Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
Transcript of Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
1/13
Progress Report to NCIS-WG
October 30, 2012
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
2/13
Minor Route Amendments > Major Impact
2
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
3/13
Backbone Route Changes Add Value
Hudsons Bay East Shore route facilitates landings in Nunavik
Hudsons Bay East Shore route facilitates eventual mesh ring with Kivalliq spur at
Arviat
Hudsons Bay East Shore route facilitates eventual fibre connection to Sanikiluaq at
cost ~$8 million
Hudsons Bay East Shore route extends Eeyou Network reach to Whapmagoostuui
and Kuujjuarapik Second Canadian international gateway created from Montreal hub to Europe
Revised routing reduces subsea network build by ~ 580 km - capex reduced
Tokyo-New York City distance lowered by ~2,300 km
Arctic Fibre latency < 137 milliseconds (RTD) fastest route between Tokyo & NYC
Greater international traffic creates domestic economies of scale
3
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
4/13
Over the Top Telecommunications
Estimated Arctic Fibre Latency (Milliseconds-RTD)@100G
Boston NYC Montreal Toronto Chicago London Frankfurt
Shanghai 178 170 162 171 179 192 201
Seoul 163 155 147 154 164 172 181
Tokyo 145 137 129 136 146 159 168
Hong Kong 195 187 179 186 197 209 218
Least Latent Alternative Carrier (Advertised and Inservice)
Boston NYC Montreal Toronto Chicago London Frankfurt
4
Shanghai 181 174 200 171 161 212 199Seoul 166 159 185 156 146 202 200
Tokyo 148 141 167 138 128 189 187
Hong Kong 197 192 197 188 176 215 224
Arctic Fibre Advantage (Disadvantage)
Boston NYC Montreal Toronto Chicago London FrankfurtShanghai 3 4 38 0 -18 20 -2
Seoul 3 4 38 2 -18 30 19
Tokyo 3 4 38 2 -18 30 19
Hong Kong 2 5 18 2 -21 6 6
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
5/13
Progress Regulatory and Permitting
Formal application for landing licence filed with Industry Canada on October 2, 2012
Application amended this week to enable Hudsons Bay landing alternatives near Chisasibi
and Moosonee Permit Coordination underway with CanNor, Nunavut Impact Review Board, Industry Canada
WFN Strategies completed Desk Top Study on original route Tokyo-London in July and
amendments this week ice issues manageable
Landing permit process in Japan and United Kingdom underway
5
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
6/13
Progress Technical Network Backbone
Decision made to utilize 100G technology over four fibre pairs = 32 Terabits system capacity
Formal request for turnkey proposal issued August 2012 to TE Subcom and Alcatel/Lucent
Revised RFP amendments will delay submissions until end of November
Discussions underway with various entities on terrestrial fibre builds, swaps and dark fibre
leases in Ontario and Quebec
Marine surveys will commence in 2013Q2 and continue through October 2013
erres r a c v wor s o e un er a en n pr or o mar ne opera ons n
Nearshore landing alternatives identified in DTS
Partnering with existing telcos in most Arctic communities for collocation
Cambridge Bay CLS alternatives being evaluated
Arctic Fibre will sponsor Inuktitut-language internet portal in Iqaluit
RFS date of November 2014
6
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
7/13
Technical Microwave Extensions
Arctic Fibre collaborated with WireIE to engineer microwave extensions from backbone CLS
Each community will receive minimum 50 Mbps with low-cost upgrades available to 1Gbps
Hybrid fibre optic microwave network reaches ~96.5% of Nunavut population at capital costof $9 million (inc. power) over and above Nunavut fibre spur cost of $111 million.
Communities served by microwave:
Kimmurut, Baker Lake, Whale Cove, Kugarruk, Repulse Bay, Arctic Bay
es ua sa e e- epen en commun es:
Resolute Bay, Grise Fiord, Sanikiluaq (combined population 1,233)
Sanikiluaq (population 850) could be fibred off Hudsons Bay backbone for ~$8 million
Fibre-microwave outlay of $128 million leaves only 343 Nunavut residents (1%) on satellite
Virtually unlimited (100Gbps) fibre capacity inc. 1 Gbps microwave links for $128 million
Satellite with limited 3Gbps capacity costs $300 million and has shorter lifespan
7
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
8/13
Progress - Marketing
Domestic Open Season Capacity Nomination Process concluded successfully with seven
entities participating
Three other entities still in negotiations based upon specific technical requirements Tuktoyaktuk spur dropped due to lack of demand > potential terrestrial fibre
Assurances received from Nunavut Government on migration to fibre as satellite contracts
expire in 2015-16 working toward MOU
secondary spurs and microwave extensions based upon revised routing. Immediate requirement for Federal/provincial/territorial upfront commitment by year end
on 11 backbone underwater branching units for secondary spurs retroactive installation
impossible
Immediate requirement for other NCIS-WG connection requirements to be identified
Canadian carriers enthusiastic about prospect of second network connection to Europe American carriers and HFTNs enthusiastic about Asia-NYC low latency improvement
International carrier negotiations concluding at PTC in January 2013
8
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
9/13
Progress - Financial
Financial models being revised to reflect route changes > increased demand > lower costs
Strong investor interest from financial institutions and foreign carriers ownership likely a
hybrid carrier consortium + institutional investor model
9
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
10/13
Progress Corporate Resources
Arctic Fibre has recently hired North American carrier sales staff
Potential marketing partnership with major carrier collocation entity
Arctic Fibre has engaged former Iqaluit Mayor Madeleine Redfern to assist with Nunavutpermitting issues
Search for in-house legal counsel underway
Bennett Jones acts as regulatory counsel in Ottawa
10
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
11/13
Required Steps NCIS-WG
1. Ensure Shared Services Canada is fully aware of your Departments short-term and longer-
term bandwidth requirements having taken price-elasticity into effect
2. Ensure Shared Services Canada and Arctic Fibre are aware of your High Arctic requirementswhich might require additional underwater branching units
3. Ensure Shared Services Canada and Arctic Fibre are aware of subsea sensor requirements/
locations on an immediate basis for engineering purposes
11
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
12/13
Cable Ships in the Arctic
12
-
7/31/2019 Arctic Fibre Progress Report to NCIS-WG Oct 31, 2012
13/13