Arkansas State
Highway and Transportation
Department
Rotary Club of West Pine Bluff
Pine Bluff Country Club Thursday, November 7, 2013
![Page 2: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/2.jpg)
12th Largest System in USA
43rd Highway Revenue Per Mile
The Facts:
![Page 3: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/3.jpg)
Recent Voter Approved
Programs
November 2011
November 2012
![Page 4: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/4.jpg)
Scheduled Under Construction
Complete
![Page 5: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/5.jpg)
Construction Planned
Big Rock Interchange $150 million Early 2015
Bingham Rd. – Grant Co Line $14 million
Summer 2014
Interchange
Construction Central Arkansas
I-30 - Bingham Rd. $38 million
Scheduled: Mid 2014
![Page 6: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/6.jpg)
4+ Lane Highways (Existing, Under Construction, Scheduled , and Proposed)
Planned Jefferson County
I-530 Overlay Jefferson – Hwy 104
Scheduled: 2016 $6.3 million
I-530 Overlay Hwy 104 – Hwy 65B
Scheduled: 2017 $20 million
I-530 Overlay Hwy 65B – Hwy 65
Scheduled: TBD
![Page 7: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/7.jpg)
½ Cent Sales Tax Approved in November 2012 58% of the vote $1.8 billion over 10 years
![Page 8: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/8.jpg)
Planned Construction
![Page 9: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/9.jpg)
4+ Lane Highways (Existing, Under Construction, Scheduled , and Proposed)
Planned Central View
I-30/40 Widening I-530 – Hwy 67
Scheduled: 2018 $323 million
I-630 Widening Bapt. Hosp. – Fair Park
Scheduled: 2017 $50 million
I-40 Widening Hwy 365 – I430
Scheduled: Mid 2014 $35 million
Hwy 67 Widening Vandenberg – Hwy 5
Scheduled: 2019 $40 million
Hwy 67 Widening Main St. - Vandenberg
Scheduled: 2016 $95 million
![Page 10: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/10.jpg)
4+ Lane Highways (Existing, Under Construction, Scheduled , and Proposed)
Planned W. Central View
Highway 270 Widening Hwy 227 – Ouachita River
Scheduled: Mid 2016 $15 million
Highway 70 Widening Hot Springs – Hwy 128 Scheduled: Early 2018
$42 million
Interstate 30 Widening Hwy 70 – Sevier St.
Scheduled: Mid 2015 $75 million
![Page 11: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/11.jpg)
4+ Lane Highways (Existing, Under Construction, Scheduled , and Proposed)
Planned W. Central View
Highway 270 Widening Hwy 227 – Ouachita River
Scheduled: Mid 2016 $13 million
Highway 70 Widening Hot Springs – Hwy 128 Scheduled: Early 2018
$42 million
Interstate 30 Widening Hwy 70 – Sevier St.
Scheduled: Mid 2015 $75 million
Highway 70 Widening Hwy 128 – I-30
Scheduled: Early 2016 $41 million
![Page 12: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/12.jpg)
4+ Lane Highways (Existing, Under Construction, Scheduled , and Proposed)
Planned Southeast View
Highway 167 Widening Hwy 79 - South
Scheduled: 2018 $30 million
Highway 167 Widening Hwy 274 - North Scheduled: 2018
$45 million
Highway 167 Widening Hampton – Hwy 274
Scheduled: 2016 $35 million
Highway 167 Widening Hampton
Scheduled: 2016 $10 million
Highway 425 Widening Hwy 425 - Hamburg
Scheduled: 2016 $25 million
Highway 425 Widening LA State Line – Hwy 82
Scheduled: 2017 $45 million
![Page 13: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/13.jpg)
Sheridan Bypass
Cost: $25,885,924.51
Est. Complete: December
![Page 14: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/14.jpg)
Sheridan Bypass
Cost: $25,885,924.51
Est. Complete: December
![Page 15: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/15.jpg)
Sheridan Bypass
Cost: $25,885,924.51
Est. Complete: December
![Page 16: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/16.jpg)
Sheridan Bypass
Cost: $25,885,924.51
Est. Complete: December
![Page 17: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/17.jpg)
Sheridan Bypass
Cost: $25,885,924.51
Est. Complete: December
![Page 18: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/18.jpg)
Projects Miles Cost
Completed 141 $131,384,547
Under Construction 7 $7,681,831
Planned 53 $211,057,066
Total 175 $350,123,444
18
Jefferson County Construction
![Page 19: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/19.jpg)
Will connect I-530 to Hwy 278 Construction :
Between Hwy 212 and Hwy 11/425
Between Hwy 212 and Hwy 114
Complete: Late 2014
![Page 20: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/20.jpg)
Will connect I-530 to Hwy 278 Construction :
Between Hwy 212 and Hwy 11/425
Between Hwy 212 and Hwy 114
Complete: Late 2014
![Page 21: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/21.jpg)
Widening $6.7 million
Est. Comp: Mid 2014
University Dr.
