APPENDIX I (See paragraph 6) FORM 1 (I) SL.No. ITEM...
Transcript of APPENDIX I (See paragraph 6) FORM 1 (I) SL.No. ITEM...
1
APPENDIX I
(See paragraph – 6)
FORM 1
(I) Basic Information:
SL.No. ITEM DETAILS
1. Name of the Project/s M/s Nirani Cements Pvt Ltd.
2. S.No. in the Schedule Category A (3(b) as per EIA
Notification, 2006).
3. Proposed capacity/area/length/tonnage to
be handled/command area/lease
area/number of wells to be drilled
We have already received
Environmental clearance for the
expansion of present Cement Plant
from 90000 TPA to 02 Million TPA
capacity along with establishment of
Captive Power Plant (50MW). Total
land area of the Proposed Project
(Existing + Expansion) is around 240
Acres. Due to financial constriants the
company could'nt take the expansion.
Now seeking extension of validity of
EC as planning to implement the
expansion with financial aid from
bankers.
4. New/Expansion/Modernization Expansion
5. Existing capacity/Area etc. Existing capacity 90000 TPA cement
plant
6. Category of Project i.e., ‘A’ or ‘B’ A
7. Does it attract general condition? If yes,
please specify.
No
8. Does it attract specific condition? If yes,
please specify.
No
9. Location at Sy Nos. 111/1, 111/2B, 111/2A, 112,
113/1, 113/2, 114/2, 114/1+2+3+4+5+6+7B
and 114/1+2+3+4+5+6+7A for existing
and for expansion at Sy Nos. 98, 99,
100, 101, 102, 103, 104, 105, 106, 107, 108,
109, 110, 125, 126, 127, 128, 129, 130, 131
at Halki Ningapur village, Mudhol
Taluk, Bagalkot District, Karnataka
State.
Plot/Survey/Khatha No.
Village
Tehsil
District
State
10. Nearest railway station/airport along Nearest Railway station: Guledagudda
2
with distance in Kms. Railway station- 48 kms towards SE
Nearest Air port: Belgaum airport 82
kms towards SW
11. Nearest Town, City, District
Headquarters along with distance in
Kms.
Nearest Town: Mudhol
Bagalkot district
12. Village Panchayat, Zilla Parishad,
Municipal Corporation, Local body
(complete postal addresses with
Telephone Nos. to be given).
Mudhol taluk, Bagalkot district
13. Name of the Applicant Sri.Sangamesh. R.Nirani,
Executive Director,
14. Registered Address
M/s Nirani Cements Pvt Ltd.
Ningapur Industrial Area,
Halki Ningapur Village,
Mudhol Taluk
Dist: Bagalkot.
Mobile: 9986414598
15. Address for Correspondence
Name Sri.Sangamesh. R.Nirani,
Executive Director,
M/s Nirani Cements Pvt Ltd.
Ningapur Industrial Area,
Halki Ningapur Village,
Mudhol Taluk
Dist: Bagalkot.
Mobile: 9986414598
Designation (Owner/Partner/CEO)
Address
Pin Code
Telephone No.
Fax No.
16. Details of Alternative Sites examined, if
any. Location of these sites should be
shown on a toposheet.
None
17. Interlinked Projects None
18. Whether separate application of
interlinked project has been submitted?
Not Applicable
19. If yes, date of submission Not Applicable
20. If no, reason Not Applicable
21. Whether the proposal involves
approval/clearance under: if yes, details
of the same and their status to be given.
(a) The Forest (Conservation) Act,
1980?
(b) The Wildlife (Protection) Act,
1972?
No
No
3
(c) The C.R.Z Notification, 1991? Not Applicable.
22. Whether there is any Government
Order/Policy relevant/relating to the Site?
No
23. Forest land involved (hectares) No
24. Whether there is any litigation pending
against the project and/or land in which
the project is propose to be setup?
(a) Name of the Court
(b) Case No.
(c) Orders/directions of the Court, if
any and its relevance with the
proposed project.
No
(I) Activity:
1. Construction, operation or decommissioning of the Project involving
actions, which will cause physical changes in the locality (topography,
land use, changes in water bodies, etc.)
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.1 Permanent or temporary change in
land use, land cover or topography
including increase in intensity of
land use (with respect to local
land use plan)
Yes
Land use pattern of the plant area
already been modified for Cement
manufacturing Unit (90000 TPA).
Now, the project envisages capacity
expansion of present Cement
manufacturing Unit from 90000 TPA
to 02 Million TPA capacity along
with Captive Power Plant (50MW).
