Appendix 3 - JICAopen_jicareport.jica.go.jp/pdf/12253902_03.pdf · I=1/2,000 (Main canal) N o. 0 +...

208
Appendix 3

Transcript of Appendix 3 - JICAopen_jicareport.jica.go.jp/pdf/12253902_03.pdf · I=1/2,000 (Main canal) N o. 0 +...

  • Appendix 3

  • 3-1 HALECOU IRRIGATION SCHEME IN BOBONARO DISTRICT

    3-1

  • N

    NR1389 320

    3-2

  • No.0+225Diversion gateMa

    in canal

    Seconda

    ry canal

    Main canal

    I=1/2,000 (Main canal)

    No.0+

    0

    No.0+

    225

    Divers

    ion ga

    te

    No.0+

    500

    Cros

    s sec

    . P1

    2,5001,000750 750

    1,50

    0

    350

    EL 83.50

    C

    Crushed stone

    150

    0.5

    T.EL 88.00

    T.EL 87.00

    T.EL 86.00

    T.EL 85.00

    T.EL 84.00

    T.EL 83.00

    T.EL 82.00

    Wet masonry (t=350)

    1

    No.0+000

    Seco

    ndar

    y

    600

    Main canal

    Concrete lining (t=100mm)

    1,40

    0

    150

    200 3,300Gate BxH=1.6m x 1.4m

    3,50

    01,

    000

    1,50

    01,

    000

    Wet masonry

    T.EL 11.822

    1,000

    2001,500

    2001,000

    3,900

    150

    1,50

    025

    010

    0

    1,75

    0

    Gate BxH=1.6m x 1.4m

    B

    B

    Sec. A-A Sec. B-B

    Wet masonry

    No.0+225

    C

    C

    Crushed stone Crushed stone

    2,200

    700750 750

    1,50

    0350

    EL 83.388

    C

    Crushed stone

    150

    0.5

    Wet masonry (t=350)

    3,500

    3,100200200

    2,7001,000 700 1,000

    Slop

    e c

    hang

    ing

    Slope changing

    Slop

    e c

    hang

    ing

    Slope changing

    Gate BxH=0.8m x 1.0m

    3,500

    2,5001,000750 750

    1,50

    0

    350

    EL 83.388

    C

    Crushed stone

    Wet masonry (t=350)

    0.5

    1

    150

    1

    Sec. of Secondary canal

    Sec. of Main canal

    EL 83.254

    0.5

    T.EL 88.00

    T.EL 87.00

    T.EL 86.00

    T.EL 85.00

    T.EL 84.00

    T.EL 83.00

    T.EL 82.00

    2,5001,000750 750

    1,50

    0

    350C

    Crushed stone

    Wet masonry (t=350)

    1

    150

    No.0+500

    3-3

  • I=1/2,000 (Main canal)

    No.0+

    650

    Divers

    ion ga

    te

    No.1+

    000

    Cros

    s sec

    . P2

    Main cana

    l

    Earth

    cana

    l

    600

    Main canal

    Gate BxH=0.7m x 0.6m

    EL 83.175

    Concrete lining (t=100mm)

    1,40

    0

    250

    2005,000

    Gate BxH=1.6m x 1.4m

    5,000

    700 700 3,200

    3,50

    01,

    000

    1,50

    01,

    000

    200

    Wet masonry

    EL 83.175

    1,000

    2001,500

    2001,000

    3,900

    150

    1,50

    025

    010

    0

    Gate BxH=1.6m x 1.4m

    B

    B

    Sec. A-A Sec. B-B

    200

    Wet masonry

    No.0+500

    C

    C

    Crushed stone Crushed stone

    Slop

    e c

    hang

    ing

    Slope changing

    Slop

    e c

    hang

    ing

    Slope changing

    2,5001,000750 750

    1,50

    0350

    EL 83.175

    C

    Crushed stone

    Wet masonry (t=350)

    0.5

    1

    150

    Sec. of Main canal

    2,500Cross bridge

    Gate BxH=1.6m x 1.4m

    2,050 2,500Cross bridge

    200

    1,50

    0

    T.EL 88.00

    T.EL 87.00

    T.EL 86.00

    T.EL 85.00

    T.EL 84.00

    T.EL 83.00

    T.EL 82.00

    2,5001,000750 750

    1,50

    0

    350

    EL 83.175

    C

    Wet masonry (t=350)

    0.5

    1

    150

    No.1+000

    3-4

  • NORTH

    I=1/2,000 (Main canal)I=1/1,000 (Secondary canal)

    No.1+

    350

    No.1+

    500

    Cros

    s sec

    . P3

    0.50

    Main cana

    l

    Secondary

    canal

    T.EL 86.00

    T.EL 85.00

    T.EL 84.00

    T.EL 83.00

    T.EL 82.00

    Earth

    cana

    l

    600

    Main canal

    Gate BxH=0.7m x 0.6m

    EL 82.825

    Concrete lining (t=100mm)

    1,40

    0

    250

    2005,000

    Gate BxH=1.6m x 1.4m

    5,000

    700 700 3,200

    3,50

    01,

    000

    1,50

    01,

    000

    200

    Wet masonry

    EL 82.825

    1,000200

    1,500200

    1,000

    3,900

    150

    1,50

    025

    010

    0

    Gate BxH=1.6m x 1.4m

    B

    B

    Sec. A-A Sec. B-B

    200

    Wet masonry

    No.1+350

    C

    C

    Crushed stone Crushed stone

    Slop

    e c

    hang

    ing

    Slope changing

    2,5001,000750 750

    1,50

    0

    350

    EL 82.825

    C

    Crushed stone

    Wet masonry (t=350)

    0.5

    1

    150

    Sec. of Main canal

    2,500Cross bridge

    Gate BxH=1.6m x 1.4m

    2,050 2,500Cross bridge 200

    1,50

    0

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    2,5001,000750 750

    1,50

    0

    350

    EL 82.825

    C

    Crushed stone

    Wet masonry (t=350)

    0.5

    1

    150

    Slop

    e c

    hang

    ing

    Slope

    cha

    nging

    500

    1,00

    0

    Secondary canalMain canal

    Sec. of Secondary canal

    Wet masonry

    Secondary canal

    Wet masonry

    Main canal

    I=1/2000 I=1/1000

    I=1/1000

    I=1/2000

    No.1+350

    T.EL 85.00

    T.EL 84.00

    T.EL 83.00

    T.EL 82.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 82.175

    No.1+500

    3-5

  • NORTH

    I=1/1,000

    No.1+

    550

    No.2+

    000

    Cros

    s sec

    . P4

    I=1/1,000 0.50

    Main canal

    Secondary canal

    1,60

    030

    01,

    000

    300

    B

    B

    C

    C1,5001,000250 250

    1,00

    0C

    Crushed stone

    Wet masonry (t=250)

    Sec. of Secondary canal

    Wet masonry

    Secondary canal

    Sec. A-A

    100

    1,00

    0

    300500

    500 1,00

    0

    Secondary canal

    I=1/1000

    I=1/1000

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    Sec. of Secondary canal(B-B)

    EL. 82.125

    EL. 81.625

    (Drop)(C-C)

    T.EL 85.00

    T.EL 84.00

    T.EL 83.00

    T.EL 82.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 82.125

    EL. 81.625

    No.1+550

    T.EL 83.00

    T.EL 82.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 81.175

    No.2+000(Cross no. P4)

    T.EL 81.00

    T.EL 80.00

    Earth

    cana

    l

    600

    Secondary canal

    Gate BxH=0.7m x 0.6m

    EL 81.175

    Concrete lining (t=100mm)

