Arr Transco Fy09 10
-
Upload
dipenkhandhediya -
Category
Documents
-
view
234 -
download
0
Transcript of Arr Transco Fy09 10
-
8/13/2019 Arr Transco Fy09 10
1/39
ANNUAL REVENUEREQUIREMENT
&TARIFF APPLICATION
FY 2009-10
Uttar Pradesh Power Transmission Corporation
Limited
LUCKNOW
-
8/13/2019 Arr Transco Fy09 10
2/39
ARR & TARIFF: FY10
Uttar Pradesh Power Transmission Corporation Ltd. i
Table of Contents
1. Introduction.................................................................................................................. 1-1
1.1. U P Power Transmission Corporation Limited (UPPTCL) ................................................. 1-1
1.2. Procedure Envisaged for ARR FY 08 & 09 ....................................................................... 1-1
UP Power Transmiss ion Corporation Limited: ............................................................................. 1-3
2. Exist ing Transmiss ion System- a preview: ............................................................... 2-3
2.1. Interconnections and Northern Region Load Dispatch Centre (NRLDC)........................... 2-4
2.2. Availability of Lines ........................................................................................................... 2-4
2.3. Load Levels ...................................................................................................................... 2-4
2.4. Bulk Transmission System Flows: .................................................................................... 2-5
3. Performance Analysis of ARR FY 08 & FY 09 Filing: .............................................. 3-6
3.1. Review of UPERC FY 08 & FY 09 Tariff Order: ................................................................ 3-6
3.2. Comparison of Estimated Cost and Actual Figures To-Date ............................................. 3-7
3.2.1. Demand Forecast-Tariff Order and Actual FY (2007-08): .............................................. 3-73.2.2. Expense items- Approved and Estimated:..................................................................... 3-7
3.3. Investments: ..................................................................................................................... 3-8
3.3.1. Proposal for Ensuing Year:............................................................................................ 3-9
3.3.2. Normal Development Works: ......................................................................................... 3-9
3.3.3. Transmission Works in NCR.......................................................................................... 3-9
3.3.4. Renovation and Modernization ...................................................................................... 3-9
3.3.5. Augmentation of Transmission System due to RE works............................................... 3-9
3.4. Compliance of UPERC Directives: .................................................................................. 3-18
4. Power Wheeling & Demand: ..................................................................................... 4-20
4.1. Losses external to UPPTCL system:............................................................................... 4-20
5. Annual Revenue Requirement: FY 2009-10 ............................................................. 5-21
5.1. ARR FY 2009-10:......................................................................................................... 5-21
5.1.1. Escalation Index/Inflation Rate .................................................................................... 5-22
5.2. Operation & Maintenance Expenses............................................................................... 5-22
5.2.1. Employee Costs: ......................................................................................................... 5-23
5.3. Administration and General (A&G) Expenses: ................................................................ 5-24
5.4. Gross Fixed Assets (GFA) Balances and Capital Formation Assumptions ..................... 5-25
5.5. Repair and Maintenance (R&M) Expenses..................................................................... 5-27
5.6. Depreciation Expense:.................................................................................................... 5-27
5.7. Interest and Financing costs: .......................................................................................... 5-275.8. Other Income:................................................................................................................. 5-29
5.9. Reasonable return/ Return on Equity:............................................................................. 5-29
5.10. Service tax:..................................................................................................................... 5-30
5.11. TransCo ARR: ................................................................................................................ 5-31
6. Proposed Transmiss ion Tariff : ................................................................................. 6-32
6.1. Derivation of Tariff:.......................................................................................................... 6-32
7. SLDC Charges: .......................................................................................................... 7-33
-
8/13/2019 Arr Transco Fy09 10
3/39
ARR & TARIFF: FY10
Uttar Pradesh Power Transmission Corporation Ltd. ii
List of TablesTable 2-1: Total existing Sub-Stations: ..................................................................................... 2-3
Table 2-2: Total existing Lines (Circuit Km).............................................................................. 2-4
Table 2-3: Yearly System Peak in M.W. ..................................................................................... 2-5
Table 2-4: Monthly System Peak for current Year.................................................................... 2-5
Table 3-1: Approved and Actual FY 2007-08: Energy Demand (MU)..................................... 3-7
Table 3-2: Approved and Actual FY 2008-09: Energy Demand (MU)..................................... 3-7
Table 3-3: Estimated and Actual ARR FY 08, Components: ................................................... 3-8
Table 3-4: Estimated and Actual ARR, Components: .............................................................. 3-8
Table 3-5: Proposed Program for Transmission Works (Rs. Cr.)......................................... 3-10
Table 3-6: Detailed Program of Transmission Works for ensuing Year (Augmentation): .. 3-16
Table 3-7: Compl iance of UPERC Direct ives: ......................................................................... 3-18
Table 4-1: Actual & Est imated Energy Profi le: ....................................................................... 4-20
Table 5-1: Escalation Index ..................................................................................................... 5-22Table 5-2: Details o f Employee Cost: ..................................................................................... 5-23
Table 5-3: A &G Expenses: ..................................................................................................... 5-25
Table 5-4: Transco Investment Plan: (Rs. Cr) ........................................................................ 5-26
Table 5-5: Capital Formation dur ing FY 09 ............................................................................ 5-26
Table 5-6: Capital Formation during FY 10 ............................................................................ 5-26
Table 5-7: R&M Expenses: ...................................................................................................... 5-27
Table 5-8: Details o f Interest & Finance Cost: ....................................................................... 5-28
Table 5-9: Interest on Working Capital: ................................................................................. 5-29
Table 5-10: Summary of Other Income: ................................................................................... 5-29
Table 5-11: Return on Equity: .................................................................................................. 5-30
Table 5-12: Annual Revenue Requirement : ............................................................................ 5-31
Table 6-1: Derivation of Transmission Tariff: ....................................................................... 6-32
Table 7-1: Break-up of SLDC Charges................................................................................... 7-33
-
8/13/2019 Arr Transco Fy09 10
4/39
ARR & TARIFF: FY10
Uttar Pradesh Power Transmission Corporation Ltd. ii i
Executive Summary:
In accordance with the Section 62 of the Electricity Act2003 and provisions of the
Transmission Tariff Regulations notified by the Commission, UP Power
Transmission Corporation Limited is submitting before UPERC the Aggregate
Revenue Requirement and Tariff petition for FY 2009-10.
As prescribed in the Regulation, the petit ioner is required to fi le the Aggregate
Revenue requirement complete in all respect along with requisite fee as prescribed in
the Commissions Fee and Fine Regulations each year containing the details of the
estimated expenditure and the expected revenue that it may recover in the ensuing
financial year at the prevailing tariff. Further the petitioner is required to file ARR for
the ensuing financial year indicating the manner in which the gap between the
expenses, which is permitted to recover and expected revenue for ensuing financial
year, shall be bridged.
As per provis ions under Elect ri ci ty Act 2003, separate State Load Despatch Centre
(SLDC) is to be established by the state government to ensure integrated operation
of Power system in the State. Further Transmission Regulation prov ides that till
such t ime the State Govt establishes separate SLDC ,STU shall operate SLDC
function & till complete segregation of accounts between SLDC function &
transmission function , STU shall apportion its Cost between (i) SLDC function and
(ii) Transmission Function based on an allocation statement& basis of such
apportionment shall be clearly indicated in the ARR petition. Currently the function
of SLDC is being discharged by a separate section within UPPTCL. Expenses of
SLDC funct ion & ARR has been worked out on the basis of best estimate available. In
present petition, expenses of SLDC are being charged through UPPTCL ARR
however in the a separate section of SLDC ARR has been added for approval of
SLDC charges for other practical purposes such charges being levied to open
access consumers.