Hence there is already a permanent
change in the land use pattern of
the plot area.
1.2 Clearance of existing land, vegetation
and buildings?
No. Presently there is an existing
Cement manufacturing Unit (90000
TPA). There will be no clearing of
vegetation /buildings.
1.3 Creation of new land uses?
Yes The project envisages capacity
expansion of present Cement
Manufacturing Unit from existing
90000 TPA to 02 Million TPA
capacity along with Captive Power
Plant (50MW).
4
1.4 Pre-construction investigations e.g.
bore houses, soil testing?
No Already carried out.
1.5 Construction works?
Yes More of fabrication job.
1.6 Demolition works? No Not required.
1.7 Temporary sites used for
construction works or housing of
construction workers?
No The present site area will be used
for construction works and
construction workers will be from
the nearby villages and involves
day working only.
1.8 Above ground buildings, structures
or
Earthworks including linear
structures, cut and fill or
excavations?
No Expansion of existing Cement
Manufacturing Unit from 90000
TPA to 02 Million TPA capacity
along with Captive Power Plant
(50MW).
1.9 Underground works including
mining or tunneling?
No Not Applicable
1.10 Reclamation works?
No Not Applicable
1.11 Dredging?
No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing
processes?
Yes The technology of manufacturing
Portland Cement adopted in this
unit is known as Vertical Shaft Kiln
(VSK) Technology. In the expansion
Rotary kiln technology will be used.
1.14 Facilities for storage of goods or
materials?
Yes Necessary raw material storage yard
will come up within the plant
premises.
1.15 Facilities for treatment or disposal of
solid waste or liquid effluents?
Yes The proposed project will possess
facilities for treatment or disposal
of solid waste or liquid effluents.
1.16 Facilities for long term housing of
operational workers?
No Not Applicable.
1.17 New road, rail or sea traffic during
construction or operation?
Yes. Internal Roads shall be
strengthened.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes and
stations, ports, airports etc?
Yes Internal Roads shall be
strengthened.
5
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No Not Applicable
1.20 New or diverted transmission lines
or pipelines?
No Not Applicable
1.21 Impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or
aquifers?
No Not Applicable
1.22 Stream crossings? No Not Applicable
1.23 Abstraction or transfers of water
form ground or surface waters?
Yes Source of water is from River
Ghataprabha. For total 02 Million
TPA proposed expansion capacity,
2100 KLD water is required. At
present, 24 KLD is used. For
proposed expansion, additional
2076 KLD is required.
1.24 Changes in water bodies or the land
surface affecting drainage or run-off?
No Not Applicable
1.25 Transport of personnel or materials
for construction, operation or
decommissioning?
Yes Transport of construction materials
will be mainly through trucks and
personnel will be recruited shortly
as per the requirement. Man power
requirement for additional
manufacturing capacity of 2 Million
TPA is 700 No.s. Total manpower
will be 144 (Existing) + 700
(additional for expansion) = 844
No.s.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No Not Applicable
1.27 Ongoing activity during
decommissioning which could have
an impact on the environment?
No Existing Cement Manufacturing
Unit of capacity 90000 TPA is under
operation.
1.28 Influx of people to an area in either
temporarily or permanently?
No Not Applicable
1.29 Introduction of alien species?
No Local native plants will be planted
in and around the plant premises
and existing green belt will be
enhanced.
6
1.30 Loss of native species or genetic
diversity?
No If any, shall be compensated
through green belt development.
1.31 Any other actions? No Not Applicable
2. Use of Natural resources for construction or operation of the Project (such as
land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
S.No
.
Information/checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
2.1 Land especially undeveloped or
agricultural land (ha)
Yes
Developed land. Existing Cement
Manufacturing Unit of capacity 90000
TPA is developed on a plot area of
about 39.9 Acres 5 Guntas. Now the
proposal for expansion is proposed
to be developed on a plot area of
about 200 Acres.
2.2 Water (expected source &
competing users) unit: KLD
Yes
Source of water is from River
Ghataprabha. For total 02 Million
TPA proposed expansion capacity,
2100 KLD water is required. At
present, 24 KLD is used. For
proposed expansion, additional 2076
KLD is required.
2.3 Minerals (MT)
Yes
Raw materials required are Lime
Stone, Coke Breeze, Gypsum and
Clay (Silica).