    900

    250

    2505,000

    Gate BxH=1.6m x 1.4m

    700 700

    Wet masonry

    Sec. A-A

    Wet masonry

    Crushed stone

    2,500Cross bridge

    Gate BxH=1.2m x 0.9m

    2,500Cross bridge

    1,00

    0

    1,00

    0

    Secondary canalMain canal

    Wet masonry

    Secondary canal

    Wet masonry

    Main canal

    I=1/2000 I=1/1000

    I=1/1000I=1/1000

    5,000

    EL 81.175

    3-6

  • NORTH

    No.2+

    465

    Cros

    s sec

    . P5

    I=1/1,000

    Secondary can

    al

    T.EL 83.00

    T.EL 82.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 80.710

    No.2+465(Cross no. P5)

    T.EL 81.00

    T.EL 80.00

    C

    3-7

  • NORTH

    No.2+

    550

    Cros

    s sec

    . P7

    No.2+

    500

    Cros

    s sec

    . P6

    No.2+

    975

    Cros

    s sec

    . P8

    I=1/1,0000.50

    Secondary can

    al

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 80.675

    No.2+500(Cross no. P6)

    C

    Secondary canal

    1,60

    030

    01,

    000

    300

    B

    B

    No.2+500

    C

    C1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    Sec. of Secondary canal

    Wet masonry

    Secondary canal

    Sec. A-A

    100

    1,00

    0

    300500

    500 1,00

    0

    Secondary canal

    I=1/1000

    I=1/1000

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    Sec. of Secondary canal(B-B)

    EL. 80.675

    EL. 80.175

    (Drop)(C-C)

    T.EL 83.00

    T.EL 82.00

    T.EL 81.00

    T.EL 80.00

    EL. 80.675

    EL. 80.175

    EL. 80.175

    T.EL 79.00

    T.EL 78.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 80.125

    No.2+550(Cross no. P7)

    T.EL 83.00

    T.EL 82.00

    T.EL 81.00

    T.EL 80.00

    CT.EL 79.00

    T.EL 78.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 79.700

    No.2+975(Cross no. P8)

    C

    T.EL 83.00

    T.EL 82.00

    T.EL 81.00

    T.EL 80.00

    T.EL 79.00

    T.EL 78.00

    3-8

  • NO

    RTH

    No.3+

    300

    Cros

    s sec

    . P9

    No.3+

    500

    Cros

    s sec

    . P10

    I=1/1,000I=1/600

    2.00

    Secondary can

    alT.EL 80.00

    T.EL 79.00

    T.EL 78.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 77.042

    No.3+350(Cross no. P10)

    T.EL 77.00

    Secondary canal

    1,60

    030

    01,

    000

    300

    B

    B

    C

    C1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    Sec. of Secondary canal

    Wet masonry

    Sec. A-A

    100

    1,00

    0

    1,935

    2,00

    0

    1,00

    0

    Secondary canal

    I=1/1000

    I=1/1000

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    Sec. of Secondary canal(B-B)

    EL. 79.375

    EL. 77.375

    (Drop)

    (C-C)

    EL. 79.375

    EL. 77.375

    Concrete wall Wet masonry

    3,60

    0

    300

    1,00

    01,

    000

    1,00

    030

    0

    350 1,000 600 300

    T.EL 81.00

    T.EL 80.00

    T.EL 79.00

    T.EL 78.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 77.375

    No.3+300(Cross no. P9)

    3-9

  • NO

    RTH

    No.3+

    950

    Cros

    s sec

    . P11

    I=1/600

    Secondary can

    al

    T.EL 80.00

    T.EL 79.00

    T.EL 78.00

    1,5001,000250 250

    1,00

    0

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 76.292

    No.3+950(Cross no. P11)

    T.EL 77.00

    3-10

  • No.4+

    115

    Cros

    s sec

    . P12

    No.4+

    150

    Cros

    s sec

    . P13

    No.4+

    450

    Cros

    s sec

    . P14

    I=1/600

    T.EL 80.00

    T.EL 79.00

    T.EL 78.00

    1,5001,000250 250

    500

    C

    Crushed stone

    Wet masonry (t=250)

    EL. 76.017

    No.4+115(Cross no. P12)

    T.EL 77.00

    T.EL 80.00

    T.EL 79.00

    T.EL 78.00

    EL. 75.958

    No.4+150(Cross no. P13)

    T.EL 77.00

    T.EL 76.00

    1,5001,000250 250

    500

    C

    Crushed stone

    Wet masonry (t=250)

    T.EL 75.00

    T.EL 76.00

    T.EL 75.00

    T.EL 80.00

    T.EL 79.00

    T.EL 78.00

    EL. 75.458

    No.4+450(Cross no. P14)

    T.EL 77.00

    T.EL 76.00

    1,5001,000250 250

    500

    C

    Crushed stone

    Wet masonry (t=250)

    T.EL 75.00

    (Seasonal stream)

    3-11

  • End of canal : Adjust to site condition and discharge to seasonal river

    No.4+

    630

    Cros

    s sec

    . P15

    No.4+

    950

    Cros

    s sec

    . P16

    I=1/600

    Secondary can

    alEL. 75.158

    No.4+630(Cross no. P15)

    T.EL 77.00

    T.EL 76.00

    1,5001,000250 250

    500

    C

    Crushed stone

    Wet masonry (t=250)

    T.EL 75.00

    No.4+950(Cross no. P16 : End of canal)

    T.EL 76.00

    CT.EL 75.00

    T.EL 74.00End of canal : Adjust to site condition and discharge to seasonal river

    3-12

  • PLAN 1 : HALECOU IRRIGATION SCHEME IN BOBONARO DISTRICT

    3-13

  • GRID N:9013970.000GRID E:736259.000LATITUDE: -8°54'50.371"LONGITUDE: 125°08'54.607"

    BM.0

    Z +88.000

    ±84.00

    83.60

    ±86.5

    ± 86.5~87.5083.90EL83.75

    150,000

    15,00

    0

    Bed protection for water guide

    150,000

    110,000 40,000(Intake)

    (Approach canal) (Flash gate)Head of intakewith gate Groin L=10m

    15,000

    Concrete block (2tf~3tf)

    Gabion

    River bedRiver bed

    1,50

    0~2

    ,000

    N

    Plan 1 : General plan of Halecou irrigation scheme

    Typical Sec. of bed protection for water guide

    3-14

  • EL86.50

    EL83.60 EL83.75

    EL87.00

    EL89.20

    EL87.00

    EL83.20EL±83.00River bed

    2,900

    500

    500

    3,400

    3,250

    650

    3,400

    500

    2,000

    800 2,000 800 2,000 800400400 150 500 150 400 400

    6,400 2,000

    2,200

    BxH=2.0m x 2.0m

    2,700

    EL83.75 EL83.60

    EL86.5086.50

    FLOW

    EL83.60 EL83.60I=1/67

    EL86.50

    EL86.50

    2,700

    2,900

    500

    1,500 1,000 2,500

    10,000 5,0005,000

    200

    200

    600

    300300

    3,800300

    3005,000

    300 82.50

    9,000

    7,000 2,000

    2,90

    0~4,0

    002,0

    00

    400

    4004

    0 0

    BxH=2.0m x 2.0m

    2,50

    0~2,6

    0040

    0

    400 2,000 400

    2,800

    Gabion

    Concrete Block(2.5t/block)