The layout of this petition among other things includes background, proposed
expenditure plan for the ensuing year ,estimation of the Aggregate Revenue
Requirement , explanatory notes where ever required and status of directive issued
by the Honble Commission and other information as mandated in the regulation.
The objective of the petitioner in this filing has been to contain the expenses to a
reasonable level to offset inflationary pressure as prevailing in the market. For the
current year petitioner has endeavoured to limit the expenses with in the approved
limit . For ensuing year petitioner has also taken a daunting task to control the
-
8/13/2019 Arr Transco Fy09 10
5/39
ARR & TARIFF: FY10
Uttar Pradesh Power Transmission Corporation Ltd. iv
expenses to the reasonable level but due to prevailing market condition some time it
is not possible to limit expenses to current level due to uncontrollable factors.
The petitioner in the current and ensuing year has con tinued with the execution with
the all major capital investment project as also the must do projects for meeting the
demand growth ,creating adequate capacity for reducing the over load of heavy
loaded feeders and transformers. The petitioner has proposed a capital expenditure
of Rs 794 Cr for FY2008-09 and Rs 2870 Cr for FY2009-10 .Detail of major capital
investment plan is described in subsequent section with the proposed funding
mechanism.
The petitioner while estimating expenses for current & ensuing year has taken into
account the actual expenses incur red in previous years as per its audited /un
audited balance sheet and up to date expenses for current year to drive the
expenses at a reasonable level.
The petitioner has endeavoured to control the employee expenses in the current year
to the approved level. While projecting the expenses for ensuing year petitioner has
adopted the same method to contain inflationary pressure but due to announcement
of 6th pay commission, it is bound to increase.
The petitioner while projecting A& G expenses for ensuing year has proposed a
marginal increase in the A&G expenses this is only in order to off-set inflationary
pressure. This is in real term can be termed as reduction in expenses as virtually in
nearly same expenses are ensured to be incurred in spite of creation of additionalDivision & Circle.
The petitioner has projected R&M expenses for current year taking into account
actual trends and for ensuing year R&M expenses has been estimated as per
methodology adopted in previous years. The petitioner is making all round effort to
optimize the R&M expenses despite steep rise in metals & fuels costs. The proactive
preventive maintenance initiatives and capital expenditure are done in various
improvement schemes which would result in improvement in quality of supply and
reduction in number of overloaded lines &substations.
The petitioner has projected Rs 0.243 per un it Tariff for FY2009-10.
-
8/13/2019 Arr Transco Fy09 10
6/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 1-1
1. Introduction
1.1. U P Power Transmission Corporation Limited (UPPTCL)
The U P Power Transmission Corporation Limited (hereinafter referred to as TransCo) is the company
incorporated under the Companies Act, 1956 by making amendment in the Object and Name clause of
Uttar Pradesh Vidhyut Vyapar Nigam Ltd and having duly passed Special Resolution on 7th June 2006
in term of Section 21 of the Companies Act, 1956 which was originally incorporated on 31stMay, 2004.
UPPTC started functioning with effect from 26th July 2006 and is entrusted with the business of
transmission of electrical energy to various utilities with the help of its transmission lines and substations
within the geographic area of Uttar Pradesh. Before incorporation of UPPTC, transmission work was
entrusted with UPPCL. Govt of UP in exercise of power under section30 of the Electricity Act 2003
vide notification No: 122/U.N.N.P/24-07 dated 18 July 2007 notified U P Power Transmission
Corporation Limited as the State Transmission Utility of Uttar Pradesh.The UPPTCL now deal with the
transmission of electricity for catering power requirement of four distribution companies viz
Madhayanchal Vidyut Vitran Nigam Ltd, Dakshinanchal Vidyut Vitran Nigam Ltd, PashchimanchalVidyut Vitran Nigam Ltd and Poorvanchal Vidyut Vitran NigamLtd in addition to two other distribution
companies serving Kanpur (KESCO) and Noida (NPCL).
1.2. Procedure Envisaged for ARR FY 08 & 09
Uttar Pradesh Power Transmission Corporation submitted before U.P. Electricity Regulatory
Commission the Annual Revenue Requirement (ARR) and Tariff proposal for FY 2008-09 on 19th
December, 2007 along with the information/data for FY 2007-08in accordance with the provisions
of the Transmission Tariff Regulations notified by the Commission on 6th October 2006.These
regulations are applicable for the purpose of ARR Filing and Tariff determination of the transmission
Licensee with in the State of UP.
The Commission vide its order dated 4th January 2008 observed certain deficiencies in the above
petitions, which were clarified by the licensee as under-
Licensee has submitted that as per requirement of Commission under electricity act 2003 the
UPPTCL is in the process of taking action for obtaining separate licence.
Draft Transfer Scheme has been formulated and submitted to the GoUP for their consideration
and shall be notified by the GoUP.
All the new PPAs are being allocated to DisComs and a proposal for allocation of old PPAs to
the DisComs has been submitted to the GoUP.
With reference to the Intra-State ABT in the state Licensee has submitted that the work of
installation of boundary meters is in progress.
The Commission admitted the petition filed by the Licensee on 25th January 2008 and
directed the Licensees to advertise the salient features of ARR/Tariff petition in the widely
circulated newspapers of the area of supply.
-
8/13/2019 Arr Transco Fy09 10
7/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 1-2
Comments of general public including electricity consumers on ARR/Tariff proposals were also
invited. An advertisement in this regard appeared in five leading news papers on 31st January
2008.
The Commission conducted public hearing at Lucknow, Kanpur, Ghaziabad and Gorakhpur
.Various stakeholders, industry associations and consumer forums participated in the public
hearing and submitted their comments.
UPERC issued a Joint Tariff Order for FY 2007-08 & 2008-09 on 15 th April 2008 with an
average hike in Retail Tariff of about 14%.
The structure of this submiss ion:
In accordance with the provisions of Transmission Tariff Regulations UPPTCL is filing Annual
Revenue Requirement of the Transmission business including tariff and charges. This ARR
filing includes detailed Tariff proposal for transmission and wheeling of Electricity. Thestructure of this submission is as follows
Section 1. Introduction: This contains a brief background and rationale used for the submission;major assumptions used and describe the structure of the submission.
Section 2. UPPTCL, Transmission System- a preview
Section 3. Performance Analysis of ARR FY2008&FY2009 Filing: This includes:
a) A review of the UPERC FY 08&FY09 Tariff Order.
b) Comparison of estimated cost and actual figures to-date;
c) An action plan undertaken by UPPTCL for improvement of Transmission Loss
d) Investment plans.
e) Compliance of UPERC directives.
Section 4. Power Wheeling & Demand: This includes demand forecasts for FY10, alsosummarised actual FY 08 & FY09.
Section 5. Annual Revenue Requi rement: (ARR) for FY 2009-10: This includes the ARRforecast for FY10 for UPPTCL.
Section 6. Proposed Transmission Tariff: This provides the proposed transmission tariff forUPPTCL, which will be a simple postage stamp tariff. This tariff would be applied toall DisComs and current Bulk Supply consumers.
Section 7. SLDC-Annual Revenue Requirement (ARR) for FY 2009-10:This includesthe ARRforecast for FY10 for SLDC and provides the proposed SLDC charges, for the capacityhandled by UP Power Transmission Corporation Ltd.
Notes:
In this petition:
Previous year is defined as financial year FY2007-08.
Current year is defined as financial year FY2008-09
Ensuing year is defined as financial year FY2009-10
-
8/13/2019 Arr Transco Fy09 10
8/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 2-3
UP Power Transmission Corporation Limited:
2. Existing Transmission System- a preview:
The transmission system in UP is composed of 400 kV, 220 kV and 132 kV AC lines and substations.
