Arhi-Tektons Systems Ltd-Profile 060715.

41
ARKHI-TEKTONS SYSTEMS LTD COMPANY PROFILE Architects. Planners. Interior Designers . Construction Project Managers. Facility Managers. Fit-out Contractor's. Occidental Plaza,Westlands, 3 rd Floor. P.O. Box 67674-00200, NAIROBI,KENYA. Cellphone: 0720300638 0734703549 Email: [email protected] [email protected]

Transcript of Arhi-Tektons Systems Ltd-Profile 060715.

Page 1: Arhi-Tektons Systems Ltd-Profile 060715.

ARKHI-TEKTONS SYSTEMS LTD

COMPANY PROFILE

Architects. Planners. Interior Designers .

Construction Project Managers. Facility

Managers. Fit-out Contractor's.

Occidental Plaza,Westlands,

3rd Floor.

P.O. Box 67674-00200, NAIROBI,KENYA.

Cellphone: 0720300638

0734703549

Email: [email protected]

[email protected]

Page 2: Arhi-Tektons Systems Ltd-Profile 060715.

Letter of Introduction.

Page 3: Arhi-Tektons Systems Ltd-Profile 060715.

Letter of Introduction.

Page 4: Arhi-Tektons Systems Ltd-Profile 060715.

Registration Certificate PIN Certificate

Page 5: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

Page 6: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Residential house at Garden Estate.

PROJECT COST;KSH 30Million.

PROJECT STATUS; Construction commencement; January2012.

CLIENT; Mr.Ndinika.

LOCATION;Niarobi. .

1

Perspective from the entry

Floor Plan

Front elevation

Side Elevation

Page 7: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Maisonette at Dumberi.

PROJECT COST;KSH 11.5 Million.

PROJECT STATUS; Construction commencement; March 2011.

CLIENT; C.N Kariuki.

LOCATION;Kiambu .

2

Perspective from the entry

Floor Plan

Front elevation

Side Elevation

Page 8: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed 3-bedroom bungalow in Eldoret.

PROJECT COST;KSH 4.5 Million.

PROJECT STATUS; Construction commencement, August 2010.

CLIENT; Aaron Biwott.

LOCATION;Sergoi,Uasin-Gishu district,Eldoret.

3

Perspective from the entry

Floor Plan

Front elevation

Side Elevation

Page 9: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed maisonette.

PROJECT COST;KSH 11.2 Million.

PROJECT STATUS; Local authority approval stage.Feb 2011.

CLIENT; Mr. Kivuti S.M

LOCATION; Rongai,Nairobi.

4

Perspective from the entry

Floor Plans

Rear perspective

Page 10: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Maisonette in Rongai.

PROJECT COST;KSH 14 Million.

PROJECT STATUS; Construction stage.

CLIENT; Albert Nyambaso Kerongo.

LOCATION;Rongai,Nairobi Metro..

5

Perspective from the entry

Floor Plans

Rear Perspective

Page 11: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Maisonette in Juja,Thika.

PROJECT COST;KSH 5.5Million.

PROJECT STATUS; Construction stage

Commencement date ;April 2008.

CLIENT; Samson Kamau.

LOCATION;Juja,Nairobi Metro..

6

Perspective from the entry

Floor Plans

Front Elevation

Page 12: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Refurbishments at Oscar’s Residence.

PROJECT COST;KSH 3.3Million.

PROJECT STATUS; Complete.

CLIENT; Oscar Muriu.

LOCATION;Karen,Nairobi Metro..

7

Photo of the complete scheme

Floor Plans

Works in progress

Page 13: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Executive Apartments at Kikuyu.

PROJECT COST;KSH 45Million.

PROJECT STATUS; Construction Stage

Commencement date; May 2010.

CLIENT; Jack Tharamba.

LOCATION;Kikuyu,Nairobi Metro..

8

Perspective showing the frontage

Floor Plans

Elevations

Page 14: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Apartments Juja, NAIROBI.

PROJECT COST;KSH 37.9Million.

PROJECT STATUS; Construction Stage

CLIENT; Dr.Joyce Njenga.

LOCATION;Juja,Nairobi Metro..

9

Perspective showing the frontage

Floor Plan

Side Elevations

Page 15: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Apartments Langata, NAIROBI.

PROJECT COST;KSH 18.2Million.

PROJECT STATUS; Local authority approval stage.

CLIENT; MR. Boniface Irungu.

LOCATION;Langata,Nairobi Metro..

10

Perspective showing the frontage

Floor Plan

Side Elevations

Page 16: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Apartments Thindigwa, Kiambu,NAIROBI.