    I=1/8

    EL83.75

    EL89.20

    EL87.00

    EL83.90

    10,000

    EL84.00 I=1/1100

    EL86.50

    110,000

    Concrete Block(2.5t/block)

    FLOWFLOW

    (Flash gate)14,400

    (Bed protection)

    2,90

    0~4,0

    0040

    0

    400 4,000 400

    4,800

    Gabion

    EL83.60~82.50

    EL84.00~83.90

    EL86.50

    EL86.50

    EL86.50

    EL83.75EL83.90

    EL86.50

    1,500 1,000 2,500

    EL86.50

    2,200

    3,250

    550

    300300

    3003,800

    300300

    5,000

    10,000 5,0005,00010,000(Intake gate)

    2,750

    400 2,000~4,800 400

    2,800~5,600

    Gabion

    EL83.90~83.75

    EL86.50

    200

    1,350

    200

    BxH=1.85m x 2.0m

    Exist

    ing in

    take

    600

    I=1/450I=1/67

    3,250

    400 2,000 400

    2,800

    Gabion

    EL83.75

    EL87.00

    400

    FLOW FLOW

    8,000

    EL±84.00~±83.00River bed

    A

    A

    B

    B

    D

    D

    E

    E

    Sec. A-A

    Gabion

    8,000

    EL±84.00~±83.00River bed

    Sec. B-B

    EL86.50

    C

    C

    2,750

    ~2,90

    0

    400 2,000~4,800 400

    2,800~5,600

    Gabion

    EL83.75~83.60

    EL86.50

    EL83.75

    2,000 0~2,800

    Gabion

    8,000

    EL±84.00~±83.00River bed

    Sec. C-C

    EL86.50

    2,750

    400

    400

    400~

    550

    Sec. D-D

    8,000

    Gabion

    Sec. E-E

    EL±83.00River bed

    8,000

    Sec. F-F

    (for flash gate)

    F

    F

    600 600 600

    1,800

    600

    600

    6001

    ,800

    600

    Concrete Block(2~2.5t/bolck)

    G

    G

    3,25

    0~3,5

    00

    400 1,500 400

    2,300

    Gabion

    EL83.75~83.50

    EL87.00

    400

    Sec. G-G(for intake canal)

    (Flash gate) (Flash gate)

    (Main canal)

    (Settlement pond) (Settlement pond)

    (Settlement pond) (Settlement pond)

    BxH=1.85m x 2.0m

    Guide of stoplog

    EL89.60

    BxH=2.0m x 2.0m

    2,500

    3100

    Longitudinal Sec. of Intake(for Flash gate)

    Longitudinal Sec. of Intake(for Intake gate)

    (for intake canal)

    Irrigation water

    Flashed sedimentation

    FLOW

    5,0005,000 9,00010,000110,000(Flash gate)

    14,400(Bed protection) (Flash gate)(Settlement pond) (Settlement pond)

    10,000

    Nunura river

    Flashed sedimentation

    Irrigation water

    General plane of Intake

    Plan 1 : Structure of Intake

    3-15

  • PLAN 2 : HALECOU IRRIGATION SCHEME IN BOBONARO DISTRICT

    3-16

  • GRID N:9013970.000GRID E:736259.000LATITUDE: -8°54'50.371"LONGITUDE: 125°08'54.607"

    BM.0

    Z +88.000

    ±84.00

    82.7~83.0

    150,00015

    ,000

    Bed protection for water guide

    150,000

    110,000 40,000(Intake)

    (Approach canal) (Flash gate)Head of intakewith gate Groin L=10m

    83.60

    ±86.5

    ± 86.5~87.50

    ±87.0

    83.90

    83.7583.75

    ±86.5

    Colleting drain channel

    300,000

    (HP φ1,200mm covere

    d by concrete)

    15,000

    Concrete block (2tf~3tf)

    Gabion

    River bedRiver bed

    1,50

    0~2

    ,000

    Plan 2 : General plan of Halecou irrigation scheme

    Typical Sec. of bed protection for water guide

    3-17

  • EL86.50

    EL83.60 EL83.75

    EL87.00

    EL89.20

    EL87.00

    EL83.20EL±83.00River bed

    2,90

    050

    0

    500

    3,40

    0

    3,25

    065

    0

    3,40

    050

    0

    2,000

    800 2,000 800 2,000 800400400 150 500 150 400 400

    6,400 2,000

    2,20

    0

    BxH=2.0m x 2.0m

    2,70

    0

    EL83.75 EL83.60

    EL86.5086.50

    FLOW

    EL83.60 EL83.60I=1/67

    EL86.50

    EL86.50

    2,70

    02,

    900

    500

    1,500 1,000 2,500

    10,000 5,0005,000

    200

    200

    600

    300300

    3,800300

    3005,000

    300 82.50

    9,000

    7,000 2,000

    2,900

    ~4,00

    02,

    000

    400

    4004

    0 0BxH=2.0m x 2.0m

    Concrete Block(2.5t/block)

    I=1/8

    EL83.75

    EL89.20

    EL87.00

    EL83.90

    10,000

    EL84.00 I=1/1100

    EL86.50

    110,000

    Concrete Block(2.5t/block)

    FLOWFLOW

    (Spill way gate)14,400

    (Bed protection)

    Guide of stoplog

    EL86.50

    EL83.75EL83.90

    EL86.50

    1,500 1,000 2,500

    EL86.50

    2,20

    03,

    250

    550

    300300

    3003,800

    300300

    5,000

    10,000 5,0005,00010,000(Intake gate)

    200

    1,35

    0

    200

    BxH=1.85m x 2.0mEx

    isting

    intak

    e

    600

    I=1/450I=1/67

    FLOW FLOW

    A

    A

    B

    B

    D

    D

    E

    E

    C

    C

    Sec. D-D

    8,000

    Gabion

    F

    F

    600 600 600

    1,800

    600

    600

    6001

    ,800

    600

    Concrete Block(2~2.5t/bolck)

    G

    G

    (Spill way) (Spill way)

    (Main canal)

    (Settlement pond) (Settlement pond)

    (Settlement pond) (Settlement pond)

    BxH=1.85m x 2.0m

    2,000400(Outlet of drainpipe)

    3,700

    HP φ

    1,200

    mm

    FLOW

    1,20

    050

    0

    400 2,000 400

    2,800

    400

    2,500

    (Outlet of drainpipe)

    From collecting drain channel

    (Spill way gate)2,00

    0

    BxH=1.5m x 1.5m

    FLOWL=

    7.5m

    EL86.50

    BxH=2.0m x 2.0m

    H H

    HP φ1200mm (L=300m)

    Sec. H-H (Detail of outlet)

    Longitudinal Sec. of Intake(for Flash gate)

    Longitudinal Sec. of Intake(for Intake gate)

    2,50

    0~2,6

    0040

    0

    400 2,000 400

    2,800

    Gabion

    2,90

    0~4,

    000

    400

    400 4,000 400

    4,800

    Gabion

    EL83.60~82.50

    EL84.00~83.90

    EL86.50

    EL86.50

    2,75

    0

    400 2,000~4,800 400

    2,800~5,600

    Gabion

    EL83.90~83.75

    EL86.50

    3,25

    0

    400 2,000 400

    2,800

    Gabion

    EL83.75

    EL87.00

    400

    8,000

    EL±84.00~±83.00River bed

    Sec. A-A

    Gabion

    8,000

    EL±84.00~±83.00River bed

    Sec. B-B

    EL86.50

    2,75

    0~2,

    900

    400 2,000~4,800 400

    2,800~5,600

    Gabion

    EL83.75~83.60

    EL86.50

    EL83.75

    2,000 0~2,800

    Gabion

    8,000

    EL±84.00~±83.00River bed

    Sec. C-C

    EL86.50

    2,75

    0

    400

    400

    400~

    550

    Sec. E-E

    EL±83.00River bed

    8,000

    Sec. F-F

    (for flash gate)