UPPTCL has also built one 765 kV AC single circuit line which connects the Anpara thermal station in
the southern part of UP to Unnao s/s (Unnao District). Presently, this line is being operated at 400 kV.
Majority of the transmission lines & substations in UP are owned and operated by UPPTCL. However,
there are other transmission lines & substations in UP (including a 500 kV HVDC line from Rihand to
Dadri) that carry electricity from the central sector plants to the neighbouring states and these are
owned and operated by the Power Grid Corporation of India Limited (PGCIL). In addition, some of the
above transmission facilities are jointly owned by UPPTCL & PGCIL.
Until the 400 kV grid was fully developed, the 132 kV lines were part of the transmission network. Now
the 400 kV and 220 kV network forms the transmission grid while the 132 kV systems can be treated as
a sub transmission system. Over a period of time, some of the 132 kV lines formed local grids while a
majority of them are radial lines.
The total circuit lengths of the existing 765 kV, 400 kV, 220 kV and 132 kV lines are given in Table
2-1 & sub station are given in Table 2-2.
Table 2-1: Total existing Sub-Stations:
Sl. NO. Transmission Area The No. of Sub Centres Capacity (MVA)
400 K.V.
1- Transmission Central Area 4 22202- Transmission Eastern Area 4 1750
3- Transmission Southern Area 2 1110
4- Transmission Western Area 4 2850
Total 14 7930
220 K.V.
1- Transmission Central Area 12 3000
2- Transmission Eastern Area 10 3010
3- Transmission Southern Area 15 3740
4- Transmission Western Area 17 4980
Total 54 14730
132 K.V.1- Transmission Central Area 46 3500
2- Transmission Eastern Area 74 4850
3- Transmission Southern Area 52 4705
4- Transmission Western Area 64 6002
Total 236 19057
-
8/13/2019 Arr Transco Fy09 10
9/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 2-4
Table 2-2: Total existing Lines (Circuit Km)
132 KV L ines
409
42606904
11384
T r an s m i s s i o n L i n e s c k t .k m
765KV L ines (charged at 400 kV)
400 KV L ines220 KV L ines
2.1. Interconnections and Northern Region Load Dispatch Centre (NRLDC)
UPPTCLs existing transmission system is interconnected to the electrical grids of its neighbouring
States, namely, Uttaranchal, Haryana, Rajasthan and the central system of New Delhi. In addition, it
maintains asynchronous ties (i.e. AC-DC-AC) with the electrical grids of Bihar in the east and Madhya
Pradesh in the South.
Until November 2002, there was only one State of UP and one transmission grid for the entire erstwhile
UP. The ownership of lines and substations have changed since division of UP into two States, i.e. UP
& Uttaranchal.
The UPPCL power system is a part of the Northern Regional Grid of India. The Northern Grid is
controlled from a unified regional load dispatch centre at Delhi. The Northern Regional Load Dispatch
Center (NRLDC) is equipped with modern SCADA and Energy Management System Software. The
SCADA system is fully functional as are key applications like State Estimation, Economic Dispatch and
security assessment. The NRLDC modified its economic dispatch software to take into account the
Availability Based Tariff (ABT). UPPTCL has been upgrading its own unified load dispatch centre at its
head office in Lucknow and the four area control centres.
2.2. Availability of Lines
Availability of lines and other equipments of UPPTCL system is positively around 98% and with this
system UPPTCL handles Transmission of energy from different generating units to the Distribution
Licensees (Points) effectively.
2.3. Load Levels
The load centre power demands and their daily, monthly & yearly load levels and associated load power
factors are important factors that influence the planning of the bulk transmission system. UPPTCL loads
are generally scattered throughout the state with heavy demands in Varanasi, Allahabad, Lucknow,
Kanpur, Agra and Meerut areas. The annual peak load generally occurs in summer month. Figure 2-3 &
Figure2-4 typically show the yearly peak demand of previous years & monthly current year peak demand.
-
8/13/2019 Arr Transco Fy09 10
10/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 2-5
Table 2-3: Yearly System Peak in M.W.
Month AvailabilityR.D.M.
(MW)
Restriction
(MW)
UDM
(MW)
2003-04 5403 6788 600 7368
2004-05 5717 6870 1100 79702005-06 6112 7437 1100 8537
2006-07 7188 7653 1100 8753
2007-08 7504 8604 1500 10104
2008-09 8222 8337 2250 10587
Table 2-4: Monthly System Peak for current Year
Month AvailabilityR.D.M.
(MW)
Restriction
(MW)
UDM
(MW)
Apr-08 7130 8045 1500 9545
May-08 7617 8417 1500 9917
Jun-08 8036 8066 1500 9566
Jul-08 7521 8281 1500 9781
Aug-08 7725 8115 1500 9615
Sep-08 7889 9064 1500 10564
Oct-08 8222 8337 2250 10587
Nov-08 6466 7946 1500 9446
Dec-08 7413 8098 1100 9198
Jan-09 7546 7621 2250 9871
Feb-09 7555 8040 1500 9540
Mar-09 7474 7982 1500 9482
2.4. Bulk Transmission System Flows:
Bulk transmission system flow characteristics are dominated by the coal based thermal generating
plants available in southeast of UP. These plants at Anpara, Obra, Rihand and Singrauli generate
about 6300 MW out of which 4500 to 5000 MW generation flows to the western regions after meeting
Varanasi regional demand. This power transfer level continues through Sultanpur-Allahabad, Lucknow-
Kanpur, Moradabad-Agra interfaces since the available generation in each of the regions almost
matches with its respective demand. In the east, power from the aforementioned plants flows towards
north to supply Varanasi, Azamgarh and Gorakhpur load centers. A small amount of power is imported
from Bihar through a connection at 132 kV level. Power supply to Uttaranchal in the North West is
normally less than 500 MW due to the available hydroelectric generation in the state. In the west, more
than 3000 MW flows to Delhi and Rajasthan through 500 kV HVDC bi-pole line and 400 kV
transmission network across the state. The existing bulk transmission system capacity with the current
level of power transfer requirements is well equipped to handle the flow of energy.
-
8/13/2019 Arr Transco Fy09 10
11/39
-
8/13/2019 Arr Transco Fy09 10
12/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-7
3.2. Comparison of Estimated Cost and Actual Figures To-Date
3.2.1. Demand Forecast-Tariff Order and Actual FY (2007-08):
Table 3-1 provides a summary of UPERC approved demand in Tariff Order FY 08 and actual demand
for FY 08. In Table 3-2 the same values are given for FY 09.
