Application of the Fault Tree Analysis for Assessment of Power System Reliability

12
Application of the fault tree analysis for assessment of power system reliability Andrija Volkanovski , Marko C ˇ epin, Borut Mavko Reactor Engineering Division, Joz ˇef Stefan Institute, Jamova 39, 1000 Ljubljana, Slovenia article info Article history: Received 14 November 2007 Received in revised form 22 August 2008 Accepted 15 January 2009 Available online 30 January 2009 Keywords: Fault tree Safety Reliability Power system abstract A new method for power system reliability analysis using the fault tree analysis approach is developed. The method is based on fault trees generated for each load point of the power system. The fault trees are related to disruption of energy delivery from generators to the specific load points. Quantitative evaluation of the fault trees, which represents a standpoint for assessment of reliability of power delivery, enables identification of the most important elements in the power system. The algorithm of the computer code, which facilitates the application of the method, has been applied to the IEEE test system. The power system reliability was assessed and the main contributors to power system reliability have been identified, both qualitatively and quantitatively. Crown Copyright & 2009 Published by Elsevier Ltd. All rights reserved. 1. Introduction The power systems are usually large, complex and, in many ways, nonlinear systems. They include subsystems and compo- nents such as generators, switching substations, power lines and loads. Switching substations include buses, transformers, circuit breakers and disconnect switches. The evaluation of the overall system reliability is extremely complex as it is necessary to include detailed modeling of both generation and transmission facilities and their auxiliary elements. A failure of components or subsystems can result in a failure of power delivery to specific loads or in certain cases in a full blackout of the power system. The purpose of this paper is to develop a new method for power system reliability analysis, because several blackouts have been reported recently [1,2]. The need for analysis of power system reliability additionally emerges from the aspect of the consequent terrorist threats on major infrastructures including the power systems [3]. 1.1. State of the art of power system reliability analysis Most of the approaches for determination of power system reliability use approximation or simplification of the problem in order to degrade the problem on a solvable level. The quasi- transient approach [4] and examination of cascading failure using the linear programming [5] method were proposed assuming only single components failure and identification of only one critical point in the system, excluding the probability of failure of components. Evaluation of system reliability concerning only the generation facilities and their adequacy to satisfy load using heuristic methodology was proposed, but this methodology does not include transmission in the analysis [6]. The minimal cut set and the frequency duration method are used for the planning and design of industrial and commercial electric power distribution systems and their reliability evalua- tion, but the whole methodology considers only lines and transformers and is applicable only to small systems [7–9]. The minimal cut-set method of evaluating load-point reliability indices is proposed but it accounts for only topology of the network [10]. Screening methodology for the identification and ranking of infrastructure vulnerabilities, including a small power system, due to terrorism based on a minimal cut-set approach and event tree method was proposed [11,12], and also needing conditional success rate estimation. A method for assessing and improving the vulnerabilities of electric power transmission grids, based on load-flow algorithm using direct current (DC) power flow, is proposed but it accounts for only power grid reliability [13]. An application of Monte Carlo network analysis for reliability assessment of multiple infrastructures, including power system, for terrorist actions [14] is proposed, but this method is inadequate when infrastructures are analyzed individually. Ap- plication of the sum-of-disjoint products technique for evaluating stochastic network reliability is proposed [15] with the simplifica- tion of the problem considering only one path between source and sink nodes and assuming that each node is perfectly reliable. A hybrid model that includes both power system dynamic ARTICLE IN PRESS Contents lists available at ScienceDirect journal homepage: www.elsevier.com/locate/ress Reliability Engineering and System Safety 0951-8320/$ - see front matter Crown Copyright & 2009 Published by Elsevier Ltd. All rights reserved. doi:10.1016/j.ress.2009.01.004 Corresponding author. E-mail address: [email protected] (A. Volkanovski). Reliability Engineering and System Safety 94 (2009) 1116–1127

description

Reliability, Fault Tree Analysis

Transcript of Application of the Fault Tree Analysis for Assessment of Power System Reliability

  • ARTICLE IN PRESS

    Reliability Engineering and System Safety 94 (2009) 11161127Contents lists available at ScienceDirectReliability Engineering and System Safety0951-83

    doi:10.1

    CorrE-mjournal homepage: www.elsevier.com/locate/ressApplication of the fault tree analysis for assessment of powersystem reliabilityAndrija Volkanovski, Marko Cepin, Borut Mavko

    Reactor Engineering Division, Jozef Stefan Institute, Jamova 39, 1000 Ljubljana, Sloveniaa r t i c l e i n f o

    Article history:

    Received 14 November 2007

    Received in revised form

    22 August 2008

    Accepted 15 January 2009Available online 30 January 2009

    Keywords:

    Fault tree

    Safety

    Reliability

    Power system20/$ - see front matter Crown Copyright & 20

    016/j.ress.2009.01.004

    esponding author.

    ail address: [email protected] (A. Volka b s t r a c t

    A new method for power system reliability analysis using the fault tree analysis approach is developed.

    The method is based on fault trees generated for each load point of the power system. The fault trees are

    related to disruption of energy delivery from generators to the specific load points. Quantitative

    evaluation of the fault trees, which represents a standpoint for assessment of reliability of power

    delivery, enables identification of the most important elements in the power system. The algorithm of

    the computer code, which facilitates the application of the method, has been applied to the IEEE test

    system. The power system reliability was assessed and the main contributors to power system

    reliability have been identified, both qualitatively and quantitatively.

    Crown Copyright & 2009 Published by Elsevier Ltd. All rights reserved.1. Introduction

    The power systems are usually large, complex and, in manyways, nonlinear systems. They include subsystems and compo-nents such as generators, switching substations, power lines andloads. Switching substations include buses, transformers, circuitbreakers and disconnect switches. The evaluation of the overallsystem reliability is extremely complex as it is necessary toinclude detailed modeling of both generation and transmissionfacilities and their auxiliary elements. A failure of components orsubsystems can result in a failure of power delivery to specificloads or in certain cases in a full blackout of the power system.

    The purpose of this paper is to develop a new method forpower system reliability analysis, because several blackouts havebeen reported recently [1,2]. The need for analysis of powersystem reliability additionally emerges from the aspect of theconsequent terrorist threats on major infrastructures includingthe power systems [3].1.1. State of the art of power system reliability analysis

    Most of the approaches for determination of power systemreliability use approximation or simplification of the problem inorder to degrade the problem on a solvable level. The quasi-transient approach [4] and examination of cascading failure usingthe linear programming [5] method were proposed assuming only09 Published by Elsevier Ltd. All

    anovski).single components failure and identification of only one criticalpoint in the system, excluding the probability of failure ofcomponents. Evaluation of system reliability concerning only thegeneration facilities and their adequacy to satisfy load usingheuristic methodology was proposed, but this methodology doesnot include transmission in the analysis [6].

