Are You suprised - alltender.combpdb.alltender.com/upload/tender_schedule/tender_445118d.pdf · The...
Transcript of Are You suprised - alltender.combpdb.alltender.com/upload/tender_schedule/tender_445118d.pdf · The...
-
BANGLADESH POWER DEVELOPMENT BOARD
BIDDING DOCUMENT Single-Stage, Two-Envelope System
FOR PROCUREMENT OF
DESIGN, SUPPLY AND INSTALL FOR
PACKAGE-1-CONVERSION OF 100 MW BAGHABARI GAS TURBINE POWER PLANT TO 150 MW COMBINED CYCLE POWER PLANT AND THE CONVERSION OF 2X35 MW SHAHJIBAZAR GAS TURBINE POWER PLANT TO 105 MW COMBINED CYCLE POWER PLANT ON TURNKEY BASIS
LOT-2: CONVERSION OF 2X35 MW SHAHJIBAZAR GAS
TURBINE POWER PLANT TO 105 MW COMBINED CYCLE POWER PLANT
VOLUME 3 - SCHEDULES
December, 2016
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
2
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
3
1. Schedules Page Schedule-A Guarantees………………….…………………………...5 Schedule-B Technical Data Sheet…………………….……………7 Schedule-C Drawings to be furnished with Contract…………..85 Schedule-D Delivery time……………………………………………89 Schedule-E Tools and Appliances…………………………………91 Schedule-F Spare Parts…………………..…….………………..….93 Schedule-G Deviation………………………………………………107 Schedule-H Civil and Building Works…………………………...109 Schedule-I List of Subcontractor………………………………..111 Schedule-J Description of Training Programme………………113 Schedule-K Mobilisation and demobilisation Schedule for
Construction Equipment …………………………...115 Schedule-L Method of Transportation and Unloading of
heavy Cargo …………………………………………..117
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
4
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
5
Schedule A
1. Combined Cycle Guarantees
The guaranteed performance of the complete Combined Cycle Power Plant at site condition (350 C, 1.013 bar, 98% Relative Humidity) and Generator power factor of 0.80 shall be as follows: MCR Load :Natural Gas Net Power Output , KW :----------
Net Heat Rate (LHV of fuel) at loads :100% 75% 50%
At Ambient Air Temp.350 C, KJ/Kwh -------- -------- --------
i) Net Power Output
Net power output shall mean the power output produced by Gas Turbine Generator and Steam Turbine Generator in Combined Cycle mode measured at the high voltage side of step up transformers. ii) Net Heat Rate Net heat rate shall mean the heat equivalent of the fuel consumed by complete Combined Cycle Plant per unit time, based upon the Lower Calorific Value, divided by the net power output as defined above. iii) Cooling Water Temperature Cooling water Temperature from cooling tower at inlet of Steam Turbine Condenser and auxiliary cooling water Coolers is to be of 380C at site condition (350C, 1.013 bar, 98% R.H). However, the net output of complete Combined Cycle Power Plant and Steam Turbine Generator shall not be less than the guaranteed figure at site condition. iv) The guarantee performance data are to be based on the proposed Heat Balance Diagram (will be submitted during detailed design stage) and Correction Curves and/or Tables (will be submitted during detailed design stage), which are to be submitted with this Contract and which are only to adjust the guarantee performance data, should the operating conditions during the performance tests differ from the above guarantee data. v) Starting and Loading Time The Steam Turbine Generator starting time to reach Full speed no load (3000 rpm) counting from Gas Turbine start-up command to be as follows (to be guaranteed): - Cold Start (from ambient Conditions) : --------hr ------- min ( max 4 hours)
- Warm Start (after 8 hrs shut down period): ------hr ------ min ( max 2 hours)
The Steam Turbine Generator loading time up to MCR counting from Synchronisation -------- min, to be guaranteed.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
6
Start-up and loading diagram of Combined Cycle up to MCR for each cold and warm start for the following cases shall be submitted: HRSG and Steam Turbine simultaneously with GTG start-up.
3. Date of completion of Initial Commercial Operation
The Initial Commercial Operation of the unit shall be completed within the period from Effective date of Contract: Combined Cycle unit: ----------------------------------------- days
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
7
SCHEDULE-B
TECHNICAL DATA SHEET B-1 Existing Gas Turbine Generator and Ancillaries: [The Tenderer have to fill up the following data to ascertain that they have been acquainted with the existing equipment]
Description Data Gas Turbine : Standard : IEC -34 & IS -5422 Type :Open Cycle, Single Shaft ,Heavy
Duty Industrial Package type Gas Turbine
Model PG9171E Compressor Type Inlet Guide Vane Casing Split Combustor Type
Fuel Nozzle No of Chambers Turbine Type No of Stages Shaft speed Generator Type : TARI 1080 -36F Drive : KVA Volts KW P.F Log Frequency Voltage & frequency variation for continuous output
Rpm Phase Connection Volts(Stator) Volts(Rotor) Amps (Rotor) Cooling Duty Cycle
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
8
Description Data Altitude Winding Insulation Class & Temperature rise Degree of Protection Year Excitation System (With all Auxiliaries)
Type Volts Ampere KW Rpm Duty Cycle Insulation Class Excitation Permanent magnet generator Type KVA Voltage Ampere Hz Starting System A . Starting Motor Type Capacity Volts Freq. Sync. Speed Duty B. Torque Converter Type Model Specific Torque Lube Oil Pump & Motor Motor Capacity Service Factor Rpm Voltage Ampere Made PF Pump Head Capacity Speed Model Made In Impeller Diameter Emergency Lube Oil Pump DC MOTOR
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
9
Description Data Capacity Speed Volts Duty Type Made in Pump Head Capacity Model Impeller Diameter Made in Turbine Cooling Exhaust Frame Blower Blower Quantity Vibration Level Service Factor Model P.F Motor Quantity Capacity Volts Frequency Speed Made in Lube Oil System Main Lube Oil Pump Capacity Auxiliary Oil Pump Capacity Emergency Lube oil Pump Capacity
Total Quantity of Oil In the System Type of Filter Degree of Filtration Lube Oil Grade A. Lube Oil Reservoir B. Lube oil Mist Separator Motor Voltage Speed Phase , Freq. C. Jacking Oil Pump Motor Capacity Volts Frequency Compressor Water wash Pump Model Head Speed Discharge Made Motor Capacity Speed
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
10
Description Data Made Atomizing Air Booster Comp. Type Model Speed Made in Cooling Water Module Motor Capacity Voltage Made in Fan Fan Dia Speed No. of Blade Quantity Cooling Air Fan Motor (Turbine Compartment) Capacity Voltage Speed Turning Gear (AC) Type Model Ratio Turning Gear (DC) Type Model Ratio Cooling Water Module Design Pressure Operating Fluid Dyty /Surface Full nof Water Manufacturer Cooling Water Pump Model Head Motor Capacity Pump Made in Discharge Air Intake System for Turbine Material of Intake Duct Type of air Filter Material of filter medium Max. Intake Velocity Amount of Air required for GT at ISO Type of Silencer Material of Absorber Total Air Flow throw air Filter Maximum pressure loss Inlet Air Filter Manufacturer Model No
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
11
Description Data Filter P/N 11 KV Generator Circuit Breaker
Manufacturer Year of Manufacture Rated Maximum Voltage Rated Frequency Rated Continuous Current at 35 C Circuit Breaker Rated full-wave impulse with stand voltage (peak)
Power frequency withstands voltage, 1min. Rated short circuit duty cycle Rated short circuit current, symmetrical Max asymmetrical short circuit peak current Short time current Interrupting time Earthing switch:
Rated peak withstand current (KA peak)
Rated short time withstand current (KA rms)
Operating time (s)
Surge Protection equipment
Metal oxide surge arrester
Rated discharge current 8/20 micro-sec
Line discharge according to IEE C62.11 , IEC 99-4
Surge Capacitors
Step up - Transformer
Type Standard Type of cooling Rating H.V.(MVA) (ONAF/ONAN) No load Voltage H.V.(kV) No load Voltage L.V.(kV) Line Current (HV)(Amps)(ONAN/ONAF Line Current (LV)(Amps)(ONAN/ONAF Connection Symbol Guaranteed Impedance at Normal Tap Voltage % HV –LV at 75Deg.C
a) of top oil by thermometer b) of winding by resistance Insulation level (bushing) EHV- (LI/AC) EHV Neutral- (LI/AC) LV- (LI/AC) Vector group Type of taps provided Taps to be on
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
12
Description Data Range of taps Method of Tap charge control- Manual local Electrical local Electrical Remote Automatic
Voltage Class kV (r.m.s) EHV LV EHV-N
Unit Auxiliary Transformer Connection Symbol MVA No load Voltage H.V.(kV) No load Voltage L.V.(kV) Amps. at HV Side Amps. at LV Side Phase HV/LV Type of Cooling Insulation level HV (LI /AC) LV (LI/AC) HV Neutral LV Neutral Type of taps provided Taps to be on Range of taps Method of Tap charge control- Manual local Electrical local Electrical Remote Automatic Bushing HV (LI/SI/AC) LV (LI/AC) LVN (-/AC) Station Service Transformer KVA/MVA No load Voltage H.V.(kV) No load Voltage L.V.(kV) Amps HV Amps. LV Phase HV/LV Type of Cooling Insulation level HV (LI /AC) LV (LI/AC)
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
13
Description Data HV Neutral LV Neutral Type of taps provided Taps to be on Range of taps Method of Tap charge control- Manual local Electrical local Electrical Remote Automatic Bushing HV (LI/SI/AC) LV (LI/AC) LVN (-/AC) Existing Diesel Engine Description (3 MW) Manufacturer SACM Diesel Country France Capacity Year of Manufacturer Voltage RPM Existing Diesel Engine Description (125 KW) Manufacturer Alsthom Country France Capacity Voltage RPM B-2 Existing Gas Booster Compressor: [The Tenderer have to fill up the following data to ascertain that they have been acquainted with the existing equipment]
Sl. No
Description Gas Booster No A
Gas Booster No B
Gas Booster No C
1 Capacity 2 Ambient Air
Temperature
3 Relative humidity 4 Ambient Air Pressure 5 Minimum Inlet
Pressure
6 Maximum Inlet Pressure
7 Minimum Gas Temperature
8 Maximum Gas Temperature
9 Maximum Volume flow
10 Minimum Volume
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
14
Sl. No
Description Gas Booster No A
Gas Booster No B
Gas Booster No C
flow 11 Outlet/Service
Pressure
12 Outlet/Service Temperature
13 Motor Rated Capacity 14 Name of the
Manufacturer
B-3 Heat Recovery Steam Generator and Ancillary Equipment
3.1 General -Type of HRSG [Vertical/ Horizontal] -------------------------------
-Model Number -------------------------------
-Manufacturer of HRSG, Country -------------------------------
3.2 Performance (1) at MCR
Maximum Continuous Rating at
Hot Gas Input with Gas Turbine
Generator base rating, kg/hr -------------------------------
- Superheater exit pressure, bar -------------------------------
- Superheater exit temperature, 0C -------------------------------
- Feed Water temperature at Economiser -------------------------------
inlet, 0C
- Total Pressure loss through the -------------------------------
steam generator, mm Aq.
- Pressure loss though the -------------------------------
superheater section, mm Aq. -------------------------------
- Pressure loss though the -------------------------------
Evaporator section, mm Aq. -------------------------------
- Pressure loss though the -------------------------------
economiser section, mm Aq. ------------------------------- -Gas leakage through bypass damper -------------------------------
- Heat absorbing rate
Superheater section, kg/m2/hr -------------------------------
Evaporator section, kg/m2/hr -------------------------------
Economiser section, kg/m2/hr -------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
15
- Gas Temperature ---------------------------------
Gas Turbine exhaust temp., 0C ---------------------------------
Superheater inlet, 0C ---------------------------------
Evaporator inlet, 0C ---------------------------------
Economiser outlet, 0C ---------------------------------
- Pinch point temperature, 0C ---------------------------------
- Approach Temperature, 0C ---------------------------------
- Gas Velocities
Superheater section, m/sec ---------------------------------
Evaporator section, m/sec ---------------------------------
Economiser section, m/sec ---------------------------------
- Exhaust gas temperature ---------------------------------
at HRSG outlet, 0C
- Water temperature
Entering economiser, 0C ---------------------------------
Leaving economiser, 0C ---------------------------------
- Design pressure for high ---------------------------------
pressure portion, bar
- Working pressure at superheater ---------------------------------
outlet, bar
- Working pressure at HRSG ---------------------------------
steam drum, bar
- Static head, drum water level to ---------------------------------
economiser inlet, bar
- Working pressure at economiser, bar --------------------------------
(2) at Partial Load
(Gas Turbine output at Site Condition)
100% 75% 50% 25%
- Exhaust gas flow, kg/hr ------- ------- ------- -------
- Exhaust gas temp., 0C ------- ------- ------- -------
- Steam Output, kg/hr ------- ------- ------- -------
- Superheater exit pressure, bar ------- ------- ------- -------
- Superheater exit temp., 0C ------- ------- ------- -------
- Feed Water temp. at ------- ------- ------- -------
economiser inlet, 0C
- Pinch point temp., 0C ------ ------- ------- -------
- Approach temp.,0C ------- ------- ------- -------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
16
Gas Temperature
Superheater inlet, 0C ------- ------- ------- -------
Evaporator inlet, 0C ------- ------- ------- -------
Economiser outlet, 0C ------- ------- ------- -------
3.3 Operating Limit - Max. gas temperature at
superheater inlet during start-up, 0C ---------------------------
- Max. superheater metal temperature at
during start-up, 0C ---------------------------
- Max. drum metal differential
temperature during pressure raising, 0C ---------------------------
- Max. rate of decrease in
saturation temperature, 0C ---------------------------
- Max. water temperature before
draining HRSG, 0C ---------------------------
- Max. superheater steam pressure, bar ---------------------------
- Max. superheater steam temp., 0C ---------------------------
- Min. load for superheater spray, % ---------------------------
- Max. casing design pressure, mm Aq. ---------------------------
3.4 Evaporator Section - Manufacturer, country ---------------------------
- Heating surface, m2 ---------------------------
- Heat absorbing rate, kj/m2/hr ---------------------------
- Method of joining long tubes ---------------------------
- Method of fixing tubes to header or
or drum ---------------------------
- Tube outside diameter, mm ---------------------------
- thickness, mm ---------------------------
- Tube pitching, mm ---------------------------
- Casing thickness, mm ---------------------------
3.5 Drum - Manufacturer, country ----------------------------------
- Construction ----------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
17
- Internal diameter, mm ----------------------------------
- Thickness, mm ----------------------------------
Length, mm ----------------------------------
Steam purifier,
Manufacturer, country
Type
- Design pressure, bar ----------------------------------
Operating pressure, bar ----------------------------------
3.6 Safety Valve - Manufacturer, country ----------------------------------
1) for Drum
- Type ----------------------------------
Number ----------------------------------
Size of valve, mm ----------------------------------
Capacity, kg/hr ----------------------------------
Design lifting pressure, bar ----------------------------------
2) for superheater
- Type ----------------------------------
Number ----------------------------------
Size of valve, mm ----------------------------------
Capacity, kg/hr ----------------------------------
Design lifting pressure, bar ----------------------------------
-Details of assessment of
safety valve capacity, Ref. No. ----------------------------------
3.7 Superheater - Manufacturer, Country ----------------------------------
- Type ----------------------------------
- Design Pressure, bar ----------------------------------
- Heating Surface, m2 ----------------------------------
- Tube outside diameter, mm ----------------------------------
- Tube thickness, mm ----------------------------------
- Length, mm ----------------------------------
- Effective length per element, m ----------------------------------
- Method of arrangement ----------------------------------
- Number of elements ----------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
18
- Number of steam flow ----------------------------------
-Tube pitching ----------------------------------
-Max. design tube temp., 0C ----------------------------------
-Tube class and finish ----------------------------------
-Method of fixing tubes to header ----------------------------------
-Type of tube support and material ----------------------------------
-Method of jointing long tube ----------------------------------
- Header Inlet Outlet
Construction ----------------------------------
Inside diameter, mm ----------------------------------
Thickness, mm ----------------------------------
Material ----------------------------------
Particular of terminal point, Ref. No. ----------------------------------
3.8 Superheater Steam Temperature Control Equipment - Description of Control equipment ------------------------------------
Control range ------------------------------------
1) In case of surface or condenser type ------------------------------------
-Heating surface of cooling tube, m2 ------------------------------------
-Outside diameter of cooling tubes, mm ------------------------------------
Thickness of cooling tubes, mm ------------------------------------
Diameter of shell inside, mm ------------------------------------
Thickness of shell, mm ------------------------------------
Type of joint ------------------------------------
Temperature of cooling water, 0C ------------------------------------
2) In case of spray type
- Nozzle diameter, mm ------------------------------------
Diameter of sleeve, mm ------------------------------------
Length of sleeve, mm ------------------------------------
Water pressure of inlet, bar ------------------------------------
- Water temperature at inlet, 0C ------------------------------------
- Maximum quantity of spray water, kg/hr ------------------------------------
3.9 Economiser - Manufacturer, Country ------------------------------------
- Type ------------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
19
- Design Pressure, bar ----------------------------------
- Heating Surface, m2 ----------------------------------
- Tube outside diameter, mm ----------------------------------
- Tube thickness, mm ----------------------------------
- Tube Length, m ----------------------------------
-Tube arrangement ----------------------------------
-Tube pitching, mm ----------------------------------
- Tube class and finish ----------------------------------
Method of fixing tubes to header ----------------------------------
Type of tube support and material ----------------------------------
Header
Outside diameter, mm ----------------------------------
Thickness, mm ----------------------------------
3.10 Auxiliary Pumps (1) Circulating pump (Evaporator)
- Manufacturer, Country ----------------------------------
- Type ----------------------------------
- Discharge flow, kg/sec ----------------------------------
- Speed, rpm ----------------------------------
- Power required, KW ----------------------------------
Material of
Casing ----------------------------------
Impeller ----------------------------------
Shaft ----------------------------------
- Type of motor ----------------------------------
(2) Circulating pump (Economiser)
- Manufacturer, Country ----------------------------------
- Type ----------------------------------
- Discharge flow, kg/sec ----------------------------------
- Speed, rpm ----------------------------------
- Power required, KW ----------------------------------
Material of
Casing ----------------------------------
Impeller ----------------------------------
Shaft ----------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
20
- Type of motor ------------------------------------
(3) Others (if any), Tenderers should use additional sheet
3.11 Weights - Total steam generator (dry), kg ------------------------------------
- Total steam generator (operational), kg ------------------------------------
- Evaporator section, (dry), kg ------------------------------------
Superheater section (dry), kg ------------------------------------
Economiser section (dry), kg ------------------------------------
Casing, kg ------------------------------------
Supporting steel works, kg ------------------------------------
Flues and ducts, kg ------------------------------------
Soot blower, kg ------------------------------------
Instrument and control, kg ------------------------------------
Galleries and ladders, kg ------------------------------------
Insulation and lagging, kg ------------------------------------
Drum, kg ------------------------------------
3.12 Materials - Drum ------------------------------------
- Drum plates, shell ------------------------------------
- Evaporator tube ------------------------------------
- Evaporator header ------------------------------------
- Superheater tube ------------------------------------
- Economiser tube ------------------------------------
- Soot blower supply piping ------------------------------------
- Insulation and lagging ------------------------------------
3.13 Other information - Statement of min. load and duration, Ref. No. ----------------------------
- Statement of min. time for start-up, Ref. No. ----------------------------
- After 8 hours shut down ----------------------------
- After 48 hours shut down ----------------------------
- From cold condition ----------------------------
(Note: Information shall be furnished in graphic form showing gas
entering temperature, steam temperature and steam pressure vs. time)
- Statement of drum metal temperature and
metal differential temperature during
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
21
start-up and shut-down. Ref. No. --------------------------
---
- Statement of permissible forced cooling
rates and any limitations Ref. No. -------------------------
- Performance curves showing superheater
temperature from min. load up to MCR Ref. No. --------------------------
B-4 Steam Turbine and Ancillary Equipment
4.1 Steam Turbine
-Type of steam turbine -------------------------------
-Model Number -------------------------------
-Manufacturer of steam turbine, Country -------------------------------
- Rating at generator terminal, MW -------------------------------
- Minimum safe continuous load, MW -------------------------------
- Overload rating -------------------------------
- Maximum load at 48 Hz for up to
30 min. duration -------------------------------
- Speed, rpm -------------------------------
- Steam Condition -------------------------------
Temp. at turbine stop valve, 0C -------------------------------
Pressure at turbine stop valve, bar -------------------------------
Design temp. at exhaust, 0C -------------------------------
Design vacuum press. at exhaust, mmHg -------------------------------
- Number of bleed points -------------------------------
- Number of exhaust -------------------------------
- Guaranteed heat rate at rated output, kj/kwh --------------------------
- Expected heat rate at max. expected
capability, kj/kwh -------------------------------
- Expected heat rate under turbine
overload condition, kj/kwh -------------------------------
- Type of governing, throttle or -------------------------------
nozzle control system
- Size (mm) and number of main steam
inlet coections -------------------------------
- Size (mm) and number of exhaust
connections -------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
22
- Critical speed above 3000 rpm ----------------------------
- Critical speed below 3000 rpm ----------------------------
- Distance between bearing centres, mm ----------------------------
- Max. steam pressure in wheel case at MCR, bar ----------------------------
- Velocity compounded stage
Mean diameter of moving blades, mm ----------------------------
Clear height of 1st moving blades, mm ----------------------------
- Impulse stages
Number of stages ----------------------------
Mean diameter of 1st moving blades, mm ----------------------------
Clear height of 1st moving blades, mm ----------------------------
Mean diameter of last moving blades, mm ----------------------------
Clear height of last moving blades, mm ----------------------------
- Reaction stages
Number of flows ----------------------------
Number of stages per flows ----------------------------
Mean diameter of 1st moving blades, mm ----------------------------
Clear height of 1st moving blades, mm ----------------------------
Mean diameter of last moving blades, mm ----------------------------
Clear height of last moving blades, mm ----------------------------
- Total actual annulus area last stage blades, m2 ----------------------------
- Minimum running clearance of blades
or shrouding
Radial clearance, mm ----------------------------
Axial clearance, mm ----------------------------
- Casing bursting diaphragm press, bar ----------------------------
- Number of built-up diaphragm, ----------------------------
- Speed at which turning gear rotates rotor, rpm ----------------------------
- Number of branches required on auxiliary
steam manifold and for what purpose ----------------------------
- Description of blade protection from erosion, Ref. No.-----------------------
- Description of method of testing of blade
harmonics, Ref. No. ----------------------------
- Description of turbine pre-warming
and start-up cycle, Ref. No. ----------------------------
- Description of method of bolting casing
halves, supporting individual casing,
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
23
provision to accommodate expansion and
means of equalising differential expansion, Ref. No. --------------------------
- Description of thermal treatment for turbine
casings, Ref. No. ----------------------------
- Description of thermocouples in
turbine casing, Ref. No. ----------------------------
- Maximum allowable loads on turbine casing
At steam inlet, kg ----------------------------
kg-m ----------------------------
At extraction points, kg ----------------------------
kg-m ----------------------------
At exhaust, kg ----------------------------
kg-m ----------------------------
-Moment of Inertia, GD2 of Rotor, (kg-m2) ----------------------------
- Type of thrust block ----------------------------
- Description of on load testing of steam
valve, Ref. No. ----------------------------
- Description of start-up following on outage
of few minutes, 8 hours and 48 hours, Ref. No. ----------------------------
- Description of gland sealing
arrangement, Ref. No. ----------------------------
- Description of vacuum unloading
and trip gear, Ref. No. ----------------------------
- Description of low pressure unloading
and trip gear, Ref. No. ----------------------------
- Scheme for turbine drainage and
automatic traps, Ref. No. ----------------------------
- Material of construction for major
components, Ref. No. ----------------------------
4.2 Speed Governing System - Type --------------------------------
- Model Number --------------------------------
- Manufacture, country --------------------------------
- Steady state speed regulation, % --------------------------------
- Max. dead band at rated speed, % --------------------------------
- Speed changer synchronising, % --------------------------------
- Speed changer governing range, % --------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
24
- Range of speed droop, % --------------------------------
- Permanent speed after full load
has been rejected, rpm --------------------------------
- Max. momentary speed after full
load has been rejected, rpm --------------------------------
- Turbine speed at which emergency
governor operates, rpm (%) --------------------------------
- Acceleration time, sec --------------------------------
- Description of automatic turbine
start-up system, Ref. No. --------------------------------
4.3 Lubricating Oil system (1) Main oil pump
- Type --------------------------------
- Manufacturer, Country --------------------------------
- Driven by --------------------------------
- Capacity of pump, lit/min --------------------------------
- Lube oil pressure, bar --------------------------------(2)
Auxiliary oil pump (full duty)
- Type --------------------------------
- Model No. --------------------------------
- Manufacturer, Country --------------------------------
- Speed of pump --------------------------------
- Capacity of pump, lit/min --------------------------------
- Pressure at which pump cuts in, bar --------------------------------
- Brake horsepower, kw --------------------------------
- Material of construction for major
components, Ref. No. ---------------------------------
- Complete description of operation ---------------------------------
including performance curves of
capacity vs suction pressure, Ref. No.
