Army Team C4ISR BRAC Update
description
Transcript of Army Team C4ISR BRAC Update
FOUO – For Official Use Only
Army Team C4ISR Army Team C4ISR BRAC UpdateBRAC Update
Presented By:Sue Nevin, G3/5CECOM Life Cycle Management Command8 October 2009
FOUO – For Official Use Only
Page 2 of 29
In accordance with Report to Congress and BRAC Strategic Plan: Developed Phased Early Relocation strategy using temporary
facilities at APG – combination of military, civilian volunteers, new hires and contractors
2007 2008 2009 2010 2011 2012
Phase 1Early Relocation
32 positions (11 Vol.) (11 Vol.)
GroundbreakingFor
PermanentFacilities
Phase 2Early Relocation
340 positions (140 Vol.)(140 Vol.)
Phase 3Early Relocation1317 positions
(542 Vol. Currently)(542 Vol. Currently) Main Moves Into
Permanent Facilities
What We’ve DoneWhat We’ve DonePhased Relocation Status and TimelinePhased Relocation Status and Timeline
(FY07 – FY11)(FY07 – FY11)
1,131 “Boots on
the Ground”Time Now
FOUO – For Official Use Only
Page 3 of 29
HQ BES WEST
MTF
GMS LAB
C2/CNT WEST
GMS TOWER
Phase 1 Estimated Move In Dates Domains
GMS Lab 1 Aug 10 Ground Based Radars, Multi-Intel,
Sensors, Force Protection (FP),
Night Vision (NVEO)GMS Tower 1 Aug 10
HQ East 1 Oct 10HQ, Business
Enterprise Systems, Operations Support
HQ West 1 Oct 10
Auditorium 1 Oct 10
C2/CNT West 1 Nov 10
Command & Control (C2), Navigation, Future Combat System (FCS)
Mission Training Facility
1 Nov 10 Mission Training Facility
HQ BES EASTAuditorium
FOUO – For Official Use Only
GMS Lab & GMS TowerEstimated Date that Moves will begin: 1 August 2010
Aug-Sep 10 Oct - Dec 10 Jan-Mar 11 TOTALCERDEC 75 107 33 215IEWS 73 104 32 209LRC 60 85 26 171SEC 41 58 18 117
249 354 109 712
Building Occupancy: 1,410
FOUO – For Official Use Only
HQ East & HQ WestEstimated Date that Moves will begin: 1 October 2010
Oct - Dec 10 Jan-Mar 11 Apr - Jun 11 TOTALC3T 8 11 4 23CCCE 68 96 29 193HQ CECOM 84 119 84 287CERDEC 18 26 8 52IEWS 3 4 2 9LRC 126 179 54 359SEC 72 103 21 196
379 538 202 1,119
Building Occupancy: 2,143
FOUO – For Official Use Only
C2/CNT West & Mission Training FacilityEstimated Date that Moves will begin: 1 November 2010
Nov - Dec 10 Jan-Mar 11 Apr - Jun 11 TOTALARL 5 12 3 20G2, G8, Safety 1 3 1 5CERDEC 28 66 17 111FCS 21 49 13 83LRC 26 62 16 104PEO C3T 116 278 70 464PEO IEW&S 7 17 5 29SEC 23 55 14 92
227 542 139 908
Building Occupancy: 1,800
FOUO – For Official Use Only
Army Team C4ISR Phase IIArmy Team C4ISR Phase II
Phase 2 Estimated Move In Dates Domains
C2/CNT East 1 Mar 11 Comm System Network Transport (CNT)
Consolidated North 1 Mar 11 C3T SPO, CECOM Safety
Power & Cooling (5100) 1 Mar 11 Power and Cooling (P&C)
JSEC 1 Mar 11 JSEC
C2 Integration 15 Jul 11 Fabrication
JSECConsolidated North C3/CNT EastPower & Cooling
Mar-11 Apr - Jun 11 Jul - Sep 11 TOTALCECOM Safety 3 14 2 19CERDEC 53 264 36 353LRC 41 204 28 273PEO C3T 42 210 28 280PM DCATS 9 43 6 58SEC 20 96 13 129
168 831 113 1,112
Building Occupancy:
2,213