PROJECT COST;KSH 45.2Million.

PROJECT STATUS; Local authority approval stage.

CLIENT; MR. C.N Wachira.

LOCATION;Thindigwa,kiambu,Nairobi Metro..

11

Perspective showing the frontage

Floor Plan

Entry point perspective

Page 17: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Residential house at Garden Estate.

CLIENT; Mr.Rajan A.

LOCATION;Niarobi. .

12

Perspective from the entry

Perspective from the rear.

Page 18: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Residential house at Kakamega.

CLIENT; Mrs.Shavuya Zainabu.

LOCATION;Kakamega. .

13

Perspective from the entry

Perspective from the rear.

Page 19: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Apartments Kilimani,NAIROBI.

PROJECT COST;KSH 200Million.

PROJECT STATUS; Local authority approval stage.

CLIENT; MR. Ramesh.

LOCATION;Kilimani,Nairobi Metro..

14

Perspective showing the frontage

Floor Plan

Entry point perspective

Page 20: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Town Houses Kilimani,NAIROBI.

PROJECT COST;KSH 128Million.

PROJECT STATUS; Local authority approval stage.

CLIENT; MR. Dinesh.

LOCATION;Kilimani,Nairobi Metro.

15

Perspective showing the frontage

Floor Plan

Entry point perspective

Page 21: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Apartments Thika.

PROJECT COST;KSH 140Million.

PROJECT STATUS; Local authority approval stage.

CLIENT; MR. Edwin Kadudu.

LOCATION;Thika,Kiambu County.

16

Perspective showing the frontage

Floor Plan

Entry point perspective

Page 22: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed Maisonette at Ngong.

CLIENT; Bjohn Maaskart.

LOCATION;Ngong –Kajiado county.

17

Perspective from the entry

Perspective from the side.

PROJECT COST;

PROJECT STATUS; Construction stage.

Construction Commencement Date; August 2015.

Floor plans.

Page 23: Arhi-Tektons Systems Ltd-Profile 060715.

RESIDENTIAL PROJECTS

PROJECT; Proposed refurbishments at Ngong.

CLIENT; Bjohn Maaskart.

LOCATION; Ngong –Kajiado county.

18

Perspective from the side.

Perspective from the Front.

PROJECT COST;

PROJECT STATUS; Construction stage.

Construction Commencement Date; Jan 2016.

Floor plans.

Page 24: Arhi-Tektons Systems Ltd-Profile 060715.

COMMERCIAL,HOSPITALITY,INDUSTRIAL &

INSTITUTIONAL PROJECTS

100

Page 25: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed SYNOD house, Bondo.

PROJECT COST;KSH 185Million.

PROJECT STATUS; Construction Stage

Commencement date; July 2008.

CLIENT; A.C.K Church, Diocese of Bondo.

LOCATION;Bondo,Nyanza Kenya.

101

Perspective showing the frontage

Floor Plan

Northern Perspective

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 26: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Rapids camp-sagana.

PROJECT COST;KSH 9Million.

PROJECT STATUS; Construction Commencement date; January 2012.

CLIENT; Rapids camp sagana.

LOCATION;Muranga Kenya.

102

Perspective showing the frontage

Floor Plan

Rear Perspective

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 27: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Trade Circle Go-Downs.

PROJECT COST;KSH …………………..Million.

PROJECT STATUS; Local Authorities approval stage

CLIENT; Trade Circle Lmtd.

LOCATION;Industrial Area,NairobiKenya.

103

Frontage Elev

Floor Plan

Side Elevation

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 28: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed PEFA church, Githurai.

PROJECT COST;KSH …………………..Million.

PROJECT STATUS; Local Authorities approval stage

CLIENT; PEFA Church Githurai.

LOCATION;Githurai,Nairobi Metro.

104

Perspective showing the frontage

Floor Plans

Side Elevation

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 29: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Cottages at Ole-polos.

PROJECT COST;KSH …………………..Million.

PROJECT STATUS; Clients approval stage

CLIENT; Dr. Alice.

LOCATION;Ole-polos,Nairobi Metro.

105

Perspective showing the frontage

Floor Plans

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 30: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Administration block and Library.

PROJECT COST;KSH 12.4 Million.

PROJECT STATUS; Local Authorities approval stage

CLIENT; Board of governors and P.T.A

Mt.Kinangop Girls Sec School.

LOCATION; Engineer ,Kinangop.

106

Perspective showing the frontage

Floor Plan

Perspective showing the rear

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 31: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Bomas ii.