2.4 Construction material – stone,
aggregates, sand / soil (expected
source – MT)
Yes
As estimated:
Sand - 5000 MT
Coarse aggregate - 6200m3
Fine aggregate -4800 m3
Cement - 124 MT
Steel - 600 MT
Bricks - 5200 MT
2.5 Forests and timber (source – MT) No
Wood – 09 MT
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes The power required would be
additional 58250 KVA for additional
capacity of 2 Million TPA Cement
7
Manufacturing Facility. At present,
1750 KVA is required. Total power
requirement will be 60000 KVA or
60 MVA.
The expansion proposal involves
establishment of Captive Power
Plant (50MW).
2.7 Any other natural resources (use
appropriate standard units)
No Not Applicable
3. Use, storage, transport, handling or production of substances or materials, which
could be harmful to human health or the environment or raise concerns about
actual or perceived risks to human health.
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health or
the environment (flora, fauna, and
water supplies)
Yes Used Oil from the D.G.Sets.
3.2 Changes in occurrence of disease
or affect disease vectors (e.g.
insect or water borne diseases)
No During the construction period
especially in monsoon, the activities
may result pondage of water in the
dug - out areas of the site. This has
the potential for creation of
mosquitoes breeding and spreading
of vector borne diseases. The most
important construction aspects are
the impediment of temporary
drainage by blocked silt traps or the
ponding of water within foundation
works. Other mosquito breeding
sites may be created through the use
of uncovered water tanks. During
the construction careful attention
will be given to the design and
maintenance of earthworks and
drainage systems to avoid the
creation of significant habitat areas
for mosquito larvae. The use of
8
larvicides may be required to
prevent mosquito breeding in silt
traps.
3.3 Affect the welfare of people e.g.
by changing living conditions?
Yes Socio-economic status of the
surrounding area will improve.
3.4 Vulnerable groups of people who
could be affected by the project
e.g. hospital patients, children, the
elderly etc.,
No Not Applicable
3.5 Any other causes No Not Applicable
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
S.No.
Information/Checklist
confirmation
Yes/N
o
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
4.1 Soil, overburden or mine wastes Yes As soon as construction is over the
rubbish will be cleared and all
unbuilt surfaces reinstated.
Appropriate vegetation will be
planned and all such areas shall be
landscaped.
4.2 Municipal waste (domestic and or
commercial wastes)
Yes Papers, garden trash, plastics,
vegetable wastes, floor sweepings
etc are the domestic solid wastes to
be generated from the industry
premises. These wastes are handed
over to Local Municipality.
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
Yes Used Oil from the D.G.Sets.
4.4 Other industrial process wastes
Yes Dust from Crusher Sections, Raw
Mill Sections, Raw Mill Storage
Sections, Kiln Sections, Cement Mill
Sections and Cement Storage Silos.
4.5 Surplus product
No Not Applicable
4.6 Sewage sludge or other sludge from
effluent treatment
No Not Applicable
4.7 Construction or demolition wastes Yes The generation of waste material is
inevitable during the construction
9
activity. Waste is generated at
different stages of the construction
activity. Waste during construction
activity relates to excessive cement
mix or left over concrete after the
work is over, rejection caused due to
change in design or wrong
workmanship etc. Concrete appears
in two forms in the waste. Structural
elements of building have reinforced
concrete, while foundations have
mass non-reinforced concrete.
Excavation of earth and rock
generates muck. Other wastes
include topsoil, clay, sand, and
gravel. These are normally re-used as
filler material at the plant site after
completion of excavation work, for
internal road
works/pavements/drains etc.
4.8 Redundant machinery or equipment No Not Applicable
4.9 Contaminated soils or other
materials
No Not Applicable
4.10 Agricultural wastes
No Not Applicable
4.11 Other solid wastes
No Any other solid waste generation
will be suitably collected and will be
disposed off scientifically as per
KSPCB norms.
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever
possible) with source of
information data
10
5.1 Emissions from combustion of fossil
fuels from stationary or mobile
sources
Yes
Air emissions comprising SPM,
RSPM, NOx, unburnt hydrocarbon
and SO2 will be from the operating
D.G. sets, Kilns and from air
pollution sources as listed which
is used as the standby power
source. Besides DG sets, air
emissions will also be from the raw
material carrying vehicles. Hence,
expected air emissions in the
vicinity of the proposed project
will be PM10, PM2.5, NO2, SO2 and
un-burnt HC.
5.2 Emissions from production
processes
Yes
Dust from Crusher Sections, Raw
Mill Sections, Raw Mill Storage
Sections, Kiln Sections, Cement
Mill Sections and Cement Storage
Silos.
Emissions from D.G Set can also
be noticed.