    The minimal cut set and the frequency duration method areused for the planning and design of industrial and commercialelectric power distribution systems and their reliability evalua-tion, but the whole methodology considers only lines andtransformers and is applicable only to small systems [79]. Theminimal cut-set method of evaluating load-point reliabilityindices is proposed but it accounts for only topology of thenetwork [10]. Screening methodology for the identification andranking of infrastructure vulnerabilities, including a small powersystem, due to terrorism based on a minimal cut-set approach andevent tree method was proposed [11,12], and also needingconditional success rate estimation. A method for assessing andimproving the vulnerabilities of electric power transmission grids,based on load-flow algorithm using direct current (DC) powerflow, is proposed but it accounts for only power grid reliability[13]. An application of Monte Carlo network analysis for reliabilityassessment of multiple infrastructures, including power system,for terrorist actions [14] is proposed, but this method isinadequate when infrastructures are analyzed individually. Ap-plication of the sum-of-disjoint products technique for evaluatingstochastic network reliability is proposed [15] with the simplifica-tion of the problem considering only one path between sourceand sink nodes and assuming that each node is perfectly reliable.A hybrid model that includes both power system dynamicrights reserved.

    www.sciencedirect.com/science/journal/resswww.elsevier.com/locate/ressdx.doi.org/10.1016/j.ress.2009.01.004mailto:[email protected]

  • ARTICLE IN PRESS

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 11161127 1117simulations and event trees for the protection was anticipated forpower system reliability estimation, accounting for only linesprotection failure [16].

    Several variations of Monte Carlo simulation methods includ-ing cellular automata and system state transition samplingapproach were developed to probabilistically evaluate powersystem long-term reliability [1723]. These methods do notinclude all functional zones of the power system and some ofthem face difficulty with convergence. A method based on loadcurtailment model is proposed to perform risk assessment of acombinative system of transmission network and substationconfigurations [24] and excluding generators failure from theanalysis.

    A method for evaluating the terminal-pair reliability of thenetwork, based on an edge expansion tree and ordered binarydecision diagram, and a method for consideration of node failureswere developed [25,26].

    The power system is usually divided into generation, transmis-sion and distribution functional zones, which are analyzedseparately [27,28]. These functional zones can be combined toform a series of hierarchical levels for conducting the systemreliability analysis. System reliability is usually predicted usingone or more indices that quantify the system reliability and thatare implemented using the criteria based on acceptable values ofthese indices.

    A methodology for the automated generation of fault trees forelectrical/electronic circuits from a representation of a schematicdiagram is developed [29]. The application of the fault treeanalysis approach for power system reliability analysis andsystem design, development and modification is demonstrated[30,31]. A recent probabilistic method for transmission gridreliability evaluation uses event trees and fault trees andcombines them with power system dynamic simulations. Thesubstation protection and the trip operations after line faults aremodeled with the event trees. The power system reliability isstudied with a substation model, which includes possiblemalfunctions of the protection and circuit breakers. Single faultsof lines, due to the protection failure, are accounted for in theanalysis [32,33].2. Method description

    The failure probability of power delivery to ith load (QGDi) iscalculated through the top event probability of the respective faulttree, and the values of weighted failure probabilities of powerdelivery to loads are considered to get the overall measure of thepower system reliability:

    RPS 1XNLi1

    QGDiKi

    K 1 QPS (1)

    where RPS is power system reliability; QPS, power systemunreliability; QGDi, failure probability of power delivery to ithload (top event probability of the respective fault tree); NL,number of loads in system; Ki, capacity of ith load; K, totalcapacity of the system; Ki/K, weighting factor for ith load, where

    K XNLi1

    Ki (2)

    The fault tree analysis is performed separately for each of theloads in the power system, and the power system reliability, givenby Eq. (1), is calculated. Calculation of the power flows within thepower system is considered, in addition.2.1. Fault tree analysis

    The report entitled Reactor Safety Study: an assessment ofaccident risk in US Commercial Nuclear Power Plants(NPPs)WASH 1400 [34] was an important attempt to providea detailed assessment of the risks associated with the utilizationof commercial nuclear power plants. A systematic probabilisticmethodology for assessment of reliability and safety of complexsystems was developed and applied. In most countries, themethod is referred to as probabilistic safety assessment (PSA).The event tree and the fault tree are two basic methods used inprobabilistic safety assessment [35].

    The fault tree is a tool to identify and assess the combinationsof the undesired events in the context of system operation and itsenvironment that can lead to the undesired state of the system[3537]. It is recognized worldwide as an important tool forevaluating safety and reliability in system design, developmentand operation [35,3844]. The undesired state of the system isrepresented by a top event. The fault tree is based on Booleanalgebraic and probabilistic basis that relates probability calcula-tions to Boolean logic functions. The fault tree analysis is used forassessment of reliability indices in the power system withinclusion of the major components of the system. The logicalgates integrate the primary events to the top event, whichcorresponds to the undesired state of the system. The primaryevents are the events that are not further developed, e.g. the basicevents (BE) and the house events. The basic events are theultimate parts of the fault tree, which represent the undesiredevents, e.g. the component or system failures.

    The classic fault tree is mathematically represented by a set ofBoolean equations. The qualitative fault tree analysis (in theprocess of Boolean reduction of a set of equations) identifies theminimal cut sets, which are combinations of the smallest numberof basic events, which, if occur simultaneously, lead to the topevent.

    The quantitative fault tree analysis represents a calculation ofthe top event probability, equal to the failure probability of thecorresponding load. The calculation of the top event probability:

    QGD Xni1

    QMCSiXioj

    QMCSi\MCSj

    Xiojok

    QMCSi\MCSj\MCSk . . . 1n1Q\ni1

    MCSi (3)

    can be simplified and approximated (using rare event approxima-tion) as

    QGD Xni1

    QMCSi (4)

    where QGD is top event probability of the fault tree, correspondingto probability of disruption of energy delivery to the correspond-ing load.

    Probability of each minimal cut set is calculated using therelation of simultaneous occurrence of independent events:

    QMCSi Ymj1

    QBj (5)

    where QMCSi is probability of minimal cut set i; m, number of basicevents in minimal cut set i; QBj, probability of the basic event Bjdescribing failure of the component (i.e. failure probability ofcomponent Bj).