(3)Ac motor driven flushing oil pump
- Type ---------------------------------
- Model No. ---------------------------------
- Manufacturer, Country ---------------------------------
- Speed of pump ---------------------------------
- Capacity of pump, lit/min ---------------------------------
- Pressure at which pump cuts in, bar ---------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
25
- Brake horsepower, kw --------------------------------
- Material of construction for major --------------------------------
components, Ref. No.
- Complete description of operation --------------------------------
including performance curves of
capacity vs suction pressure, Ref. No.
(4) DC motor driven flushing oil pump
- Type --------------------------------
- Model No. --------------------------------
- Manufacturer, Country --------------------------------
- Speed of pump --------------------------------
- Capacity of pump, lit/min --------------------------------
- Pressure at which pump cuts in, bar --------------------------------
- Brake horsepower, kw --------------------------------
- Material of construction for major --------------------------------
components, Ref. No.
- Complete description of operation --------------------------------
including performance curves of
capacity vs suction pressure, Ref. No.
(5) AC & DC (back-up) motor driven jacking oil pump
- Type --------------------------------
- Model No. --------------------------------
- Manufacturer, Country --------------------------------
- Speed of pump --------------------------------
- Capacity of pump, lit/min --------------------------------
- Pressure at which pump cuts in, bar --------------------------------
- Brake horsepower, kw --------------------------------
- Material of construction for major --------------------------------
components, Ref. No.
- Complete description of operation --------------------------------
including performance curves of
capacity vs suction pressure, Ref. No.
(6) Oil coolers
- Manufacturer, country --------------------------------
- Type --------------------------------
- Effective surface, m2 --------------------------------
- Gross surface, m2 --------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
26
- Number of flows ---------------------------------
- Number of tubes ---------------------------------
- Internal diameter of tubes, mm ---------------------------------
- Gauge of tubes material ---------------------------------
- Tubes material ---------------------------------
- Straight length of 'U', mm ---------------------------------
Internal dia. of heater, mm ---------------------------------
Material of shell ---------------------------------
Material of water box ---------------------------------
Heat transfer rate, kj/m2/hr ---------------------------------
Mean temperature difference, 0C ---------------------------------
Duty, kj/hr ---------------------------------
Circulating water flow rate, lit/hr ---------------------------------
Oil flow rate, lit/hr ---------------------------------
Inlet circulating water temperature, 0C ---------------------------------
- Outlet circulating water temperature, 0C ---------------------------------
Inlet oil temperature, 0C ----------------------------------
Outlet oil temperature, 0C ---------------------------------
- Pressure drop, bar water------------------------------------
oil ---------------------------------------
- Overall length, mm ---------------------------------
(7) Start-up procedures with respect to oil
temperature, Ref. No. ---------------------------------
(8) Treatment to avoid acid attack on lubricating
oil tank interior, pedestals oil wells, etc., Ref. No., ------------------------------
(9) Complete description of oil
purifier, Ref. No. ---------------------------------
4.4 Condenser and Auxiliaries (1) Condenser
- Erected weight
- Empty, kg ---------------------------------
- Operating, kg ---------------------------------
- Steam & water spaces flooded, kg ---------------------------------
- Max. depth of hot-well, high water ---------------------------------
level to top of condensate outlet, mm
- Condenser duty, kj/hr ---------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
27
- Total effective surface, m2 ---------------------------------
- Circulating water required ---------------------------------
- Circulating water velocity through tubes
at design inlet temp. and flow, m/sec ---------------------------------
- Max. permissible water pressure, bar ---------------------------------
- Tube cleaning factor, % ---------------------------------
- Heat transfer rate, kj/m2/hr ---------------------------------
- Design circulating water temp., 0C ---------------------------------
- Condensate temperature leaving
hot-well ( normal cir. water flow) , 0C ---------------------------------
- Max. free oxygen in condensate leaving
hot-well, cc/lit. ---------------------------------
- Terminal temp. difference, 0C ---------------------------------
- Hot-well capacity, litre ---------------------------------
- Hot-well storage, ---------------------------------
- Temperature of gas vapour mixture
leaving condenser, 0C ---------------------------------
- Condenser vacuum
100% 75% 50% 25% duty
and 300C inlet water, mm Hg ---------------------------------
100% 75% 50% 25% duty
and 350C inlet water, mm Hg ---------------------------------
100% 75% 50% 25% duty
and 400C inlet water, mm Hg ---------------------------------
- Absolute pressure at turbine
exhaust, mm Hg ---------------------------------
- Circulating water friction loss between
inlet and outlet flanges
Tubes, m ---------------------------------
Water boxes, m ---------------------------------
Total, m ---------------------------------
- Circulating water friction loss at
inlet , m ---------------------------------
- Circulating water friction loss at
outlet , m ---------------------------------
- Total number of tubes ---------------------------------
- Effective tube length, m ---------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
28
- Tube materials
- Tube O D and thickness, mm ---------------------------------
- Tube sheet materials ---------------------------------
- Tube sheet thickness, mm ---------------------------------
- Shell material ---------------------------------
- Shell thickness, mm ---------------------------------
- Hot-well material ---------------------------------
- Hot-well thickness, mm ---------------------------------
- Water box material ---------------------------------
- Water box thickness, mm ---------------------------------
- Number of tube support plates --------------------------------
- Tube support plate material ---------------------------------
- Tube support plate thickness, mm ---------------------------------
- Internal bolts, nuts and studs ---------------------------------
- Circulating water inlet and outlet connections
Size, mm ---------------------------------
Flange rating ---------------------------------
- Describe method of compensating for
differential thermal expansion between
tubes and shells, Ref. No. ---------------------------------
- Describe steam inlet hood expansion joint
and state allowable axial and lateral
displacement, Ref. No. ---------------------------------
- Describe manholes on water boxes, Ref. No. ---------------------------------
- Size of steam hood equalising line, mm ---------------------------------
Describe cathodic protection provided, Ref. No. ---------------------------------
Itemised list of all special wrenches and tools
required for maintaining and servicing
the proposed equipment, Ref. No. ---------------------------------
- Description of condensate control
system and method of operation, Ref. No. ---------------------------------
- Description of automatic sequential
condenser back washing facility, Ref. No. ---------------------------------
- Description of on -load condenser tube
cleaning system and method of operation, Ref. No. ----------------------------
(2) Condensate pumps
- Manufacturer, country ---------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
29
- Type ---------------------------------
- Model No. ---------------------------------
- Total 'dry' weight of an assembled
unit (pump coupling & drive) on the
foundation, kg ---------------------------------
- Total weight 'full of water' of an assembled
unit on the foundation, kg ---------------------------------
Total pump weight ( less driver and
coupling), kg ---------------------------------
- Required hoisting clearance (hoisting
hook to pump mounting flange) to remove
pump and motor, m ---------------------------------
- Number of stages ---------------------------------
- Design capacity, lit./hr ---------------------------------
- Design total dynamic head, m ---------------------------------
- Pump shut-off head, m ---------------------------------
- Rated speed, rpm ---------------------------------
- Specific speed, rpm ---------------------------------
- Efficiency at design conditions, % ---------------------------------
- Rated power at design conditions, kw ---------------------------------
- Discharge velocity at design flow, m/sec ---------------------------------
- Design suction temperature, 0C ---------------------------------
- Max. permissible increase in pump design
head and/or capacity from specified
values without change in price
Head, m ---------------------------------
Capacity, lit./hr ---------------------------------
- Min. required flow when operating at rated
speed, lit./hr ---------------------------------
- Sealing water required
Flow, lit./hr ---------------------------------
Pressure, bar ---------------------------------
- Pump material
Mounting flange ---------------------------------
Motor support ---------------------------------
Coupling ---------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
30
Casing ---------------------------------
Impeller ---------------------------------
Impeller wear rings ---------------------------------
Casing wear rings ---------------------------------
Impeller shaft bearings ---------------------------------
Shaft guide bearings ---------------------------------
Shaft guide bearings retainers ---------------------------------
Impeller shaft ---------------------------------
Drive shaft ---------------------------------
Shaft materials at bearings and stuffing box ---------------------------------
Shaft sleeves ---------------------------------
Stuffing box ---------------------------------
Stuffing box packing ---------------------------------
- Type, manufacturer & country, description
of thrust bearing including lubrication, Ref. No. ---------------------------------
- State Max. thrust and describe at what
operating condition it occurs, Ref. No. ---------------------------------
(3) Condenser vacuum pump
- Manufacturer, country ----------------------------------
- Type ----------------------------------
- Model No. ----------------------------------
- Pump speed, rpm ----------------------------------
- Brake horsepower, kw ----------------------------------
- Condenser evacuation time from 760 mmHg
to 260 mmHg abs., min. ----------------------------------
to 110 mmHg abs., min. ----------------------------------
- Maintaining capacity at 110 mmHg abs.