Table 3-1: Approved and Actual FY 2007-08: Energy Demand (MU)
Agra DisCom (Incld. Bulk) 14053 14,246 -1.4%
Meerut DisCom(Incld. Bulk) 17751 16,968 4.4%
Lucknow DisCom 9426 8,683 7.9%
Varanasi DisCom 12377 11,596 6.3%
Total 53607 51,493 3.9%
Licensee
(Rs Cr)
Tariff Order
FY2007-08
Actual
FY2007-08Diff
Table 3-2: Approved and Actual FY 2008-09: Energy Demand (MU)
Agra DisCom (Incld. Bulk) 14712 14,409 2.1%
Meerut DisCom(Incld. Bulk) 18294 17,214 5.9%
Lucknow DisCom 9684 8,958 7.5%
Varanasi DisCom 12722 12,198 4.1%
Total 55412 52779 4.8%
Licensee
(Rs Cr)
Tariff Order
FY2008-09
Estimated
FY2008-09Diff
3.2.2. Expense items- Approved and Estimated:
Table 3-3 & Table 3-4 provide a summary of the various ARR components of Tariff Order FY08 & FY
09. It is evident from the tables that all expenses are well with in the approved limit.
-
8/13/2019 Arr Transco Fy09 10
13/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-8
Table 3-3: Estimated and Actual ARR FY 08, Components:
Em ployee cost 286.73 252.49 -12%
A&G ex pe nse s 29 .24 21 .52 -26%
R&M expenses 60.45 67.89 12 %Interest charges 252.73 242.92 -4%
Depriciation 270.8 257.38 -5%
Gro ss Exp end itu re 899.95 842.19 -6%
Expenses capi ta l isat ion
Employee cost capitalised 83.15 73.22 -12%
Interest ca pitalised 50.49 15.81 -69%
A&G ex pe ns es ca pita lised 5.55 6.62 19 %
Net exp en d itu re 760.76 746.53 -2%
Prior period Adjustment 15.30
To tal n et exp en d itu re w ith p rov is io n 760.76 761.83
add: Return on Equity 278.24 293.81 6%
Less: Non Tariff Incom e (13.61) (17.17) 26 %
Ann u al Rev en u e Req u irem en t(A RR) 1,02 5.39 1,038.47 1%
Expense Items
(Rs Cr)
Tariff Order
FY2007-08
Actual
FY2007-08Diff
Table 3-4: Estimated and Actual ARR, Components:
Employee cost 316.99 285.72 -10%
A&G expenses 32.32 31.88 -1%
R&M expenses 66.83 101.18 51%
Interest charges 305.51 265.77 -13%
Depriciation 325.65 280.82 -14%Gross Expend itu re 1047.3 965.38 -8%
Expenses capitalisation
Employee cost capitalised 91.93 82.86 -10%
Interest capitalised 61.74 34.52 -44%
A&G expenses capitalised 6.14 6.06 -1%
Net expend iture 887.49 841.94 -5%
add: Return on Equity 321.96 314.49 -2%
Less: Non Tariff Income (14.33) (18.47) 29%
Annual Reven ue Requirem en t(ARR ) 1195.12 1,137.96 -5%
Expense Items
(Rs Cr)
Tariff Order
FY2008-09
Estimated
FY2008-09Diff
3.3. Investments:
Investments will be made in key areas with the objective of strengthening the transmission networks,
thus contributing to the reduction of losses and reliability of supply. This work will be conducted with the
help of loans from financial institution and equity from GoUP.
-
8/13/2019 Arr Transco Fy09 10
14/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-9
3.3.1. Proposal for Ensuing Year:
It will be necessary to execute many works for ensuring reliability, stability and quality of transmission
system but on the basis of experience of the past years, availability of money and other special reasons
the restricted list of transmission works. During FY 2009-10 investments will be made in key areas with
the objective of strengthening the transmission networks, thus contributing to the reduction of losses &
reliability of supply. Most of the works are to be financed by M/s. Power Finance Corporation, New
Delhi, NCR Board, Rural Electrification Corporation, New Delhi and HUDCO loan.
The transmission works have been categorized as follows:-
1. Normal Development Works
2. Transmission works in National Capital Region
3. Renovation and Modernization
4. Transmission works on account of 100% electrification of villages
5. Installation of Capacitors
3.3.2. Normal Development Works:
Due to increase demand of electricity, some of the sub-stations/lines are overloaded. To meet out
this demand it is essential to increase the capacity of the sub-stations and to create new sub-
stations and lines.
3.3.3. Transmission Works in NCR
All the district of Meerut Commissionery is covered in National Capital Region. Industries from
Delhi are to be shifted to National Capital Region for which Electricity Supply position has to be
improved. NCR Board will provide financial aid by way of loan.
3.3.4. Renovation and Modernization
A large number of S/Ss, Transmission lines & communication equipment are around 30 years old
and equipment's like transformer, Circuit breakers, Relay Panels etc. needs replacement for
prolong service as spares for same are not available anymore and more they based on obsolete
technology. Hence, provision has been made for the renovation and modernization of various
equipments.
3.3.5. Augmentation of Transmission System due to RE works
In order to meet increased demand due to electrification of villages in REC scheme and mazras in
Rajiv Gandhi village electrification scheme, various transmission sub-stations and lines are to be
strengthened and new sub-stations and lines are proposed to be constructed.
-
8/13/2019 Arr Transco Fy09 10
15/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-10
Table 3-5: Proposed Program for Transmission Works (Rs. Cr.)
-
8/13/2019 Arr Transco Fy09 10
16/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-11
-
8/13/2019 Arr Transco Fy09 10
17/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-12
-
8/13/2019 Arr Transco Fy09 10
18/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-13
-
8/13/2019 Arr Transco Fy09 10
19/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-14
-
8/13/2019 Arr Transco Fy09 10
20/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-15
-
8/13/2019 Arr Transco Fy09 10
21/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-16
Table 3-6: Detailed Program of Transmission Works for ensuing Year (Augmentation):
-
8/13/2019 Arr Transco Fy09 10
22/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-17
-
8/13/2019 Arr Transco Fy09 10
23/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-18
3.4. Compliance of UPERC Directives:
In compliance with the directive issued by Honble commission in its Tariff Order for financial year 2007-
08 & 2008-09 issued on 15th April 2008 under chapter 9 regarding the compliance of UPERC
directives. It is to submit that directives are under various stage of compilation and will be submitted to
Commission by the Licensees. However partial compliances are submitted as under:-
Table 3-7:Compliance of UPERC Directives:
Sr.No
Ref.
No
Description of Directivefor TransCo
Time Periodfor
complianceAction Taken
1 6.3.6 The Commission directsthe transmission licenseeto submit voltage wisetransmission loss studyreport for last three years
along with the estimationfor current and ensuingyear
3 Month Voltage wise transmission losses are submittedin the Regulatory Format P1 along with theARR.
2 6.6.5.5 The Commission directsthe licensees to submit thestudy report on actuarialvaluation for the purpose ofestimating employerscontribution towardspension and gratuity.
The licensees are alsodirected to intimate theCommission on the status
of the study within a periodof one month from the dateof issue of Tariff Order.
6 Months
Status report
within 1month
ction is being taken as per direction. Statusreport will be submitted to the Commission.
3 6.6.12.3 The Commission directsthe Licensees to carry outa proper cost benefitanalysis before taking upany new initiatives andsubmit the same for theapproval to theCommission.
As and when
required
Action is being taken as per the directives.
4 6.7.13 The Commission directsthe licensee to submit theinvestment plan for nextyear filing strictly inaccordance withTransmission TariffRegulation 2006 failingwhich no investmentswould be approved.
Next Year
Filing
TransCo Investment Plan are submitted with
ARR.
5 6.7.13 As regards to theinvestments approved forFY 2007-08 and FY 2008-
2 Months Action is being taken as per directive.
-
8/13/2019 Arr Transco Fy09 10
24/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 3-19
Sr.No
Ref.
No
Description of Directivefor TransCo
Time Periodfor
complianceAction Taken
09, the Commissiondirects the licensee tosubmit the necessaryinformation required underthe Transmission TariffRegulations approved bythe Commission within twomonth from the issue ofthis tariff order
6 6.8.6 The Commission directsthe licensees to maintainproper and detailed fixedassets registers at fieldoffices to work out thedepreciation expense asspecified in the UPERC
(Terms and Conditions ofTransmission Tariff)Regulations, 2006 anddirects the Licensees tosubmit a report to theCommission citing clearlyas to how they are
maintaining fixed assetsregisters for the variousassets.
2 Months All units have been directed to take maintainfixed assets register to workout the depreciationexpenses. The report will be submitted to theCommission.