    The fault tree analysis results include importance measuresrisk achievement worth (RAW) and risk reduction worth (RRW) inaddition to the top event probability [39,43]. Risk achievementworth identifies components that should be maintained well in

  • ARTICLE IN PRESS

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 111611271118order that the reliability of the system is not reduced significantly.Risk reduction worth identifies components that are probablyredundant, because their reliability significantly increases systemreliability(i.e. risk is reduced):

    RAWk QGDQk 1

    QGD(6)

    RRWk QGD

    QGDQk 0(7)

    where RAWk is risk achievement worth for component k; RRWk,risk reduction worth for component k; QGD(Qk 1), top eventprobability when failure probability of component k is set to 1;QGD(Qk 0), top event probability when failure probability ofcomponent k is set to 0; QGD, top event probability.2.2. New importance measures

    New risk importance measures are developed to evaluate thepower system [44]. The network importance risk measures,namely network risk achievement worth (NRAW) and networkrisk reduction worth (NRRW), are defined using the definition ofthe importance measures from a single fault tree given in Eqs. (6)and (7) and the power system unreliability expression given in Eq.(1). As the term network is a descriptive term for the powersystem in this paper, NRAW and NRRW can be expressed as powersystem risk achievement worth and power system risk reductionworth:

    NRAWk QPSQk 1QPS

    PNLi1

    QGDiQk 1Ki

    PNLi1

    QGDiKi

    PNLi1

    QGDiQkKiRAWkGDi

    PNLQGDiKi

    (8)

    where NRAWk is power system risk achievement worth ofcomponent k; QPS, power system unreliability; QPS(Qk 1), powersystem unreliability when unreliability of component k is set to 1;QGDi(Qk 1), failure probability of power delivery to ith load whenunreliability of component k is set to 1; NL, number of loads in thesystem; QGDi(Qk), failure probability of power delivery to ith load;RAWkGdi, value of RAW for component k corresponding to load i;and Ki, capacity of ith load.

    NRRWk is defined as

    NRRWk QPSQPSQk 0

    PNLi1

    QGDiKi

    PNLi1

    QGDiQk 0Ki

    PNLi1

    QGDiKi

    PNLi1

    QGDiQkKiRRWkGDi

    (9)

    where NRRWk is power system risk reduction worth of componentk; QPS(Qk 0), power system unreliability when unreliability ofcomponent k is set to 0; QGDi(Qk 0), failure probability of powerdelivery to ith load when unreliability of component k is set to 0;RRWkGdi, value of RRW for component k corresponding to load i.

    The system importance measures NRAW and NRRW forcomponents groups are defined similarly as importance measuresfor single components, substituting QPS and QGDi in Eqs. (8) and (9)with

    QPS(Qg 1)power system unreliability when unreliability ofcomponents in group g is set to 1.

    QGDi(Qg 1)failure probability of power delivery to ith loadwhen unreliability of components in group g is set to 1.

    QPS(Qg 0)power system unreliability when unreliability ofcomponents in group g is set to 0.

    QGDi(Qg 0)failure probability of power delivery to ith loadwhen unreliability of components in group g is set to 0.

    Component groups may contain components (elements) of thesame type, components corresponding to specific substation or/and any other combination.2.3. Approximate DC load-flow model and line overload test

    The approximate direct current power flow model is obtainedfrom the alternating current model of power system if taken to beapproximated, voltages in all buses are equal to the nominal,differences of angles of voltages are very small and neglecting thelosses in power system. The DC power flow model gives a linearrelationship between the power flowing through the lines and thepower input at the nodes. The DC power flow equations can bewritten as

    F AP (10)

    where F is a vector whose components are the active power flowsthrough the lines; P, vector whose components are power ofgenerators in the substations; A, constant matrix with elementscalculated from the impedance of the lines and load in substations(dimensions of A are NlNg, where Nl is the number of lines andNg the number of substations directly connected to a generator orgenerators in a system).

    Using the calculated active power flows from Eq. (10) and theapproximate methodology [45], reactive power flows and voltagesin the buses are calculated for normal regime and for the singleline failure state (when each of the lines in the system fails). Thecalculated flows and voltages are stored and used for the overloadchecking procedure.

    The procedure for overload checking contains the followingsteps:1. Compare flows through the lines, which constitute tested flowpath, with continuous load rating of those lines, when linesthat are not included in the flow path fail (single line failure).2. If the overloaded line is found in step 1, then discard that flowpath and check the next flow path.3. Check if there are violated voltages (outside the predeterminednominal range) in the buses constituting flow path when linesthat are not included in the flow path fail.4. If flow path passes the overload and voltage tests, accept it forthe fault tree construction.5. Go to step 1, until all flow paths are checked.

    In step 1, the maximum (absolute value) of the reactive powerflow thought to line together with active power flow is consideredin the evaluation. The single peak load model is used in theanalysis accounting for the size of the loads during peakconsumption.

    Continuous load rating of the lines is updated with theambient temperature using the correction factor defined as

    kcorr ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi80 Tamb

    40

    r(11)

  • ARTICLE IN PRESS

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 11161127 1119where kcorr is correction factor for continuous load rating and Tambis ambient temperature.

    Many power systems are built or have been designed with arelatively strong transmission network. When analysis is done tothose systems, several modifications are made in order [20] toweaken the system for conducting the transmission reliabilitystudies. Those modifications are mostly connected with thedisconnection of multiple lines in the power system. With thedisconnection of lines, the overall structure and power flowswithin the system are changed, not corresponding to flows in areal system. In the proposed method, power flows in normal andsingle line failure regime are accounted for together with voltagesin the substations. Only selected energy paths are accounted for inthe fault tree construction, discarding those that are overloaded asa result of limitations of transfer capacity of lines or violatedvoltages in substations. Discarded flow paths, depending onpower flows, have direct implication on the reliability of powerdelivery and on overall power system reliability (a smallernumber of flow paths results in a smaller number of alternativepower delivery paths and higher failure probability). Reducing thenumber of flow paths reduces the number of gates in a fault treeand the overall size of the fault tree, decreasing the calculationtimes.2.4. Procedure

    Switching substations are important elements of powersystems. A generator and/or a load can be connected to theswitching substation. Switching substations are connected withpower lines, through which the power is transferred fromgenerators and other switching substations to loads. The mainFig. 1. Example substation and simptask of the analysis is to identify the possible paths of interruptionof power supply to the load, to evaluate the probability of thatinterruption and to recognize the main components that con-tribute to the interruption of supply.