per pump, lit/hr ----------------------------------
- Rated capacity, lit/hr ----------------------------------
- operating weight, kg ----------------------------------
- Construction & material of construction
for major components, Ref. No. ----------------------------------
- Specification of cooling water and seal
water required
Quantity, lit/hr ----------------------------------
Pressure, bar ----------------------------------
- Complete description of operation including
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
31
performance curves of capacity vs suction
pressure, Ref. No. ---------------------------------
- Quantity of free air handled , lit/hr ---------------------------------
- Inlet air and vapour pressure at 00 C
(mmHg abs.) ---------------------------------
- Inlet air and vapour temp. 0C ---------------------------------
- Itemised list of all special wrenches and flaring
tools required to maintain and service the
furnished the equipment, Ref. No. ---------------------------------
(4) Steam jet air ejector
- Manufacturer, country --------------------------------
- Number of stages --------------------------------
- Nozzle diameter, mm --------------------------------
- Initial steam pressure, bar --------------------------------
- Initial steam temperature, 0C --------------------------------
- Steam consumption, kg/hr --------------------------------
- Maintaining capacity at 110 mmHg abs. --------------------------------
- Complete description of operation including
performance curves of capacity vs suction
pressure, Ref. No. --------------------------------
- Rated capacity (free air), lit/hr --------------------------------
- Quantity of free air handled, lit/hr --------------------------------
- Inlet air and vapour pressure at 0C (mmHg abs.) -------------------------------
- Inlet air and vapour temperature, 0C --------------------------------
4.5 De-aerator - Weight of de-aerator section, empty, kg --------------------------------
- Storage tank, empty, kg --------------------------------
- operating weight of unit completely assembled, kg -------------------------------
- Flooded weight of unit completely assembled, kg --------------------------------
- Shipping weight, kg --------------------------------
- Heaviest piece to be handled during erection
weight & name, kg --------------------------------
- Heaviest piece to be handled during maintenance
weight & name, kg --------------------------------
- Describe internal vent condenser, stating
materials, path of steam, water and non-
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
32
condensable gases; length, thickness and
diameter of distributor; number and size
of spray valves, Ref. No. ---------------------------------
- Proposals for minimising dissolved oxygen
levels during start-up, Ref. No. ---------------------------------
- Describe internal steam distribution
path, Ref. No. ---------------------------------
- Describe internal water distribution path, Ref. No. ------------------------------
- Tray removal and/or access doors
Number ---------------------------------
Size and materials ---------------------------------
- Manholes
Number ---------------------------------
Size and materials ---------------------------------
- Describe anti-vortex baffling, Ref. No. ---------------------------------
- Storage tank active capacity, lit. ---------------------------------
- Height of stored water level measured from
tank contains above capacity, m ---------------------------------
- Deaerator section
Shell thickness, mm ---------------------------------
Head thickness, mm ---------------------------------
- Storage tank section
Shell thickness, mm ---------------------------------
Head thickness, mm ---------------------------------
- Tray, size
Number ---------------------------------
Thickness, mm ---------------------------------
- Materials
Deaerator shell ---------------------------------
Storage shell ---------------------------------
Trays ---------------------------------
Internal compartments ---------------------------------
All other internal parts ---------------------------------
Spray valves ---------------------------------
Impingement baffles ---------------------------------
Antivortex baffles ---------------------------------
- Describe number, location, type of
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
33
manhole and access doors, Ref. No. ---------------------------------
- List of special tools provided, Ref. No. ---------------------------------
- Pressure drop from steam inlet nozzle to
storage tank steam space above stored
water at design conditions, bar ---------------------------------
- Temperature of deaerator effluent at
design conditions, 0C ---------------------------------
- Static pressure required at inlet to water
distribution at design conditions, bar ---------------------------------
- Max. steam quantity leaving deaerator
vents at design conditions, kg/hr ---------------------------------
- Pressure drop across condensate inlet
valves at design conditions, bar ---------------------------------
B-5 Generator and Ancillaries (for Steam Turbine) 5.1 Generator -Manufacturer, Country ----------------------------------
-Type ----------------------------------
-KVA rating / power factor 0.8 ----------------------------------
-Continuous Output at 110% of rated voltage ----------------------------------
-Max. leading & lagging KVAR capability at pf ----------------------------------
-Rated voltage between lines, KV ----------------------------------
-Connection of armature winding ----------------------------------
-Rated Current, A ----------------------------------
-Rated frequency, Hz ----------------------------------
-Efficiency
at pf 0.8, % ----------------------------------
at pf 1.0, % ----------------------------------
-Stator overloading, % ----------------------------------
-Critical speed, rpm ----------------------------------
-Max. torque when the stator is short-circuited, Nm ----------------------------------
-Generator Characteristics
Instantaneous Max. short-circuit current
at nominal voltage, Apeak ----------------------------------
sub-transient reactance, Xd” pu ----------------------------------
transient reactance, Xd’ pu ----------------------------------
synchronous reactance, Xd pu ----------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
34
negative sequence reactance, pu ----------------------------------
zero sequence reactance, pu ----------------------------------
field time Constant, Td’0 sec ----------------------------------
Transient time Constant, Td sec ----------------------------------
initial time Constant, Td” sec ----------------------------------
-Moment of inertia GD2 of rotor, Kg-m2 ----------------------------------
-percent rise on voltage when full load is
rejected and operating at pf 0.8 , % ----------------------------------
pf 1.0 , % ----------------------------------
-Telephone influence factor Balanced ----------------------------------
Residual ----------------------------------- -Class of winding insulation Armature winding ----------------------------------
Field winding ---------------------------------- -Type of cooling -Short circuit ratio, (sat.) -Generator rated excitation requirements for operation at rated kVA
Excitation voltage, V ------------------------ Excitation current, A ------------------------
- Generator calculated losses at 100% Base rating Total generator iron loss, kW ------------------------- Generator stator I2 R loss, kW ------------------------- Generator rotor I2R loss, kW ------------------------- Generator stray load loss, kW ------------------------- Generator windage loss, kW ------------------------- Total generator loss, kW -------------------------
-Generator weights Weight of rotor, kg ------------------------- Weight of complete stator, kg -------------------------
5.2 Exciter (Brushless or Static)
- Manufacturer, Country ------------------------- - Type ------------------------- - Rated output, kW -------------------------
-Rated load field voltage at 0.80 pf/1.00 pf ------------------------- -Rated exciter current at 0.80 pf./l.00 pf ------------------------- - Exiter ceiling voltage, V ------------------------- -Maximum continuous exciter current, A ------------------------- -Excitation system voltage response ratio ------------------------- 5.3 Automatic Voltage Regulator -Manufacturer, Country -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
35
- Type ------------------------- - Description of AVR, Ref. No. ------------------------- 5.4 Generator Protection (Manufacturer Cat. No. or Type) Relay Manufacturer ------------------------ -Generator differential relay ------------------------- -Generator ground over-current relay ------------------------- -Field / rotor ground detection system ------------------------- -Reverse power relay ------------------------- -Loss of field relay ------------------------- -Voltage restraint over-current relays ------------------------- -Negative phase sequence relay ------------------------- -Under/Over Frequency relay ------------------------- - Synchro-Check Relay ------------------------- - Auxiliary relays ------------------------- -Lockout relays -------------------------
5.5 Generator Switchgear
-Manufacturer, Country ------------------------- -Circuit breaker Interrupting Media SF6 Catalogue No. ------------------------- Type ------------------------- Closing current at 125 volts DC, A ------------------------- Time to close, m sec ------------------------- Tripping current at 125 volts DC, A ------------------------- Time to trip, m sec ------------------------- - Rating and capabilities
Current rating, A ------------------------- Voltage rating, V -------------------------
Nominal 3 phase interrupting capacity, MVA ------------------------- Maximum symmetrical interrupting capacity, kA -------------------------
3 second short time rating, kA ------------------------- Closing and latching capability, kA -------------------------
- Operating Mechanism ------------------------ -Instruments and devices Manufacturer Type
Current transformers Single ratio ------------------------- Multi ratio ------------------------- Potential transformers ------------------------- Control and instrument switches ------------------------- Indicating lights -------------------------
-Lightning arresters ------------------------- -Surge protection devices ------------------------- -Type of bus insulation ------------------------- -Type of bus supports ------------------------- -Type of insulation on connections ------------------------- -Size of completely assembled switchgear
Length, mm ------------------------- Width, mm -------------------------
Height, mm ------------------------- - Total weight of switchgear, kg -------------------------
B-6 Mechanical Auxiliary Equipment
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
36
6.1 HRSG Feed Water Pump
(1) Feed Pump - Manufacturer, country --------------------------- - Type --------------------------- - Model Number --------------------------- - Number of stages --------------------------- - Running speed, rpm --------------------------- - Critical speed, rpm --------------------------- - Pump capacity at design conditions, kg/hr -------------------------- - Max. leak-off quantity, lit/hr --------------------------- - Pressure at pump discharge, bar --------------------------- - Pressure at outlet of non-return valve, bar --------------------------- - Min. NPSH, m --------------------------- - Bore of suction branch, mm --------------------------- - Bore of discharge branch, mm --------------------------- Type of branches, mm --------------------------- Min. diametrical clearance at specified temp., mm --------------------------- Type of coupling --------------------------- Pump automatic cut-in pressure, bar --------------------------- Min. load pump can operate, % of MCR ---------------------------
(2) Feed Pump Motor - Manufacturer, country --------------------------- Type --------------------------- Model No. --------------------------- Frame size --------------------------- Speed at rated output, rpm --------------------------- Rated output, KW --------------------------- Nominal supply voltage, KV --------------------------- Frequency, Hz --------------------------- Full load currency, A --------------------------- Power factor at full load --------------------------- Class of insulation --------------------------- Quantity of cooling water required, lit/hr --------------------------- Max. temperature rise, 0C --------------------------- Enclosure --------------------------- Type of bearings --------------------------- Full load torque, kg-m --------------------------- Starting torque in percent of full load torque, % --------------------------- Max. torque in percent of full load torque, % ---------------------------
(3) Weight - Weight of pump shaft and impellers, kg --------------------------- Weight of pump complete, kg --------------------------- Weight of motor stator, kg --------------------------- Weight of motor rotor, kg --------------------------- - Weight of bedplate, kg ---------------------------
(4) Materials - Pump casing --------------------------- - Pump shaft --------------------------- - Impellers --------------------------- - Guide vanes --------------------------- - Shaft sleeves --------------------------- - Wearing rings --------------------------- - Balance disc ---------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
37
- Balance disc wearing plate --------------------------- - Grand packing ---------------------------
6.2 Circulating Water System (1) Circulating water pump
- Manufacturer, country --------------------------- - Type --------------------------- - Model Number --------------------------- - Number of stages --------------------------- - Running speed, rpm --------------------------- - Critical speed, rpm --------------------------- - Pump capacity at design conditions, kg/hr --------------------------- - Pressure at pump discharge, bar --------------------------- - Bore of suction branch, mm --------------------------- - Bore of discharge branch, mm --------------------------- ---Min. diametrical clearance at specified temp., mm --------------------------- Type of coupling --------------------------- Type of thrust bearing --------------------------- - Distance between centre line of impeller and lowest water level, m --------------------------- - CW pump suction head loss, m ---------------------------
(2) CW Pump Motor - Manufacturer, country --------------------------- Type --------------------------- Model No. --------------------------- Frame size --------------------------- Speed at rated output, rpm --------------------------- Rated output, KW --------------------------- Nominal supply voltage, KV --------------------------- Frequency, Hz --------------------------- Full load currency, A --------------------------- Power factor at full load --------------------------- Class of insulation --------------------------- Quantity of cooling water required, lit/hr --------------------------- Max. temperature rise, 0C --------------------------- Enclosure --------------------------- Type of bearings --------------------------- Full load torque, kg-m --------------------------- Starting torque in percent of full load torque, % --------------------------- Max. torque in percent of full load torque, % --------------------------- - Overload capacity, % --------------------------- - Provision of anti-condensation heater --------------------------- - Provision of winding temperature indicators ---------------------------
(3) Discharge Valve -Manufacturer, country --------------------------- - Type --------------------------- - Model No. --------------------------- - Bore, mm --------------------------- - Design pressure, bar --------------------------- - Test pressure, bar --------------------------- - Max. flow, lit/hr ---------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
38
- Normal flow, lit/hr -------------------------- - Opening time, sec -------------------------- - Closing time, sec -------------------------- - Valve actuation --------------------------
(4) Reversing Valve -Manufacturer, country -------------------------- - Type -------------------------- - Bore, mm -------------------------- - Model No. -------------------------- - Design pressure, bar -------------------------- - Test pressure, bar -------------------------- - Max. flow, lit/hr -------------------------- - Normal flow, lit/hr -------------------------- - Reversing time, sec -------------------------- - Valve actuation --------------------------
(5) Cathodic Protection Equipment -Manufacturer, country -------------------------- - Type -------------------------- - Model No. - Nominal supply voltage, v -------------------------- - Nominal supply frequency, Hz -------------------------- - Nominal supply phase --------------------------
Number of anodes -------------------------- Material of anodes --------------------------
- Max. anode current, A --------------------------
(6) Pipework - Manufacturer, country --------------------------- Bore, mm --------------------------- Material --------------------------- Design pressure, bar --------------------------- Test pressure, bar --------------------------- Wall thickness, mm --------------------------- Details of lining, Ref. No. ---------------------------
(7) Weight - Weight of pump & column pipe , kg --------------------------- Weight of pump complete, kg --------------------------- Weight of motor, kg --------------------------- Max. dynamic load on foundation, kg --------------------------- - Max. load on crane hook, kg ---------------------------
(8) Materials - C W pump --------------------------- Suction of bellmouth --------------------------- Casing ball --------------------------- Diffuser --------------------------- Impellers --------------------------- Pump shaft --------------------------- Shaft sleeves --------------------------- Delivery bend --------------------------- Foundation ring --------------------------- Stuffing box packing ---------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
39
- Discharge pipework ------------------------- - Venting pipework -------------------------
6.3 Compressed Air Equipment
(1) Air Compressor - Manufacturer, country ------------------------- - Type ------------------------- - Capacity, lit/hr ------------------------- - Discharge pressure, bar ------------------------- - Speed, rpm ------------------------- - Efficiency at rated output, % ------------------------- - Power required, kw ------------------------- - Description of compressor (main components), Ref. No. ------------------------- - Weight, kg -------------------------
(2) Compressor Motor - Manufacturer, country -------------------------
- Type ------------------------- - Voltage, KV ------------------------- - Speed at rated output, rpm ------------------------- - Rating, KW ------------------------- - Max. starting current as percentage of full load, % ------------------------- - Efficiency, % ------------------------- - Class of insulation ------------------------- - Weight, kg ------------------------- (3) Inlet Air Filter
- Manufacturer, country ------------------------- - Type ------------------------- - Size ------------------------- - Description, Ref. No. -------------------------
(4) Moisture Separator - Manufacturer, country -------------------------
- Type ------------------------- - Size ------------------------- - Capacity ------------------------- (5) Automatic Drain Trip
- Manufacturer, country ------------------------- - Type ------------------------- - Size ------------------------- - Capacity ------------------------- (6) Air Receiver
- Manufacturer, country ------------------------- - Capacity, lit ------------------------- - Dimension, mm ------------------------- - Thickness of shell plate, mm ------------------------- - Type of construction ------------------------- - Design pressure, bar ------------------------- - Weright, kg ------------------------- - Safety valve setting pressure, bar -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
40
B-7 132 kV Switchgear, Equipment (Steam Turbine Unit) 7.1 132 kV Circuit Breaker
- Manufacturer, Country ------------------------- - Type designation ------------------------- - Number of poles ------------------------- - Rated voltage, KV ------------------------- - Maximum design voltage -Minimum voltage for rated interrupting capacity, KV -------------------------
- Rated continuous current, A ------------------------- - Rated frequency, Hz ------------------------- - Rated insulation level
Impulse withstand voltage, kV-peak ------------------------- -Power frequency withstand
voltage (1 mm.), KV ------------------------- -Rated interrupting capacity, MVA -------------------------
- Maximum interrupting current, kA ------------------------- - Rated momentary current -------------------------
- Rated duration of short-Circuit, sec ------------------------- - Rated making current, kA-peak ------------------------- -Operating duty -------------------------
- Operating time, m sec. ------------------------- -Rated interrupting time, m sec ------------------------- -Closing time, m sec -------------------------
-Opening time, m sec. ------------------------- -Minimum dead time, m sec. ------------------------- -Reclosing time, m sec. -------------------------
-First-pole-to clear factor At 100% breaking capacity ------------------------- At 10% breaking capacity ------------------------- -Out of phase breaking current At 2.0 times rated voltage, KA ------------------------- At 2.5 times rated voltage, KA ------------------------- -Creepage distance of the insulator, mm ------------------------- -Weight of complete circuit breaker, Kg ------------------------- -Type of operating mechanism ------------------------- -Outline drawings, No ------------------------- -Standard specifications to which the circuit breaker shall conform ------------------------- -Attached type test report, No -------------------------
7.2 132 kV Current Transformer
- Manufacturer , Country ------------------------- - Type designation ------------------------- - Rated voltage, KV ------------------------- - Maximum design voltage, KV - Rated Primary Current, A -------------------------
- Rated Secondary current, A ------------------------- - Rated frequency, Hz ------------------------- - Rated insulation level
Impulse withstand voltage, kV-peak ------------------------- - Power frequency withstand
voltage (1 mm.), KV ------------------------- - Number of cores -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
41
For metering service ------------------------- For relaying service -------------------------
- Accuracy Class ------------------------- For metering service ------------------------- For relaying service -------------------------
- Rated Burden ------------------------- For metering service, VA ------------------------- For relaying service, VA -------------------------
- Rated continuous thermal current, % - Short-time current rating,(1 sec), KA -------------------------
- Creepage distance of insulator, mm ------------------------- - Weight of single phase unit, Kg -Out line drawing, No ------------------------- -Standard specification to which the CT shall conform ------------------------- -Attached type test report, No -------------------------
7.3 132 KV Voltage Transformer
- Manufacturer, Country ------------------------- - Type designation ------------------------- - Rated voltage, KV ------------------------- - Maximum design voltage, KV ------------------------- - Rated Primary Voltage, KV ------------------------- - Rated Secondary Voltage, V ------------------------- - Rated Tertiary Voltage, V ------------------------- - Rated frequency, Hz ------------------------- - Rated insulation level
Impulse withstand voltage, kV-peak ------------------------- - Power frequency withstand voltage (1 mm.), KV ------------------------- - Number of cores -------------------------
For metering service ------------------------- For relaying service -------------------------
- Accuracy Class ------------------------- For metering service ------------------------- For relaying service -------------------------
- Rated Burden ------------------------- For metering service, VA ------------------------- For relaying service, VA -------------------------
- Rated continuous thermal current, % ------------------------- - Short-time current rating,(1 sec), KA ------------------------- - Creepage distance of insulator, mm ------------------------- - Weight of single phase unit, Kg ------------------------- - Out line drawing, No ------------------------- - Standard specification to which the PT shall conform ---------------------- - Attached type test report, No -------------------------
7.4 132 KV Lightning Arrester
- Manufacturer , Country ------------------------- - Type designation ------------------------- - Rated voltage, KV -------------------------
- Discharge Class ------------------------- - Maximum design voltage, KV -------------------------
- Rated frequency, Hz -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
42
- Rated discharge current, KA ------------------------- - Min. power frequency spark-over voltage ------------------------- - Impulse protective level
- Max. spark-over voltage for a standard full wave, KVpeak -------------------------
- Max. front wave impulse spark-over voltage, KVpeak -------------------------
- Max. discharge voltage at the rated discharge current, KVpeak -------------------------
- Creepage distance of insulator, mm ------------------------- - Weight of single phase unit, Kg ------------------------- - Type of operating counter ------------------------- - Out line drawing, No ------------------------- - Standard specification to which the LA
shall conform ------------------------- - Attached type test report, No -------------------------
7.5 132 KV Isolators - Manufacturer, Country -------------------------
- Type ------------------------- - Rated voltage, KV -------------------------
- Rated normal current, A ------------------------- - Rated short time withstand duration, 1 sec., KA -------------------------
3 sec., KA ------------------------- Dynamic peak, KA ------------------------- - Impulse withstand voltage Across the isolating distance, KVpeak ------------------------- To earth and between poles, KVpeak ------------------------- - Power Frequency withstand voltage, 1 min. Across the isolating distance, KV ------------------------- To earth and between poles, KV ------------------------- - Operating mechanism ------------------------- - Number of auxiliary contacts ------------------------- - Method of interlocking ------------------------- - Creepage distance of insulators ------------------------- - Weight of complete Isolator -------------------------
- Out line drawing, No ------------------------- - Standard specification to which the Isolator shall conform ------------------------- -Attached type test report, No -------------------------
7.6 Steel Structure
- Manufacturer , Country -------------------------
- Standard specifications to which the ------------------------- steel structure shall conform
-Type ------------------------- -Minimum thickness of members ------------------------- - Outline drawings -------------------------
7.7 Busbar and Connectors
- Manufacturer , Country -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
43
- Standard specifications to which the busbar and connectors shall conform -------------------------
-Type of busbar ------------------------- - Characteristics of bus conductor
Material ------------------------- Nominal sectional area ------------------------- Construction of conductor ------------------------- Calculated sectional area ------------------------- - Ultimate minimum breaking strength, kg -------------------------
- Outside diameter, mm ------------------------- - Standard unit weight, kg/ m -------------------------
- Calculated resistance at 200C, ohm / Km ------------------------- - Outline drawing of conductor, No. ------------------------- - Outline drawing of connection, Nos -------------------------
7.8 Post Insulator - Manufacturer, Country ------------------------- - Number of units in complete post insulator ------------------------- - Diameter (max.), mm ------------------------- - Length of each unit, mm ------------------------- - Weight of complete post insulator, Kg ------------------------- - Creepage distance , mm -------------------------
- Min. Power frequency (dry) flash-over voltage, KV -------------------------
- 50% lightning impulse (+ve), KV ------------------------- - 50% lightning impulse (-ve), KV ------------------------- - Max. vertical working load Tension, Kg ------------------------- Compression, Kg ------------------------- - Mechanical routine test load (tension), Kg ------------------------- - Mechanical type test load (tension), Kg ------------------------- - Vertical breaking load (tension), Kg ------------------------- - Max. torsional working load, Kg-m ------------------------- - Max. cantilever working load (complete post insulator), Kg ------------------------- - Min. cantilever breaking load upright (complete post insulator), Kg ------------------------- - Outline drawings -------------------------
- Standard specification to which the Post Insulator shall conform -------------------------
7.9 Suspension Insulator Assembly - Manufacturer , Country ------------------------- - Type ------------------------- - Insulator materials
- Characteristics of disc element Diameter Diameter, mm ------------------------- Unit spacing, mm ------------------------- Creepage distance, mm ------------------------- Electro-mechanical failing load, Kg ------------------------- Mechanical routine test load , Kg ------------------------- Min. Power frequency flash-over voltage
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
44
Dry, KV ------------------------- Wet, KV ------------------------- 50% lightning impulse (+ve), KV ------------------------- 50% lightning impulse (-ve), KV ------------------------- Ball and Socket size, mm -------------------------
- Characteristics of Insulator assembly Number of discs
Total length, mm Creepage distance, mm ------------------------- Min. Power frequency flash-over voltage Dry, KV ------------------------- Wet, KV ------------------------- 50% lightning impulse (+ve), KV ------------------------- 50% lightning impulse (-ve), KV ------------------------- - Breaking strength of complete set, Kg ------------------------- - Materials to be used Compression type dead end clamp ------------------------- Bolted type clamp ------------------------- Miscellaneous hardware ------------------------- - Outline drawings -------------------------
- Standard specification to which the Post Insulator shall conform -------------------------
7.10 Outdoor Cable Termination End - Manufacturer, Country ------------------------- - Number of units ------------------------- - Diameter (max.), mm ------------------------- - Length of each unit, mm ------------------------- - Weight of complete post insulator, Kg ------------------------- - Creepage distance , mm -------------------------
- Min. Power frequency (dry) flash-over voltage, KV ------------------------- - 50% lightning impulse (+ve), KV ------------------------- - 50% lightning impulse (-ve), KV ------------------------- - Max. vertical working load Tension, Kg ------------------------- Compression, Kg ------------------------- - Mechanical routine test load (tension), Kg ------------------------- - Mechanical type test load (tension), Kg ------------------------- - Vertical breaking load (tension), Kg ------------------------- - Max. torsional working load, Kg-m ------------------------- - Max. cantilever working load
(complete post insulator), Kg ------------------------- - Min. cantilever breaking load upright
(complete post insulator), Kg ------------------------- - Outline drawings -------------------------
- Standard specification to which the termination end shall conform -------------------------
B.8 Generator Step-up Transformer for STG and Associated Equipment &
Isolated / Insulated Phase Bus Duct (IPBD)
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
45
For STG#1 8.1 Generator Step Up Transformer
- Manufacturer , Country ------------------------- - Standard -------------------------
- Type ------------------------- - Rated output (ONAN/ONAF), MVA ------------------------- - Vector group ------------------------- - Nominal ratio of transformation ------------------------- at no load, KV/KV - Type of cooling ------------------------- - Total range of variation of transformation ratio expressed as percentage of high voltage
with low voltage Constant Increasing ratio, % ------------------------- Decreasing ratio, % -------------------------
- Size of each step, % ------------------------- - Type of tap changer (Made: only MR, Germany/ABB, Sweden) - Type of gas/oil actuated relay
- Impedance voltage at 759C expressed as a percentage of normal voltage (ONAF rating) +ve / zero Seq.