![Page 22: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/22.jpg)
Widening $6.7 million
Est. Comp: Mid 2014
University Dr.
![Page 23: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/23.jpg)
Widening $6.7 million
Est. Comp: Mid 2014
University Dr.
![Page 24: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/24.jpg)
Jefferson County Improvements Complete in 2012
Location Work Area Miles Description Cost
I-530 Hwy 104 – Hwy 65 15 Cable Median Barrier $2,297,318.52
79B/Hwy 190 Pine Bluff 3 Resurfacing $1,010,170.67
Co Rd 14 Near Pine Bluff 4 Resurfacing $413,848.45
Hwy 270 Grant Co – Rolling Hills Rd. 5 Resurfacing $779,565.24
Nevins Creek Bridge
Nevins Rd./Pine Bluff Bridge Replacement $302,939,43
Hwy 63 Paper Mill Rd – Hwy 65B
3 Resurfacing $540,143.13
![Page 25: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/25.jpg)
Jefferson County Improvements Complete in 2013
Location Work Area Miles Description Cost
Co Rd 53/54 Hwy 63 – Hwy 88 4 Resurfacing $413,372.22
Hwy 81 Hwy 65 – Fairfield Rd. 2 Resurfacing $422,688.30
Hwy 65 RR Overpass – Linwood 6 Resurfacing $629,637.72
Co Rd 25 Ryburn Rd to Whiteville Rd 3 Resurfacing $329,329.66
![Page 26: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/26.jpg)
Job Number Location Miles Est. Award Date Cost
BB0201 Jefferson to Hwy 104
6 Early 2015 $7.4 million
BB0202 Hwy 104 to Hwy 65B
5 2017 $20 million
BB0203 Hwy 65B to Hwy 65
10 2022 $46 million
Future Projects
![Page 27: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/27.jpg)
Turnback Funds
for cities and counties.
![Page 28: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/28.jpg)
70/15/15 Formula
70% Arkansas Highway & Transportation Dept
15% Arkansas Counties
15% Arkansas Cities
Highway Revenue
Distribution
![Page 29: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/29.jpg)
City Ten Year Cumulative
Altheimer $637,041
Pine Bluff $31,776,214
Redfield $839,673
Sherrill $54,382
Wabbaseka $165,091
White Hall $3,577,516
Jefferson County Turnback Funds
County Ten Year Cumulative
Jefferson $23,599,334
![Page 30: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/30.jpg)
State Aid Street Program
Created in 1973
Funded with Fed Revenue Sharing Funds
Federal money was eliminated in 1981
2012 program funded with one penny of existing state fuel tax
30
![Page 31: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/31.jpg)
State Aid Street Program
31
Name City
Mike Gaskill, Chairman Paragould
Jerry Boen, Vice Chairman Lamar
Chris Claybaker Camden
Tab Townsell Conway
Shane Kilgore Jasper
Harold Perrin Jonesboro
JoAnne Bush Lake Village
Mark Stodola Little Rock
Doug Sprouse Springdale
![Page 32: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/32.jpg)
State Aid Street Program
Requests received from 26 cities
15 approved totaling $2.9 million
7 jobs awarded totaling $1.6 million
32
District 2
![Page 33: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/33.jpg)
State Aid Street Program
Altheimer DeWitt
Eudora
Hamburg
Humphrey
Lake Village
McGehee
33
District 2
![Page 34: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/34.jpg)
Construction Zone Locations Live Traffic Conditions
Weather Radar Live Traffic Cameras (Coming Soon)
![Page 35: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/35.jpg)
![Page 36: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/36.jpg)
![Page 37: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/37.jpg)
![Page 38: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/38.jpg)
![Page 39: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/39.jpg)
![Page 40: Arkansas State Highway and Transportation Department · 2013-11-21 · Jefferson County Improvements Complete in 2012 Location Work Area Miles Description Cost I-530 Hwy 104 – Hwy](https://reader034.fdocuments.net/reader034/viewer/2022050415/5f8bcbf58e6f9a1c1228e8d0/html5/thumbnails/40.jpg)