    In order to start with the fault tree analysis, the correspondingfault tree should be built first for each switching substation,which is connected to a load. The principle of continuum ofenergy delivery is taken in account during the analysis. The faulttree structure corresponds to the configuration of the system andincludes all possible flow paths of disruption of the power supplyfrom generators to loads. The power transfer limitations andcommon cause failures (CCF) of power lines are included in themodel together with power flows and capacity of generators andloads in the power system. Common cause failures are failures ofmultiple equipment items occurring from a single cause that iscommon to all of them [46]. The failure of the multiple lines dueto the severe weather conditions or earthquakes in a specifiedregion can be additionally modeled adding supplementary CCFgroups for each initiator.

    Switching substations used in the model correspond tosubstations in real power systems, which normally include severalcomponents including circuit breakers, protective relays, cut-outswitches, disconnect switches, lightning arresters, fuses, transfor-mers and other communication and protection equipment.

    The first step in the proposed method is the building of faulttrees for each substation in the power system and the calculationof corresponding top event probabilities. Example of a switchingsubstation, consisting of load, two buses, four generators andthree lines (up) together with a corresponding simplified modelrepresentation of the substation (down), is given in Fig. 1.

    In the simplified substation representation, given in thebottom of Fig. 1, bus BUS01 failure will result in interruption oflified model of the substation.

  • ARTICLE IN PRESS

    Fig. 2. Fault tree for simplified substation representation.

    Fig. 3. An example system consisting of six substations.

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 111611271120energy delivery from generators and lines to load, disruption ofpower delivery from generators to lines and disruption of energyexchange between power lines, representing substation failuremode in the developed method. Disruption of energy deliverypaths through elements of the substation is accounted for duringthe construction of the fault tree. Fig. 2 shows a part of the faulttree of the substation. Normal states of the circuit breakers anddisconnect switches (normally open or normally closed) areassumed and modeled in the fault tree using two failureprobabilities, for active and passive failures, for each of theelements (fails to close, fails to remain closed). Building of thefault trees and calculation of top event probability and corre-sponding importance measures are done using commercial soft-ware [47].

    The presented reliability assessment of the substation does notinclude protection and control systems. The inclusion of thesesystems can improve the models, but it can additionally increasethe complexity of the overall procedure [48].

    The next step in developing the corresponding fault trees isidentification of all the possible energy delivery flow paths fromthe adjacency matrix of the corresponding power system. The sixsubstations system, which is shown in Fig. 3, is presented as anexample for description of the methodology.

    The system consists of six substations, five generators insubstations 13 and 6 and two loads in substations 1 and 4. Thereare multiple generators (two in substation three) and multiplelines (marked Li1 and Li2 in Fig. 3) between substations 1 and 2 inthe example system. The lines for which common cause failuresare accounted for are marked in Fig. 3: CCF of lines due to thecommon tower and CCF1 for lines that are assumed to be on acommon right-of way for part of their length.

    The adjacency matrix A of a simple graph is a matrix with rowsand columns labeled by graph vertices, with a 1 or 0 in position(vi, vj) according to whether graph vertices vi and vj are adjacentor not. Using the adjacency matrix A, all possible flow pathsbetween generation (source) and consumer (load) substations areidentified, using developed recursive procedure for the formationof rooted trees of the graph of the system. The energy flow pathsbetween the load and other substations in the system areidentified using the rooted tree. A rooted tree is a tree in whicha labeled node is singled out. The rooted tree for substation 1 isgiven in Fig. 4. Dashed lines identify the energy flow pathsbetween substations 3 and 6 and substation 1.

  • ARTICLE IN PRESS

    Fig. 4. Rooted tree for substation 1 with energy flow paths to substations 3 and 6for example system.

    Fig. 5. Discarded and accepted flow paths for test system.

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 11161127 1121The identified flow paths of energy delivery between substa-tions are tested for consistency, namely:1. Only a part of the flow path ending with substation, which isdirectly connected to generators with total installed capacityequal or larger than load, is taken further for the overload test.2. If there is an overloaded line in the flow path obtained from theprevious test, then that flow path is discarded.Test of overloaded lines or violated voltages in a flow path isdescribed in Section 2.3.

    In these consistency tests, it is assumed that energy isdelivered to the load only from substations, where the totalinstalled capacity of generators is equal to or larger than the load.This assumption does not correspond to real power systemswhere each generator has a share of energy delivered to each loadin the power system. However, taking into account the fact that allpossible combinations of flow paths of all substations withgenerators and loads are included in the model, it is postulatedthat the model will correspond to the state of a real power system.

    Example of a consistency test, for load 1 with tree shown in Fig.4, is given in Fig. 5. Let the total installed capacity of the generatorin substation 2 be smaller than the load in substation 1, lines 24are overloaded for the specific flow path corresponding to energydelivery from substations 3 to 1 and voltage in bus 5 is higherthan nominal in case of the failure of lines 13. In that case, onlyflow paths marked with dark solid lines in Fig. 5 will be acceptedfor the fault tree construction. All other flow paths will bediscarded due to the lack of generator (black dashed lines,substation 4), smaller generation than load (green lines, substa-tion 2), violated voltage (blue line from substation 6) or overloadof the line (red dashed line between substations 2 and 4 showsoverloaded line; red line between substations 2 and 3 is discardedtoo).

    Flow paths, which were accepted in a previous test ofconsistency, are used in the next step for fault tree construction.The fault tree for each substation, which is connected to a load, iscreated using the modular fault tree, shown in Fig. 6, with thestructure and the failure probabilities inserted depending on theelements modeled. Basic events marked in red squares areoptional, depending if there are CCF between lines or if thereare multiple generators in the substation. The procedure ofbuilding fault tree includes the following steps:1. Add OR gate (top gate named 50,000) corresponding to failureof power delivery to that substation.2. If the previously added gate is top gate, exclude the linefailures gate, else add OR gate for those failures (named600,000 or above) and corresponding basic events for linefailures and CCF of lines (named with numbers starting from200,000 and 650,000).3. Add OR gate corresponding to substation failure (named withnumbers starting from 700,000).4. Add OR gates corresponding to substation failure (named withnumbers starting from 800,000) and corresponding basicevents (named with numbers starting from 100,000).5. Add AND gate corresponding to failure to deliver energy tospecific substation (named 900,000 or above).6. Add OR gates corresponding to generators failure in thatsubstation (750,000 and above) or no energy from othersubstations connected to that substation (500,001 and above).7. Go to step 1 until all energy flow paths are accounted for.Fig. 7 shows the top section of the fault tree constructed for load1 in substation 1 in Fig. 3. The maintenance activities of thecomponents in the power system can be implemented byexcluding the components planned for maintenance from inputdata.