    3,25

    0~3,

    500

    400 1,500 400

    2,300

    Gabion

    EL83.75~83.50

    EL87.00

    400

    Sec. G-G(for intake canal) (for intake canal)

    Irrigation water

    Flashed sedimentation

    FLOW

    5,0005,000 9,00010,000110,000(Flash gate)

    14,400(Bed protection) (Flash gate)(Settlement pond) (Settlement pond)

    10,000

    Nunura river

    Flashed sedimentation

    Irrigation water

    General plane of Intake

    2,800(Outlet of drainpipe)

    FLOWBxH=1.5m x 1.5m

    FLOW

    HP φ1200mm (L=300m)

    180,000(HP covered by concrete)

    120,000(HP)

    Flash gate

    Intake gate

    From collecting drain channel

    Plan 2 : Structure of Intake

    3-18

  • EL84.00R

    iver bed

    EL±84.00 EL84.00

    600 11,900 500 11,900 500

    4,100

    500

    1,000

    2,000

    1,100

    500

    26,300

    4,100 3

    ,000

    1,100

    2,100

    500

    2,500

    2,500

    500

    1,500

    500

    500

    5,000

    500

    5,000

    500

    5,000

    500

    17,00

    0

    3,000600

    3,000

    600

    18,00

    050

    050

    016

    ,000

    500

    500

    EL81.30EL81.00

    EL84.00

    17,00

    0

    Concrete cover : L=180 m

    H P φ 1

    ,2 00 m

    m

    SP

    φ600mm

    @ 5

    SP

    φ600m

    m @

    5S

    P φ

    600mm

    @ 5

    EL81.30EL81.00

    EL81.00

    EL82.85

    EL±84.00

    25,400

    B

    A

    A

    Sec. A-A

    Sec. B-B

    Sec. Typical of pipe under river bed

    HP φ1200mm : L=300 m

    FLOW

    B

    FLOW

    Plan 2 : Structure of Collecting drain channel

    3-19

  • PLAN 3 : HALECOU IRRIGATION SCHEME IN BOBONARO DISTRICT

    3-20

  • GRID N:9013970.000GRID E:736259.000LATITUDE: -8°54'50.371"LONGITUDE: 125°08'54.607"

    BM.0

    Z +88.000

    200,0

    00

    16,50028,500

    7,400

    150,000

    28,500

    130,00

    0

    83.60

    ±86.5

    ±86.5~87.5083.90

    83.7583.75

    ±86.5

    (Fixe

    d we

    ir)(F

    lash

    gate)

    (Bank

    protec

    tion

    for low

    water

    at D.S

    .)

    (Bank protection

    for low water at U.S.)

    150,000

    87,500 40,000(Intake)

    (Approach canal) (Flash gate)

    N

    Plan 3 : General plan of Halecou irrigation scheme

    3-21

  • EL84.30

    EL86.50

    EL83.80

    EL86.50

    EL84.00

    EL83.00

    10,000

    EL83.60EL83.60

    10,500 8,400 7,000 47,000

    EL86.50

    (Flash gate) (Intake / U.S. apron)(D.S apron) (Retaining wall at U.S.)(Retaining wall at D.S)90,000

    (Gabion)

    C

    FLOW

    EL86.50 EL86.50

    400

    2,000

    2,900

    1,55

    0

    1,000500

    6,500

    500

    1,000 5,000 900500

    500500

    8,000

    1,50

    01,

    500

    3,500

    5002,500

    500

    5,600

    500500 1,500 600 1,500 500

    500

    400

    1,800

    2,70

    01,

    500

    600

    3,20

    0

    1,200 960 400

    600

    4,100

    1,200 1,230 400

    EL83.00

    EL84.00

    EL85.00

    1,5002,000

    15,000

    4,00

    0

    1,000450

    2,050

    16,500

    2,00

    01,

    550

    EL84.00

    EL83.00

    28,500

    600

    13,0001,450

    C

    (Bed protection block) (Fixed weir)

    EL84.30~83.90

    EL85.10

    EL86.30

    FLOW

    BxH=1.1m x 1.5m

    EL88.70

    WL85.10

    200

    2,80

    0

    300

    2,000 6,600 7,400 200,000 10,000

    600 3,000 800 3,000 600

    400

    2,00

    02,

    900

    1,55

    060

    0

    2,00

    01,

    550

    7,600

    EL86.50

    EL85.00

    EL83.60EL83.00

    EL84.30

    A

    A

    Sec. A-A

    B

    B

    Sec. B-B

    C

    C

    D

    D

    Typical Sec. C-C Typical Sec. D-D(Retaining wall at D.S) (Retaining wall at U.S.)

    FLOW

    200

    1,80

    030

    0

    200

    2,80

    030

    0

    Sec. U.S. retaining wall at lfet bank (L=149.5m ) Sec. D.S. retaining wall at left bank (L=130.0m )

    Front sec. of Headworks

    (Fixed weir)(Flash gate)(Head of Intake)(Approach canal)

    Plan 3 : Structure of Headworks

    3-22

  • 3-2 SAKETO IRRIGATION SCHEME IN VIQUEQUE DISTRICT

    3-23

  • NORTH

    Drop and diversion gate

    Beginning of main canalDiversion gate

    Diversion gate

    Diversion gateDiversion gate

    Diversion gate

    Drop

    End of main canal

    3-24

  • FLOW

    3,628 4,200 5,000 2,825

    1,000 3,200 3,500 1,500 2,425 400

    5,00

    04,

    500

    500 1/354

    00

    700

    200

    1/35

    4,00

    0

    800

    6,000500 5,000 500

    3,50

    0

    4,00

    0

    5,000

    3,50

    0

    12,025

    4,2003,500 1,500

    2,425 400

    5,000

    3,628

    FLOW

    Existing Intake

    FLOW

    Assumed river bed line

    Assumed canal bed line

    (Wet masonry)Existing intake Existing canal

    FLOW

    800

    4,50

    0

    BxH=1.5m x 2.0m

    BxH=1.3m x 1.3m

    BxH=1.3m x 1.3m

    BxH=1.5m x 1.5m

    1,50

    0Fi

    xed w

    eir

    H P fo

    r san

    d fla s

    h

    6 ,500

    2,000

    HP φ1,200

    (Wet masonry)

    (Sedimentation pond)5,000

    Flash gate bed line

    60°

    0.3

    1

    2 ,500

    Assumed river bed line

    1,20

    0

    400

    5,50

    0

    2,500

    4,90

    060

    0

    600 1,900

    HP for sand flash

    Concrete lining (t=200mm)

    3,50

    0

    4,300

    1,050 2,200 1,050

    Wet masonry (t=350)

    350

    Crushed stone

    1,30

    040

    040

    0

    5,80

    0

    400

    5,00

    040

    0

    2,10

    0

    2,20

    01,

    550

    1,55

    0

    Existing canal

    1,30

    0

    Top of HW

    SAKETO RIVER

    2,500

    (L=1.0km)(Bank)

    Protection wall by gabion along river bank

    Drop and diversion gate

    Beginning of main canalDiversion gate

    Diversion gate

    Diversion gate

    Sedimentation pond

    Bank protection at Saketo

    Loction of Bank protection

    3-25

  • DATUM +5.00

    STATION

    OF CANAL ELEVATI0N

    OF CANAL ELEVATIONDESIGN CENTER

    EXISTING CENTER

    P0

    P1

    No.0 + 0

    No.0 +50

    Cross section No.