7 6.11.3 The Commission directsthe licensee to submit theinformation regarding the
basis used for computationof the Opening Equity andthe detailed working on ayear to year basis andsupporting financialstatements used for thesame.
1 Month Draft Transfer scheme for notification has beensubmitted to GoUP. As per the draft notificationpresented on consultation with M/s PWC theopening equity as on 01.04.2007 is Rs.1843crore and in the year 2007-08 GoUP providedRs. 365.3652 crore as equity for transmissionworks through the budget of GoUP. During2008-09 GoUP provided equity of Rs. 428.55crore for the transmission work through thebudget. The total equity as on 01.04.2009 workout to Rs. 2637 crore.
8 6.13.1 The Commission herebydirects the SLDC that theARR/budget for SLDCshould be submittedseparately along with the
ARR submission ofTransco.
Next Tariff
Filing
Budget for the SLDC is being submittedseparately.
9 6.14.7 The Commission directsthe Transmission Licenseeto formulate the billingprocedure for transmissioncharges and submit thesame for approval of theCommission.
1 Month Actions have already been taken and billing isbeing done as per the directives of theCommission.
-
8/13/2019 Arr Transco Fy09 10
25/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 4-20
4. Power Wheeling & Demand:
UPPTCL (Transco) is performing the business of transmission of electricity received at UP periphery
from various central generating station and station out side state as well as energy generated with in the
state. UPPCL is purchasing power from various sources including State and Central Generating stations
and dispatching to the Distribution Licensees as required, using Transmission system of UP Transco.
In purchasing/ wheeling of electricity from various generating station out side the state, losses out side
the UP transmission system also come into the picture. Therefore it is prudent to separately analyses
losses internal as well as external to the system so that petitioner should not be accountable for loses
external to the system i.e. losses in PGCIL system.
4.1. Losses external to UPPTCL system:
The petitioner submits that while considering losses to meet the requirement of various distribution
licensees, losses external to UPPTCL system, i.e. in the Northern Region PGCIL system need to be
accounted for. The availability of power from various sources out side the state gets reduced to theextent of these losses and the petitioner has to bear these losses as commission is approving total
transmission losses irrespective of loses occurring in PGCIL or other lines. NRLDC computes the losses
in the regional transmission system on a weekly basis and the same are used by it in the scheduling
process subsequently. These losses have varied between 3.76% and 5.24% between 5thJan 2009 and
22nd March 2009. UPPTCL has considered an average level of 4.35% losses in its energy transactions
with the Northern Region for FY2009-10. Here it is to noted that these losses are applicable to only
energy received external to state, therefore petitioner has taken a weighted average of 2.06% for
FY2009-10.
On the basis of Power requirement provided by DisCom a detailed energy balance is summarized for
Distribution Licensees of the state using Transmission system of TransCo for dispatching the energy in
Table 4-1: -
Table 4-1: Actual & Estimated Energy Profile:
L ic e n c s ee FY 2 00 7 - 0 8 F Y 2 0 08 - 09 F Y 2 0 09 - 10
M E E R U T (Inc ld . B u lk ) 1 8 ,1 24 .5 1 18 ,386.40 18 ,469.15
A G R A (I nc ld . B u lk ) 1 5 ,2 16 .2 2 15 ,391.08 16 ,458.76
LU C K N O W 9,2 74 .8 8 9 ,568.35 9 ,788.56
V A R A N A S I 1 2 ,3 86 .0 8 13 ,029.17 13 ,083.52
P u r c h a s e d & B i l le d E n e r g y ( M U ) 55,001.69 56,375.00 57,800.00
Per iphera l Loss (Upto in te r conne c t ion Po in t ) 2 .3 5% 2.3 5% 2.0 6%Energy Ava i lab le fo r Transmiss ion(MU) 53 ,708 .32 55 ,049 .34 56 ,609 .32
C o n s o l i d a te d D i s c o m 51 ,493 .10 52 ,778 .81 54 ,344 .95
M E ER U T ( I nc ld . Bu l k ) 16 ,968 .34 17 ,213 .52 17 ,365 .14
A G R A (I nc ld . B u lk ) 14 ,245 .57 14 ,409 .27 15 ,474 .92L U C K N O W 8 ,683 .23 8 ,957 .98 9,203.44V A R A N A S I 11 ,595 .97 12 ,198 .03 12 ,301 .44
U P P T C L 4 .12 % 4 .12 % 4.00 %
Ie n e r g y D e l iv e r e d t o D i s C o m D i s C o m ( M U )
T r an s m i s s io n L o s s e s
-
8/13/2019 Arr Transco Fy09 10
26/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-21
5. Annual Revenue Requirement: FY 2009-10
The development of the FY 2009-10 ARR follows the methodology as adopted in the Terms and
Conditions for Determination of Transmission Tariff Regulations, 2006.
5.1. ARR FY 2009-10:
Honble Commission has issued Transmission Tariff regulation 2006 which require that ARR shall
consist of following items:
1. Operation & Maintenance expenses
Employee Expenses
Administrative & General Expense.
Repair & Maintenance Expenses
2. Interest expenses
Loan capital Working Capital
3. Depreciation Expenses
4. Other Expenses
5. Return on equity
6. Contingency Reserve
7. Taxes on Income
8. Any other relevant expenditure
Further regulation provide that the State Transmission Utility, when also looking after the SLDC
function, shall file segregated costs for SLDC operations and any surplus / deficit in recovery of SLDC
costs vis--vis SLDC fee and charges collected by the STU shall form part of its ARR.
This section provide ARR for FY2009-10 in accordance with the Tariff regulation and each component
of ARR as mentioned above is dealt in detail in following section. Further it is to submit that UP
TransCo is also looking after the function of SLDC as such SLDC cost is embedded in TransCo cost.
How ever as prescribed in Tariff Regulation segregated costs for SLDC has also been computed at the
end. The petitioner has estimated ARR for ensuing year based on provisional un-audited account of
FY2007-08 and expenses available till date of FY2008-09. In order to put the various proposed amounts
in proper context, the corresponding figures for actual FY08, estimates for FY09 & forecast for FY10
based on year-to-date experience are also presented for certain account categories. For each such
major account category of expenses, an explanation of the derivation is given, along with the logic for
departing from FY08 values.
Further Tariff regulation provide that O&M expenses and other expense shall be escalated on the
basis of prevailing rate of inflation from base figure & inflation shall be calculated on the basis of indexes
notified by central government .Therefore Petitioner has calculated inflation index in following section:
-
8/13/2019 Arr Transco Fy09 10
27/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-22
5.1.1. Escalation Index/Inflation Rate
Regulation issued by Honble commission provides that expenses of the base year shall be escalated at
inflation rate notified by central government for different years. The inflation rate for this purpose shall
be weighted average of wholesale Price Index and Consumer Price Index in the ratio of 60:40.
