Approved Contractor Corporate Induction
Transcript of Approved Contractor Corporate Induction
Approved Contractor
Corporate Induction
Coorong District Council is committed to achieving a high
level of pro-active Work Health and Safety (WHS)
management during the application of contracts.
To facilitate this Coorong District Council is dedicated to a
contractor management system which provides for the
selection of contractors with appropriate safety controls, the
exchange of information between Coorong District Council
and its Contractors to facilitate the identification of hazards,
risk management, and the appropriate monitoring of the
contractors engaged by Council.
Approved Contractor
Corporate Induction
2
Work Health Safety
Act 2012
3
The Work Health and Safety Act and Regulations 2012
came into effect on 1 January 2013.
PCBU – Person Conducting a Business or Undertaking
Under the act both Council and the Contractor are classified
as PCBU’s.
In regards to Contractor Management both the Council and
the Contractor are defined as a PCBU and have the same
responsibilities under the WHS Act 2012.
Contractor
Responsibilities
4
Contractors working at any Council work site must place
health and safety at the centre of their work and ensure
that they do not create risks for themselves or any
workers.
They must meet all requirements of relevant WHS
legislation, codes of practice and standards and must
include the process of hazard identification, risk
assessment and control in their work planning.
Council Contractor
Management Policy
5
Policy Objective To achieve high level of pro-active WHS management during its application of
contracts by;
Utilising Contractors who can demonstrate WHS management system
capability; and
Achieving specific WHS issues focus, to optimise safety management for the
workforce contracted by Council
Key Elements
A defined process for the selection of Contractors with appropriate WHS
Controls;
Communication process with Contractors to ensure hazards are identified and
controlled; and
Appropriate monitoring by Council of WHS systems/work practices undertaken
by Contractors to confirm safe systems are followed.
Council’s Approved
Contractor Program
6
In order for Council to execute the principles of the
Contractor Management Policy, the Approved Contractor
Program has been developed.
The Approved Contractor Program is designed to ensure
compliance with the Work Health and Safety Act 2012 and
the Performance Standards for Self Insurers.
Approved Contractor
Eligibility
7
Approved Contractors are required to provide: proof of public liability insurance – minimum $20M;
identification of a person within the organisation responsible for
safety;
copy of current relevant licences and certifications;
Job Safety Analysis’ (JSA), risk assessments or safe work method
statements (SWMS) for the activities to be undertaken by the
Contractor;
proof of current workers compensation authority registration
(if applicable);
proof of Professional Indemnity coverage (if applicable); and
evidence of WHS policies and procedures that comply with
Council’s minimum standards.
Approved Contractor
Program Process
8
Documentation provided meets Council requirements.
Contractor placed on Approved Register.
Council Contractor Selection process.
Review safety requirements specific to the contract.
Site induction.
Monitoring of contract by Contract Manager.
Review of Contractor performance.
Subcontractors
9
Where a Principal Contractor utilises a sub contractor, it is
the Principal Contractor’s responsibility to ensure:
selected subcontractor has safe systems of work;
all workers are inducted into the work site; and
identified hazards and control measures outlined.
General Safety Expectations
10
All Contractors, their workers, sub contractors and their
workers must abide by the following
Hazard and Incident Reporting
Whilst performing work for Council all hazards and incidents must be
reported to your Council contact AS SOON AS POSSIBLE, but no later than
24 hours after the event.
Incidents include any near miss, accident, damage or injury.
UV Procedure For effective protection against UV Radiation, workers engaged in outdoor work
are to adopt the following, at a minimum:
A broad brimmed hat or legionnaires style cap;
Long sleeve shirts and long trousers;
Water resistant sunscreen, with a 30+ sun protection factor, to be applied at
least two hourly on exposed parts of the body; and
Sun glasses with UV absorbing lenses.
General Safety Expectations
11
All Contractors, their workers, sub contractors and their
workers must abide by the following
Personal Protective Equipment (PPE)
Contractors are responsible for ensuring appropriate PPE for all
workers. They are also responsible for ensuring that any site visitors
are wearing appropriate PPE.