At highest ratio, % ------------------------- At normal ratio, % ------------------------- At lowest ratio, % -------------------------
- Voltage regulation at normal ratio, 750C and a power factor of, Unity, % ------------------------- 0.8, % ------------------------- - Magnetising current at normal ratio High tension winding, A ------------------------- Low tension winding, A -------------------------
- Auxiliary Plant losses Forced air plant, KW - Fixed losses at normal ratio and 750C, KW - Load losses at IEC rating, normal ratio and 750 C ONAF rating, pf 1.0/0.8, KW ------------------------- ONAN rating, pf 1.0/0.8, KW ------------------------- - Total losses at IEC rating, normal ratio and 750C At ONAF rating, pf 1.0/0.8, KW -------------------------
At ONAN rating, pf 1.0/0.8, KW ------------------------- - Efficiency at IEC rating normal ratio and 75'C
At ONAF rating, pf 1.0/ 0.8, % ------------------------- At ONAN rating, pf 1.0/0.8, % ------------------------- -Type of transformer, shell or core ------------------------- -Type of core joint Minimum magnetic flux density in core iron at normal voltage and frequency based upon the net section of iron Cores, T ------------------------- Yoke, T -------------------------
-Type of windings High tension winding -------------------------
Low tension winding ------------------------- - Maximum current density in windings
High tension winding, A/ sq. mm -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
46
Low tension winding, A/ sq. mm ------------------------- -Type of radial coil supports High tension winding -------------------------- Low tension winding -------------------------- -Type of insulation used for, High tension winding -------------------------- Low tension winding -------------------------- -Tapping -------------------------- -Tapping connection -------------------------- -Core bolt -------------------------- -Core bolt washers -------------------------- -Maximum observable oil temperature at IEC rating, 0C -------------------------- - Calculated thermal time Constant At ONAF rating, hour -------------------------- At ONAN rating, hour -------------------------- -Type of winding maximum temperature indicator -------------------------- -Total quantity of oil required to fill complete transformer up to lowest visible level in conservator, litres -------------------------- -Volume of oil to be removed to the level of the top yoke, litres -------------------------- -Volume of oil required to raise oil in conservator from lowest visible level to highest level, litres -------------------------- -Total volume of conservators, litres -------------------------- -High above transformer foundation pad of conservator highest oil, mm -------------------------- -Proposed filling medium for transformers shipped light and empty of oil -------------------------- -Makes and grades of oil suitable for filling transformer -------------------------- -Thickness of transformer tank Sides, mm -------------------------- Bottom, mm -------------------------- -Number of cooling fan unit -------------------------- -Surface area of each cooler unit, mm2 -------------------------- -Heat dissipation of each cooler unit as percentage of total heat dissipation at IEC rating, % -------------------------- -Average rate of oil flow through each cooler unit, litres/min -------------------------- -Weight of parts Weight of copper, Kg -------------------------- Weight of core sheets, Kg -------------------------- Weight of all other ferrous parts, Kg -------------------------- -Weight of core and winding assembly, Kg -------------------------- -Weight of complete transformer, Kg -------------------------- -Weight of transformer arranged for shipment, Kg -------------------------- -Dimension of transformer including all fittings Length, mm -------------------------- Breadth, mm -------------------------- Height, mm -------------------------- -Dimension of transformer arranged
for shipment Length, mm --------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
47
Breadth, mm ------------------------- Height, mm ------------------------- -Weight of each cooler, Kg -Lightning impulse insulation level High tension winding, KV peak ------------------------- Low tension winding, KV peak ------------------------- High tension neutral, KV peak ------------------------- -Power frequency withstand voltage for 1 minute High tension winding, KV ------------------------- Low tension winding, KV ------------------------- - Temperature rise Winding, 0C ------------------------- Top insulation oil, 0C -------------------------
- Audible sound level at 1 meter from transformer surface, dB -------------------------
-Creepage distance of bushing High tension bushing, mm ------------------------- Low tension bushing, mm ------------------------- Neutral bushing, mm ------------------------- Outline drawing, No ------------------------- 8.2 Generator Transformer Protection (Manufacturer Cat. No. or Type) - Relay Manufacturer -------------------------
- Transformer Differential relay ------------------------- - Cable Differential relay ------------------------- - Restricted Earth Fault relay ------------------------- - Over-current relays (LV & HV) ------------------------- - Earth Fault relays (HV, LV & Neutral) ------------------------- - Pressure relays ------------------------- - Temperature relays ------------------------- - Lockout relays ------------------------- - Auxiliary relays ------------------------- - Grid Interconnection Relays ------------------------- 8.3 Isolated / Insulated Phase Bus Duct (IPBD) (Manufacturer Cat. No. or Type)
------------------------ Service ------------------------ Cooling System ------------------------ System Nominal Voltage ------------------------ System Maximum Voltage ------------------------ Continuous Current Rating ------------------------ Frequency ------------------------ Short Circuit Current Rating for 3 Sec withstand ------------------------ a) Main Run ------------------------ b) Tap-off ------------------------ Short Circuit Current (Peak) ------------------------ Insulation Level ------------------------ 1-Min. Dry Power Frequency Withstand ------------------------ 10-Sec. Wet Power Frequency Withstand. ------------------------ Impulse Withstand ------------------------ Service Voltage ------------------------ a) Hot Air Blowing ------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
48
b) Space Heating, Cubicle Lighting etc. ------------------------ Degree of Protection ------------------------ 1 min Dry Power Frequency Withstand Voltage of Auxiliary Circuit ------------------------ Material of Busbar ------------------------ Shape ------------------------ Type of Joints ------------------------ Material of Insulator ------------------------ Paint Shade ------------------------
B-9 Station Service Transformers - Manufacturer, Country ------------------------- - Cooling class ------------------------- - Continuous kVA rating, kVA -------------------------
- Impedance at maximum kVA with ONAN rating, % ------------------------- -Guaranteed efficiency at 100
per cent of maximum kVA with ONAN rating, % -------------------------
- Standard, IEC ------------------------- -Excitation current at 100 per cent rated voltage,
in per cent based on maximum kVA with ONAN rating, % -------------------------
- Guaranteed losses at 100 percent rated voltage No load loss, kW ------------------------- Voltage Ratio -------------------------
Total losses at maximum with ONAN rating, kW -------------------------
Manufacturer Type
-Bushing High voltage -------------------------
Low voltage ------------------------- Neutral ------------------------- - Current transformers -------------------------
- Approximate weight, Kg ------------------------- - Total assembled, Kg -------------------------
- Type of oil preserver system, Ref. No ------------------------- -Primary and secondary voltage, V ------------------------- - No. of taps ------------------------- - Tap range ------------------------- - Vector group ------------------------- - Class of insulation ------------------------- - Temperature rise at'400C, 0C ------------------------- - ambient temperature, 0C ------------------------- - Winding temperature, 0C ------------------------- - Oil temperature, 0C ------------------------- Transformers Protection (Manufacturer Cat. No. or Type) - Manufacturers ------------------------- - Over-current relays (LV & HV) ------------------------- - Earth Fault relays (HV & LV) ------------------------- - Pressure relays -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
49
- Lockout relays ------------------------- - Auxiliary relays -------------------------
B-10 Unit Auxiliary Transformer
- Manufacturer , Country ------------------------- - Cooling class -------------------------
- Continuous kVA rating, kVA ------------------------- - Impedance at maximum kVA with ONAN rating, % ------------------------- - Guaranteed efficiency at 100 per cent of maximum kVA with ONAN rating, % ------------------------- - Standard ------------------------- - Excitation current at 100 percent rated voltage, in percent based on maximum kVA with ONAN rating, % -------------------------
- Guaranteed losses at 100 percent rated voltage
No load loss, kW ------------------------- Voltage Ratio -------------------------
Total losses at maximum with
ONAN rating, kW ------------------------- Manufacturer Type
-Bushing High voltage ------------------------- Low voltage ------------------------- Neutral -------------------------
-Current transformers ------------------------- -Approximate weight, kg ------------------------- -Total assembled, Kg ------------------------- -Type of oil preserver system, Ref. No. -------------------------
- Primary and secondary voltage, V ------------------------- - No. of taps ------------------------- - Tap range ------------------------- - Vector group ------------------------- - Class of insulation ------------------------- - Temperature rise at 400C , 0C -------------------------
-ambient temperature, 0C ------------------------- - Winding temperature, 0C ------------------------- Oil temperature, 0C ------------------------- Transformer Protection (Manufacturer Cat. No. or Type) - Manufacturers ------------------------- - Differential relay ------------------------- - Restricted Earth Fault relay ------------------------- - over-current relays (LV & HV) ------------------------- - Earth Fault relays (HV, LV & Neutral) ------------------------- - Pressure relays ------------------------- - Temperature relays ------------------------- - Lockout relays -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
50
- Auxiliary relays ------------------------- (Note: The Tenderer shall attach additional sheets as required)
B-11 6.6 kV Switchgear
- Manufacturer , Country ------------------------- - Circuit breaker -------------------------
-Catalogue number ------------------------- -Type ------------------------- -Operating mechanism -------------------------
Closing current at 250 volts DC, A ------------------------- Time to close, m sec ------------------------- Tripping current at 250 volts DC, A ------------------------- Time to close, m sec -------------------------
- Rating and capabilities Current rating, A ------------------------- Voltage rating, A ------------------------- Nominal 3 phase interrupting capacity, MVA ------------------------- Maximum symmetrical interrupting capacity at 6.6 kV, kA (rms) 3 second short time rating, kA (rms) ------------------------- Closing and latching capability, kA(rms) ------------------------- - Protective relays Manufacturer Type Manufacturers -------------------------
Phase over-current ------------------------- Ground over-current ------------------------- Transformer differential -------------------------
- Type of bus insulation ------------------------- - Type of bus supporters ------------------------- - Type of insulation on connections ------------------------- - Size of completely assembled switchgear -------------------------
Length, mm ------------------------- Width, mm ------------------------- Weight, Kg ------------------------- - Total weight of switchgear, Kg ------------------------- B-12 415 V Switchgear and Motor Control Centre (For Steam Turbine Unit) 12.1 415 V Switchgear and Motor Control Centre - Manufacturer, Country ----------------------- Manufacturer Type
- Air circuit breaker Type designation -------------------------
Nominal current, A ------------------------- Rated Voltage, V ------------------------- Method of closing ------------------------- Power required to: Close ------------------------- Open ------------------------- Short circuit current rating, kA ------------------------- Short circuit current, 3 sec, kA ------------------------- Combination starter units -------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
51
Starter contactor ------------------------- Control transformer ------------------------- Circuit breaker ------------------------- Starter contactor coil ------------------------- operating characteristics Size1 Size2 Minimum pickup, V ------------------------- Maximum dropout, V ------------------------- Dimension of each switchgear PCC MCC Length, mm ------------------------- Depth, mm ------------------------- Height, mm ------------------------- Weight, Kg ------------------------- Number of vertical section -------------------------
12.2 Switchboard Design
- Degree of protection ------------------------- -Short time rating Current, kA ------------------------- Associated time, sec ------------------------- - Type of insulation provided on
bus bars and connections ------------------------- - Type of protection provided within cubicles(shutter, insulating, cover, etc) -------------------------
-Bus bars ------------------------- Current rating of bus bars, A ------------------------- System short time current,
3 sec, kA ------------------------- Short time current rating, 3 sec, KA ------------------------- Bus bar material
Cross sectional area of bus, mm2 ------------------------- -Type of connection ------------------------- - Minimum clearance in air:
Between phases, mm ------------------------- Live parts and earth, mm ------------------------- B-13 DC & UPS Supply System 13.1 Battery Units (220 V) (Not Applicable) - Manufacturer, Country ------------------------------------ - Type ------------------------------------ - Catalogue No. ------------------------------------
-Capacity (AH at 5 Hr discharge) ------------------------------------
-Number of cells per unit ------------------------------------ -Weight per cell, kg ------------------------------------ -Total battery weight, kg ------------------------------------ -Overall dimension of battery rack length, mm ------------------------------------ Width, mm ------------------------------------ Height, mm ------------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
52
13.2 Battery Chargers (220 V) (Not Applicable)
- Manufacturer, Country ------------------------------------ - Type ------------------------------------ - Capacity, A/kW ------------------------------------
- DC Voltage adjusting range ------------------------------------ 13.3 Battery Units (110 V) (Not Applicable) - Manufacturer, Country ------------------------------------ - Type ------------------------------------ - Catalogue No. ------------------------------------
-Capacity (AH at 5 Hr discharge) ------------------------------------
-Number of cells per unit ------------------------------------ -Weight per cell, kg ------------------------------------ -Total battery weight, kg ------------------------------------ -Overall dimension of battery rack length, mm ------------------------------------ Width, mm ------------------------------------ Height, mm ------------------------------------ 13.4 Battery Chargers (110 V) (Not Applicable)
- Manufacturer, Country ------------------------------------ - Type ------------------------------------ - Capacity, A/kW ------------------------------------
- DC Voltage adjusting range ------------------------------------ 13.5 Battery Units (125 V) - Manufacturer, Country ------------------------------------ - Type ------------------------------------ - Catalogue No. ------------------------------------
-Capacity (AH at 5 Hr discharge) ------------------------------------
-Number of cells per unit ------------------------------------ -Weight per cell, kg ------------------------------------ -Total battery weight, kg ------------------------------------ -Overall dimension of battery rack length, mm ------------------------------------ Width, mm ------------------------------------ Height, mm ------------------------------------ 13.6 Battery Chargers (125 V)
- Manufacturer, Country ------------------------------------ - Type ------------------------------------ - Capacity, A/kW ------------------------------------
- DC Voltage adjusting range ------------------------------------ 13.7 UPS System
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
53
UPS rating UPS configuration Testing standards Enclosure Degree of Protection CRCA Sheet steel thickness Space heater rating Paint shade Input power supply Rectifier Unit MCCB Isolation Transformer ACDB 13.8 Inverter and Auxiliary Equipments Type
Overload capacity
Voltage regulation Frequency variation for all condition of input supply, load
and temperature occurring simultaneously or in any
combination.
Total harmonic content at rated load
Efficiency (watts output / watts input) at rated load at 0.8p.f.
B-14 Lighting and Small Power Supply Manufacturer Cat. No. or Type
- Panel boards, AC ------------------------------------ - Panel boards, DC ------------------------------------ - Lighting fixtures ------------------------------------
- List of buildings for Solar System ------------------------------------ - Module Wattage (Wp) ------------------------------------- - Make of Module -------------------------------------
Type of material of Module ------------------------------------- - Module DC voltage (V) ------------------------------------- - Module S.C Current (A) ------------------------------------- - No. of Module ------------------------------------- - Inverter Make ------------------------------------- - Inverter Wattage -------------------------------------
No. of Inverter ------------------------------------- B-15 Emergency Diesel Generating Set 15.1 Engine
- Manufacturer, Country ----------------------------
-Model Number ----------------------------
Installed capacity, KW ----------------------------
-Number, type and arrangement of
cylinders ----------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
54
Number of strokes ----------------------------
Compressor pressure ratio ----------------------------
Starting system ----------------------------
Description of Speed governing system
and fuel control system ----------------------------
Fuel consumption ----------------------------
-Description of cooling system ---------------------------
-Auxiliary power consumption, KW ----------------------------
Lubricating oil, litres ----------------------------
- Coolant, litres ----------------------------
- Fuel oil day tank capacity, litres ----------------------------
Recommended Time between overhauls, ---------------------------
15.2 Existing Diesel Generator (Diesel) -Manufacturer, Country ---------------------------
-Type ---------------------------
-KVA rating at power factor 0.8
-Max. leading & lagging KVAR capability at 0.8 pf ---------------------------
-Rated voltage between lines, KV ---------------------------
-Connection of armature winding ---------------------------
-Rated Current, A ---------------------------
-Rated frequency, Hz ---------------------------
-Efficiency
at pf 0.8, % ---------------------------
at pf 1.0, % ---------------------------
-Stator overloading, % ---------------------------
-Max. torque when the stator is short-circuited, Nm As per design
-Generator Characteristics
Instantaneous Max. short-circuit current
at nominal voltage, Apeak ---------------------------
sub-transient reactance, Xd” pu ---------------------------
transient reactance, Xd’ pu ---------------------------
synchronous reactance, Xd pu ---------------------------
negative sequence reactance, pu ---------------------------
zero sequence reactance, pu ---------------------------
field time Constant, Td’0 sec ---------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
55
Transient time Constant, Td sec ---------------------------
initial time Constant, Td” sec ---------------------------
- Moment of inertia GD2 of rotor, Kg-m2 ---------------------------
- Percent rise on voltage when full load is
rejected and operating at pf 0.8 , % ---------------------------
pf 1.0 , % ---------------------------
-Telephone influence factor
Balanced --------------------------- Residual ---------------------------
-Class of winding insulation Armature winding ---------------------------
Field winding --------------------------- -Type of cooling --------------------------- -Short circuit ratio, sat --------------------------- -Generator rated excitation requirements for operation at rated kVA
Excitation voltage ---------------------------Excitation current --------------------------- Generator calculated losses at 100% Base rating Total generator iron loss, kW ----------------- Generator stator I2 R loss, kW -----------------Generator rotor I2 R loss, kW ----------------- Generator stray load loss, kW -----------------Generator windage loss, kW ----------------- Total generator loss, kW -----------------Generator weights Weight of rotor, kg -----------------
Weight of complete stator, kg ----------------- - Protective Relays ----------------- B-16 Control and Protection System (for each unit, transformer, auxiliary ) 16.1 Control and Protection panel -Manufacturer, Country -Type of construction ------------------------------------ -Dimension, mm ------------------------------------
-Instrument ------------------------------------ AC Voltmeter ------------------------------------ AC Ammeter ------------------------------------ Power factor meter ------------------------------------ Wattmeter ------------------------------------ Varmeter ------------------------------------ Synchroniser ------------------------------------ Annunciator ------------------------------------ Watt-hour meter ------------------------------------ Var-hour meter ------------------------------------ Control switch ------------------------------------ -Protection relay Gen. protection relays ------------------------------------ Transformer protection relays ------------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
56
Gen. Bus protection relays ------------------------------------ Inter-connection protection relays ------------------------------------ Auxiliary system protection relays ------------------------------------ EDG protection relays ------------------------------------ -Lockout relays ------------------------------------
-Control relays ------------------------------------ -Trip relays ------------------------------------ -Auxiliary relays ------------------------------------ (Note: The Contractor shall attach additional sheets as required.) 16.2 Descriptive Matter -Control system, Ref. No. ------------------------------------ -Protection system, Ref. No. ------------------------------------ -Data logging system, Ref. No. ------------------------------------ -List of annunciator, Ref. No. ------------------------------------ -Drawing of panels, Ref. No. ------------------------------------ 16.2.1 Description of On-Line Performance monitoring
& Optimisation system and also to interface with DCS, Ref. No. ------------------------------------
16.3 Distributed Control System ( DCS ) (ABB, Germany, USA, Singapore / Foxboro, USA, Singapore / Siemens, Germany) A fully integrated unitary DCS has to be supplied for monitoring, control, display, alarm and recording of selected physical and electrical parameters associated with all relevant plant areas. All monitoring and control interactions shall be done via VDU, keyboard and mouse/trackball. No conventional control desk equipment shall be required. All existing installed pen recorder functions shall be replaced by the new system (data acquisition functions). The controls must be completely shared in Hardware and Software. Interconnections between the controllers shall be done via a redundant data bus. All signals shall be available on the redundant data bus. The DCS must be reliable and unique, covering all automation functions of the power plant.- Manufacturer of DCS, country ------------------------------ Type of DCS ------------------------------ 16.3.1 Operator Stations Manufacturer, Country Type Max number of operations (expandable to) Offered number of operator stations Max number of monitors per operator station (expandable to)
----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- -----------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
57
Offered number of monitors per operator station Monitors Screen diagonal, inch, 21" Resolution (horizontal x vertical), pixel, 1280x1024 Call time for picture change Number of colours Screen refresh rate Graphics Max number of process graphic displays Offered number of process graphic displays Updating of process variables and conditions Analogue inputs s, ≤ 2 Digital inputs s, ≤ 1 Reaction time from issuing command up to execution(Switching relay of control actuators) s, ≤ 1.5 Signal change (check back signal from individual control level) up to display on monitor) s, ≤ 1 Representation of graphs (for trending) on monitor Max. number of standard curve displays Max. number of operator configurable curve displays Max. number of curves in each curve field Resolution of rapidly charging variables like P of the water steam cycle One hour long s, 2 A further seven hours long s, 10 Resolution of slowly changing variables like T, A One hour long s, 10 Printers Number Manufacturer, country Type Characters/line 132 Resolution dpi, 300x300 Noise lever dB(A), 45 Paper size Din, A4 Colour hardcopy devices Number Manufacturer Type Hardcopy image memory size (RAM) MB, 6 Processing time/hardcopy s Resolution dpi 600x600 16.3.2 Data bus (terminal bus) Manufacturer, country Type "Open" bus as per ISO reference model Redundancy Transmission rate (useful data rate) bit/s Transmission medium LWL Max. Bus length without using repeaters etc. m
----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- -----------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
58
Max. Number of stations that can be connected 16.3.3 Process station Number of offered automation units Power failure protection for the program Scanning periods Data acquisition Analogue values ms, 500 Binary values ms, 250 Time critical binary values like position of torque Check back signals ms, ≤ 10 Close loop control Fast control loops ms, 250 Slow control loops ms, 500-1000 Closed-loop control modules Type Number of control loops per module Drive control modules Type Number of control loops per module Binary input modules No. of DI considered for the new Add on Type Number of inputs per module Galvanic isolation between input channels yes/no Binary output modules Type Number of outputs per module Galvanic isolation between output channels yes/no Output current at signal "1" max. mA, 120 Short-circuit protection yes/no No. of DO considered for the new Add on Analogue input modules Type Number of inputs per module Galvanic isolation between input channels yes/no Digital representation of output signal bit, 12 Fault signal if range exceeded (<4mA, 20mA) yes/no No. of AI considered for the new Add on Analogue output modules Type Number of outputs per module Galvanic isolation between output channels yes/no Output ranges mA Digital representation of output bit, 12 Short-circuit protection, yes/no No. of AO considered for the new Add on 16.3.4 Data bus (plant bus) Manufacturer, country Type "Open" bus as per ISO reference model Redundancy bit/s Transmission Rate bit/s Transmission medium LWL