    No.0 +511

    No.0+

    0

    No.0+

    50

    I=1/2,500 (Main canal)

    No.0+

    511

    Cros

    s sec

    . P1

    Divers

    ion ga

    te

    Diversion gate

    Drop and diversion gate

    Beginning of main canalDiversion gate

    3,1001,500800 800

    1,00

    0150T.EL 13.192

    C

    Crushed stone

    150

    0.5

    1

    Concrete lining (t=100mm)

    T.EL 12.00

    Wet masonry (t=150)

    T.EL 13.00

    Seco

    ndar

    y

    600

    Main canal

    from

    H.W

    Gate BxH=0.7m x 0.6m

    T.EL 13.172

    Concrete lining (t=100mm)

    1,00

    015

    0

    200 3,100

    Gate BxH=1.45m x 1.0m

    3,250

    800200

    1,250200

    800

    3,100700 700 1,500

    3,25

    01,

    000

    1,25

    01,

    000

    200

    3,35

    0

    200

    2,95

    020

    0

    Wet masonry

    T.EL 13.172

    800200

    1,250200

    800

    3,250

    150

    1,00

    025

    010

    01,

    400

    Gate BxH=1.45m x 1.0m

    AA

    B

    B

    Sec. A-A Sec. B-BCrushed stone Crushed stone

    T.EL 14.00

    T.EL 15.00

    No.0+000

    No.0+000

    Wet masonry

    Concrete lining (t=100mm)

    Gate BxH=0.7m x 0.6m

    FLOW

    FLOW

    T.EL 13.172 T.EL 13.172

    T.EL 11.672T.EL 12.00

    Concrete lining (t=100mm)

    Wet masonry (t=150)

    Wet masonry (t=150)

    Seco

    ndar

    y

    6,900

    200 2,700 2,600 1,200 200

    1,00

    0

    3,25

    0

    1,00

    01,

    250

    600

    600

    1,00

    015

    01,

    250

    250

    250

    250 2,000 600 1,400

    4,250

    2,900

    200 2,700

    4,0002,600 1,200

    200

    Wet masonry

    Gate BxH=1.45m x 1.0m

    Crushed stone

    Gate BxH=1.45m x 1.0m

    3,35

    0

    No.0+50

    3,1001,500800 800

    1,00

    0150 T.EL 12.00

    T.EL 11.00

    C

    Crushed stone

    150

    0.5

    1

    Concrete lining (t=100mm)

    T.EL 12.00

    Wet masonry (t=150)T.EL 13.00

    T.EL 14.00

    No.0+54

    Seco

    ndar

    y

    600

    Main canal

    Gate BxH=0.7m x 0.6m

    T.EL 11.822

    Concrete lining (t=100mm)

    1,00

    015

    0

    200 3,100

    Gate BxH=1.45m x 1.0m

    3,300700 700 1,500

    3,25

    01,

    000

    1,25

    01,

    000

    200

    Wet masonry

    T.EL 11.822

    800200

    1,250200

    800

    3,250

    150

    1,00

    025

    010

    01,

    400

    Gate BxH=1.45m x 1.0m

    B

    B

    Sec. A-A Sec. B-B

    200

    Wet masonry

    T.EL 11.822

    600 1,650 800

    3,050

    250

    100

    1,40

    0

    Sec. C-C

    150 500 150

    600

    750

    150

    800

    T.EL 10.322

    1,50

    0

    Secondary canal : Wet masonry

    Typical Sec.(Secondary canal)

    600

    150

    C

    C

    Crushed stone Crushed stone

    Crushed stone

    No.0+511

    3-26

  • STATION

    DESIGN CENTER OF CANAL ELEVATION

    EXISTING CENTER OF CANAL ELEVATI0N

    DATUM +5.00

    P2

    Cross section No.

    I=1/2,500 (Main canal)

    No.1+

    112

    Cros

    s sec

    . P2

    No.0 +980

    No.0+

    980

    Divers

    ion ga

    te

    Diversion gate

    Seco

    ndar

    y

    600

    Main canal

    Gate BxH=0.7m x 0.6m

    T.EL 11.630

    Concrete lining (t=100mm)

    1,00

    015

    0

    200 3,100

    Gate BxH=1.45m x 1.0m

    3,300700 700 1,500

    3,25

    01,

    000

    1,25

    01,

    000

    200

    Wet masonry

    T.EL 11.630

    800200

    1,250200

    800

    3,250

    150

    1,00

    025

    010

    01,

    400

    Gate BxH=1.45m x 1.0m

    B

    B

    Sec. A-A Sec. B-B

    200

    Wet masonry

    No.0+980

    T.EL 11.630

    600 1,650 800

    3,050

    250

    100

    1,40

    0

    Sec. C-C

    150 500 150

    600

    750

    150

    800

    T.EL 11.300

    Secondary canal : Wet masonry

    Typical Sec.(Secondary canal) 60

    015

    0

    C

    C30

    0

    600

    Crushed stone Crushed stone

    Crushed stone

    3,1001,500800 800

    1,00

    0150 T.EL 11.570

    T.EL 11.00

    C

    150

    Crushed stone

    0.5

    Concrete lining (t=100mm)

    1

    Wet masonry (t=150)

    T.EL 12.00

    T.EL 13.00

    T.EL 14.00

    No.1+1123-27

  • STATION

    DESIGN CENTER OF CANAL ELEVATION

    EXISTING CENTER OF CANAL ELEVATI0N

    DATUM +5.00

    P3

    P4

    I=1/2,500 (Main canal)

    No.1 +500

    No.1 +855

    No.1+

    500

    No.1+

    616

    Cros

    s sec

    . P3

    Divers

    ion ga

    te

    No.1+

    855

    Divers

    ion ga

    te

    No.2+

    119

    Cros

    s sec

    . P4

    Diversion gate

    Diversion gate

    Seco

    ndar

    y

    600

    Main canal

    Gate BxH=0.7m x 0.6m

    T.EL 11.422

    Concrete lining (t=100mm)

    1,00

    015

    0

    200 3,100

    Gate BxH=1.45m x 1.0m

    3,300700 700 1,500

    3,25

    01,

    000

    1,25

    01,

    000

    200

    Wet masonry

    T.EL 11.422

    800200

    1,250200

    800

    3,250

    150

    1,00

    025

    010

    01,

    400

    Gate BxH=1.45m x 1.0m

    B

    B

    Sec. A-A Sec. B-B

    200

    Wet masonry

    No.1+500

    T.EL 11.422

    600 1,650 800

    3,050

    250

    100

    1,40

    0

    Sec. C-C

    150 500 150

    600

    750

    150

    800

    T.EL 11.122

    Secondary canal : Wet masonry

    Typical Sec.(Secondary canal)

    600

    150

    C

    C

    300

    600

    Crushed stone Crushed stone

    Crushed stone

    3,1001,500800 800

    1,000150 T.EL 11.375

    C

    T.EL 11.00

    T.EL 10.00

    150

    Crushed stone

    0.5

    Concrete lining (t=100mm)

    1

    Wet masonry (t=150)

    T.EL 12.00

    No.1+616

    Seco

    ndar

    y

    600

    Main canal

    Gate BxH=0.7m x 0.6m

    T.EL 11.280

    Concrete lining (t=100mm)