5.3 Emissions from materials handling
including storage or transport Yes
Dust emissions arise during
loading and unloading of the Raw
materials and products.
5.4 Emissions from construction
activities including plant and
equipment
Yes
The potential impacts on ambient
air quality from the proposed
expansion project would occur
mainly during project construction
phase. Particulate Matter10 (PM10)
and Particulate Matter2.5 (PM2.5)
would be the predominant
pollutant generated from
construction activities. The gaseous
emissions such as SO2, NOx and
unburnt hydrocarbons would be
generated from the construction
equipments and vehicles.
Impact of construction activities on
air quality is a cause for concern
mainly in the dry months due to
settling of dust particles. The main
sources of emission during the
construction period are the
11
movement of construction
equipments at site and dust
emitted during the leveling,
grading, earthworks, foundation
works and other construction
related activities. The dust emitted
during the above mentioned
activities depend upon the type of
soil being excavated and the
ambient humidity levels. The
impact is likely to be for short
duration and confined locally to
the construction site itself. The
composition of dust in this kind of
operation is however mostly coarse
particles, inorganic and non-toxic
in nature. These are not expected to
travel long distance before settling.
Exhaust emissions from vehicles
and equipment deployed during
the construction phase also result
in marginal increase in the levels
of SO2, NOx, PM, and unburnt
hydrocarbons. It may, therefore, be
deduced that construction activities
may cause changes in the PM10
and PM2.5 levels locally. The
impact will, however, be
reversible, marginal, and
temporary in nature.
The impact of such activities
would be temporary and restricted
to the construction phase only. The
impact will be confined within the
project boundary and is expected
to be negligible outside the project
boundaries. Proper upkeep and
maintenance of vehicles,
sprinkling of water on roads at
construction site, providing
sufficient vegetation etc. are some
12
of the proposed measures that
would greatly reduce the impact on
the air quality during the
construction phase of the project.
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
Yes Dust can be noticed during loading
and unloading of raw materials
and products.
5.6 Emissions from incineration of
waste No
Not Applicable
5.7 Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
No
Not Applicable
5.8 Emissions from any other sources
No
Not Applicable
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
Sl.No. Information/Checklist
confirmation Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data with
source of information data
6.1 From operation of equipment e.g.
engines, ventilation plant, crushers
Yes
During the operational phase, noise
generation will be from the DG set,
vehicles movement and general
noise characteristic of a industry.
The DG set room is isolated from the
outside environment and proper
acoustic arrangements are made to
control the noise generated from the
DG Set. The noise levels in and
around the proposed industry are
maintained within the stipulated
norms both during the day and night
time as per KSPCB norms.
6.2 From industrial or similar
processes
Yes
Refer 6.1
6.3 From construction or demolition Heavy construction traffic for
loading and unloading, fabrication
and handling of equipment and
construction materials are likely to
13
cause an increase in the ambient
noise levels. The areas affected are
those close to the site. At the peak
period of the construction, marginal
increase in noise levels is expected
to occur locally at the construction
site.
Further to minimize potential noise
level impacts, major construction
activities would be scheduled during
normal daylight working hours and
would be implemented consistent
with the applicable standards. The
construction contractor will use
equipments that are adapted to
operate with appropriate noise
muffling devices resulting in the
least possible noise. Every effort
would be taken to minimize the
noise levels including the mandatory
use of construction equipment with
operable mufflers.
Overall, the impact of noise
generated on the environment is
likely to be insignificant, reversible
and localized in nature and mainly
confined to daytime and reduces
gradually as the project progresses.
6.4 From blasting or piling
No Not Applicable
6.5 From construction or operational
traffic
Yes
Heavy construction traffic for
loading and unloading, fabrication
and handling of equipment and
construction materials are likely to
cause an increase in the ambient
noise levels. The areas affected are
those close to the site. At the peak
period of the construction, marginal
increase in noise levels is expected
to occur locally at the construction
14
site.
Further to minimize potential noise
level impacts, major construction
activities would be scheduled during
normal daylight working hours and
would be implemented consistent
with the applicable standards. The
construction contractor will use
equipments that are adapted to
operate with appropriate noise
muffling devices resulting in the
least possible noise. Every effort
would be taken to minimize the
noise levels including the mandatory
use of construction equipment with
operable mufflers. Overall, the
impact of noise generated on the
environment is likely to be
insignificant, reversible and
localized in nature and mainly
confined to daytime and reduces
gradually as the project progresses.