    The evaluation of the network reliability is an NP-hardproblem [15] requiring processor power and memory allocation.Two major elements identify the necessary calculation time. Firstis the size of the fault trees built for each of the loads in thesystem. Fault trees size depend on the number of substations(correlated to size of adjacency matrix), loads (number ofgenerated fault trees), lines in the power system (related tonumber of possible energy flow paths) and size of the loads andgenerators and their disposition in the system (number ofaccepted flow paths accounting for power transfer capabilities ofthe lines and substation voltages). Second is the efficiency of theused fault tree analysis module and the used cut-off values in the

  • ARTICLE IN PRESS

    Fig. 6. Modular fault tree used for fault tree construction.

    Fig. 7. Part of the fault tree built for load 1 in substation 1.

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 111611271122

  • ARTICLE IN PRESS

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 11161127 1123calculations and this element is most time demanding andlimiting in the method.

    During the construction of the fault tree model for each of thesubstations in the system, the following important issues areconsidered: Logical looping was avoided by careful consideration of flowpaths. All ends of flow paths are considered in order not to double-count contributions modeled previously in the tree.The verification of a proper fault tree modeling was donethrough the examination of minimal cut sets of small test systemsin sense: If all minimal cut sets are really minimal.

    If all expected minimal cut sets appear in their respective

    listing.Fig. 8. IEEE one a3. Results

    The new method is tested on the IEEE One Area RTS-96(IEEEInstitute of Electrical and Electronics Engineers,RTSReliability Test System), consisting of 24 substations17substations that are directly connected to loads and 7 substationsthat are directly connected to generators32 generators and 38power lines [49]. For 14 lines, the common cause failures areconsidered. The IEEE reliability test system is specially designed tobe used for different static and dynamic analyses and to comparethe results obtained by different methods. Diagram of the IEEEOne Area RTS-96 is given in Fig. 8.

    The available data for component reliability are used in theanalysis [49,50]. Each substation is approximated with substationfailure basic event calculated by the procedure given in Section2.4. The extended single line diagram of IEEE One Area RTS-96Substation System [49], including station configurations, wasused for substations reliability assessment. Failures of thedisconnect switches at the end of the power lines, circuit breakersand transformers in the lines were included in the calculation ofrea RTS-96.

  • ARTICLE IN PRESS

    Table 1Failure data for selected elements of the IEEE test system.

    Component name Component failure probability Subsystem failure

    probability

    Beta factor for common

    cause failures

    Substation one failure 3.57E8

    Substation two failure 3.57E8

    Substation three failure 2.33E9

    Substation eleven failure 3.00E9

    Line between substations 1 and 2 4.39E4

    Line between substations 1 and 3 5.83E4

    Line between substations 1 and 5 3.77E4

    Beta factor for lines 89 2.00E1

    Beta factor for lines 1722 3.00E1

    Circuit breaker (active failure: fails to close) 8.14E05

    Circuit breaker (passive failure: fails to remain closed) 6.16E06

    Disconnect switch (active failure: fails to close) 4.09E06

    Disconnect switch (passive failure: fails to remain closed) 6.16E07

    Generator size 12MW 2.00E02

    Generator size 20MW 1.00E01

    Generator size 50MW 1.00E02

    Generator size 76MW 2.00E02

    Generator size 100MW 4.00E02

    Generator size 155MW 4.00E02

    Generator size 197MW 5.00E02

    Generator size 350MW 8.00E02

    Generator size 400MW 1.20E01

    Bus section 138kV 5.44E05

    Bus section 230 kV 4.43E05

    Table 2Calculated top event probabilities of IEEE RTS.

    Load

    substation

    Failure

    probability of

    power delivery

    to respective

    load

    Weight FT top event

    prob.weightCapacity

    (MW)

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 111611271124failure probabilities of the lines. Only the length of the commonstructure or the common path of power lines is given in IEEE data;therefore, the estimated values are considered for the Beta factorfor CCF of lines. Table 1 shows the component reliability data forselected elements of the test system as used in the analysis.Ambient temperature Tamb 40 1C is considered in the analysis.

    The following results are obtained for the test system:15 2.31E03 1.10E01 2.54E04 317

    18 2.30E03 1.16E01 2.66E04 333

    13 1.39E04 9.20E02 1.28E05 265

    20 4.47E05 4.44E02 1.99E06 128fault tree model and top event probability for each of theselected loads,7 4.11E05 4.34E02 1.79E06 125 system unreliability,

    10 9.96E06 6.77E02 6.74E07 195

    9 9.96E06 6.08E02 6.05E07 175power system risk achievement worth for all elements of thesystem,14 3.71E06 6.74E02 2.50E07 194

    19 3.55E06 6.28E02 2.23E07 181

    3 2.56E06 6.25E02 1.60E07 180power system risk reduction worth for all elements of thesystem and6 7.29E07 4.72E02 3.44E08 136

    8 6.56E07 5.94E02 3.90E08 171importance measures for components and selected groups ofcomponents in the system.4 1.88E07 2.57E02 4.83E09 74

    5 1.51E07 2.47E02 3.71E09 71

    2 3.59E08 3.37E02 1.21E09 97

    1 3.57E08 3.75E02 1.34E09 108

    16 1.99E08 3.47E02 6.91E10 100The selected quantitative results are presented in the followingtables.

    Results in Table 2 include failure probability of the powerdelivery to respective loads in the power system, correspondingweighting factor for each load and final weighted failureprobability for each load separately. The total system failureprobability is evaluated as 5.41E04. The total capacity of thesystem is 2850MW. The results in Table 2 show that the loadswith the highest top event probability are loads in substations 15,18, 13 and 20, mainly due to the size of the loads and failureprobabilities of those substations. The obtained results werecompared with the results obtained for bus indices for IEEE RTSshown in Table 3 taken from Table 3.16 of the corresponding Ref.[50]. Comparison of the obtained results show that samesubstations have the highest failure probabilities in the first fourpositions of both tables. The energy index of unreliability in Table3.17 of the corresponding Ref. [50] was estimated to be 5.84E3.This value is of an order of magnitude higher than the systemunreliability measure obtained from the proposed method, but itshould be noted that both measures have been obtained bydifferent approaches and they correspond to different powersystem elements (the power deliver capability in the first and theenergy in the second case).