    1,00

    015

    0

    200 3,100

    Gate BxH=1.45m x 1.0m

    3,300700 700 1,500

    3,25

    01,

    000

    1,25

    01,

    000

    200

    Wet masonry

    T.EL 11.280

    800200

    1,250200

    800

    3,250

    150

    1,00

    025

    010

    01,

    400

    Gate BxH=1.45m x 1.0m

    B

    B

    Sec. A-A Sec. B-B

    200

    Wet masonry

    No.1+855

    T.EL 11.280

    600 1,650 800

    3,050

    250

    100

    1,40

    0

    Sec. C-C

    150 500 150

    600

    750

    150

    800

    T.EL 10.980

    Secondary canal : Wet masonry

    Typical Sec.(Secondary canal)

    600

    150

    C

    C

    300

    600

    Crushed stone Crushed stone

    Crushed stone

    3,1001,500800 800

    1,00

    0150 T.EL 11.174

    C

    T.EL 11.00

    T.EL 10.00

    Crushed stone

    0.5

    Concrete lining (t=100mm)

    1

    Wet masonry (t=150)

    T.EL 12.00

    No.2+119

    3-28

  • STATION

    DESIGN CENTER OF CANAL ELEVATION

    EXISTING CENTER OF CANAL ELEVATI0N

    DATUM +5.00

    P5

    P6

    P7

    P8

    I=1/2,500 (Main canal)I=1/2,500 (Main canal)

    No.2+

    357

    Cros

    s sec

    . P5 +

    2Dr

    op No.2+

    560

    Cros

    s sec

    . P6

    No.2+

    760

    Cros

    s sec

    . P7

    No.2+

    971

    Cros

    s sec

    . P8

    No.2 +357Drop

    0.50

    3,1001,500800 800

    1,00

    0150 T.EL 11.079

    C

    T.EL 11.00

    2,350

    750800 800

    1,00

    0

    150

    T.EL 10.579

    C

    T.EL 11.00Crushed stone

    150

    0.5

    Concrete lining (t=100mm)

    Crushed stone

    0.5

    Concrete lining (t=100mm)

    1

    1

    Wet masonry (t=150)

    Wet masonry (t=150)

    T.EL 12.00

    T.EL 13.00

    T.EL 12.00

    T.EL 13.00

    No.2+357 (upstream)

    No.2+357 (downstream)T.EL 10.497

    C

    T.EL 11.00

    T.EL 10.00

    2,350

    750800 800

    1,00

    0

    150C

    150

    Crushed stone

    Concrete lining (t=100mm)Wet masonry (t=150)

    No.2+560

    T.EL 10.497

    C

    T.EL 11.00

    T.EL 10.00

    2,350

    750800 800

    1,00

    0

    150C

    150

    Crushed stone

    Concrete lining (t=100mm)Wet masonry (t=150)

    No.2+760

    T.EL 10.332

    T.EL 11.00

    T.EL 10.00

    2,350

    750800 800

    1,00

    0

    150C

    Crushed stone

    150

    Crushed stone

    Concrete lining (t=100mm)Wet masonry (t=150)

    T.EL 9.00

    No.2+971

    3-29

  • STATION

    DESIGN CENTER OF CANAL ELEVATION

    EXISTING CENTER OF CANAL ELEVATI0N

    DATUM +5.00

    P9

    P10

    P11

    P12

    I=1/2,500 (Main canal)

    No.3+

    170

    Cros

    s sec

    . P9

    No.3+

    371

    Cros

    s sec

    . P10

    No.3+

    554

    Cros

    s sec

    . P11

    No.3+

    750

    Cros

    s sec

    . P12

    End o

    f main

    cana

    l

    Adjust to actual slop (Secondary canal)

    No.3 +371End of main canal

    T.EL 10.254

    T.EL 11.00

    T.EL 10.00

    2,350

    750800 800

    1,00

    0

    150C

    Crushed stone

    150

    Crushed stone

    Concrete lining (t=100mm)Wet masonry (t=150)

    No.3+170

    T.EL 10.174

    T.EL 11.00

    T.EL 10.00

    2,350

    750800 800

    1,00

    0

    150C

    Crushed stone

    150

    Transition

    Crushed stone

    Concrete lining (t=100mm)Wet masonry (t=150)

    T.EL 10.00

    C

    150 500 150

    600

    750

    150

    800

    T.EL 10.174

    150

    1,000850

    Main canal1,000 Secondary canal

    Main canal Secondary canal

    Transition

    1,00

    015

    0

    600

    Concrete lining (t=100mm)

    Gate BxH=0.8m x 0.8m

    FLOW

    FLOW

    (L=380m)

    (L=380m)

    (L=378m)

    Wet masonry (t=150)T.EL 11.00

    No.3+371 (upstream)

    No.3+371 (downstream)

    T.EL 9.485

    T.EL 11.00

    T.EL 10.00

    T.EL 9.00

    ±300

    150 500 150

    600

    750

    150

    800

    C Wet masonry (t=150)

    No.3+554

    T.EL 8.781

    T.EL 11.00

    T.EL 10.00

    T.EL 9.00

    150 500 150

    600

    750

    150

    800

    CWet masonry (t=150)

    No.3+7503-30

  • 3-3 BIKALIU IRRIGATION SCHEME IN VIQUEQUE DISTRICT

    3-31

  • Existing canal alignment

    Beneficial area

    Residence area

    3-32

  • Project site

    Average river slope I = 1/80

    A C

    3-33

  • T.EL 396.80

    T.EL 396.00

    T.EL 397.8(±)

    T.EL 395.0

    T.EL 396.5

    T.EL 396.8

    T.EL 395.40

    500

    200

    6,500

    6,300

    1,800

    800

    600

    400

    250250

    500 5,500

    250250

    350

    1,000

    7,000

    14,500

    500 500 500 500 500 500

    3,000

    500

    150 60 290

    17,850

    350

    1,800

    800

    600

    400

    400

    250250

    500250

    250

    350

    1,000

    1,000

    WL 396.8T.EL 396.80 T.EL 396.80

    T.EL 396.00T.EL 396.00

    Stop log(BxHx t =0.75m x

    0.20m x 0.05m)

    Stop log(BxHx t =0.75m x

    0.20m x 0.05m)

    (Spillway)(Fixed weir)

    VP φ150mm

    T.EL 396.80

    T.EL 396.00

    T.EL 396.00

    14,500

    500 500 500 500 500 500

    3,000

    17,850

    350(Spillway)(Fixed weir)

    FLOW

    FLOWVP φ150mm

    (Gabion)50

    0 200

    6,300

    7,000

    7,000

    7,000 7,000(Fixed weir)(Fixed weir) (Gabion)(Gabion)

    17,850

    (Bed

    pro

    tectio

    n)

    (Fixe

    d we

    ir)

    2,000(Bank protection)

    Stop log(BxHx t =0.75m

    x 0.20m x0.05m)

    7,000

    (Gabion)

    (Gabion)

    (Gabion)

    7,300

    5,000

    (Gab

    ion)

    (Gab

    ion)

    (Gab

    ion)

    1,800 1,4

    0040

    0

    3,0002

    ,000

    600

    400

    FLOW

    B

    B

    C

    C

    (Intake)

    Rock

    Sec. A-A

    A ANo. 0 + 350C

    Sec. B-B Sec. C-C

    T.EL 397.9(±)

    1,500

    (Gab

    ion)

    Typical Sec. of Bank pro.