6.6 From lighting or cooling systems
No Not Applicable
6.7 From any other sources
No Not Applicable
7. Risks of contamination of land or water from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
7.1 From handling, storage, use or
spillage of hazardous materials Yes
HSD is used in D.G Sets. DG set
used oil will be stored in
barrels/drums and will be handed
over to KSPCB authorised
15
reprocessors.
7.2 From discharge of sewage or
other effluents to water or the
land (expected mode and place of
discharge)
No
Water will be used for cooling
purpose and shall be completely
recirculated. Hence, no effluent
generation from the process, and it
will be a Zero discharge unit.
Domestic sewage generated will be
treated in Septic Tank and Soak Pit.
7.3 By deposition of pollutants
emitted to air into the land or into
water
No Not Applicable
7.4 From any other sources
No Not Applicable.
7.5 Is there a risk of long term build
up of pollutants in the
environment from these
sources?
No
There is no risk anticipated for long
term build up of pollutants in the
environment from any of the source.
8. Risk of accidents during construction or operation of the Project, which could
affect human health or the environment
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever
possible) with source of
information data
8.1 From explosions, spillages, fires
etc from storage, handling, use or
production of hazardous
substances
No
Construction labourers will be
provided with necessary PPE
depending upon their nature of
activity. Risk Assessment and
Disaster Management Plan will be
prepared. Environment Health and
Safety will be the Industry’s top
priority.
8.2 From any other causes
No
Not Applicable
8.3 Could the project be affected by No The plant area falls in Zone-II of
16
natural disasters causing
environmental damage (e.g.
Floods, earthquakes, landslides,
cloudburst etc)?
Seismic Zoning Map of India. The
seismic factors will be
appropriately incorporated in the
civil designs for the project. No
records on floods, Earth
quakes/land slides/cloud burst in
the area.
9. Factors which should be considered (such as consequential development)
which could lead to environmental effects or the potential for cumulative
impacts with other existing or planned activities in the locality
S. No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
9.1 Lead to development of
supporting
Utilities, ancillary development
or development stimulated by
the project which could have
impact on the environment e.g.:
• Supporting infrastructure
(roads, power supply, waste or
waste water treatment, etc.)
• housing development
• extractive industries
• supply industries
• other
No Not Applicable
9.2 Lead to after-use of the site,
which could have an impact on
the environment
No Not Applicable
9.3 Set a precedent for later
developments No Not Applicable
17
9.4 Have cumulative effects due to
proximity to other existing or
planned projects with similar
effects
No Not Applicable
(III) Environmental Sensitivity
S.No. Areas
Name/
Identity
Aerial distance (within 15 km.)
Proposed project location
boundary
1 Areas protected under international
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
Nil Not Applicable
2 Areas which are important or
sensitive for ecological reasons -
Wetlands, watercourses or other
water bodies, coastal zone,
biospheres, mountains, forests
Yes
Ghataprabha River located at a
distance of 10 Kms from the
plant in the Northern direction.
Ningapur Reserved Forest
located at a distance of 6.0 Kms
from the plant in the northern
direction.
3 Areas used by protected, important or
sensitive species of flora or fauna for
breeding, nesting, foraging, resting,
over wintering, migration
Nil Not Applicable
4 Inland, coastal, marine or
underground waters
Nil Not Applicable
5 State, National boundaries
Nil Not Applicable
6 Routes or facilities used by the public
for access to recreation or other tourist,
pilgrim areas
SH44
SH55
SH34
Within 15 kms from the project
site
7 Defence installations
Nil Not Applicable
18
8 Densely populated or built-up area
Yes
Nearest village
Bamanbudni is located on
East direction at about 1.5
Km away.
Village Ningapur is
located about 2 Km on
NW direction, Village
Halaki is located about 2.5
Km away on West
direction
Village Kamakeri is
located on south direction
about 3 Km away from
the unit.
9 Areas occupied by sensitive man-made
land uses (hospitals, schools, places of
worship, community facilities)
Yes
Nearest village
Bamanbudni is located on
East direction at about 1.5
Km away.
Village Ningapur is
located about 2 Km on
NW direction, Village
Halaki is located about 2.5
Km away on West
direction
Village Kamakeri is
located on south direction
about 3 Km away from
the factory.
10 Areas containing important, high
quality or scarce resources
(ground water resources, surface resources,
forestry, agriculture, fisheries, tourism,
minerals)
Nil Not Applicable
11 Areas already subjected to pollution or
environmental damage. (those where
existing legal environmental standards
are exceeded)
Nil Not Applicable
12 Areas susceptible to natural hazard
which could cause the project to
present environmental problem
Nil Not Applicable.
19