Therefore for the purpose of this ARR petitioner has used this methodology in arriving at Escalation
Index/ Inflation Rate. Calculation as tabulated below:
Inflation Rate=0.6*Inflation based on WPI + 0.4*Inflation based on CPI
Table 5-1: Escalation Index
M o n t h
2007 2008 2009 2007 2008 2009
J an 208.8 218.1 0 127 134 148
Feb 208.9 219.9 0 128 135 148M ar 209.8 225.5 0 127 137
A p r 211.5 228.5 0 128 138
M ay 212.3 231.1 0 129 139
J u n 212.3 237.4 0 130 140
J u l 213.6 240 0 132 143
A u g 213.8 241.2 0 133 145
Sep 215.1 241.5 0 133 146
O c t 215.2 239 0 134 148
No v 215.9 234.2 0 134 148
Dec 216.4 229.7 0 134 147
In f lat io n 6.15% 9.70%
W eig h ted A v erag e (CPI 40% :W PI 60% ) 7.57%
W holesale Price Index Con sumer Price Index
WPI-http://eaindustry.nic.in CPI-http://labourbureau.nic.in/intab.html
5.2. Operation & Maintenance Expenses
Operation & maintenance expenses comprise Employee costs, Administrative & General Expenses and
Repair & Maintenance expenses. The regulation 4.2 of the Transmission Tariff Regulation issued by the
Commission stipulates:
The O&M expenses for the base year shall be calculated on the basis of historical/audited costs and
past trend during the preceding five years. However, any abnormal variation during the preceding
five years shall be excluded. O & M expenses so calculated for the base year shall then be
escalated on the basis of prevailing rates of inflation for the year as notified by the Central
Government and shall be considered as a weighted average of Wholesale Price Index and
-
8/13/2019 Arr Transco Fy09 10
28/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-23
Consumer Price Index in the ratio of 60:40. Base year, for these regulations means, the first year of
tariff determination under these regulations.
However in last tariff order Commission was of the opinion that a suitable norm for allowance of
O&M expenses could be adopted only after undertaking a thorough study of the O&M expenditure
based on the past performances, and the cost drivers of the same, through a separate process.
This study also has to be backed by audited information for the past which needs to be made
available by the licensees. Only then the true picture if the trend in the O&M expenses may emerge.
Till any such norm for O&M expenditure is determined, the Commission emphasised considering
the individual elements of O&M expenditure.
As stated above, in the absence O&M norms petitioner has estimated individual components of O&M
expenses based on methodology described in following section:
5.2.1. Employee Costs:
The projection of employee costs involves a detailed examination of the various components of salary
such as basic pay and dearness allowance for the various grades of employees. It would also involve
an understanding of the extent of retirements as well as the manpower additions planned. Considering
above Petitioner has estimated employee cost for FY2009-10 based on un-audited data of FY2007-08
and data available for FY2008-09 to date. Here it is also to mention that in FY 2009-10 petitioners have
taken impact of increase due to implementation of sixth pay commission. Details of Employee Cost for
FY08 to FY10 are provided in Table 5-2 below.
Table 5-2: Details of Employee Cost:
DetailsFY 2007-08 FY 2008-09 FY 2009-10
(Rs.Cr) Unaudited Estimated Projected
Basic Salaries 137.06 142.54 240.89
Overtime 0.00 0.00 0.00
Dearness Allowance 54.63 74.48 60.22
Other allowances 9.72 11.40 19.27
Bonus / Ex-gratia 2.96 3.62 5.02
Medical expenses re-imbursem ent 7.22 8.00 8.86
Leave travel assistance 0.00 0.01 0.02
Interim Relief/ Other 1.34 0.00 0.00
Earned leave encashm ent 5.22 3.16 17.57
Leave Salary contribution 0.00 0.00 0.00
Payment under workmen's com pensation Act 0.04 0.29 0.48Staff welfare expenses 0.79 0.82 1.39
Employers Contribution for Pension & Gratuity 33.51 41.41 57.45
Em p loyee Cos ts (before ch arg e to cap ital) 252.49 285.72 411.18
Less expenses capitalized 73.22 82.86 119.24
Net employee cost 179.27 202.86 291.93
As mentioned above evolution of sub account of employee cost has been forecasted from base figure of
FY2007-08 balance sheet and actual figure available for FY2008-09 till date. While projecting the
expenses for ensuing year, petitioner has endeavoured to control the employee expenses but cost has
-
8/13/2019 Arr Transco Fy09 10
29/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-24
increased due to impact of pay commission factor which is totally beyond the control of the petitioner.
Various sub account are estimated as follows:
Basic salary: The petitioner would like to submit that the projected growth in basic salaries
in FY2008-09 due to mainly time bound increment and annual increase in pay. The annual
increase depends on the pay scale of an employee and such increase is mandatory for
employees. Therefore petitioner has estimated basic salaries for FY2008-09 as per actual
cost incurred on this account till date & for FY2009-10 basic salaries has been projected to
increase by 69% from FY2008-09 cost due to implementation of sixth pay commission
recommendation.
Dearness Allowance (DA) is estimated to be 52.25 %( 47% for 3 month&54% for 9 month)
for FY2008-09 and for FY2009-10 DA has been projected 25%.
Other allowance has been forecast to be 8% of basic salary.
Likewise, Medical Expenses have been forecast to increase by inflation index per year from
FY07, taking 3% as contingency.
Pension and Gratuity have been calculated at 16.7% and 2.38% (i.e., 19.08%) of Basic
Salary and Dearness Allowance.
Leave travel Assistance & compensation is assumed to be .01% & 0.2%of Basic Pay
respectively.
Staff welfare ex. Is assumed to in same ratio as actually incurred in FY09.
Employee Expenses Capitalized has been taken 29% as approved by Honble Commission
in last Tariff order.
5.3. Administration and General (A&G) Expenses:
These expenses are incurred by the petitioner for meeting the day-to-day expenses relating to the
administration of its offices, insurance, communication, professional charges, audit fees, advertisement
expenses, freight etc. All these expenses are directly affected by inflation .Therefore A&G expenses
have been projected considering the impact of inflation and need for addition of more substation and
offices.
Forecast A&G expenses for Transco are summarised below in Tables 5-3, beginning with the figures
from the provisional figures for FY08.
-
8/13/2019 Arr Transco Fy09 10
30/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-25
Table 5-3: A &G Expenses:
DetailsFY 2007-08 FY 2008-09 FY 2009-10
(Rs.Cr) Unaudited Estimated Projected
Rent, Rates & Taxes 0.55 0.59 0.64Insurance 0.10 0.11 0.11
Telephone,Postage&Telegrams,Telex charges 1.83 1.97 2.12
Legal charges 1.11 1.19 1.28
Audit fees 0.11 0.11 0.12
Consultancy charges 0.26 6.28 6.75
Technical fees and professional charges 0.61 0.66 0.71
Conveyance and traveling 4.80 5.16 5.55
Regulatory expenses - 2.74 2.82
Electricity Charges 2.36 2.54 2.73
Other expenses 9.80 10.54 11.34
Total 21.52 31.88 34.17
Capitalized 6.62 6.06 6.49Net 14.89 25.82 27.67
It may be noted that licensee is capitalizing a portion of A&G cost .For current submission licensee has
taken capitalization as 19%, approved by commission in its last tariff order.
As a reflection of the continuing commitment of the Petitioner to keep costs under control,
almost all A&G Expenses are forecast to increase by only inflation index per year across the
board to only offset the effect of inflation.
In FY2008-09 & FY2009-10 under the head consultancy charges an amount of Rs 6 Cr has
been added for IT related expenses which are urgently required to cope with the present pace
of technological development in Power sector.
In addition to above regulatory expenses Rs 10 lacs application fees and Rs 500 per MU
energy delivered to distribution licensees as license fees has been added in A&G expenses in
FY2008-09& FY2009-10 which is Rs 2.64& 2.72 crs respectively.
5.4. Gross Fixed Assets (GFA) Balances and Capital Formation
Assumptions
The estimate of a number of ARR components is dependent on the FY10 opening balance of GFA, oneof which is R&M in the next section. It is therefore appropriate at this point to provide FY10 GFA
estimates, as well as estimates for other fixed asset accounts. The assumptions used for projecting
GFA and CWIP are as follows:
The opening GFA and CWIP for Lucknow DisCom for FY 2008-09 have been taken as per the
closing figures provisional annual accounts of FY 2007-08.