    T.EL 397.8

    T.EL 396.5 T.EL 396.5

    T.EL 397.6

    T.EL 396.5

    VP φ150mmT.EL 397.3

    250 2,150

    48,500

    48,5002,400

    T.EL 396.3

    1,750 1,5

    0025

    0

    1,250

    950800

    150

    2,400

    250 1,500 500 150

    250

    1,000

    250

    800

    150

    500

    150

    (Sedimentation pond) (Canal 1)

    (Wet masonry) (Wet masonry)

    L=1,616 mL=15m(VP φ150mm) (Canal 2)

    L=1,616 m(Canal 2)

    L=15m(VP φ150mm)

    Crushed stone

    FLOW

    FLOW

    1,100

    150

    Outlet general plan

    Outlet longitudinal

    C C

    200

    950~

    750

    800

    450

    Main canal

    Earth canal

    Stop log(t=0.1m)

    800

    600

    Seco

    ndar

    y can

    al

    Wet masonry

    FLOW

    (L=3m)

    Typical general plan and sec. of canal and diversion

    General plan of Headworks

    7,000

    5,500

    3-34

  • I=1/400 (Main canal)

    No.0+

    811

    Cros

    s sec

    . P4

    No.1+

    23Cr

    oss s

    ec. P

    5

    No.1+

    215

    Cros

    s sec

    . P6

    No.1+

    417

    Cros

    s sec

    . P7

    No.1+

    616

    Cros

    s sec

    . P8

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0 150 500 150

    600

    750

    150

    800

    T.EL 394.471

    Center of surveyCenter of plan

    No.0 + 811

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 393.942

    T.EL 393.0

    Center of surveyCenter of plan

    No.1 + 23

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 393.463T.EL 393.0

    Center of survey

    Center of plan

    No.1 + 215

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 392.957

    T.EL 393.0

    Center of survey

    Center of plan

    No.1 + 417

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 392.458

    T.EL 393.0

    Center of survey

    Center of plan

    No.1 + 616

    3-35

  • I=1/400 (Main canal)

    No.0+

    202

    Cros

    s sec

    . P2

    No.0+

    000

    Cros

    s sec

    . P0

    No.0+

    402

    Cros

    s sec

    . P3

    No.0+

    592

    Cros

    s sec

    . P3

    T.EL 395.0

    T.EL 396.0

    150 500 150

    800

    950

    150

    800

    T.EL 396.5

    Center of surveyCenter of plan

    No.0 + 000(Beginning of Canal)

    T.EL 395.0

    T.EL 396.0

    150 500 150

    800

    950

    150

    800

    T.EL 395.996

    Center of surveyCenter of plan

    No.0 + 200

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    800

    750

    150

    800

    T.EL 395.494

    Center of survey

    Center of plan

    No.0 + 400

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 395.021

    Center of surveyCenter of plan

    No.0 + 592

    3-36

  • I=1/400 (Main canal)

    No.0+

    811

    Cros

    s sec

    . P4

    No.1+

    23Cr

    oss s

    ec. P

    5

    No.1+

    215

    Cros

    s sec

    . P6

    No.1+

    417

    Cros

    s sec

    . P7

    No.1+

    616

    Cros

    s sec

    . P8

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0 150 500 150

    600

    750

    150

    800

    T.EL 394.471

    Center of surveyCenter of plan

    No.0 + 811

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 393.942

    T.EL 393.0

    Center of surveyCenter of plan

    No.1 + 23

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 393.463T.EL 393.0

    Center of survey

    Center of plan

    No.1 + 215

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 392.957

    T.EL 393.0

    Center of survey

    Center of plan

    No.1 + 417

    T.EL 395.0

    T.EL 394.0

    T.EL 396.0

    150 500 150

    600

    750

    150

    800

    T.EL 392.458

    T.EL 393.0

    Center of survey

    Center of plan

    No.1 + 616

    3-37

  • Examination on main structures for priority irrigation schemes 1. Examination of Headworks on Halecou irrigation scheme Plan 3 and Bikaliu irrigation scheme

    1) The apron is calculated as following examination.

    2) The protection block is calculated as following examination.

    Irrigation scheme Halecou (Plan 3) Bikaliu

    Targeted water depth

    Q: discharge (m3/s) 2,600 120 L: width of flow (m) 200.0 17.85 q: unite discharge (m3/s/m) 13.0 7.72 hc: critical flow depth (m) 2.58 1.66 Fr: Froude number 1.00 1.00

    Required length of apron by Bligh : L=0.6・C・√D1 D1: Difference crest and apron (m) 2.00 0.80 C : Co-efficient of creep 9 6 L : Required length of apron (m) 7.63 →10.0m 3.21→3.5m

    Irrigation scheme Halecou (Plan 3) Bikaliu

    Targeted water depth

    Q: discharge (m3/s) 2,600 120 L: width of flow (m) 200.0 17.85 q: unite discharge (m3/s/m) 13.0 7.72 hc: critical flow depth (m) 2.58 1.66 Fr: Froude number 1.00 1.00

    Required length of protection block : L=Lb-La La: Length of apron (m) 10.0 3.5 Lb : 0.67・C・√(Ha・q)・f 30.75 10.0 C : Co-efficient of creep 9 6 Ha : Maximum difference US and DS 2.00 0.80 q: unite discharge (m3/s/m) 13.0 7.72 f: Co-efficient of Headworks type 1.0 1.0 L: Lb- La 20.75 →25.0 m 6.5→ 7.0 m

    3-38

  • 3) Size of protection block

    In general, adoption of the protection block is subject to targeted velocity or degree of slope in river. The

    large classification of a block weight are shown as followings.

    Weight of a block almost 2 ton almost 3 ton almost 4 ton more than 5 ton

    Maximum allowable velocity almost 0.5 ~2 m/s almost 1m/s ~4m/s more than 4m/s

    allowable velocity river slope less than 1/1,000 1/1,000 ~ 1/500 1/500 ~ 1/200 more than 1/200

    According to site survey, river slope around intake is assumed to almost 1/200~1/300. Hence 4ton block

    is applied to site.

    2. Examination of Collecting drain channel in Halecou irrigation scheme on Plan 2

    Collecting drain channel is usually used in the small scale irrigation which is required to 30 ~50

    litter/second. However, this type could be innovative type in middle scale irrigation scheme. Because in

    general, Timor-Leste has adopted fixed type wire in order to endure the flood effect and which cause to

    high construction cost. Collecting drain channel will give one of solution for issue in Timor-Leste.

    Collecting drain channel is embedded under the river bed to collect under grand water, while its structure

    alleviate the flood adverse effect. On the other hand, the scale of structure will be larger than adoption for

    small irrigation scheme. Therefore adoption on such as Halecou scheme is subject to take into account as

    followings;

    ・Condition of main water stream and river bed which stable location should be planed

    ・Embedded depth of structure to secure stability and avoid flood effect

    ・The maximum design intake volume should be 1.0m3/s from the view point of cost and performance.