    The importance measures NRRW and NRAW for selectedcomponents in the power system are given in Table 4. Resultsshow that components with the highest value of NRRW impor-tance measure are generators situated in substations 18, 21 and 23and this result is expected accounting for that those units are thelargest generating units in the power system. The high value ofNRRW implies that the reliability of the respective components isworth increasing in order that the system reliability is signifi-cantly increased. The identified power plants are candidates fordesign change, e.g. installation of redundant components in the

  • ARTICLE IN PRESS

    Table 3The results for the IEEE RTS from Ref. [50].

    Load Failure probability

    18 8.34E02

    13 7.13E02

    15 5.65E02

    20 4.62E02

    2 4.10E02

    16 2.60E02

    3 2.26E02

    5 2.24E02

    1 2.24E02

    6 2.24E02

    4 2.24E02

    8 1.60E02

    7 1.59E02

    19 1.17E02

    14 9.56E03

    9 3.17E03

    10 3.17E03

    Table 4Importance measures for selected components of IEEE RTS.

    Component identification NRRW NRAW

    G2 118-1 1.04E+02 8.26E+00

    G2 121-1 1.04E+02 8.26E+00

    G2 123-3 1.98E+00 6.70E+00

    G2 123-1 1.33E+00 6.94E+00

    G2 123-2 1.33E+00 6.94E+00

    B1-118 1.00E+00 2.20E+02

    B1-115 1.00E+00 2.05E+02

    L1-107 108 1.00E+00 1.07E+01

    L1-116 119 1.00E+00 1.31E+00

    L2-120 123 1.00E+00 1.29E+00

    Table 5Power flows through lines in IEEE RTS.

    Line Power flow

    (MW) start

    Power flow

    (MVAr)

    start

    Power flow

    (MW) end

    Power flow

    (MVAr)

    end

    Lines 1416 343.3 38 343.3 25.3Lines 1617 322.2 19.2 322.2 43.1Lines 1323 250.6 31.6 250.6 9Lines 1223 243.9 21.9 243.9 19.8Lines 324 236.7 35.5 236.7 10.6Lines 1524 233.2 28.6 233.2 10.2Lines 1521 214.9 41.9 214.9 57.7Lines 1521 214.9 41.9 214.9 57.7Line 1718 181 51.4 181 53.9Lines 1012 166.2 57.2 166.2 30.2Lines 2122 158.9 24.6 158.9 21.6Lines 1114 149.3 63.8 149.3 62.5Lines 1619 143.5 68.1 143.5 68.4Lines 1722 141.1 10.1 141.1 11.5Lines 1011 140.7 66.3 140.7 45.9Lines 912 122.2 20.1 122.2 34Lines 78 115 26.5 115 18.2Lines 1516 109.6 70.1 109.6 69Lines 911 96.7 10.5 96.7 18.9Lines 610 84.4 73 84.4 210.1Lines 1113 83.1 36.4 83.1 30Lines 2023 82.7 58.3 82.7 55.7Lines 2023 82.7 58.3 82.7 55.7Lines 15 64.8 1.2 64.8 0.4Lines 1821 57 8.9 57 14Lines 1821 57 8.9 57 14Line 26 51.6 28.4 51.6 28.4Lines 89 39.2 12.9 39.2 15Lines 1213 38.5 21.5 38.5 11.5Lines 24 37.9 31.3 37.9 31Lines 39 37.8 27.3 37.8 26.1Lines 49 36.1 16.9 36.1 18.4Lines 1920 18.8 53 18.8 45.1Lines 1920 18.8 53 18.8 45.1Lines 810 16.8 27.2 16.8 24.3Lines 13 15.3 40.8 15.3 43.4Lines 12 14.5 40 14.5 13.2Lines 510 6.2 13.4 6.2 10.9

    Table 6Importance measures for selected components of substation 15.

    Component ID Failure probability RRW RAW

    DS15024 5.00E04 1.43E+00 6.01E+02DS15023 5.00E04 1.43E+00 6.01E+02BUS15A1 1.67E05 1.00E+00 5.27E+01BUS15B2 1.67E05 1.00E+00 2.61E+01BUS15A2 1.67E05 1.00E+00 2.52E+01CB15010 6.60E03 1.12E+00 1.72E+01CB15011 6.60E03 1.12E+00 1.72E+01

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 11161127 1125corresponding substations where those generators are connected.The identified components with the highest NRAW in Table 4 areas follows: substations 18 and 15, line between switchingsubstations 7 and 8, line between substations 16 and 19 andCCF of the lines between substations 20 and 23. Components withthe highest value of NRAW should be maintained well, in orderthat the reliability of the system is not reduced significantly, sothe maintenance priority should be high for those components.The high value of NRAW for substations 18 and 15 is expectedaccounting for the size of the loads connected in those substa-tions. The failure of line between substations 7 and 8 will disruptpower delivery from the generator and to the load situated insubstation 7, resulting in a high value of NRAW. The high values ofNRAW for the line between substations 16 and 19 and CCF of thelines between substations 20 and 23 are obtained because failureof those lines will disrupt power delivery from generators situatedin substations 19 and 20 to the power system and interrupt powertransfer between substations 16 and 23.

    The calculated power flows through lines in the power systemusing DC power flowmethod for the normal operation are given inTable 5. The minus sign indicates the reverse flow between twosubstations. The highest power flows are between lines 1416 and1617. Comparison of the most important power lines in thesystem given in Table 4 and the power flows given in Table 5shows that the most important power lines are not always thosethat have the highest power flows during normal regime of work.

    The importance measures for selected components ofsubstation 15, identified to have the highest failure probabilityin Table 2, are given in Table 6. The results show that twodisconnect switches DS15023 and DS15024 are the most im-portant components with the highest values of RRW and RAW.3.1. Additional application of the results

    The data for causes of major blackouts in USA in the period19941997 [51] clearly indicate that the equipment failures andthe weather conditions are the main initiators of blackouts.Quantification of reliability of the power system is importantowing to the social, economical and safety implications of theoverall population. On August 14, 2003, a widespread loss of the

  • ARTICLE IN PRESS

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 111611271126US electrical power grid (blackout) resulted in the loss of offsitepower (LOOP) initiating event (IE) at nine US commercial NPPs.