-
8/13/2019 Arr Transco Fy09 10
31/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-26
30% the opening CWIP and 30% of investment made during the year, expenses capitalised &
interest capitalised (30% of total investment) has been assumed to get capitalised during the
year.
Investment through deposit work has not been taken for capital formation as per policy
adopted by commission in its last tariff Order. Thus investment shown in capital formation table
below table 5.4&4.5 dont include work funded through deposit work.
Table 5.3 shows Licensees investment plan for FY09 and FY10 along with the proposed funding of
each component of the investment plan. The detail of activities carried out in each scheme has
already been explained in section 3.3.
Table 5-4: Transco Investment Plan: (Rs. Cr)
Loan Grant Deposit Equity Total Loan Grant Deposit Equity Total
Equity from GoUP for Transmission Works - - - 428.55 428.55 - - - 891.57 891.57
Loans for Transmission Works - - - - - - - - - -
PFC 88.55 - - - 88.55 826.94 - - - 826.94
REC 52.09 - - - 52.09 826.94 - - - 826.94
NCR - - - - - - - - - -
HUDCO - - - - - - - - - -
Deposit Works - - 225.00 - 225.00 - - 325.00 - 325.00
Total Transmission 140.64 - 225.00 428.55 794.19 1,653.88 - 325.00 891.57 2,870.45
FY 2008-09 FY 2009-10Particulars
Table 5-4 and Table 5-5 shows the forecast evolution of the GFA, Accumulated Depreciation and Workin Progress Accounts under the assumptions noted below the table.
Table 5-5: Capital Formation during FY 09
Table 5-6: Capital Formation during FY 10
Rs croreBalance 31-
Mar-09Invest-ments Cap interest Cap expenses To GFA Depreciation
Balance 31-
Mar-10
(1) (2) (3) (4) (5)
Gross Fixed Assets 5,598.2 1,220.5 6,818.8
Accumulated Depreciat ion 2,307.7 327.2 2,634.9Work in Progress 1,258.1 2,545.5 139.2 125.7 (1,220.5) 2,847.9
Notes: (1) FY08 Balances as per provisional financial statements.
(2) Capitalized interest - see Table 5-8.
(3) Capitalized expenses are from Table 5-2 &5-3.
(4) Depreciation expense for FY09 = 5.27% of average GFA.
-
8/13/2019 Arr Transco Fy09 10
32/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-27
5.5. Repair and Maintenance (R&M) Expenses
Forecast R&M expenses for TransCo are summarised below in Tables 5-7, beginning with the figures
from the provisional figures for FY08.The forecast R&M Expenses are estimated as 2.0% of the opening
GFA balances. In the last tariff order commission approved Rs 66.83 cr for FY2008-09 while petitioner
has estimated Rs 101.18 cr , This increase is mainly attributed to substantial increase in raw material
and fuel cost. The metal prices have increased phenomenally as compared to past few years. This has
substantially increased the cost burden of the petitioner. Moreover, the petitioner has added a number
of transformers, cables, grid substation, etc for which there has been an increase in the amount of
annual maintenance contracts, this would have translated to a higher R&M expenses in the ensuing
year for the petitioner. The petitioner has estimated Rs 111.96 Cr for ensuing year. The amount so
estimated has been spread out proportionally among the sub-accounts.
Table 5-7: R&M Expenses:
Details FY 2007-08 FY 2008-09 FY 2009-10
(Rs.Cr) Unaudited Estimated Projected
Plant & Machinery 54.45 81.15 89.79
Building 7.39 11.01 12.18
Civil works 0.06 0.09 0.10
Other Expenses
Lines, Cable Network, etc 5.79 8.62 9.54
Vehicles
Furniture & Fixtures 0.01 0.02 0.02
Office equipment 0.20 0.29 0.32
To tal 67.89 101.18 111.96
5.6. Depreciation Expense:
FY10 Depreciation Expenses may be estimated with reference to Table 5-6, which has projected the
opening GFA balance for FY10. Applying the rate of 5.27% to average GFA during year petitioner has
projected a Depreciation Expense of Rs 327.2 crores for FY2009-10. This is line with the method used
by commission in recent Tariff order.
5.7. Interest and Financing costs:
The interest and financing costs projected for FY10 are based on the current schedule of long-term
debt, repayments and new debt requirements. The summary of the interest and finance costs is
provided in Table 5-8 below:
-
8/13/2019 Arr Transco Fy09 10
33/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-28
Table 5-8: Details of Interest & Finance Cost:
FY 2007-08 FY 2008-09 FY 2009-10
U naudited Estimated Projected
W orld Bank Loan 16.67 14.96 14.96
N C R 3.71 3.70 2.87
PFC U PPCL 97.44 103.21 94.79
I.D .B .I. Loan 0.05 0.12 0.00
R EC (UPPCL) 19.90 35.00 32.49
R EC R escheduled 15.39 9.55 9.22
H udco 37.43 29.96 15.46
R EC T ransm ission 4.53 10.57 63.82
PFC T ransm ission 0.95 10.13 62.64
G ro s s In teres t Co s t 196.06 217.20 296.24
IDC 15.81 34.52 139.19
Net Interest Cost 180.25 182.67 157.06
F inance C ha r ges
F inance Charges/ G uarantee Fees 17.20 16.21 14.29
Bank Charges 0.16 3.80 18.73To tal F in an c e Ch arg es 17.37 20.01 33.03
To tal In teres t an d F in an c e Ch arg es 197.62 202.68 190.09
Particulars (Rs C r )
Interest on Working Capital:
1. The Transmission tariff regulations provides for normative interest on working Capital based on
the methodology outlined in the regulations. The petitioner is eligible for interest on working
capital worked out on methodology specified in the regulations.
2. Further Transmission tariff regulations provide following methodology for calculating working
capital
(i) Operation and Maintenance expenses, which includes Employee costs, R&M expenses
and A&G expenses, for one month;
(ii) One-twelfth of the sum of the book value of stores, materials and supplies at the end
of each month of current financial year.
(iii) Receivables equivalent to 60 days average billing of consumers less security deposits
by the beneficiaries
3. Rate of interest on working capital shall be the Bank Rate as specified by Reserve Bank of India
as on 1st April
Based on above methodology petitioner has computed interest on working capital in following table:
-
8/13/2019 Arr Transco Fy09 10
34/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-29
Table 5-9:Interest on Working Capital:
S r .
N o .P r e v i o u s Y e a r C u r r e n t Y e a r E n s u i n g Y e a r
1 2 8 .4 9 3 4 .9 0 4 6 .4 4
2 3 4 .3 3 3 .9 5 1 7 .6 8
3 1 7 3 .0 8 1 8 9 .6 6 2 1 9 .9 8
2 3 5 . 9 0 2 2 8 . 5 1 2 8 4 . 1 0
L e s s :
1
2 3 5 . 9 0 2 2 8 . 5 1 2 8 4 . 1 0
R a te o f In te r e s t f o r W o r k in g C a p i ta l 1 2 .5 0 % 1 2 .5 0 % 1 2 .5 0 %
I n t e r e s t o n W o r k i n g C a p i t a l 2 9 .4 9 2 8 . 5 6 3 5 . 5 1
O n e - tw e l f th o f t h e s u m o f t h e b o o k
v a l u e o f s t o r e s , m a t e r ia l s a n d s u p p l i e s a tt h e e n d o f e a c h m o n t h o f s u c h f i n a n c ia l
y e a r
P a r t i c u l a r s
O n e m o n t h 's O & M E x p e n se s
R e c e i v a b le s e q u i v a l e n t to 6 0 d a y s
a v e r a g e b i l li n g o f B e n e f i c i a r ie s
G r o s s T o t a l
S e c u r i ty D e p o s i t s b y t h e b e n e f ic i a r ie s
( if a n y )
N e t W o r k in g C a p i ta l
5.8. Other Income:
Other Income includes only non-tariff income, which comprises interest on loans and advances to
employees, income from fixed rate investment deposits and interest on loans and advances to
Licensees. It is estimated that other income will increase by inflation index for FY09 from FY08
provisional financial statement & same hike projected for FY10.