----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- -----------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
59
Max. bus length without using repeaters etc. m Max. Number of stations to be connected unlimited 16.3.5 Engineering system Manufacturer, country Type Number of workstations Monitor Laser Printer A4 Manufacturer, country Type Number of work printers 1 Resolution dpi 600x600 Paper size DIN, A4 16.3.6 Control Cabinets (for DCS) Make, country, type Degree of protection IP, 31 Total Number of Cabinets Number for common and electrical Services Dimension (WXDXH) of one cubicle mm 16.3.7 Marshalling racks Make, country, type Degree of protection IP, 31 Number Dimension (WXOXH) of one marshalling rack mm Total No. of Marshalling Cabinets 16.3.8 Network switches No. of switches Manufacturer Server Redundant Automatic switchover Protocol 16.3.9 Large Video Screen (optional) Manufacturer Screen size Resolution
----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- ----------------- -----------------
16.4 Field equipment
16.4.1 Temperature measurement with thermocouples
Manufacturer, country ------------------------------- Model or type ------------------------------- Transmitter incorporated -------------------------------
SMART-type transmitter -------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
60
16.4.2 Temperature measurement with Pt100 Manufacturer, country ------------------------------- type ------------------------------- Transmitter incorporated ? yes/no ------------------------------- SMART-type transmitter ? yes/no -------------------------------
16.4.3 Pressure transmitter
Manufacturer, country ------------------------------- Model or type ------------------------------- SMART-type transmitter? yes/no -------------------------------
16.4.4 Flow meter (water/steam)
Manufacturer, country ------------------------------- Model or type ------------------------------- SMART-type transmitter? Yes/no -------------------------------
16.4.5 Flow meter (oil)
Manufacturer, country ------------------------------- Model or type ------------------------------- SMART-type transmitter? yes/no -------------------------------
16.4.6 Level transmitter
Manufacturer, country ------------------------------- Model or type ------------------------------- SMART-type transmitter? Yes/no -------------------------------
16.4.7 Differential pressure transmitter
Manufacturer, country ------------------------------- Model or type ------------------------------- SMART-type transmitter? Yes/no -------------------------------
16.4.8 02 analyser (feed water)
Manufacturer, country ------------------------------- Model or type ------------------------------- SMART-type transmitter? Yes/no -------------------------------
16.4.9 PH-value
Manufacturer, country ------------------------------- Model or type -------------------------------
16.4.10 Conductivity
Manufacturer, country ------------------------------- Model or type -------------------------------
16.4.11 O2 analyser (flue gas)
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
61
Manufacturer, country ------------------------------- Model or type -------------------------------
16.4.12 CO analyser (flue gas)
Manufacturer, country ------------------------------- Model or type -------------------------------
16.4.13 CO2 analyser (flue gas)
Manufacturer, country ------------------------------- Model or type -------------------------------
16.4.14 NOx analyser (flue gas)
Manufacturer, country ------------------------------- Model or type -------------------------------
16.4.15 Closed loop control actuators
Control valves ------------------------------- Manufacturer, country ------------------------------- Noise level of control valves (1m distance) dB(A),< 85, ------------------------------- Time for full stroke for size up to 6” s, 5, ------------------------------- Time for full stroke for size up to 12 s, 12, ------------------------------- Electrical actuators ------------------------------- Manufacturer, country ------------------------------- Type ------------------------------- Electric valve positioner (Power electronics) Solid state (thyristor) ------------------------------- Place of installation: electronic Room or incorporated in actuator (Compact type) ------------------------------- Pneumatic actuators (if applicable ------------------------------- Manufacturer, country ------------------------------- Type -------------------------------
16.4.17 HRSG Protection System
Manufacturer, country ------------------------------- Type ------------------------------- Degree protection (cubicle) IP,31, ------------------------------- Number of cubicles per unit ------------------------------- Dimension (WxDxH) of one cubicle mm, -------------------------------
16.4.18 Training Simulator Manufacturer, country ------------------------------- Type ------------------------------- License for concurrent users ------------------------------- Modelling software and license ------------------------------- No. of work stations -------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
62
B-17 Cabling and Grounding (for Steam Turbine Unit) 17.1 132 kV Power Cable (Single-core XLPE) -Manufacturer, Country ------------------------------------ -Type designation ------------------------------------ -Applicable standard ------------------------------------ -Insulation material ------------------------------------ -Cross-section of conductor, mm2 ------------------------------------
-Conductor material, Type of conductor (round, stranded, compacted) ------------------------------------ -Outer sheath material ------------------------------------ -Min. Permissible bending radius, mm ------------------------------------
-Weight per meter, Kg ------------------------------------ -Delivery length, meter ------------------------------------ -Voltage designation, V ------------------------------------
-Current carrying capacity at temperatures........ ------------------------------------ at laying conditions... ------------------------------------
-1 sec. short circuit current after full load at 700 C cond. temp., A ------------------------------------ -Max. conductor resistance at 200C DC, Ohm / KM ------------------------------------ AC, Ohm / KM ------------------------------------ (Note: The Contractor shall attach additional sheets as required.)
17.2 11 kV Isolated & Insulated Phase Bus Duct and Power Cable (XLPE, Copper)
-Manufacturer, Country ------------------------------------ -Type designation ------------------------------------ -Applicable standard ------------------------------------ -Number of cores ------------------------------------ -Insulation material ------------------------------------ -Cross-section of conductor, mm2 ------------------------------------
-Conductor material Type of conductor (round, stranded, compacted) ------------------------------------ -Outer sheath material ------------------------------------ - Min. Permissible bending radius, mm ------------------------------------
-Weight per meter, Kg ------------------------------------ -Delivery length, meter ------------------------------------ -Voltage designation, V ------------------------------------ -1 sec. short circuit current after full load at 700 C cond. temp., A ------------------------------------ -Max. conductor resistance at 200C DC, Ohm / KM ------------------------------------ AC, Ohm / KM ------------------------------------ (Note: The Contractor shall attach additional sheets as required.) 17.3 6.6 kV Power Cable (XLPE)
-Manufacturer, Country ------------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
63
-Type designation ------------------------------------ -Applicable standard ------------------------------------ -Number of cores ------------------------------------ -Insulation material ------------------------------------ -Cross-section of conductor, mm2 ------------------------------------ -Conductor material ------------------------------------ -Type of conductor (round, stranded, compacted) ------------------------------------ -Outer sheath material ------------------------------------ -Min. Permissible bending radius, mm ------------------------------------ -Weight per meter, Kg ------------------------------------ -Delivery length, meter ------------------------------------ -Voltage designation, V -1 sec. short circuit current after full load at 700 C cond. temp., A ------------------------------------ -Max. conductor resistance at 200C
DC, ohm/KM ------------------------------------ AC, ohm/KM ------------------------------------
(Note: The Contractor shall attach additional sheets as required.) 17.4 600/1000 V Power Cable
-Manufacturer, Country ------------------------------------ -Type designation ------------------------------------ -Applicable standard ------------------------------------ -Number of cores ------------------------------------ -Insulation mater ------------------------------------
- Cross section of conductor, mm2 ------------------------------------ -Conductor material ------------------------------------ - Type of conductor (round, stranded, compacted) ------------------------------------ - Outer sheath material ------------------------------------ - Min. Permissible bending radius, mm ------------------------------------ - Weight per meter, Kg ------------------------------------ - Delivery length, meter
-Voltage designation, V ----------------------------------- -1 sec. short circuit current after
full load at 700 C cond. temp. ----------------------------------- 17.5 Control and Instrument Cable
(a) -Type ------------------------------------ -Manufacturer, Country ------------------------------------ -Applicable standard ------------------------------------ -Insulation material ------------------------------------ -Number of cores ------------------------------------
- Core size, mm2 ------------------------------------ - Outer sheath material ------------------------------------ -Weight per meter, kg ------------------------------------ - Delivery length, m ------------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
64
(b) -Type ------------------------------------ -Manufacturer, Country ------------------------------------ -Applicable standard ------------------------------------ -Insulation material ------------------------------------ -Number of cores ------------------------------------
- Core size,mm2 ------------------------------------- - Over sheath material ------------------------------------- - Weight per meter, kg ------------------------------------- -Delivery length, m ------------------------------------- (Note: The Contractor shall attach additional sheets as required.) 17.6 Grounding Wire - Manufacturer, Country ------------------------------------ - Conductor size, mm2 ------------------------------------ - Conductor material ------------------------------------ - Type of Conductor ------------------------------------ - Short circuit current for 3 sec., A ------------------------------------ - Weight per meter, kg ------------------------------------ - Delivery length, m ------------------------------------ B-18 Maintenance Facilities 18.1 Overhead Electric Crane (for Steam Turbine Unit) - Manufacturer , Country ------------------------------------ -Type ------------------------------------
- Maximum safe working load Main hoist, slow speed, Kg ------------------------------------ Main hoist, fast speed, Kg ------------------------------------ Auxiliary hoist, Kg ------------------------------------ -Test load for crane, Kg ------------------------------------ -Span of crane, Centre to Centre of gantry rails, m ------------------------------------
-Geared Speeds a) Main hoist, slow speed Raising with full load , m/min ---------------------------------
Raising with no load, m/min --------------------------------- Lowering with full load, m/min --------------------------------- Lowering with no load , m/min --------------------------------- Creep speed, m/min ---------------------------------
b) Main hoist, fast speed Raising with full load, m/min ---------------------------------
Raising with no load, m/min --------------------------------- Lowering with full load, m/min --------------------------------- Lowering with no load , m/min --------------------------------- Creep speed, m/min --------------------------------- c) Auxiliary hoist Raising with full load, m/min --------------------------------- Raising with no load, m/min --------------------------------- Lowering with full load, m/min --------------------------------- Lowering with no load, m/min --------------------------------- Creep speed, m/min ---------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
65
d) Cross traverse, m/min -------------------------------- e) Long travel, m/min --------------------------------
-Crab
a) Particulars of crab rail --------------------------------- b)Type of wheel bearing ---------------------------------
c) Max. load on each wheel, Kg --------------------------------
-Power supply required by crane -Maximum current demand by crane, A & KW --------------------------------
-Motors Main Auxiliary Cross Long Hoisting Hoisting Traverse Travel
a) Number ---------------------------------------------------- b) Type ----------------------------------------------------
c) kW at full load ---------------------------------------------------- d) Speed at full load, rpm ----------------------------------------------------
e) Motor rating --------------------------------------------------- f) Manufacturer ---------------------------------------------------
-Brakes a) Number ---------------------------------------------------- b) Type ----------------------------------------------------
c) Dimensions --------------------------------------------------- d) Lining material ---------------------------------------------------
-.Type of main girder ---------------------------------------------------- - End carriage --------------------------------------------------- a) Wheelbase ---------------------------------------------------
c) Maximum load excluding impact of travelling wheels, Kg
- Hoisting wire rope ------------------------------------------ Main Auxiliary Hoist Hoist
a) Construction ---------------------------------------------------- b) Quality of steel ---------------------------------------------------- c) Diameter ---------------------------------------------------- - Collector gear
a) Type ---------------------------------------------------- b) Rating ---------------------------------------------------- c) Manufacturer, Country ---------------------------------------------------- - Gantry rails a) Size ---------------------------------------------------- b) Material ----------------------------------------------------
d) Weight , Kg ---------------------------------------------------- -Maximum deflection at Mid-span on the main girder at maximum loading, mm -----------------------------------------------------
- Vertical distance from top of gantry rail to lowest overhead obstruction required, m----------------------------------------------
- Weights
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
66
a) Net weight of complete crane, Kg ------------------------------------------- b) Net weight of complete crab, Kg -------------------------------------------
c) Weight of motors, Kg ------------------------------------------- B-19 Communication Equipment 19.1 PABX Telephone Equipment Manufacturer, Country ---------------------------- Type ---------------------------- Supply voltage, V ---------------------------- Line capacity ---------------------------- Traffic capacity ---------------------------- Facilities ---------------------------- Extension Services class ---------------------------- Signals and tones ---------------------------- 19.2 Paging Equipment Manufacturer, Country ---------------------------- Type ---------------------------- Capacity ---------------------------- Supply voltage, V ---------------------------- 1) Main Amplifier Type --------------------------- Output, W ---------------------------- Form ---------------------------- Dimension, mm ---------------------------- Weight, Kg ----------------------------
Power Consumed Paging , W ---------------------------- Waiting, W ---------------------------- Power Supply, V ----------------------------
2) Hand Set Type ----------------------------
Form ---------------------------- Dimension, mm ---------------------------- Weight, kg ---------------------------- 3) Speaker
Type ---------------------------- Form ---------------------------- Impedance, ohm ---------------------------- Output, w ---------------------------- Dimension, mm ---------------------------- Weight ,kg ----------------------------
4) CCTV System Type ----------------------------
Manufacturer, country ---------------------------- Camera resolution ---------------------------- Storing System ---------------------------- Back up time for storage ---------------------------- Camera swivel angle (max.) ---------------------------- Distance for taking picture ----------------------------
4) Compatible Multiplexer with optical fiber
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
67
------------------------------------------------------------------------------- 5) RTU (Remote Terminal Unit) -------------------------------------------------------------------------------- B.20 Fire Protection Equipment 20.1 Hydrant/ Pumps -Number of Hydrant, Pumps for yard ----------------------------
for power house ---------------------------- Hose size and length (DxL) mm x m ----------------------------
20.2 Portable Fire Extinguisher
a. 100 kg trolly mounted dry powder extinguisher
-Manufacturer, Country ---------------------------- -Type of powder ---------------------------- -Weight of powder, Kg ----------------------------
b. 10 kg portable dry powder extinguisher -Manufacturer, Country ---------------------------- -Type of powder ---------------------------- -Weight of powder, Kg ---------------------------- c. 5 kg portable gas extinguisher -Manufacturer, Country ---------------------------- -Type of powder ---------------------------- -Weight of gas , Kg ---------------------------- 20.3 Auto-Release CO2 Fire
Extinguishing System -Manufacturer, Country ---------------------------- -Type of powder ----------------------------
-System Description ----------------------------
20.4 Fire detection Equipment -Manufacturer, Country ----------------------------
-Type of Equipment ---------------------------- -Weight of panel, Kg ----------------------------
B-21 Civil Work and Building Work
21.1 Standards and Codes to be used in design and construction
No. Work Item Standard and Codes 1. Filling Works ---------------------------------- 2. Foundation Works ---------------------------------- 3. Piling ---------------------------------- 4. Steel Sheet Piling Wall ---------------------------------- 5. Concrete Works ---------------------------------- 6. Reinforcement Works ---------------------------------- 7. Structural Steel Works ---------------------------------- 8. Road ----------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
68
9. Brickwork ---------------------------------- 10. Painting ----------------------------------
11. Lighting and Power Supply ---------------------------------- 12. Air Conditioning System ----------------------------------
13. Plumbing ---------------------------------- 14. ------------------------------- ---------------------------------- 15. ------------------------------- ----------------------------------
21.2 Concrete 1) Proposed Materials -Standards:
(i) Cement ---------------------------------- (ii) Aggregates ----------------------------------
(iii) Concrete Admixture ---------------------------------- (iv) Reinforcement ---------------------------------- (v) Other ----------------------------------
2) Proposed Manufacturers/Source/Quarries (i) Cement ---------------------------------- (ii) Aggregates ----------------------------------
(iii) Concrete Admixture ---------------------------------- (iv) Reinforcement ----------------------------------
(v) Other ----------------------------------
3) Compressive Strength of Concrete at 28th Day 1) Gas/ Steam turbine generator/ HRSG foundation Kg/cm2 ----------------------------------
2) Supper-structure Kg/cm2 ---------------------------------- 3) pile Kg/cm2 ---------------------------------- 4)Concrete pavement ---------------------------------- 5) ----------------------- ---------------------------------- 6) ----------------------- ----------------------------------
21.3 Piling and Subsoil Improvement
21.3.1 Piling
1) Type of foundation pile --------------------------------- a) Diameter/cross section and length, D= --------------------------m L=---------------------------m b) Allowable working load of a pile, Kg --------------------------------
c) Method of driving in Piles -------------------------------- d) Piling Plant -------------------------------- e) Method of Jointing Piles -------------------------------- f) Name of structures, equipment and buildings to be applied ------------------------------
2) Type of foundation pile a) Diameter/cross section and length, D= ----------------------------------- m L= ----------------------------------- m b) Allowable working load of a pile, Kg ------------------------------- c) Method of driving in Piles ------------------------------- d) Piling Plant ------------------------------- e) Method of Jointing Piles ------------------------------- f) Name of structures, equipment and buildings
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
69
to be applied -----------------------------
3) Type of foundation pile a) Diameter/cross section and length, D= ------------------------------m L= ------------------------------m
b) Allowable working load of a pile, Kg ------------------------------ c) Method of driving in Piles ------------------------------
d) Piling Plant ------------------------------ e) Method Of Jointing Piles ------------------------------ f) Name of structures, equipment and buildings
to be applied ------------------------------
21.3.2 Subsoil Improvement (if any)
1) Method of subsoil improvement
2) Expected allowable bearing capacity of subsoil
(after improvement) ----------------------------Kg/m2
3) Name of structures, equipment and buildings to be applied ------------------------------
21.4 Type and Strength of Steel Sheet Piling Wall
1) Type of Sheet Pile 2) Length of a Pile, m ------------------------------ 3) Width of a Pile, mm ------------------------------ 4) Yield Point, Kg/cm2 ------------------------------ 5) Ultimate Tensile strength, Kg/cm2 ------------------------------ 6) Supplier ------------------------------ 7) Specification of tie rods Materials ------------------------------ Diameter, mm ------------------------------ Length of a tie rod, m ------------------------------ Interval, m ------------------------------
21.5 Structure Steel Works
1) Grades of Steel ------------------------------ 2) Suppliers of Steel, Bolts & Fasteners ------------------------------ 3) Methods of Welding ------------------------------ 4) Corrosion Protection
(i) Method and Materials ------------------------------ (ii) Place of preparation ------------------------------ 5) Proposed Coatings (i) Type of Product ------------------------------ (ii) Manufacturer ------------------------------ (iii) Dry Film Thickness ------------------------------ (iv) Means of application ------------------------------ (v) Place of application ------------------------------ (vi) Colour ------------------------------ 6) Yield Point ------------------------------ 7) Ultimate Tensile Strength ------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
70
21.6 Steam Turbine Generator/ HRSG 1) Weight of machine Gas turbine/ Steam turbine, Kg ----------------------------- Generator, Kg ----------------------------- Auxiliary, Kg ----------------------------- Total, Kg ----------------------------- 2) Dimension of G/T foundation Width, m ----------------------------- Length, m ----------------------------- Thickness, m ----------------------------- 3) Weight of GT/ ST foundation, Kg -----------------------------
21.7 Walls and Roofing 1) Insulation Materials ----------------------------- 2) Waterproofing Materials ----------------------------- 3) Caulking Materials -----------------------------
21.8 Metal
1) Grades of Steel ----------------------------- 2) Suppliers ----------------------------- 3) Method and Materials for
corrosion protection -----------------------------
21.9 Construction Equipment and their specifications
1) Earth Works -------------------------- 2) concrete Works -------------------------- 3) Pavement works -------------------------- 4) Structural Steel Works -------------------------- 5) Piling Works --------------------------
6) Steel Sheet Piling Wall -------------------------- B - 22 Environmental Impact (a) Air Emissions Levels With regard to project air emissions, please fill out the following table: Emission Percent Removal
Efficiency at 100% Capacity
100% Capacity
75% Capacity
50% Capacity
NOx ----------------------- ----------ppmv ----------ppmv ----------ppmv --------------------- ------- ib/hr ------- ib/hr ------- ib/hr --------------------- --------- g/kj -------- g/kj -------- g/kj ---------------------- ------- m9/m3 ------m9/m3 ------m9/m3 CO ----------------------- ------- ppmv ------ppmv ------ppmv ----------------------- --------- ib/hr -------- ib/hr -------- ib/hr ----------------------- --------- g/kj --------- g/kj --------- g/kj ----------------------- --------m9/m3 ------ m9/m3 ------ m9/m3 CO2 ------------------------ ----------ppmv ----------pmv ----------pmv
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
71
------------------------ ------------ib/hr -----------ib/hr -----------ib/hr ------------------------ -------------g/kj ------------g/kj ------------g/kj ------------------------ ---------m9/m3 --------m9/m3 --------m9/m3 Air Toxics (list)
------------------------
ppm is defined as volumetric parts per million at 15% O2 (b) Effluent Discharge P4 -------mg/e Cr ----------- ---------------mg/e BOD -------mg/e Cu---------- ----------mg/e COD --------mg/e Fe----------- ------------mg/e TSS --------mg/e Ni----------- ----------mg/e PO4 ---------mg/e Zr----------- ----------mg/e SO4 ---------mg/e Ac----------- ----------mg/e NH3 ----------mg/e Cd---------- ----------mg/e CL ----------mg/e Pb----------- ----------mg/e Detergents ----------mg/e ------------- ----------- Oil & grease ----------mg/e ------------ ---------- (c) Noise Level
Description Unit Equipments
Noise Level db (A) @ Facility boundary
..................db (A) (Day)
...................db (A) (Night)
Equipment db (A) @ 1 meter
....................db (A)
B-23 Water Treatment Plant.
