Are Zero Clearance Landfill Gas
Probes for Your Site?
Ambrose A. McCready, P.E.
April 12, 2016
54th Annual SWANA Western Regional
Symposium
San Luis Obispo, California
-
2
-
3
-
4
-
5
-
6
Monitoring Requirements
• CCR Title 27 §20921
• Perimeter Compliance Monitoring Probes
• Multiple Stages
• Perforated Zones
• Depth to Perched or High Groundwater
• Cost to Replace Probe $5-10 K
-
7
-
8
-
9
-
Zero Clearance
• What is Zero Clearance Condition?
• Old Landfill Units
• Waste Placed to Permitted Boundary
• No Buffer Between Waste and Boundary
• Can Not Drill Probe Without Hitting Waste
• Does Not Meet Title 27 Requirements
• What are Possible Solutions?
10
-
Zero Clearance LFG Probes
• Large Diameter Boring with Clean Backfill
• Standard Title 27 LFG Probe in Center
• Drill with Special Boring Equipment
• Backfill with Select Material
• Monitor as Compliance Probe
11
-
12
-
13
-
14
-
15
-
16
-
17
-
18
-
19
-
The Possible Solution
• Zero Clearance LFG Probes are a Solution
• Construct Probes on Your Site
• Approved by CalRecycle at 28th Street LF
• Talk to Agency/Obtain Regulatory Approval
• Construct With Select Materials
• Perform Like Standard Title 27 LFG Probes