PROJECT COST;KSH 447 Million.

PROJECT STATUS; Stake-holders feasibility approval stage

CLIENT; Muka-mukuu cooperative society &

Government of Kenya.

LOCATION; Ol-donyo sabuk-Kilima mbogo

Nairobi metro-politan region.

107

Perspective showing the frontage

Aerial perspective showing

the Site Plan

Perspective showing

main auditorium’s interiors

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 32: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Student Hostels ,Athi-river.

PROJECT COST;KSH 12.9Million

PROJECT STATUS; Construction stage;

Commencement date; June 2009

CLIENT; Mrs Ndungu.

LOCATION; Athi-river

Nairobi metro-politan region.

108

Perspective showing the entry façade.

Ground Floor plan.

Plan Showing a

single hostel

unit.

Front Elevation.

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 33: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Water tanks stand,Kiambu.

PROJECT COST;KSH 240,000/=

PROJECT STATUS; Completion date; June 2009.

CLIENT; Mr Peter Mungai.

LOCATION; Kiambu

Nairobi metro-politan region.

109

Perspectives showing the Water Tanks.

Ground Floor plan.

Front Elevation.

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 34: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Commercial Development

at Malili,Machakos ,Mombasa RD.

PROJECT COST;KSH 27.9Million

PROJECT STATUS; L.A approval stage;

Date; June 2011.

CLIENT; Mr. Victor Kariuki.

LOCATION; Malili I.C.T Park area,Machakos,Mombasa RD

Nairobi metropolitan region.

110

Perspective showing the entry façade.

Floor plans.

Perspective showing the side view

and service yard.

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 35: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Orthodox Church at Mai mahiu.

CLIENT; Orthodox Church.

LOCATION;Mai Mahiu .

111

Perspective from the entry

Perspective from the rear side.

PROJECT COST;

PROJECT STATUS; Completed- Date; March 2012.

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 36: Arhi-Tektons Systems Ltd-Profile 060715.

PROJECT; Proposed Galitos,Creamy Inn,Chicken Inn at Tasia in Embakasi.

CLIENT; Mohamed.

LOCATION; Tasia –Nairobi county.

112

Perspective from the front(façade).

Birds Eye view Perspective.

PROJECT COST;Kshs 20 Million

PROJECT STATUS; Planning & local authority approval stage.

Construction Commencement Date; Jan 2016.

Ground Floor plan.

COMMERCIAL,HOSPITALITY,INDUSTRIAL

& INSTITUTIONAL PROJECTS

Page 37: Arhi-Tektons Systems Ltd-Profile 060715.

INTERIOR DESIGN PROJECTS

200

Page 38: Arhi-Tektons Systems Ltd-Profile 060715.

INTERIOR DESIGN PROJECTS.

PROJECT; Proposed I&M Bank at Gigiri .

CLIENT; I&M Bank.

LOCATION;Gigiri –Nairobi County.

201

Perspective showing the interior.

Perspective from the lounge.

PROJECT COST;Kshs 27 Million.

PROJECT STATUS; Completed; May 2014.

Perspective from the main entrance.

Perspective showing the back office.

Page 39: Arhi-Tektons Systems Ltd-Profile 060715.

INTERIOR DESIGN PROJECTS.

PROJECT; Proposed I&M Bank at Kitale .

CLIENT; I&M Bank.

LOCATION;Kitale –Trans-Nzoia County.

202

Perspective showing the interior.

PROJECT COST;Kshs 18 Million.

PROJECT STATUS; Completed; Jan 2015.

Perspective from the bulk cashier door.

Perspective showing the ATM side.

Page 40: Arhi-Tektons Systems Ltd-Profile 060715.

INTERIOR DESIGN PROJECTS.

PROJECT; Proposed Maina & Mwangi Associates.

CLIENT; Mr. David Maina.

LOCATION; Fig-Tree Building –Nairobi County.

203

PROJECT COST;Kshs 4 Million.

PROJECT STATUS; Completed; Jan 2015.

PROJECT; Proposed Dental Clinic.

CLIENT; Mr. Susan Maina.

LOCATION; Nairobi County.

PROJECT COST;Kshs 11 Million.

PROJECT STATUS; Fit-Out commencement Date; October 2015.

PROJECT; Proposed I&M Bank at Thika,Lavington,Garden City.

CLIENT; I&M Bank Ltd.

LOCATION; As Indicated –Kenya.

PROJECT COST;Approx Kshs 20 Million per branch.

PROJECT STATUS; Completed; June 2015.