April 2016 Coffee with Alaska LNG – Kenai/Nikiski 2016 G&G...
Transcript of April 2016 Coffee with Alaska LNG – Kenai/Nikiski 2016 G&G...
April 2016
Coffee with Alaska LNG – Kenai/Nikiski 2016 G&G Field Program
1
Alaska LNG – Project Overview
- 2 -
- 3 -
Project Development Phases
GO
OPE
RAT
E
Concept Selection
Investigate
Decision to Build the
Project Decision Decision GO GO
1-2 years 2-3 years 5-6 years
Design Construct
WE ARE HERE
LNG Plant Overview
- 4 -
Temporary Material Offloading Facility LNGC Berths
Trestle
Admin Building
Power Generation Ground
Flare
Utilities
LNG Train 1
LNG Tanks
Laydown Area
Utilities Inlet
Treating
Refrig Storage
BOG Fractionation
LNG Train 2
North
2016 G&G Field Program - Marine
Purpose of surveys: • Collect data for design and route selection of
proposed subsea natural gas pipeline across Upper Cook Inlet and proposed marine facilities near Nikiski
Objectives: • Characterize the bottom surface and subsurface
of Cook Inlet, evaluate seabed features, and identify soil conditions within the survey area
Survey Methods/Equipment: Geophysical
• Seafloor mapping • Chirp, Sub-bottom profiler & single beam
bathymetry Shallow Geotechnical
• Grab samples • Vibracores
Timing: April – June/July
- 5 -
2016 G&G Field Program - Onshore
Purpose of surveys: • Collect data for design and
equipment placement of proposed LNG facility near Nikiski
• Test groundwater capability Survey Methods/Equipment: Geotechnical
• ~50 boreholes • Aquifer pump test
Environmental
• Cultural/archaeological surveys continue
Timing:
April – Aug/Sept
- 6 -
- 7 -
Questions and Discussion