    In a power system that consists of at least one NPP, reliabilityof the power system influences the safety of the NPP. The NRCinitiated a comprehensive program to review grid stability andoffsite power issues as they relate to the safety of NPPs [52,53].

    The presented methods for assessment of power systemreliability can be used as an alternative approach for estimationof the frequency of the loss of offsite power and station blackout(SBO) initiating events in NPP PSA, thus resulting in an overallimprovement of PSA analysis of the plants. The loss of offsitepower initiating event occurs when all power to the plant fromexternal sources (the grid or a dedicated transmission line fromanother onsite plant) is lost. The station blackout event is inducedby a loss of offsite power event followed by the failure of all onsitediesel generators (DG) to start and run.

    Taking into account that SBO and LOOP are major contributorsto CDF [54], the changes of LOOP IE frequency can result insubstantial changes of the results. For example, after initiatingevents SBO and LOOP, their corresponding scenarios contribute,respectively, 32.1% and 11.5% to the core damage frequency (CDF)of specific NPP [54]. A LOOP initiating event frequency of 5.17E2events/year is assumed. The LOOP results from three possiblecauses, namely plant centred causes (PCL), grid causes (GD) andweather related causes. If shares of 58%, 35% and 7% are assumedfor each of them correspondingly, then the value of 1.81E02events/year is obtained for the GD LOOP. If the GD LOOP initiatingevent frequency is changed based on power system evaluations,the core damage frequency may change significantly.

    If the GD LOOP initiating event frequency is changed to1.55E04 events/year, the value of LOOP is changed to 3.36E2events/year. If the linear relation between CDF contribution and IEfrequency is assumed, the calculated contributions of SBO andLOOP to CDF of the same NPP are 20.9% and 7.48%, respectively,with change of core damage frequency being around 10%.

    The presented method can be applied for reliability analysis ofother critical infrastructures such as traffic, communication andgas networks. The identification and protection of the criticalcomponents of a given networks can directly reduce theconsequences of terrorist attacks.4. Conclusions

    A new method for assessment of power system reliability isdeveloped. The method integrates the fault tree analysis and thepower flow model. The results are qualitative and quantitativeand they depend on the failure probabilities of components andon the power flows in the power system. The results identify thereliability measures connected to particular loads and thereliability measures connected to the power system as a whole:the probability of failed power delivery to selected loads, theimportance measures of components corresponding to selectedloads and the importance measures of components correspondingto the whole power system.

    An important feature of the method is that system deficienciescan be readily identified, using newly defined importancemeasures. Both quantitative and qualitative results help infocusing attention on those sections of a power system thatcontribute the most to the unreliability of power delivery tospecific loads. Application of the method on IEEE area test systemis demonstrated. The method can be adapted for reliabilityanalysis of other critical infrastructures, which have similartopology as the power system.

    Future work may include integration of evaluation of substa-tions into the power system evaluation, procedure for calculationof common cause failures and a more efficient algorithm foridentification and analysis of minimal cut sets, which is capable toconsider even larger models.Acknowledgement

    This research was supported by the Slovenian Research Agency(contract no. 1000-05-310016).

    References

    [1] Jeffrey S, Restrepo C, Zimmerman R. Risk-management and risk-analysis-based decision tools for attacks on electric power. Risk Analysis2007;27(3):54770.

    [2] Bruce F, Wollenberg B. From blackout to blackout 1965 to 2003: how far havewe come with reliability? IEEE Power and Energy Magazine, 2004;(January/February):868.

    [3] Rose A, Oladosu G, Liao S. Business interruption impacts of a terrorist attackon the electric power system of Los Angeles: customer resilience to a totalblackout. Risk Analysis 2007;27(3):51331.

    [4] Koonce AM, Apostolakis GE, Cook BK. Bulk power grid risk analysis: rankinginfrastructure elements according to their risk significance, ESD-WP-2006-19,Engineering Systems Division. Cambridge, MA: MIT Press; 2006.

    [5] Carreras BA, Lynch VE, Dobson I, Newman DE. Critical points and transitionsin an electric power transmission model for cascading failure blackouts.Chaos 2002;12(4):98594.

    [6] Volkanovski A, Mavko B, Bosevski T, Causevski A, Cepin M. Genetic algorithmoptimisation of the maintenance scheduling of generating units in a powersystem. Reliability Engineering and System Safety 2008;93(6):77989.

    [7] IEEE Gold Book, IEEE Recommended practice for the design of reliableindustrial and commercial power system. ANSI/IEEE Std 493-2007, 2007.

    [8] Save P. Substation reliabilitypractical application and system approach.IEEE Transactions on Power Systems 1995;10(1):3806.

    [9] Awosope COA, Akinbulire TO. A computer program for generating power-system load-point minimal paths. IEEE Transactions on Reliability1991;40(3):3028.

    [10] Awosope COA, Akinbulire TO. A computer program for generating power-system load-point minimal paths. IEEE Transactions on Reliability 1991;40(3):3028.

    [11] Apostolakis GE, Lemon DM. Screening methodology for the identification andranking of infrastructure vulnerabilities due to terrorism. Risk Analysis2005;25(2):36176.

    [12] Garrick BJ, Hall JE, Kilger M, McDonald JC, OToole T, Probst PS, et al.Confronting the risk of terrorism: making the right decisions. ReliabilityEngineering and System Safety 2004;86:12976.

    [13] Bier VM, Gratz ER, Haphuriwat NJ, Magua W, Wierzbicki KR. Methodology foridentifying near-optimal interdiction strategies for a power transmissionsystem. Reliability Engineering and System Safety 2007;92(9):115561.

    [14] Patterson SA, Apostolakis GE. Identification of critical locations acrossmultiple infrastructures for terrorist actions. Reliability Engineering andSystem Safety 2007;92(9):1183203.

    [15] Wei-Chang Y. An improved sum-of-disjoint-products technique for thesymbolic network reliability analysis with known minimal paths. ReliabilityEngineering and System Safety 2007;92(2):2608.

    [16] Miki T, Okitsu D, Kushida M, Ogino T. Development of a hybrid typeassessment method for power system dynamic reliability. In: IEEE interna-tional conference on systems, man and cybernetics, IEEE SMC 99 conferenceproceedings, vol. 1, 1999. p. 96873.

    [17] Zio E, Podofillini L, Zille V. A combination of Monte Carlo simulation andcellular automata for computing the availability of complex network systems.Reliability Engineering and System Safety 2006;91:18190.