The quantities shall meet the requirement of CCPP at Guaranteed full load at site condition
The following design parameters of the equipment of the Water Treatment Plant and its relevant data to be provided by the Tenderer during detailed design stage :
Sl.No.
Description of the main design parameters of the major equipment and relevant data of plant
Materials/values Remarks
1.
RAW WATER DEMAND
a. Daily raw water demand for WTP, m3 : The quantities shall meet the
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
72
Sl.No.
Description of the main design parameters of the major equipment and relevant data of plant
Materials/values Remarks
requirement of CCPP at Guaranteed full load at site condition
b. Hourly demand, m3 : c. No. of raw water pump provided : 3 X 60 % d. Capacity of each pump m3 /hr. : As per requirement The quantities
shall meet the requirement of CCPP at Guaranteed full load at site condition
e. Operation mode Auto/manual : Auto / Manual f. On-line instrument
1. Flow meter (For WTP local & control room) 2. Conductivity meter (For WTP local & control room) 3. PH meter (For WTP local & control room)
: To be provided To be provided To be provided
g. Service indication signal : h. Trip signal alarm annununciator
(Audio-visual) : Audio-visual signal
to be provided i. Low water level alarm annunciator (audio-
visual) : Audio-visual signal
to be provided 2. HRSG MAKE UP WATER DEMAND a. Daily make-up water demand, m3 : The quantity shall
meet the requirement of HRSG (s) at Guaranteed full load including other consumption
b. Hourly demand, m3 : The quantity shall meet the requirement of HRSG (s) at Guaranteed full load including other consumption
c. No. of make-up water pump provided : 3 X 60 % d. Capacity of each pump, m3/hr The quantity shall
meet the requirement of HRSG (s) at Guaranteed full load
3. COOLING WATER DEMAND a. Daily cooling water demand (including
drinking / potable water), m3 : The quantity shall
meet the requirement of CCPP at Guaranteed full
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
73
Sl.No.
Description of the main design parameters of the major equipment and relevant data of plant
Materials/values Remarks
load including drinking / potable water
b. Hourly demand, m3 : The quantity shall meet the requirement of CCPP at Guaranteed full load including drinking / potable water
c. Cooling water PH : 7- 7.5 d. Cooling water conductivity (µS/cm) : Less than 2000 4. MAKE UP WATER QUALITY a. Conductivity (µS/cm) : 0.2 - 0.3 (µS/cm) b. Max. silica (Si02), µgm/l : 20 µgm/l 5. RAW WATER QUALITY a. Monsoon period 1. Conductivity (max.) µS/cm at 250C : 2. Total minerals (max.), meq/l : b. Lean period 1. Conductivity (max.), µS/cm at
250C :
2. Total minerals (max.) meq/l : c. Design raw water quality input 1. Conductivity (max.) µS/cm at
250C :
2. Total minerals (max.) meq/l : 6. ANNUAL CONSUMPTION OF MAIN
BULK CHEMICALS
a. Hydrochloric acid (30% conc.) M. Tons : b. Caustic soda (100%), M. Tons : c. Coagulant, M-Tons : d. Auxiliary chemicals, M. Tons : e. Hydrazine hydrate, 35% M. Tons : f. Ammonium hydroxide 22-25%, M. Tons : g. Tri-sodium phosphate M. Tons : 7. Chemical consumption during
commissioning and Defect liability period operation:
a. Hydrochloric acid (30% conc.) M. Tons : b. Caustic soda (100%), M. Tons : c. Coagulant, M-Tons : d. Auxiliary chemicals, M. Tons : e. Hydrazine hydrate, 35% M. Tons : f. Ammonium hydroxide 22-25%, M. Tons : g. Tri-sodium phosphate M. Tons : 8. INITIAL FILLING MATERIALS a. Resin : b. Anthracite coal/gravel : 9. All necessary chemicals for boiler acid
clearing and preservation before start-up
10. CLARIFIERS a. No. of units provided : 2 X 100 %
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
74
Sl.No.
Description of the main design parameters of the major equipment and relevant data of plant
Materials/values Remarks
b. Design production capacity, m3/hr. : c. Max. production capacity of each unit,
m3/hr. :
d. No. of unit in operation at a time : e. Chemicals (coagulant) used for
coagulations :
f. Structure (metallic) : g. Type (vertical/Horizontal flow) : h. Inside lining to protect corrosion : i. Life durability of clarifiers lining material : j. Quality of coagulant dosing line materials
to clarifier :
k. Operating PH : l. On-line instrument
1. Flow meter (For WTP, local & control room) 2. Conductivity meter (For WTP, local & control room) 3. PH meter (For WTP, local & control room)
: : :
m. Dosing system : Coagulant :
1. No. of dosing pump 2 X 100 % 2. Mode of operation of the pumps Auto/manual 3. No. of soln. measure tan 4. Capacity of measure tank 5. Inside lining of the measure tank 6. Life durability of inside lining material
: : : : : :
2 X 100 % 100 % capacity
Auxiliary chemicals : 1. No. of dosing pump 2. Mode of operation of the pumps Auto/manual 3. No. of soln. measure tank 4. Capacity of measure tank
: : : :
2 X 100 % 2 X 100 % 100 % capacity
11. SAND FILTERS : 1. No. of unit : 2 X 100 % 2. Filtration process (by
gravity/pump) :
3. No. of unit in operation at a time : 4. Filtering chamber (double) : 5. Production capacity,
m3/hr/unit max :
6. Filling material (anthracite coal)
:
7. Bed volume, m3 : 8. Bed height, mm : 9. Height of the vessel, mm : 10. Dia of vessel, mm : 11. Free board, % : 12. Strainer material (metallic) : 13. No. of manhole provision : 14. Location of upper manhole (Top
and Body) :
15. Production quality :
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
75
Sl.No.
Description of the main design parameters of the major equipment and relevant data of plant
Materials/values Remarks
(Turbidity, NTU/JTU) 16. Local and On-line instruments
provided :
a. Flow meter : b. Pressure meter : c. Others (if any) :
17. Type of filters : 18. Inside lining : 19. Life durability of lining material : 20. Filter pump :
a. No.of pumps provided b. Capacity of each pump m3/hr c. Mode of operation Auto/manual
: : :
2 X 100 %
21. Filter back wash pump a. No.of pumps provided b. Capacity of each pump m3/hr c. Mode of operation Auto/manual
: : :
2 X 100 %
12. ION EXCHANGER UNITS : CATION UNIT ANION UNIT MB UNIT
1. No. of unit :
2 X 100 %
2 X 100 %
2 X 100 %
2. Production capacity, m3/hr/unit max
:
3. No. of unit in operation at a time : 1 X 100 % 1 X 100 % 1 X 100 % 4. Type of back wash water used : 5. Quantity of water production per
regeneration using river water (please specify input river water quality)
:
6. Running hours between the regeneration
:
7. Life durability of the lining material : 8. Direction of regenerant flow : 9. Bed compaction technique applied : 10. Dilution water used for regenerant
preparation :
11. Quantity of resin filled in each filter, litre (cation/anion/inert)
:
12. Sight glass facility : 13. Mode of unit operation,
Auto/manual :
14. Mode of regeneration process, Auto/manual
:
15. Regenerant injection system (ejector)
:
16. Air scouring facility : 17. Brand name of the resin used 18. Manufacturer and country of origin
of the resins :
19. Character of the resins (strong)
:
20. Type of the anion resin (Type –1/Type-2)
:
21. Bed volume of resin in filter m3 : 22. Resin bed height, mm : 23. Height of the vessel, mm :
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
76
12. ION EXCHANGER UNITS : CATION UNIT ANION UNIT MB UNIT 24. Dia of vessel, mm : 25. Free board, % : 26. Strainer material : 27. No. of manhole provision : 28. Location of upper manhole
(Top/Body) :
29. Total exchange capacity of the resin used
:
30. Operating exchange capacity of the resin at design regeneration level.
:
31. Useful exchange capacity, % of Sl.30 : 32. Regenerant used for cation/anion
resin :
33. Regeneration technique (co-current/Counter current)
:
34. Regeneration levels (100% basis), gm/l
:
35. Duration of each production cycle per regeneration
:
36. Process water consumption per regeneration m3
:
37. Total regeneration time, hrs. : 38. Internal lining in the vessels
(Vulcanised Rubber linings) :
39. Resin bed support (platform/without platform)
:
40. Local and On-line instruments provided - a. Flow meters b. Pressure meters c. Conductivity meters d. pH meters e. Silica analyser f. Sodium analyser g. Others(if any)
: : : : : : :
42. Production quality - After Anion unit After MB unit a. Conductivity, µS/cm
b. P-Alkalinity c. Silica
: : :
Sl.No.
Description of the main design parameters of the major equipment and relevant information of plant
Materials/values Remarks
13. DECARBONISER UNIT a. No. of unit : b. Design production capacity of each unit
m3/hr. :
c. Water storage capacity of each decarbonized water tank, m3
:
d. Internal lining meterial in decarbonizer column and storage tank
:
e. Material of decarbonized water flow pipes & valves
:
f. Life durability of lining material : g. No. of decarbonized water pump : 2 X 100 %
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
77
Sl.No.
Description of the main design parameters of the major equipment and relevant information of plant
Materials/values Remarks
h. Capacity of each pump, m3/hr. : 14. Treated Water Storage Tanks : Coagulate
d water tank
Clarified water tank
Local demineralized water tank
Main make up water reserve tank
1. No. of tank provided : 2. Capacity of each tank, m3 : 3. Structure made of (metallic) : 4. Internal lining
(Vulcanised rubber) :
5. Life durability of lining material : 6. Instrument provided (on-line) –
a. Level indicator b. Flow meters c. Others (if any)
:
7. Installation style (Vertical/Horizontal)
:
8. Type of the roofs (Flat/Elliptical) : 9. Installation level (ground level/on-
support)
Sl.No.
Description of the main design parameters of the major equipment and relevant information of plant
Materials/values Remarks
15. HYDROCHLORIC ACID STORAGE TANK and MEASURE TANK
a. No. of tank to be provided : b. Capacity of each , m3 : c. Structure (metallic) : d. Internal lining
(vulcanised rubber) :
e. Life durability of lining material : f. Material of acid flow pipes and valves : g. Installation style (Vertical/Horizontal) : h. Transfer system from transport to tank : i. Acid Transfer system from tank to service
tank (by gravity/pump) :
j. Level indicator provided (Gaze glass/float)
:
16. CAUSTIC SODA STORAGE TANK and
MEASURE TANK
a.
No. of tank provided
:
b. Capacity of each , m3 : c. Structure (metallic) : d. Material of acid flow pipes and valves : e. Installation style (Vertical/Horizontal) : f. Transfer system from transport to tank : g. Caustic transfer system from tank to
service tank (by gravity/pump) :
h. Caustic soda loading system from :
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
78
16. CAUSTIC SODA STORAGE TANK and MEASURE TANK
preparation tank (gravity/pump) i. Level indicator provided (Gaze glass/float) :
17. HRSG CONDITIONING CHEMICAL TANKS Phosphate
tank Prepn. Service
Ammonia tank Prepn. Service
Hydrazine tank Prepn. Service
1. No. of unit
:
2. Capacity of each, m3 : 3. Structure (metallic) : 4. Internal lining (Rubber lining) : 5. Life durability of lining material : 6. Installation style
(Vertical/Horizontal) :
7. Transfer system from – a. Bulk to prepn, tank b. Prepn. to service tank gravity/ pump/ others
:
8. Level indicators (gaze glass/float) : 9. No. of dosing pumps provided :
18. WASTE EFFLUENT NEUTRALISATION
FACILITY Regular waste
effluent neutralization facilities
Boiler cleaning chemicals neutralization facilities
Waste Effluent Neutralisation Facilities from over all plant (WTP, Power plant & others)
1. Type of neutralisation vessel (Tank/underground pit)
:
2. No. of unit (if Tank) : 3. Volume of each tank
(if more than-1), m3 :
4. Structure (Mild steel/Stainless steel)
:
5. Internal lining (Vulcanised rubber) : 6. Life durability of lining material : 7. Mixing process (Air
scouring/pump) :
8. Neutralised effluent quality (while disposed off) a. pH b. Conductivity, µS/cm c. Others (if any)
:
9. Spot instruments provided - a. pH meter b. Conductivity meter c. Others(if any)
:
10. Final disposed off system (Gravity/pump)
:
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
79
18. WASTE EFFLUENT NEUTRALISATION FACILITY
Regular waste effluent neutralization facilities
Boiler cleaning chemicals neutralization facilities
Waste Effluent Neutralisation Facilities from over all plant (WTP, Power plant & others)
11. Filling system (pump/operating pressure)
:
12. No. of filling pump : 13. Capacity of each filling pump,
m3/hr. :
14. Height of the filling point, m : 15. Flow meter : 16. Level meter : 17. Internal lining of the connected
pipes & valves :
18. PH of neutralised effluents before disposed
:
19. Disposal point of neutralized effluents (directly river/via pit)
:
20. Capacity of each pit, m3 : Sl.No.
Description of the main design parameters of the major equipment and relevant information of plant
Materials/values Remarks
19. INSTRUMENT IN CONTROL PANEL a. Flow meters : b. Conductivity meters : c. PH meters : d. Silica meter : e. Level indicators of all water and bulk
chemicals storage tanks :
f. Switches of all pumps and motors in addition to local switches
:
g. Audio-visual alarm for all the faults and control system
:
20. CHEMICAL LABORATORY a. Installation : b. Laboratory tables : c. Laboratory chairs : d. Gas supply facility e. Wash water supply facility : f. Demineralise water supply facility : g. Air conditions facility h. Standard and workmanship of the
laboratory furniture and room/rooms :
21. WATER STEAM QUALITY SPECIFICATION Values Remarks 1.
Make up water (Demin. Water)
a. E. Conductivity, µS/cm. at 25oC) : b. Silica Max. : c. Hardness Max. : 2. Condensate
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
80
21. WATER STEAM QUALITY SPECIFICATION Values Remarks a. E. conductivity, µS/cm. at 25oC) Without
resin column After resin column Max.
b. PH Max. : c. P-alkalinity Max. : d. Hardness : e. Ammonia (NH3) : f. Hydrazine (N2H4) : g. Chloride (Cl−) : h. Oxygen (02) : i. Iron (Fe+2) : j. Copper (Cu+2) : 3. Feed Water a. E.Conductivity, µS/cm. at 25oC-
Without resin column After resin column
: :
b. PH : c. P-Alkalinity : d. Hardness : e. Ammonia (NH3) : f. Hydrazine (N2H4) : g. Chloride (Cl−) : h. Oxygen (O2) : i. Iron (Fe+2) : j. Copper (Cu+2) : 4. Boiler Water (Middle Section ) a. E. Conductivity, µS/cm. at 25oC : b. PH
Max. Min.
:
c. p-Alkalinity : d. Hardness : e. Silica (SiO2) : f. Phosphate (P2O5) : g. Chloride (Cl−) : h. Iron (Fe) : 5. Boiler Water (Blowdown section) a. E. Conductivity, µS/cm. at 25oC : b. PH
Max. Min.
:
c. p-Alkalinity : d. Hardness : e. Silica (SiO2) : f. Phosphate (P2O5) : g. Chloride (Cl−) : h. Iron (Fe) : 6. Saturated Steam a. E. Conductivity, µS/cm. at 25oC
Without resin column After resin column
b. pH : c. p-Alkalinity : d. Silica (SiO2) : e. Ammonia (NH3) : 7. Superheated Steam
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
81
21. WATER STEAM QUALITY SPECIFICATION Values Remarks a. E. Conductivity, µS/cm. at 25oC
Without resin column After resin column
: :
b. pH : c. p-Alkalinity : d. Silica (SiO2) : e. Ammonia (NH3) : 8. Cooling Water a. E. Conductivity, µS/cm. at 25oC : b. PH :
22. LABORATORY INSTRUMENT, EQUIPMENT, GLASS WARES, REAGENT GRADE CHEMICALS AND SAFETY EQUIPMENT:
All necessary instrument & equipment to be provided by the suppliers.
Detail list of the necessary laboratory instruments, equipment, glass wares, chemical reagents and safety equipment shall be provided in which the following essential must be included:
a. Instrument and equipment: Name of items Minimum
quantity required, pcs.
1.
