    (1 Structure)B-2 buildings

    (1 Structure)B-4 buildings

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 83

  • 6 m

    90 m10 m

    Water Outlet Spillways at

    96.5 m RL

    Water inlet channel of

    1 m width at 93.70 m RL

    Water inlet channel of

    1 m width at 95.50 m RL

    Proposed Stone

    pitching weir

    by HHH

    (slope 1:2)Bottom RL - 91.30 m

    Tree

    RL - 100.25 m

    RAMP with 1:10 slope

    RWH Reservoirboundary

    Water InletChannel

    Ramp/MaintainanceTrack

    PercolationStructures

    Water outlet

    SpillwayDesilting Tank

    Bunding(2.4 m height, 12 m width

    with 6 m flat top)

    Proposed Stone

    pitching weir

    by HHH

    (Slope 1:2)

    Stone pitching to be done by HHH

    at 1:2 slope

    RL of WL - 92.50 m

    Fig.-2: Schematic diagram of Artificial Reservoir at Hero Honda Motors Premises, Haridwar

    COARSE SAND

    0.5 M

    1 MPEBBLES

    0.5 M

    GRAVEL

    Inlet with RCC inverted

    filter with 1 mm S.S. net

    0.6 m dia. Recharge

    shaft filled with

    pebbles

    3 m

    Tank Dimension

    ( 3 m x 3 m x 3.5 m)

    0.9 M

    (length*width*depth)

    30 M

    1 M

    1.5 m x 0.5 m x 0.10 mFerro covers

    Stairs

    0.6 m

    Reservoir's

    base level

    2 FEET x 2 FEET

    IRON CHAMBER

    Inlet with RCC inverted

    filter with 1 mm S.S. net

    Fig.-3: Schematic design of Percolation structure in Artificial Reservoir at Hero Honda Motors

    Premises, Haridwar

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 84

  • Fig.-4: Schematic design of Spillway for provision of Overflow in Artificial Reservoir

    Staire case

    0.25 M

    2.20 M

    0.25 M

    5.30 M

    1.2 M

    2.10 M1.20 M

    4.5 M

    Inlet

    Filters

    Silt pit

    0.75mSink

    Hole0.3M

    0.30 m dia

    inlet drain

    Precasted CC

    deattachable slabs

    Staire case

    for cleaning silt

    2 x 2 feet iron lid

    8" OUTLET

    PIPE with

    filter to be

    connected

    with

    Filtration

    chambers

    Gravel 0.5m

    BAFFLEWALL

    6" holes

    with filters

    2.55 M

    II Stage Filter

    III Stage

    Filter

    (length*width*depth)

    Desilting Tank

    (4.5 m x 4 m x 5.30/6.05 m)

    Fig.-5: Schematic design of Desilting tank before inlets to Artificial Reservoir at HHM

    Premises, Haridwar

    BundingBunding

    1.5 m

    4 m

    1.5 m

    Outlet

    spillway

    SP-1 & SP-2

    (with 1:8 Slope)

    1.70 m

    SP-1 SP-2

    RL=98.50 m

    Foundation at

    95.50 m RL

    0.5 m

    Pillar Size = 0.46 m x 0.23 mPillar

    RL=97.00 m RL=97.00 m

    0.5 m0.5 m

    RL=97.00 m

    RL=96.68 m

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 85

  • LPG TANK

    ROAD

    ROAD

    CANTEEN

    ROAD

    GATE

    GUARD ROOM8.0 M.WIDE ROAD GATE

    N H 8

    ROAD

    ROOMGUARD

    TIMEOFFICE

    GATE

    CYCLE STAND

    TWO WHEELAR

    PARKING

    PARKING

    AREA

    GREEN BELT

    100.0

    100.0

    LAKE-IIN

    INDEX

    RWH structuresBuilding

    (1 structure)

    Runoff flow direction

    Proposed extension

    plant building

    Existing Lake

    Lawn/open ground

    Old Buildings

    Existing roads

    (Width X Depth)

    Desilting Chamber

    Connecting to

    Filtration Chmaber

    (3 structures)Road storm water

    harvesting with

    desilting tank (Admin Block)

    (0.3m. x 0.3m.)Drains along road

    Connecting 8" pipes

    from Desilting/Storage

    Tank to Filtration Chambers

    (In.m.)0 20 40 60 80

    Fig.-6: Location of Road Storm water Harvesting Structures at Hero Honda Motors Premises,

    Dharuhera

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 86

  • Staire case

    (length*width*depth)

    Desilting Tank

    (6 m x 3 m x 3.20/3.95 m*)

    0.25 M

    2.20 M

    0.25 M

    3.20 M

    1.5 M

    2.10 M 1.50 M

    6 M

    Inlet

    Filters

    Silt pit

    0.75mSink

    Hole0.3M

    0.30 m dia

    inlet drain

    Precasted CC

    deattachable slabs

    Staire case

    for cleaning silt

    2 x 2 feet iron lid

    8" OUTLET

    PIPE with

    filter to be

    connected

    with

    Filtration

    chambers

    Gravel 0.5m

    BAFFLEWALL

    6" holes

    with filters

    0.75 M

    II Stage Filter

    III Stage

    Filter

    Fig.-7: Schematic design of Desilting chamber at Hero Honda motors Premises, Dharuhera

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 87

  • COARSE SAND

    0.50 M

    1 MPEBBLES

    0.50 M

    GRAVEL

    3 m

    1 M

    1.5 m x 0.5 m x 0.10 mFerro covers

    Stairs

    2 FEET x 2 FEET

    IRON CHAMBER

    Inlet

    Gravels

    6" PVC Plain &

    Screened pipe

    Bail plug

    6"injection well

    60m

    INJECTION WELL

    WITH WELL CAP

    Air vent

    Length Width Depth

    3 m 5.25 m3 m

    3 m 5.35 m3 m

    Two nos. of

    Filtration Chambers

    Outlet

    Gravels

    Charcole layer (0.1m)

    Fig.-8: Schematic design of Filtration chamber at Hero Honda motors Premises, Dharuhera

    Recent Researches in Hydrology, Geology and Continuum Mechanics

    ISBN: 978-960-474-275-2 88