Table 5-10: Summary of Other Income:
FY 2007-08 FY 2008-09 FY 2009-10
Unaudited Estimated Projected
Share of Income from the other businesses - - -
Interest on loan to Staff 0.31 0.33 0.36
Income from Investments 1.41 1.52 1.63
Revenue from surcharges for late payment - - -
Any other Income 15.45 16.62 17.88
Total Non- tariff Income 17.17 18.47 19.87
Details
(Rs.Cr)
5.9. Reasonable return/ Return on Equity:
Under provisions of the Regulation licensees are allowed a return of @ 14% on equity base, For equity
base calculation debt equity ratio shall be 70:30.Where equity involves is more than 30%, the amount of
equity for the purpose of tariff shall be limited to 30%.Equity amount more than 30% shall be considered
as loan. In case of actual equity employed is less than 30%, actual debt and equity shall be considered
for determination of tariff. Here it is to submit that GOUP has yet to notify the transfer scheme for
affecting the transfer of assets & liability. Due to this debt: equity process for calculating return is not
practical. ROE is being calculated on the equity inflow from GOUP up to FY2009 and to be received in
FY2009-10.In this ARR petitioner used same methodology for computation of return as adopted by
commission in its last tariff order.
-
8/13/2019 Arr Transco Fy09 10
35/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-30
Table 5-11: Return on Equity:
FY2007-08 FY2008-09 FY2008-10
1,843 1,948.08 2,109.84
350.37 539.19 1220.55105.11 161.76 366.16
1,948.08 2,109.84 2,476.00
285.66 301.95 327.03
8.15 12.54 28.38
Total return on regulatory equity 293.81 314.49 355.40
Return computation
Return Regulatory equity at the beginning
Returnon Equity portion of expenditure on capitalised assets
Equity portion of expenditure on capitalised assets
Regulatoryequity at the end
Particulars
Return on Equity
Regulatory equity at the beginning
Capitalised assets during the year
5.10. Service tax:
Para 4.9 of UPERC Transmission Regulations provide
Any cess or duty or royalty or tax imposed by the State Government shall be allowed as pass through
to be recovered from the distribution licensees / long term open access consumers in proportion of their
allotted capacity or quantity of energy delivered, as the case may be.
Service tax liability is imposed on the service provider which would be UPPTCL in this case. Service tax
would be chargeable on actual energy wheeled during a financial year and at the rates as notified &
amended by the Govt from time to time. The Petitioner seeks allowance of such statutory liability on the
service provider UPPTCL as pass through in tariff.
Also such liability may be imposed on UPPCTL retrospectively like it was done in the case of PGCIL. In
such an event the Petitioner would approach the Commission for allowance of such liability in its ARR
accordingly.
-
8/13/2019 Arr Transco Fy09 10
36/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 5-31
5.11. TransCo ARR:
The FY10 ARR for UP Power Transmission Corporation is summarised below in Table 5-12 from the
expenses and allowances described in previous section:
Table 5-12: Annual Revenue Requirement:
Details FY 2007-08 FY 2008-09 FY 2009-10
(Rs.Crore)Unaudited Estimated Projected
Employee Costs (net of capitalization) 179.27 202.86 291.93
A&G Costs 14.89 25.82 27.67
Repair & Maintenance Expense 67.89 101.18 111.96
Depreciation 257.38 280.82 327.19
Interest & Finance Charges 227.10 231.25 225.60
Less Other Income (17.17) (18.47) (19.87)Return on Equity 293.81 314.49 355.40
Debits, W rite-offs and any other items 15.30
Annual Revenue Requi rement 1,038.47 1,137.96 1,319.90
-
8/13/2019 Arr Transco Fy09 10
37/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 6-32
6. Proposed Transmission Tariff:
6.1. Derivation of Tariff:
The proposed transmission tariff is derived in Table 6-1 in accordance with the methodology provided inTransmission Tariff Regulation. It provides that in case of more than one long-term customers of the
Transmission system (distribution licensee/long term open access customers), utilizing transmission
system, the wheeling charges leveable on such customers shall be computed as per the following
formula:
Transmission /wheeling charges payable by the long term of customer of Transmission system for use
of transmission system for a month
= (Net ARR/12)*(CL/SCL)
CL =Allotted Transmission Capacity in MW of particular long term customer.
SCL=Sum of the Allotted Transmission Capacities (in MW) to all long-term customers.
Presently DisComs have not been allotted transmission capacity as such Transmission tariff has been
calculated on the basis of numbers of units wheeled by the transmission licensee for distribution
licensees. This is based on the same approach adopted by the Commission in its last Tariff Order.
Based on the above mentioned methodology, the transmission charges payable by all the licensees in
the state is computed bellow:
Table 6-1: Derivation of Transmiss ion Tariff:
FY2008-09 FY2009-10
Estimated Proposed
UPPCL Transco ARR (Rs Cr)1138 1320
Total energy delivered(MU) 52779 54345
Transmission Tariff (Rs/ kWh) 0.216 0.243
Details
-
8/13/2019 Arr Transco Fy09 10
38/39
ARR & TARIFF: FY10
Uttar Pradesh Power Corporation Ltd. UPPCL TransCo 7-33
7. SLDC Charges:
Table 7-1 provides a summary of estimated costs of running UPPTCL central load dispatch centre in
Lucknow and four regional load dispatch centres at Panki, Sahupuri, Modipuram and Moradabad which
are owned and operated by UPPTCL.
Table 7-1: Break-up of SLDC Charges
Details FY2008-09 FY2009-10
(Rs.Crore) Estimated Proposed
Employee Costs 5.02 7.22
A&G Costs 0.20 0.22
Repair & Maintenance Expense 0.29 0.29
Subtotal 5.51 7.73
Depreciation 4.69 5.86
Interest & Finance Charges 3.86 4.04
Less: Other Income (0.31) (0.36)
Return on Equity 5.25 6.37
Total SLDC ARR 18.99 23.64
All direct cash expenses in the above estimates, including Employee Costs, A&G and R&M, have been
obtained from central load dispatch centre. However, capital related charges including Interest &
Finance Charges, Depreciation and the Return on equity, could not be separated because SLDS is
functioning as integral part of UP Transco, such the same have been approximated as follows:
Depreciation Expense for Transco is 86% in FY09 of the sum of above cash expenses.This may be calculated from Table 4-9 in the absence of precise information on the cost of
the SLDC assets; an adder of these values has been applied to SLDC cash costs to
account for SLDC Depreciation Expense.
Interest and Finance charges & other Income have been similarly approximated.
Pending a better delineation of capital charges, the above SLDC estimates are the best available.
However, it may also be noted that the estimated SLDC costs comprise only about 1.7 % of total
transmission costs. This means that any major error in the SLDC cost estimate (which is quite likely)
will be very small when compared to total transmission costs.
-
8/13/2019 Arr Transco Fy09 10
39/39
ARR & TARIFF: FY10
PRAYER:
The petitioner prays that the Commission may be pleased to:
a. Admit the accompanying Annual Revenue Requirement and Tariff
Petition.
b. Approve the Annual Revenue Requirement for financial year 2009-10.
c. Allow the petitioner to add/change / alter / modify this application at a
future date.
d. Issue any other relief, order or direction which the commission may
deem fit.