Electrical weighing balance (Capacity 0.00001 – 100 gms)
: 2
2. Rough weighning balance (10-1000 gms)
2
3. Conductivity meter (0.05 – 1,00,000 µS/cm)
3
4. PH meter (Range : 0-14) : 3 5. Photoelectric colorimeter : 3 6. Turbidity meter : 2 7. Lab. oven
(Temp. regulation facility must be) : 1
8. Lab. furnace (Temp. upto 15000C) : 1 9. Refrigerator (Min. 8 Cft. size) : 1 10. Hot plate
(with Temp. regulation facility) : 3
11. Distillation, heater (with heating nest and Temp. regulation facility)
: 3
12. Water bath (4/3 points facilities and electrically operated)
: 1
13. Orsat Apparatus (5/4/3 points) for flue gas and Hydrogen gas analysis.
: 3
14. Microscope (high magnifying power) for I.E. resin structure examination.
: 1
15. Centrifuging machine (electrically operated, 4 points facilities and with sufficient graduated conical test tube of capacity 100 ml) for determination of water content in oil (Method : ASTM D-1796)
: 1
16. Distillation apparatus for the determination : 2
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
82
Name of items Minimum quantity required, pcs.
of water content in oil (Method : ASTM D-95)(
17. Viscometer (for the determination of viscosity of oil)
: 1
18. Flash point tester (for the determination of the flash point of oil)
: 1
19. Moisture content tester (for the determination of presence of moisture in transformer oil)
: 1
20. Equipment for the measurement of the calorific value of fuel oils.
: 1
21. Equipment for the determination of sulfur content in fuel oil.
: 1
22. Hydrometer (different necessary ranges)
: 25
23. Thermometer (different necessary ranges)
: 10
24. Stopwatch : 3 25. Platinum crucible (50ml capacity) : 1 26. Modern laboratory furniture : Sufficient as
necessary
27. Others (as per necessity) :
b. Glass wares
All necessary glass ware to be provided by the supplier. Detail list of the items must be provided in which the following essential must be included. Name of the items : Minimum quantity
required, pcs.
1. Automatic burette set (with pumping ball and reagent vessel facilities, capacity of the burette – 10 and 25 ml).
: 25 Sets (Each size)
2. Ordinary burette (Capacity – 25 ml)
: 25 Pcs.
3. Volumetric flask (Capacity – 50,100,250, 500, 1000 and 2000 ml)
: 25 pcs. (Each size)
4. Graduated pipette (Capacity-1, and 2 ml) (Capacity – 5, 10 and 20 ml)
: 10 Pcs. (Each size) 50 Pcs. each size
5. Volumetric pipette (Capacity- 5, 10 and 25 ml) (Capacity – 50 and 100 ml)
: 15 Pcs. each size 25 Pcs. each size
6. Graduated measuring cylinder (Capacity-5, 10, 25 ml and 50 ml) (Capacity – 100 ml) (Capacity – 250, 500 and 1000 ml)
: 25 Pcs. each size 100 Pcs. 25 Pcs. each size
7. Beaker (Capacity- 50 and 100 ml) (Capacity – 250 and 500 ml) (Capacity – 1000 and 2000 ml)
: 25 Pcs. each size 100 Pcs. each size 25 Pcs. each size
8. Titration flask (Capacity – 250 and 500 ml)
: 125 Pcs. each size
9. Conical flask (Capacity – 50 and 100 ml) (Capacity – 250 and 500 ml)
: 25 Pcs. each size 100 Pcs. each size
10. China crucible : 50 Pcs.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
83
Name of the items : Minimum quantity required, pcs.
11. Wash bottle (Capacity – 100 ml)
: 25 Pcs.
12. Glass weighing bottle : 25 Pcs. 13. Reagent bottle
(500 ml capacity) : 50 Pcs.
14. Plastic sampling pot (500 and 1000 ml. )
: 50 Pcs each size
15. Plastic beaker (Capacity – 250 and 500 ml)
: 50 Pcs. each size
16. Gas burner : 15 Pcs. 17. Stands and clamps : 15 Sets 18. Specula (Plastic and metallic) : 15 Pcs each size 19. Tons : 15 Pcs. 20. Others (AS PER NECESSITY) : Sufficient Quantity.
C. Chemical reagents :
All necessary chemical reagent for 6 years consumption to be provided by the supplier. All necessary items as would be required for minimum 6 years consumption to conduct the analytical work of water, oil, gas and different chemicals involved in WTP and proximate lab-according to the standard test method. Detail list of the items must be provided in which the following essential must be included. Name of the items Quantity 1. Xtlene : 2. Analytical pure potassium Bromate
(KbrO3) :
3. Copper Chloride (Cu2Cl2) : 4. Stannous Chloride (SnCl2) : 5. Potassium Dichromate : 6. Sodium Chromate : 7. Magnesium Chromate : 8. Magnesium Chloride : 9. E.D.T.A. (III) : 10. Arsenic Trioxide (As203) : 11. Sodium-Potassium Tartarate : 12. Sodium di-hydrogen phosphate : 13. Bromocresol Green indicator : 14. Chemically pure silver nitrate : 15. Citric acid : 16. Ortho-phenantrolin : 17. Aceton : 18. Toluene : 19. Glycerol : 20. Benzene : 21. Potassium hydroxide : 22. Potassium chloride : 23. Ethyl alcohol : 24. Potassium permanganate : 25. Ammonium chloride : 26. Copper sulphate : 27. Metol-A : 28. Pot. metabisulfite :
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
84
d. Safely equipment
All necessary safety equipment to be provided by the supplier.
Detail list of the items must be provided in which the followings essential must be included.
Name of the items Nos. 1. Gas masks : 6 Nos. 2. Face protectors : 12 Nos. 3. Hand gloves : 30 4. Safety goggls : 20 5. Lab. approns. : 04 sets 6. Gum boots : 6 pairs 7. Helmet : 6 Nos 8. First Aid box : 1 set
23. The Contractor shall guaranty for the production quantity of Cation, Anion and mixed bed filters under its design condition of regeneration level (chemical consumption) and design Raw Water quality specified in the design data sheet.
24. The flow diagram to be provided showing the water balance scheme of demi-water plant
25. The Contractor confirms to supply the necessary kinds of initial filling materials such as resin and anthracite/gravel for all ion-exchange and sand filter unit as per the quantities (by volume) along with 3% extra for 1(one) year make-up.
26. The Contractor confirms to supply all necessary commercial grade chemicals (viz. hydrochloric acid, caustic soda, coagulant, auxiliary chemicals, hydrazine hydrate, ammonium hydroxide, tri-sodium phosphate, boiler cleaning chemicals including inhibitors etc.) as would be required for the commissioning and defect liability period operation of WTP.
27. The Contractor would be submitted the acceptance test methodology before performing the tests. The Contractor will be confirmed that all equipment and instruments would be handed over to the customer strictly in accordance with the design data and information as furnished in the data sheet and show their operation capabilities and performance as specified in the same data sheet.
28. The Contractor shall not change the major design data/or the number of equipment without prior information to and confirmation by the customer.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
85
SCHEDULE-C
DRAWINGS TO BE FURNISHED WITH THE TENDER Drawings / diagrams as mentioned below, but not be limited to, will be furnished by the Contractor during detailed design stage, after signing the Contract. The Drawings / diagrams require to be approved by the "Engineer"/ Client as per Contract: - [
1. Drawing/diagram of River Water Pumps showing on-shore pump house, water
intake arrangement from River to on-shore intake basin. The water intake arrangement shall be such that, it shall cater the needs of total plant requirement including cooling water requirement of the complete Combined Cycle Power Plant during dry season and rainy season by means of cooling tower.
2. Drawing/diagram of complete circulating water system showing on-shore pump
house, Clarifier, Steam Turbine Condenser.
3. Drawing/diagram of complete electrical single line diagram showing Generators, Step-up Transformers, Station Auxiliary Transformers, Unit Auxiliary Transformers, Black start Diesel Generator, Batteries, Rectifiers and auxiliaries with proposed protection schemes.
4. Drawing/diagram of complete Water Treatment Plant (WTP), HRSG water
conditioning and Acid cleaning/Alkali boil out as mentioned hereunder: -
- Installation drawings of equipment, layout of equipments & pipelines, process diagrams, functional diagram, local protection and inter locking conditions, assembly drawings of the following items to be provided :
- Central chemical laboratory and proximate analysis laboratory – process part
- Water pre-treatment plant
- Water demineralization plant
- Regeneration equipment & process
- Clarified water supply system
- Cooling water supply system
- Waste water neutralization plant for WTP discharge water
- Storage facility of chemical re-agents
- Acid & alkali storage facility, loading-unloading system, preparation and supply system
- Alkali, coagulant & other auxiliary chemical mixing facility, filtering system, preparation and supply
- Dosing system, drainage system, ejector system, compressed air system, sampling point.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
86
HRSG
- Feed water correction plant
- Boiler water correction plant
- Proximate analysis laboratory- process part
- Ammonia & hydrazine storage facility loading-unloading system, preparation & supply.
- Trisodium phosphate mixing facility, filtering, preparation & supply.
- Drainage system, ejector system, cooling system, dosing system, sampling point.
ACID CLEANING
- Neutralizing and harmlessing plant for discharge water after acid cleaning/Alkali boil out of equipment.
- Mixing tank of reagent chemicals for chemical cleaning of equipment
- Chemical cleaning solution storage facility, preparation and supply.
- Acid and alkali for cleaning equipment storage facility, loading-unloading system, preparation and supply.
- Complete sodium hypo chloride (NaOCL) generation and dosing system.
5. Drawing/diagram of complete HRSG Feed water system showing De-aerator, Feed water storage tank, BFP with hydraulic coupling, etc.
6. Drawing/diagram of complete HRSG and Steam Turbine steam system
7. Drawing/diagram of ST lub oil system 8. Drawing/diagram of HRSG hydraulic operated Diverter damper control system
9. Drawing/diagram of ST lub oil cooling system
10. Drawing/diagram of complete Sampling station (For HRSG Feed water, ST
steam sample testing System)
11. Drawing/diagram of Turbine drain and HRSG drain system.
12. Drawing/diagram of Condenser Ball cleaning system
13. Drawing/diagram of Effluent and Waste water neutralization plant.
14. Drawing/diagram of Condenser air extraction system showing Vacuum pumps, Steam Jet air ejector
15. Drawing/diagram of auxiliary steam supply system
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
87
16. Drawing/diagram of Gland steam/ Steam sealing system
17. Drawing/diagram of Fire water/ Fire Hydrant system
18. Drawing/diagram of potable water system
19. Drawing/diagram of CC Control system
20. Drawing/diagram of HRSG and ST Control system (DCS)
21. Generator Capability Curves for the three Generators. 22. Drawing/diagram of Instrument air system of the CCPP.
23. The following curves, which are necessary, shall be furnished by the Contractor.
- Variation in barometric pressure
- Variation in ambient temperature
- Variation of generator efficiency with Power Factor
- Variation in pressure loss from atmosphere to compressor inlet flange
- Variation in pressure loss from turbine exhaust flange to atmosphere
- Mechanical flow diagrams
- Heat rate curve
- Heat Balance diagrams
- Flow diagram of steam, condensate and feed water.
- Inlet temperature Power correction curves
- Inlet temperature heat rate correction curves
- Starting and loading curve
- Max. Operating limit of GTG, HRSG & STG units
- Major Control & Protection system
- Generator capability curve
- Generator "V' curves
- Zero Power factor saturation curve
- Power output vs ambient temperature/ Cooling water temp. curves
- Major piping connection
- Turbine, generator and auxiliaries foundations
- Control building layout and section
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
88
- Cooling water supply system layout
- Exhaust duct damper drawing
- No load saturation curve
- Synchronous impedance curve
- Turbine generator unit equipment arrangement
- Layout plan of central control room
- General arrangement of the switchyard
- Foundation, loading and support information
- Dimensioned Outline drawing of major equipment offered
- Detail drawings and descriptions providing a complete Understanding of the equipment offered
- Other drawings specified in the Specification.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
89
SCHEDULE-D
DELIVERY TIME
Time from Date Time Time Required Total time from of Order to Required for for Erection & Date of Orderto FOB Transportation Commissioning Completion of ICO (Months) (Months) (Months) (Months) 1. Heat Recovery steam
Generating Plant- ----------------------------------------------------------------------------------- and Ancillary
2. Steam turbine Generating Plant--------------------------------------------------------------------------------------
3. 132 kV Switchgear,
Equipment -----------------------------------------------------------------------------------
4. Step-up Transformer for STG----------------------------------------------------------------------
5. ALL Crane ----------------------------------------------------------------------------------------------
6. Station Electrical Services---------------------------------------------------------------------------
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
90
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
91
SCHEDULE - E
TOOLS AND APPLIANCES
The Contractor shall list below all special tools and equipment for
operation and maintenance, which are included in total Contract Price. No. Description
Q'ty
1.
Borescope: (Manufacturer country: Japan /USA/ England) Detailed specification is as follows: Light Guide Connector: BSI/ACMI connector. Orbital Scan: 3700 Insertion Tube Outer Diameter: 10 MM Focusing Range: Model Field of View Focus range 080 100 80 mm-infinity 350 10 mm-infinity 500 5 mm-infinity Fluid Resistance: The Borescope insertion tube should withstand immersion for short periods in: Aviation, petrol and diesel fuels Synthetic and mineral based oils 1.1.1 trichloroethane. Mild salt water (5%) Water Skydrol
Temperature Range Operational Insertion tube: -200 C to 1500 C Borescope body: -200 C to 500 C Storage Complete instrument: -400 C to 700 C Pressure Range Operational Insertion tube:
0.7 to 1.7 bar absolute in air Up to 1.7 bar absolute in water
Complete instrument: 0.7 to 1.06 bar absolute in air Storage Complete instrument: .027 to 1.06 bar absolute in air Light Sources and Light Guide Cables: Light Sources: Suitable Light source with high intensity, Power source 220 V, 50 Hz, with variable light intensity. Spare bulb 2 (two) pieces with 2 (two) spare parts. Light guide cables: 2.2 meters fiber guides 2 (two) pieces. Standard Cleaning Set: The Borescopic set should have Standard Cleaning Set. Industrial Fiberscope: (Manufacturer country: Japan/ USA/ England) Specification: Optical System: Field of view, Direction of view, Depth of Field, Illumination system: 30 0, 600 ,1000 Degree convertible by means of optical adaptor,
1 (One) No. 1 (One) no.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
92
No. Description
Q'ty
Forward/side viewing convertible by means of optical adaptor. Insertion Tube: Distal End: Rigid distal end length-25.5 mm Bending section: Angualar range: UP 1200, DOWN 1200, RIGHT 1000, LEFT 1000 Flexible portion (tube): Pliability-Tapered Flex tube Max outer Dia: 11.3 mm. Working Length: 2000 mm Total Length:2250 mm Light Guide cable Length: 2000 mm Photo Documentation: Still Camera with suitable adaptor specially a digital still camera with suitable adaptor is preferred. Additional Equipment: Camera: Camera with suitable adaptor preferably a digital camera with suitable adaptor. Or a special Digital Camera with suitable adaptor Viewing adaptors: 1.600 viewing adaptor 1 (one) piece. 2.900 viewing adaptor 2 (two) pieces.
Note: The Borescopic set should have other standard accessories like rubber eyecup, objective end protective cap instruction manual (English). The above specification is furnished for reference. The industrial Fibre scope to be supplied for Generating unit.
2.
Primary Currency Injection Test Set, Manufacturer country: England, Japan, Germany/Italy/France / USA. Specification: Input: 220/240 V ac, 50 Hz, 7 KVA. Output: 0-1000 A, 0~6 V 0-2000 A, 0~3V.
1 No.
3.
Secondary Current Injection Test Set Manufacturer country: England, Japan, Germany/Italy/France / USA. Specification: Input: 220/240 V ac. 50 Hz, 1.8 KVA.
1 No.
4. Megger Manufacturer Country: England, Japan, Germany/Italy/France/USA Specification: Input: 240 V,50 Hz, 15-10-5-2.5 KV
2 nos.
5.
Digital Multimeter : (For measuring Ohms, DC/AC volt) Manufacturer Country: England, Japan, USA
2 nos.
6. Clip on Ammeter: 0-1000 A Manufacturer Country: England, Japan, USA
2 nos.
7. Special Tools (As per Art 5.3.1, 18.3.2 ) Vol. 2 of 2 special lifting and handling appliances
Note: The Contractor shall attach additional sheets as required.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
93
SCHEDULE-F
Spares & consumables during defect liability period The Contractor shall submit a list of spare parts with OEM Part No. and consumables (lube. oils, greases, air & oil filters, chemicals etc.) to be necessary for day to day operation and maintenance of the generating units and other plant equipment inclusive of emergency use that takes place in the course of operation (according to the Manufacture's recommendation and guideline) during the defect liability period (24 months). During the defect liability period of 24 months, the Contractor shall supply all necessary equipment, spare parts, materials/consumables etc. at his own cost and whether it is listed or not in their list. In preparation of the list the tenderer have to consider plant factor as 80%. During the defect liability period the Contractor have to conduct (providing all required spare parts and service) at least 1(One) CI for Gas Turbine and at least one Inspection for other equipment and any other maintenance work for force outage. 1 (one) HGPI spares is also included. Spare parts & consumables to be supplied for defect liability period under the Contract must be made available at site before start of testing.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
94
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
95
ESSENTIAL SPARE PARTS
The following spare parts list is defect liability period operation only. The Contractor have to provide all the spares required during the period whether it is listed or not. The Tenderer shall submit offer in the blank columns for item-wise essential spare parts & consumables listed below. If the items listed below do not match with the offered spares, the Tenderer must quote equivalent spare parts supported by manufacturer’s maintenance guideline. If bidder thinks that some other spares & consumables are also required in addition to the items mentioned in this schedule for 02 years of operation, bidder has to quote all those items No.
Item Quantity Unit Price
(Indicate Currency)
Total Price
(Indicate Currency
) 1. 2. 3. 4. 5. 6.
Turbine Air Inlet Filter: Self cleaning pulse type Air intake filter system comprising: a) Conical filters b) Cylindrical filter. Filter media shall be synthetic. Generator Cooling Air Filter Capital spares:
Transition Piece Nozzle (1st stage) including all hardware kits Nozzle (2nd stage) including all hardware kits Shroud (1st stage) Shroud (2nd stage) Bucket (1st stage) with Balance Chart Bucket (2nd stage) with Balance Chart Fuel Nozzle Cross-fire tube(male & female) Cap & Liner Flow Sleeve Flame Detector Scanner
Consumables for Gas Turbine
A. Filters : a. filter cartridge b. filter cartridge, 5 microns
B. Accessory Material a. Anaerobic seal ret. comp. b. Adhesive, silicon rubber c. Adhesive, silicon rubber Grease (Each box of 400gm) Generator a. Brush
a) 2 sets (2x100%) b) 2 sets (2x100%) 1 Set (1x100%)
1 Set (1x100%)
1 Set (1x100%) 1 Set (1x100%) 1 Set (1x100%) 1 Set (1x100%) 1 Set (1x100%) 1 Set (1x100%) 3 Set (3x100%) 1 Set (1X100%) 1 Set (1X100%) 1 Set (1X100%) 1 Set (1X100%) 10 pcs 100 pcs
50 pcs 50 pcs 100 pcs 20 Nos. 04 pcs
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
96
No.
Item Quantity Unit Price
(Indicate Currency)
Total Price
(Indicate Currency
) 7. 8. 9.
10. 11.
b. Brush holder c. Vibration Detector Assy. GT control system (Mark VI): Electronic cards : One spare card shall be supplied against each installed card of the Mark VI control system. i) Input Card ii) Output Card Spare Parts and Consumable Materials for Distributed Control System (DCS) The spare part materials shall include at least the following items: DCS electronic modules for signal
conditioning and control: 10% but not less than two of each type
DCS protection modules (boiler/Steam Turbine protection, generator protection) : 10% but not less than two of each type
Electrical Equipment For Excitation a. Contactor 500 VDC b. Contactor 4p, 40A, 250 VDC c. Converter 125 VDC d. Time delay relay, 1 s e. Thyristor bridge, 125 A f. Programmable Multi Transducer g. Thyrister Trigger Module h. Voltage Transformer Generator Control Panel a. Converter, b. Bi-stable relay, 125 Vdc Gas Turbine a. Contactor Thermo-couple (Exhaust
Thermocouple) b. K-type heat proof thermocouple cable
(2x1.5 sq. mm) c. Instrument Arr. Turbine
i) Thermo-couple d. Instrument Arr. Brg.
i) Vibration probe
e. Piping Arr. Control oil i) O’ Ring ii) O’ Ring iii) O’ Ring
04 pcs 1 Set (1X100%) 1 Set (1X100%) 1 Set (1X110%) 2 pcs 2 pcs 2 pcs 4 pcs 2 pcs 1 pc 1 Pc 1 Pc 2 pcs 10 pcs
4 pcs
500 meter 2pcs
2pcs
1pc
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
97
No.