At a minimum, the following is expected:
safety footwear;
high visibility vest;
long pants/long sleeved top wide brimmed hat (as outlined in UV
procedure);
hard hat – where overhead works are undertaken; and
safety gloves, glasses, gloves, hearing protection, fall
prevention/arrest systems where required.
General Safety Expectations
12
All Contractors, their workers, sub contractors and their
workers must abide by the following
First aid
It is the contractor’s responsibility to ensure that they
have adequate first aid facilities available.
White Card
All “outdoor” Contractors must ensure that workers have
undertaken the six hour Construction General Induction
Training – know as “WHITE CARD” (previously known
as “green”, “red” or “blue” card).
General Safety Expectations
13
All Contractors, their workers, sub contractors and their
workers must abide by the following
Licences, Qualifications and Competencies
The contractor shall only utilise such persons or sub
contractors who are careful, skilled and experienced in
their respective trades and professions.
The contractor must establish and maintain procedures
for identifying the training needs and provide training to
all workers.
Approved contractors must supply all documentation and
copies of licences/certificates of competency, insurances
etc, on an annual basis.
General Safety Expectations
14
All Contractors, their workers, sub contractors and their
workers must abide by the following
Plant Safety
All plant must be appropriately licensed or registered
and there are systems in place for maintenance and
inspection.
Portable Electrical Equipment
All must be tested and tagged in accordance with
AS:NZ3760:2010 prior to being brought onto or used at
any Council site.
General Safety Expectations
15
All Contractors, their workers, sub contractors and their
workers must abide by the following
Chemicals and Substances All chemicals must be stored and handled in appropriately marked
containers, with appropriate documentation.
Current Safety Data Sheets (SDS) and appropriate DOCUMENTED
risk assessments must be held for all chemicals used on site and
made available if requested.
Contractor must advise Council Contract Manager of any hazards
associated with the chemical being used.
Appropriate PPE worn and first aid provisions made.
General Safety Expectations
16
All Contractors, their workers, sub contractors and their
workers must abide by the following
Working at Heights Where there is a requirement to work at heights, Contractors
must comply with the WHS Act and Regulations, Part 4,
Regulation 78 Management of Risk of Fall.
Confined Spaces Coorong District Council maintains a Confined Space
Register and has in place a Confined Spaces Management
Procedure. All confined space work must be undertaken in
accordance with the WHS regulation, code of practice and
Council’s procedures.
General Safety Expectations
17
All Contractors, their workers, sub contractors and their
workers must abide by the following
Asbestos Councils maintain asbestos registers for all Council owned
buildings. If work relates to an area identified as having
asbestos the Contract Manager will advise the Contractor
and make the information in the asbestos register available.
If a Contractor accidently encounters asbestos on site, they
must inform the Contract Manager immediately.
Excavation and Trenching For all excavation, trenching, digging, post driving, drilling
etc, the Contractor must telephone “Dial before you dig”
(1100).
General Safety Expectations
18
All Contractors, their workers, sub contractors and their
workers must abide by the following
Hot Work Hot work is defined as any grinding, welding, thermal or
oxygen cutting or heating, and other related heat or spark
producing operations. A risk assessment must be
undertaken prior to the commencement of hot work.
Remote work If any subcontractor or employee of a contractor works
alone, the contractor’s supervisor is responsible for
ensuring that appropriate precautions are included in the
risk assessment or Job Safety Analysis.
General Safety Expectations
19
All Contractors, their workers, sub contractors and their
workers must abide by the following
Traffic management
Any required traffic management carried out by the
contractor will be in accordance with Australian Standards
and be carried out by qualified staff only and in line with
Council’s Work Zone Traffic Management procedure.
Conduct of Contractors on
Council Sites
20
Council does not tolerate any form of offensive behaviour,
particularly harassment, bullying, discrimination, and vilification.
Contractors are responsible for ensuring that they, their
employees, their subcontractors and their employees do not
harass, vilify or discriminate against any person on any basis.
Council will enforce on contractors the standards of health and
safety it considers necessary, as it would for its own staff.
Conduct of Contractors on
Council Sites
21
Contractors must place health and safety at the centre
of their work.
Contractors must meet all requirements of relevant
health and safety legislation, risk assessment and
control in their work planning.