    [18] Yishan L. Short-term and long-term reliability studies in deregulated powersystem. Doctoral dissertation, Texas A&M University, 2005. p. 155+4.

    [19] Ran M. Deterministic/probabilistic evaluation in composite system planning.Master thesis, University of Saskatchewan, Saskatoon, 2003. p. 124+35.

    [20] Yifeng L. Bulk system reliability evaluation in a deregulated power industry.Master thesis, University of Saskatchewan, Saskatoon, 2003. p. 142+45.

    [21] Rajesh UN. Incorporating substation and switching station related outages incomposite system reliability evaluation. Master thesis, University ofSaskatchewan, Saskatoon, 2003. p. 91+25.

    [22] Hua C. Generating system reliability optimization. Doctoral dissertation,University of Saskatchewan, Saskatoon, 2000. p. 160.

    [23] Billinton R, Wangdee W. Delivery point reliability indices of a bulk electricsystem using sequential Monte Carlo simulation. IEEE Transactions on PowerDelivery 2006;21(1):34552.

    [24] Wenyuan L, Jiping L. Risk evaluation of combinative transmission networkand substation configurations and its application in substation planning. IEEETransactions on Power Systems 2005;20(2):114450.

    [25] Fu-Min Yeh, Sy-Yen Kuo. OBDD-based network reliability calculation.Electronics Letters 1997;33(9):75960.

  • ARTICLE IN PRESS

    A. Volkanovski et al. / Reliability Engineering and System Safety 94 (2009) 11161127 1127[26] Netes VA, Filin BP. Consideration of node failures in network-reliabilitycalculation. IEEE Transactions on Reliability 1996;45(1):1278.

    [27] Allan RN, Billinton R. Reliability evaluation of power systems. Berlin:Springer; 1996.

    [28] Allan RN, Billinton R. Probabilistic assessment of power systems. Proceedingsof the IEEE 2000;88(2):14062.

    [29] Vries RC. An automated methodology for generating a fault tree. IEEETransactions on Reliability 1990;39(1):7686.

    [30] Galyean WJ, Fowler RD, Close JA, Donley ME. Case study: reliability of theINELsite power system. IEEE Transactions on Reliability 1989;38(3):27984.

    [31] Hessian RT, Salter BB, Goodwin EF. Fault-tree analysis for system design,development, modification, and verification. IEEE Transactions on Reliability1990;39(1):8791.

    [32] Haarla L. A method for analysing the reliability of a transmission grid.Reliability Engineering and System Safety 2008;93(2):27787.

    [33] Pottonen L. A method for the probabilistic security analysis of transmissiongrids. Doctoral dissertation, Helsinki University of Technology, 2005. p. 119+88.

    [34] Rasmussen N, et al. Reactor safety study. WASH-1400, US NRC, Washington,1975.

    [35] Standard for Probabilistic Risk Assessment for Nuclear Power Plant Applica-tions, ASME RA-S-2002, 2002.

    [36] Roberts NH, Vesely WE, Haasl DF, Goldberg FF. Fault tree handbook., NUREG-0492, US NRC, Washington, 1981.

    [37] Vesely WE, Dugan J, Fragola J, Minarick J, Railsback J. Fault tree handbookwith aerospace applications. National Aeronautics and Space Administration,NASA; 2002.

    [38] Cepin M, Mavko B. A dynamic fault tree. Reliability Engineering and SystemSafety 2002;75(1):8391.

    [39] CepinM. Method for assessing reliability of a network considering probabilisticsafety assessment. In: Proceedings of the international conference on nuclearenergy for New Europe 2005, Bled, Slovenia, September 58, 2005.

    [40] Cepin M. Development of new method for assessing reliability of a network.In: PSAM 8: proceedings of the eighth international conference onprobabilistic safety assessment and management. New Orleans: ASME;2006. p. 45/18.[41] Cepin M, Mavko B. Probabilistic safety assessment improves surveillancerequirements in technical specifications. Reliability Engineering and SystemsSafety 1997;56(1):6977.

    [42] Cepin M. Optimization of safety equipment outages improves safety.Reliability Engineering and System Safety 2002;77(1):7180.

    [43] Cepin M. Analysis of truncation limit in probabilistic safety assessment.Reliability Engineering and System Safety 2005;87(3):395403.

    [44] Volkanovski A, Cepin M, Mavko B. Power system reliability analysis usingfault trees. In: Proceedings, International conference on nuclear energy forNew Europe, Portoroz, 2006. p. 704.110.

    [45] Ackovski R. Methods for planning of development of power systems usingMonte Carlo simulation. Doctoral dissertation, Electrotechnical Faculty-Skopje, Macedonia, 1989. p. 138+18.

    [46] Breeding RJ, Leahy TJ, Young J, Cramond WR. Probabilistic risk assessmentcourse documentationvol. 1: PRA fundamentals. NUREG/CR-4350/1, USNRC, Washington, 1985.

    [47] RiskSpectrums PSA Professional, 19982003 RELCON AB.[48] Xu X, Lam BP, Austria RR, Ma Z, Zhu Z, Zhu R, et al. Assessing the impact of

    substation-related outages on the network reliability, PowerCon 2002. In:International conference on power system technology, Proceedings, vol. 2,2002. p. 8448.

    [49] A report prepared by the Reliability Test System Task Force of the Applicationof Probability Methods Subcommittee. The IEEE reliability test system1996.IEEE Transactions on Power Systems 1999;14(3):101020.

    [50] Allan RN, Billinton R. Reliability assessment of large electric power systems.Boston: Kluwer; 1988.

    [51] Carreras BA, Newman DE, Dobson I, Poole AB. Initial evidence for self-organized criticality in electric power system blackouts. In: Proceedings ofthe 33rd annual Hawaii international conference on system sciences, 2000.

    [52] Reevaluation of Station Blackout Risk at Nuclear Power Plants. NUREG/CR6890. US NRC, Washington, 2005.

    [53] Evaluation of Loss of Offsite Power Events at Nuclear Power Plants:19801996. NUREG/CR 5496, US NRC, Washington, 1997.

    [54] Cepin M, Prosen R. Update of human reliability analysis for nuclear powerplant. In: Proceedings, International conference on nuclear energy for NewEurope, Portoroz, 2006. p. 706.18.

    Application of the fault tree analysis for assessment of power system reliabilityIntroductionState of the art of power system reliability analysis

    Method descriptionFault tree analysisNew importance measuresApproximate DC load-flow model and line overload testProcedure

    ResultsAdditional application of the results

    ConclusionsAcknowledgementReferences