Item Quantity Unit Price
(Indicate Currency)
Total Price
(Indicate Currency
)
12.
f. Thermo-couple g. Gauge Cabinet i) Pressure Switch, differ. ii) Pressure gauge
h. Lube oil Heater Arr. i) Thermostat ii) Thermostat
i. Main Filter, LO i) Cover O’ Ring ii) Filter Cartridge,5 microns
j. Poro stone element i) Pressure Regulator Valve k. Valve, Drain, Flash Start
i) Body Bonnet O’ Ring ii) Gas Contact Valve(GCV)
l. ASM Thermostatic m. Flame Detector
i) Flame Detector n. Spark Plug spring positioning
i) Spark Plug assembly ii) Ignitor Assy. Spark Plug iii) Spark Plug Lead
o. Vibration Sensor Arr.
i) Vibration Sensor ii) Vibration Sensor cable
p. Connector Thermo-couple (nozzle 2) Combustion Inspection consumables : a. Chamber Arr. combustion
i) flange ii) bolt
b. Transition piece Arr. Combustion i) TP endseal ii) locking plate
c. Piping Arr. Fuel Gas
i) gasket, spiral wound ii) bolt hex. head iii) nut self-locking
d. Spark Plug Assy.
i) gasket, spiral wound ii) bolt
1pc 1pc
12pcs
1pc 6pcs 2pcs 2pcs 2pcs 10pcs 1pc
3pcs 2pcs
1pc 10pcs 10pcs 6pcs 20 pcs 3pcs 2pcs
10pcs 42pcs 294pcs 21pcs 84pcs 84pcs 168pcs 336pcs 6pcs 6pcs
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
98
No.
Item Quantity Unit Price
(Indicate Currency)
Total Price
(Indicate Currency
) 13. 14.
11/132 KV Unit Transformer a. oil thermometer b. winding thermal indicator c. oil level indicator d. Air dryer e. Pressure relief device with contacts f. set of contactors and relays (1 of
each type) g. Fan motor h. Gasket Other electrical equipment A. 132 KV SF6 circuit breaker with 3-phase Trip & Reclose. Hydraulic & spring charge system.
i) A.C. motor ii) Opening release iii) closing release iv) anti-condensation heater v) contactor
B. Transformers a. Station Auxiliary Transformers
i) HV bushing ii) LV bushing iii) set of gaskets
C. MV-LV Distribution a. Gen. C.B. i) mechanism set (motor, pump,
aux. switches etc) ii) trip coil iii) close coil iv) Bushing CT
b. Isolated Phase Bus Duct i) Insulators ii) ethylene propylene bellow, main
bus iii) ethylene propylene bellow, Tee
off iv) Gasket for inspection door v) seal of bushing vi) copper braids vii) voltage transformer
c. MV switchboard , withdraw able i) voltage indicator ii) neon lamps iii) auxiliary contacts iv) electrical motor v) anti-pumping relay vi) trip coil
2pcs 2pcs 2pcs 2pcs 2pcs 1set 3pcs 1set 1pc 1pc 1pc 1pc 1pc
1set 1set 1pc 1pc 1pc 1pc 1set 1set 1pc 1pc 1pc 1set 1pc 1pc 1pc 1pc 1pc 1pc 1pc
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
99
No.
Item Quantity Unit Price
(Indicate Currency)
Total Price
(Indicate Currency
) 15. 16. 17.
vii) close coil viii) CB disconnecting fingers, 400 A ix) Fuses x) micro contact xi) Signalling lamps xii) MCB xiii) local/remote switch
d. Switchboard, 400 V AC a. ACB
i) mechanism set ii) CT
b. MCB (one of each type & rating) c. MCCB (one of each type & rating) e. Relay & Distribution panel
i) Ammeter ii) Voltmeter iii) lamps, 3 x Installed
F. Lighting a. lighting switchboard i) circuit breaker, incoming
ii) circuit breaker, outgoing, one each rating iii) voltmeter iv) Ammeter v) lamps, 3 x Installed vi) fuses, 3 x Installed vii) MCB one of each rating
b. External lighting accessories i) high bay luminaries, 400 W ii) flood light, 250 W iii) discharge lamp, 400 W iv) discharge lamp, 250 W v) ballast, 400 W vi) ballast, 250 W
Spare Parts for Emergency Diesel generating unit Spare parts for Gas Booster Compressor Heat Recovery Steam Generator a) Positioner for isolation/ bypass
damper b) Leaf spring seal of damper
a) Spare tube for - Superheater - Evaporator
- Economiser
1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1set 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1pc 1lot 1lot 1pc 1set 1lot
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
100
No.
Item Quantity Unit Price
(Indicate Currency)
Total Price
(Indicate Currency
) 18. 19. 20. 21.
Safety valve and relief valve Spray system, complete set of nozzles Welding rods for each type Steam Turbine
a) Sealing strips, gaskets and packing materials for all glands, labyrinths, sealing and bearing seals
b) Internal elements for each type of
special valves such as main stop valve, control valve, bypass valve
c) Filter elements for each type of filter d) Pin and spring for overspeed
governor e) Standard spares for each type of
pump
1set 1pc 1lot 1pc 1pc 1pc 1pc 1pc
NOTE: 1. The contractor shall submit the detailed spares list against Mark VIe Control System, DCS, Emergency Diesel Generator and Gas Booster Compressors according to the manufacturer's recommendation (in their official letter) during detail design approval stage. However, the detailed spares list, as would be provided by the contractor, if not acceptable to BPDB, then BPDB have the option not to take the spares and deduct the corresponding quoted amount for the same. 2. Where Quantity mentioned as 'lot/set', in that case the Tenderer have to submit the details break-up of all items/materials/equipments of the 'lot/set' including quantity & price of each. This definition is applicable for spare parts, electrical/mechanical items. Other Spares & Consumables No Item Quantity Unit
price (CIF)
Total Amount
1. Turbine Air Inlet Filter : 1 lot 2. Generator Air Filter (GT & ST) 1 lot
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
101
No Item Quantity Unit price (CIF)
Total Amount
3. Consumables A. All kind of Filters for Auxiliary systems
(Lub.oil, Fuel, pneumatic, hydraulic etc) 1 lot
B. Accessory Material a. Anaerobic seal ret. comp. b. Adhesive, silicon rubber c. Adhesive, silicon rubber
1 lot 1 lot 1 lot
4. Generator d. Brush
e. Brush holder 1 lot 1 lot
5. GT control system
Electronic cards : One spare card shall be supplied against each installed card of the control system.
1 lot
Note: For Sl. No. 6 – 10, if quantities mentioned is less than 10% of installed quantities, then 10% of installed quantities must be supplied. 6. Electrical Equipment For Excitation
i. Contactor 500 Vdc j. Contactor 4p, 40A, 250 Vdc k. Converter 125 Vdc l. Time delay relay, 1 s m. Thyristor bridge, 125 A
2 pcs 2 pcs 2 pcs 4 pcs 2 pcs
7. For Generator Control Panel
c. Converter, d. Bi-stable relay, 125 Vdc
2 pcs 10 pcs
8. For Gas Turbine a. Contactor Thermo-couple 4 pcs b. Instrument Arr. Turbine
i) Thermo-couple
2 pcs
e. Instrument Arr. Brg. i) Vibration probe
2 pcs
f. Piping Arr. Control oil iv) O’ Ring v) O’ Ring vi) O’ Ring
1 pc 1 pc 1 pc
g. Thermo-couple
12 pcs
h. Gauge Cabinet iii) Pressure Switch, differ. iv) Pressure gauge
1 pcs 6 pcs
g. Lube oil Heater Arr. i) Thermostat
ii) Thermostat
2 pcs 2 pcs
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
102
No Item Quantity Unit price (CIF)
Total Amount
h. Main Filter, LO iii) Cover O’ Ring
2 pcs
i. Poro stone element i) Pressure Regulator Valve
1 pc
j. Valve, Drain, Flash Start iii) Body Bonnet O’ Ring
3 pcs
k. ASM Thermostatic 1 pc l. Flame Detector
2 pcs
m. Spark Plug spring positioning iv) Spark Plug assembly v) Ignitor Assy. Spark Plug
1 pc 1 pc
n. Vibration Sensor Arr. iii) Vibration Sensor iv) Vibration Sensor cable
1 pc 1 pc
o. Connector Thermo-couple (nozzle 2) 10 pc
9. Combustion Inspection consumables : e. Chamber Arr. combustion
iii) flange iv) bolt
42 pcs 294 pcs
f. Transition piece Arr. Combustion iii) TP endseal iv) locking plate
21 pcs 84 pcs
g. Piping Arr. Fuel Gas iv) gasket, spiral wound v) bolt hex. head vi) nut self-locking
84 pcs 168 pcs 336 pcs
h. Spark Plug Assy. iii) gasket, spiral wound iv) bolt
6 pcs 6 pcs
10. 11/132 KV Unit Transformer h. oil thermometer
i. winding thermal indicator j. oil level indicator k. Buchholz relay l. Air dryer m. Pressure relief device with contacts n. set of contactors and relays (1 of each
type) o. Fan motor p. OLTC motor control drive, motor,
contactors, aux. relays q. protective relay for OLTC
1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc
11. Other electrical equipment a. 132 KV SF6 circuit breaker with 3-
phase Trip & Reclose. Hydraulic & spring
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
103
No Item Quantity Unit price (CIF)
Total Amount
charge system. vi) A.C. motor vii) Opening release viii) closing release ix) anti-condensation heater x) contactor xi) motor protection contactor xii) hydraulic-spring mechanism
1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc
b. Transformers A. Auxiliary Transformer
iv) HV bushing v) LV bushing vi) set of gaskets
B. Station Transformers
i) HV bushing ii) LV bushing iii) set of gaskets
1 lot 1 pc 1 pc 1 pc 2 lot 2 pc 2 pc 2 pc
f. MV-LV Distribution A. Gen. C.B. v) set of LV parts (resistors, relays,
switches, fuses etc) vi) mechanism set (motor, pump, aux.
switches etc) vii) trip coil viii) close coil ix) Bushing CT x) arcing chamber set
1 lot 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc
B. Isolated Phase Bus Duct viii) Insulators ix) ethylene propylene bellow, main
bus x) ethylene propylene bellow, Tee off xi) Gasket for inspection door xii) seal of bushing xiii) copper braids xiv) voltage transformer
1 lot 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc
C. MV switchboard , withdrawable xiv) voltage indicator xv) neon lamps xvi) auxiliary contacts xvii) electrical motor xviii) anti-pumping relay xix) trip coil xx) close coil xxi) CB disconnecting fingers,400 A xxii) Fuses xxiii) micro contact xxiv) Signalling lamps xxv) MCB xxvi) local/remote switch
1 lot 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
104
No Item Quantity Unit price (CIF)
Total Amount
1 pc
D. Switchboard, 400 V AC
d. ACB iii) mechanism set iv) CT
1 pc 1 pc
e. MCB (one of each type & rating)
1 pc
f. MCCB (one of each type & rating)
1 pc
E. Relay & Distribution panel iv) Ammeter v) Voltmeter vi) lamps, 3 x Installed
1 pc 1 pc 1 pc
F. Lighting c. lighting switchboard
i) circuit breaker, incoming ii) circuit breaker, outgoing, one
each rating iii) voltmeter iv) Ammeter v) lamps, 3 x Installed vi) fuses, 3 x Installed
vii) MCB one of each rating
1 pc 1 pc 1 pc 1 pc 1 pc 1 pc 1 pc
d. External lighting accessories vii) high bay luminaries, 400 W viii) flood light, 250 W ix) discharge lamp, 400 W x) discharge lamp, 250 W xi) ballast, 400 W xii) ballast, 250 W
1 pc 1 pc 1 pc 1 pc 1 pc 1 pc
12. Spare Parts for Emergency Diesel generating unit
1 lot (as per manufacturer’s recommendation for 02 years operation including security spares)
13. Spare parts for Gas Booster Compressor & its Auxiliaries
1 lot (as per manufacturer’s recommendation for 02 years operation including security
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
105
No Item Quantity Unit price (CIF)
Total Amount
spares) 14. Spare parts for Air Compressors 1 lot
(as per manufacturer’s recommendation for 02 years operation including security spares)
15. Spare parts for each type of pump 1 lot (as per manufacturer’s recommendation for 02 years operation including security spares)
16. Spare parts for HRSG 1 lot (as per manufacturer’s recommendation for 02 years operation including security spares)
Spare parts for ST 1 lot (as per manufacturer’s recommendation for 02 years operation including security spares)
17. Others (if required; as per OEM’S Recommendation)
Total for Other Spares & Consumables: Total Price for Schedule F
Total Price for Schedule F: ** For the items where quantity is mentioned as lot, individual items to be supplied against the lot is to be mentioned and itemwise price is to be quoted in a separate sheet.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
106
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
107
SCHEDULE – G
DEVIATIONS FROM SPECIFICATIONS
The following is a list of deviations from Tender Documents. Other than the
deviations mentioned in this list, Bidder shall confirm that their offer is in
compliance with Tender Specification. Deviations taken / mentioned in any other
pages / sections / lists etc. of their offer will not be accepted during contract
execution stage.
Clause No.
and
Page No.
Description and Reference to Documents submitted by
Tender
Note : The Tenderer shall attach additional sheets as required
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
108
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
109
SCHEDULE – H
CIVIL AND BUILDING WORKS
The Contractor shall be reminded that this is Turn-key Contract in which he is entirely responsible for every aspect. No additional costs will be considered for any item which the Contractor has overlooked, but which is essential for the proper completion of the project in every respect so that the work fulfil the purpose for which they are required.
If the Board or the Engineer requires minor modifications, additions or omissions to the scope of the Civil Works during the period of construction or maintenance, adjustment to the Contract Price will be made on the basis of the rates entered in the following Schedule. The rates entered shall include all costs and expenses involved in the proper construction of the work, including overheads, profits, supervision, accommodation, insurance, transport, duties, all risks, liabilities or obligations etc but excluding design costs, which are covered by a separate item. The rates will be used to evaluate Board’s or Engineer’s minor modifications, omissions or additions to the works. Rates for any item not included shall be based on those quoted or analogous thereto.
Item Description Unit Rate Taka
1. 2. 3. 4.
Foundation Piling 1) Mobilisation and Demobilisation
(items shall be specified) 2) Form of pile type and capacity stated :
Type : Capacity :
Excavation 1) Excavate to reduce level and remove and deposit
where directed on Site – include for timbering, de-watering, etc (measured net sizes as drawing)
2) Excavate to form pit , base or trench as previously described.
3) Additional excavation beyond net sizes for working space to fix and remove formwork and to backfill
Concrete work Un-reinforced ( grade of concrete shall be specified ) ------------------------------------------------ ------------------------------------------------ ------------------------------------------------ Reinforced Concrete ( grade of concrete shall be specified ) ------------------------------------------------
linear, m m3
m3
m3
m3 m3 m3
m3
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
110
5. 6. 7.
----------------------------------------------- ----------------------------------------------- Reinforcement 1) 16 mm diameter and upward mild steel bar or round
reinforcement hooked, bent and fixed including and necessary tying wire
2) 12 mm diameter as previously described 3) 10 mm diameter and ditto as previously described 4) Fabric reinforced weighing 4 Kg per square meter,
including fixing 5) Extra over mild steel rates for high tensile
reinforcement (all sizes) Formwork
1) To sides of foundations, bases, etc 2) To sides and soffits of beam 3) To wall
Structural Steelwork (grades of structure shall be specified) --------------------------------------------- ---------------------------------------------
m3
m3
Kg Kg Kg m2 Kg m2
m2
m2
1000x Kg
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
111
SCHEDULE - I
LIST OF SUBCONTRACTORS
The following is a list of subcontractors the Contractor proposes to employ for supply of materials and equipment and for erection and civil works
No. Description of part or equipment making reference to specifications
Subcontractors full address
1 Steam Turbine 2 Steam Turbine Generator 3. HRSG 4. Transformers 5. Condenser 6. Boiler Feed Pump 7. CW Pump 8. Distributed Control System (DCS) 9. Control & Protection Equipment 10. Condensate Extraction Pump 11. Condenser Vacuum Pump 12. Generator Switchgear 13. 132kV Circuit Breaker 132 kV Isolator 14. 132kV instrument Transformer
132kV Current Transformer 132kV Voltage, Transformer
15. 132kV Lightning Arrester 16. Insulators 17. Air Compressor 18. MV & LV Equipment of Electrical 6.6 kV
Switchgear 415V PC & MCC
19. 220/110/125V Battery & Charger 20. Lighting 21. Power Cable Control Cable 22. Communication Equipment 23. Fire Protection Equipment 24. Crane
Note : The Tenderer shall attach additional sheets as required
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
112
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
113
SCHEDULE - J DESCRIPTION OF TRAINING PROGRAMME
(1) Foreign Training (As Per Development Project Proposal) The total person-months for 10 Engineers from BPDB for training will be limited
to 10 (Ten) at manufacturer's factory in the following manner: Training for Operation & Maintenance: i) Training on operation & maintenance of power plant equipment, orientation &
technology transfer: a) Executive Engineer- 2Nos. x 1 months = 2 pm [Overall operation of the power plant-1, Overall Maintenance of the power plant -1] c) SDE/AE- 6 Nos.x 1 months = 6 pm [Overall operation of the Power Plant-2, Mechanical maintenance-1, Electrical
Maintenance-1, Fuel System-1(Gas Booster), I&C including DCS system maintenance-1,]
d) Sub-Assistant Engineer-02 Nos.x 1 months = 02 pm [Overall operation of the Power Plant-1, Overall maintenance of the Power Plant -1] Travelling Charges = 10 Nos. All living expenses (including US $ 100 pocket allowances per day per person),
transport expenses of the trainees to and from Bangladesh to the country of Manufacturer's factory and during the period of training including incidental expenses or medical expenses or Medical Insurance from time to time will be covered by the Contractor. The Contractor must indicate in technical offer the practical arrangements he is offering for ensuring the training, as well as the methodology used.
The Contractor will provide all maintenance and operation manual, drawings
relating to all the equipment to each trainee on the first day of his arrival at the Contractor's Works.
(2) Training at the Site for O & M Training at site for O & M Personnel
a) Executive Engineer: 2 nos b) SDE/AE/Chemist: 10 nos. c) Sub-Assistant Engineer: 4 nos. d) Technician: 24 nos.
The BPDB shall make available, free of cost, to the Contractor the above
mentioned personnel (total 40 nos) for the purpose of on-the-job training at site during installation, testing, commissioning and initial operation of the plant for two (2) month. During defect liability period, it shall be the responsibility of the Contractor to train them adequately and properly in a planned manner so that these member of the Board's staff could take over the responsibility of operation and maintenance of the plant and equipment independenly at the time of handing over of such plant and equipment as well as before issuing of FAC.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
114
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
115
SCHEDULE - K
MOBILISATION AND DEMOBILISATION SCHEDULE FOR CONSTRUCTION EQUIPMENT
The following is the specification, numbers, purpose of use and phasing for the
mobilisation and demobilisation of construction equipment to be used on the Contract.
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
116
Volume 3 of 3 – Schedules ___________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________
LOT-2: Conversion of 2X35 MW Shahjibazar Gas Turbine Power Plant to 105 MW Combined Cycle Power Plant Procurement of Plan December 2016 Single – Stage: Two- Envelope
117
SCHEDULE - L
METHOD OF TRANSPORTATION AND UNLOADING
The following is a description of the Contractor’s method for transportation to Site and
unloading and installation at Site of the equipment for the Works.