Contractors are expected to act promptly to address any
evidence or report of inappropriate behaviour on any
Council worksite.
Site Induction
Council & the Contractor
22
The Council is responsible for conducting a Site
Induction for the Principal Contractor prior to the
commencement of work. It is then the Principal
Contractor’s responsibility to ensure that all workers
are inducted into the work site.
NOTE: Where the Contract Manager deems a site induction is
not reasonably practicable due to the location, duration or
frequency of the contract works, the Contract Manager may
arrange to advise the contractor of the know hazards through a
different method, by telephone, fax or email.
Site Induction
Council & the Contractor
23
The Contractor will be inducted into the work site and
provided with the following information:
• how to access Council contact;
• daily start/finish times;
• access to work area/any restricted access;
• known hazards;
• amenities;
• emergency equipment and assembly points;
• environmental cleanup; and
• no children on site
Interaction with vulnerable
people
24
Should the nature of the contracted work necessitate
interaction with indentified vulnerable people (i.e. aged,
children, disabled) the Contractor shall ensure that they or
their employee’s have required police clearances, and that
evidence of this is provided to Council contact. This is in
accordance with Council’s Safe Environment Policy.
Hazard Management Core Principals
25
Councils are committed to eliminating or minimising
hazards in the workplace.
Core Principals of Hazard Management are to:
identify
assess
control
monitor
Contractors must effectively control all hazards which are
identified and/or arise from the course of their work.
Hazard Management Core Principals
26
When awarding contracts the Council will ensure that the
Contractor chosen can effectively address the identified
hazards and suggested controls.
The identified hazards and controls will be monitored
throughout the contract.
Hazard Management Job Safety Analysis (JSA) /
Safe Work Method Statement (SWMS)
27
A JSA/SWMS must be undertaken for all contract work
that involves:
electrical work
fall risks or falling objects
hot work
remote or isolated work
hazardous manual tasks
demolition
excavation
confined space work
Hazard Management Job Safety Analysis (JSA) /
Safe Work Method Statement (SWMS)
28
JSA/SWMS are completed at the time of the job being
undertaken. This should address any hazards identified
by the Council prior to the commencement of work.
The information contained in the JSA/SWMS must be
communicated to all workers and be signed off
accordingly.
A copy of this document should be forwarded to Council
and shall be made available to view by the Contract
Manager during the works.
Hazard Management Safe Work Procedures
29
Contractors should have documented Safe Work
Procedures for routine tasks. These documents should
be made available to the Contract Manager when
requested.
These documents should form part of the Contractor’s
work health and safety management system.
Monitoring/Inspection
30
The Contract Manager will monitor the Contract and
retains the right to inspect safety measures and if
necessary, interrupt work if safety standards are
considered insufficient.
The frequency of inspections will be determined by, but
not limited to the level of risk, complexity and the
duration of the contract.
Monitoring will be documented.
Council reserves the right to reject the work systems
proposed if the hazards are not eliminated or
adequately controlled.
Monitoring/Inspection
31
Monitoring will be undertaken on:
hazards which have been identified for the Contract
control measure identified and implemented
availability of risk assessments/job safety analysis/safe
work method statements
reporting processes
legislative compliance
housekeeping
non-compliances
any corrective and preventative actions identified.
WHS non-compliance
32
If, during the performance of the works under the Contract,
the Superintendent informs the contractor that it is his
opinion that the Contractor is not conducting the work in a
safe manner and within the agreed risk assessment
processes, procedures or legislation, Council may:
direct the contractor to suspend works until all issues
are resolved to Council’s satisfaction (costs incurred
will be the contractor’s responsibility including the right
for council to claim any costs);
WHS non-compliance
33
terminate the contract and seek damages for consistent
breaches or substantial breaches of WHS practices;
remove the Contractor from the Council’s Approved
Contractor Register;
report the Contractor to Safe Work SA.
Woohoo you made it!
34
Congratulations!! You have completed the Coorong District
Council Approved Contractor Corporate Induction. Please
return the completed induction questionnaires and
induction contractor sign off by:
post to Coorong District Council, PO Box 399, Tailem
Bend, SA 5260;
via email [email protected]
fax 08 8572 3822; or
in person at any Council office