91 PROJECT UPDATE Riverside County Transportation Commission Anne Mayer, Executive Director Corona City Council April 20, 2016

Transcript of April 20, 2016 City Council 91 Project Update

Page 1: April 20, 2016 City Council 91 Project Update

91 PROJECT UPDATE Riverside County Transportation Commission

Anne Mayer, Executive Director

Corona City CouncilApril 20, 2016

Page 2: April 20, 2016 City Council 91 Project Update

Upcoming ConstructionRIVERSIDE COUNTY TRANSPORTATION COMMISSION

• Turn lane for southbound Main Street motorists turning onto westbound on-ramp – open April 21

• Full closure of eastbound 91, night of May 3, to place overhead signs, similar to last night’s closure

• Serfas Club undercrossing to be closed nightly for falsework installation, April 20 to May 4, Mon-Sat, 10 pm to 5 am. No pedestrian access

All dates/times estimated and subject to change

Page 3: April 20, 2016 City Council 91 Project Update

Upcoming ConstructionRIVERSIDE COUNTY TRANSPORTATION COMMISSION

• Full closure of E. Grand Blvd., April 21 and 22, 9 pm to 5 am both nights, to remove falsework. Full closure to occur May 2-8; roadway to reopen May 9

• Full closures of 91, three nights eastbound, three nights westbound, for Maple Bridge falsework placement, first two weeks in May

• Westbound Serfas Club off-ramp to be closed two months, starting in late May

All dates/times estimated and subject to change

Page 4: April 20, 2016 City Council 91 Project Update

On-Ramps, Off-RampsRIVERSIDE COUNTY TRANSPORTATION COMMISSION

Estimate that: • 1/3 of ramps to be completed by end of spring• 1/3 of ramps to be

completed by end of summer

• 1/3 of ramps to be completed by end of year

All dates/times estimated and subject to change

Page 5: April 20, 2016 City Council 91 Project Update

Ramp/Street Completion StatusRIVERSIDE COUNTY TRANSPORTATION COMMISSION

Available on website: http://www.sr91project.info/design-build-schedule

Page 6: April 20, 2016 City Council 91 Project Update

Lincoln AvenueRIVERSIDE COUNTY TRANSPORTATION COMMISSION

• Utilities to be complete in early May • Reducing Lincoln roadway to widen bridge, following

three May activities: • New eastbound Lincoln on-ramp from Second St. to open

• New eastbound Main Street on-ramp to open

• Main Street westbound on-ramp returns to three lanes

All dates/times estimated and subject to change

Page 7: April 20, 2016 City Council 91 Project Update

Maple Street BridgeRIVERSIDE COUNTY TRANSPORTATION COMMISSION

• Maple Street bridge continuing as two northbound lanes until summer

• Westbound Maple Street flyover on-ramp to be completed in July

• Maple Street bridge to close for rest of year

All dates/times estimated and subject to change

Page 8: April 20, 2016 City Council 91 Project Update

Tolled Express LanesRIVERSIDE COUNTY TRANSPORTATION COMMISSION

• FasTrak tolling signs being installed on 91, 15• Signs to be covered until ready for use• Reminder: 3+ carpools with transponder can use

FasTrak lanes for free, except for eastbound 91, Mon-Fri, 4-6 pm, when fares are half-price

• Policies to be consistent with OCTA 91 Express Lanes

Page 9: April 20, 2016 City Council 91 Project Update

Tolled Express Lanes

• Toll Utility Buildings (TUBs) being placed in median for enforcement

• Major milestone last week with turnover of electronic tolling system

RIVERSIDE COUNTY TRANSPORTATION COMMISSION

Page 10: April 20, 2016 City Council 91 Project Update

Safety: RCTC’s Top Priority

• Slow down! Watch for workers and equipment• Allow extra time• Be extra careful at night or in the rain• Watch for changing conditions• Use alternate routes; follow detours• Avoid lane splitting by motorcyclists• Traffic fines are doubled in

construction zones

RIVERSIDE COUNTY TRANSPORTATION COMMISSION

Page 11: April 20, 2016 City Council 91 Project Update