    In the condition of above remarks, collecting drain channel is designed as followings;

    ① ② ③ ④ ⑤ ⑥ ※1

    internal φratio of hole at

    pipe

    Intakevol./pipedesign :1.0m3/s

    Necessity oflength of one

    pipe

    (mm) (m3/sec) (mm/s) (m/s) (m)φ300 50% 1.000 15.0 0.015 0.3 471.6 1φ300 50% 0.017 15.0 0.015 0.3 7.9 60φ400 50% 1.000 15.0 0.015 0.3 353.7 1φ400 50% 0.022 15.0 0.015 0.3 7.9 45φ600 50% 1.000 15.0 0.015 0.3 235.8 1φ600 50% 0.040 15.0 0.015 0.3 9.4 25φ800 50% 1.000 15.0 0.015 0.3 176.8 1φ800 50% 0.040 15.0 0.015 0.3 7.1 25φ1000 50% 1.000 15.0 0.015 0.3 141.5 1φ1000 50% 0.500 15.0 0.015 0.3 70.7 2

    ※1) : ③/(①/1000 × π × ④/1000 × ② × ⑥) = Necessity of length of one pipe

    SUS or steel

    Velocity of intake=15mm/s : assumed value in

    generalvoid ration of

    filter layer

    Pipe type

    Necessityof pipe

    number fortargeted

    intake vol.

    3-39

  • 3. Examination of targeted capacity of canal

    SAKETO(open canal)

    Bikaliu (open canal)

    Canal type Concrete canal Masonry canal Masonry canal Masonry canal

    m1 0.0 0.5 0.0 0.0m2 0.0 0.5 0.5 0.0Hfb 0.90 0.46 0.90 0.38H 0.70 1.04 0.85 0.12

    hmax 1.50 1.50 1.00 0.50

    ① 2.20 1.50 1.50 0.50

    ② 2.20 2.54 1.92 0.50

    ③ 2.20 3.00 2.37 0.50A (m2) 1.536 2.101 1.452 0.061P(m) 3.597 3.825 3.296 0.743

    R = A/P 0.427 0.549 0.440 0.082n 0.015 0.021 0.021 0.025I 1/1,500 1/2,000 1/2,500 1/400

    v (m/s) 0.98 0.71 0.55 0.38Q (m3/s) 1.50 1.50 0.80 0.02

    Harecou (open canal)

    3-40

  • Example of Cost Estimation

    3-41

  • Halecou irrigation scheme : Plan 1

    3-42

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    1. Preparatory Work1-1. Mobilization (Transportation) to Site(1) Excavator (0.45m3) trip 2 1,500.00 3,000 (2) Excavator (0.10m3) trip 2 750.00 1,500 (3) Bulldozer (4 ton class) trip 1 1,500.00 1,500 (4) Roller Compactor (4 ton) trip 1 1,500.00 1,500 (5) Dump Truck (4 ton) trip 2 135.69 271 (6) Water Tank Truck trip 2 158.28 317 (7) Agitator truck (3.2m3) trip 1 176.76 177 (8) Concrete Pump Truck (30m3/hr) trip 1 148.46 148 (9) Crane Truck (Hydraulic, 20ton) trip 1 189.12 189 (10) Concrete Mixer etc. trip 1 1,500.00 1,500 (11) Others trip 2 1,500.00 3,000 1-2. Site Office etc. set 1 24,445.00 24,445 1-3. Site Clearing (Cutting & Clearing of Grass, Bushes) m2 2,500 0.24 600 1-4. Transportation of Labor day 90 72.00 6,480 1-5. Demobilization (Transportation) from Site(1) Excavator (0.45m3) trip 2 1,500.00 3,000 (2) Excavator (0.10m3) trip 2 750.00 1,500 (3) Bulldozer (4 ton class) trip 1 1,500.00 1,500 (4) Roller Compactor (4 ton) trip 1 1,500.00 1,500 (5) Dump Truck (4 ton) trip 2 135.69 271 (6) Water Tank Truck trip 2 158.28 317 (7) Agitator truck (3.2m3) trip 1 176.76 177 (8) Concrete Pump Truck (30m3/hr) trip 1 148.46 148 (9) Crane Truck (Hydraulic, 20ton) trip 1 189.12 189 (10) Concrete Mixer etc. trip 1 1,500.00 1,500 (11) Others trip 2 1,500.00 3,000

    2. Temporary Work2-1. Temporary Road (Gravel Pavement)(1) Embankment with Compaction m3 4,288 7.20 30,874 (2) Concrete Pipe (Dia. 600mm * 10m) unit 3 1,534.40 4,603 (3) Sand Bag m3 2 105.95 212 (4) Gravel m3 285 36.04 10,271 (5) Gravel Pavement m3 285 4.59 1,308 2-2. Cofferdam(1) Embankment with Compaction for Cofferdam m3 3,900 7.20 28,080 (2) Sand Bag m3 758 105.95 80,310 2-3. Dewatering (by Pumping System) day 60 75.74 4,544

    Sub-total 217,931

    Halecou Irrigation Scheme Bill of Quantity (1/3)

    3-43

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    2. Temporary Work2-4. Removal of Cofferdam(1) Removal for Cofferdam m3 3,900 3.75 14,625 (2) Removal for Sand Bag m3 758 3.75 2,843

    3. Earth Work3-1. Common Excavation for Chipping (Existing Intake & Canal)

    m3 1,680 10.11 16,985 3-2. Chipping Work for Existing Intake & Existing Canal (Excavator 0.4m3)

    m3 367 14.69 5,391 3-3. Common Excavation for Construction of Intake & Spillway

    m3 488 7.83 3,821 3-4. Backfill for Intake & Spillway m3 1,861 2.10 3,908 3-5. Embankment with Compaction m3 840 7.20 6,048 3-6. Sand Bag for Slope Protection m3 586 105.95 62,087 3-7. Excavation for Banking Material (Soil) from Borrow Pit m3 4,300 7.83 33,669 3-8. Loading & Transportation of Banking Material (Soil) from Borrow Pit

    m3 4,300 4.28 18,404 3-9. Loading & Transportation of Surplus Soil to Borrow Pit m3 4,300 4.28 18,404 3-10. Backfill of Surplus Soil at Borrow Pit m3 4,300 0.89 3,827 3-11. Transportation & Dispose of Chipping Material (Concrete & Reinforcement Bar)

    m3 367 85.00 31,195

    4. Concrete Work (Intake & Connecting Canal)4-1. Concrete Type-A (fc' = 22.5 Mpa) m3 995 140.35 139,648 4-2. Reinforcement Bar ton 78 1,425.70 111,205 4-3. Form m2 1,483 20.44 30,313 4-4. Lean Concrete m3 82 126.30 10,357 4-5. Gravel (Leveling) m3 123 36.04 4,433 4-6. Gravel Pavement (Leveling) m3 123 2.25 277 4-7. Supply and Installing Hand Rail, GSP Pipe dia. 2.5 inch m 40 18.70 748 4-8. Gate Facilities(1) Supply and Installing Slide Gate (B2.00 * H2.00) unit 1 10,000 10,000 (2) Supply and Installing Slide Gate (B2.00 * H1.85) unit 1 9,000 9,000 (3) Other Gate Facilities set 1 30,000 30,000 4-9. Concrete Block unit 1,921 185.14 355,691

    5. Canal Work (Main Canal)5-1. Common Excavation m3 14,100 7.83 110,403 5-2. Embankment with Compaction (Manual Work) m3 14,100 3.51 49,491 5-3. Concrete Type-A (fc' = 22.5 Mpa) m3 1,858 149.46 277,697

    Sub-total 1,360,470

    Halecou Irrigation Scheme Bill of Quantity (2/3)

    3-44

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    5. Canal Work (Main Canal)5-4. Reinforcement Bar ton 29 1,425.70 41,345 5-5. Form m2 742 16.03 11,894 5-6. Lean Concrete m3 346 126.30 43,700 5-7. Gravel (Leveling) m3 519 36.04 18,705 5-8. Gravel Pavement m3 519 2.25 1,168 5-9. Slope Protection (River Bank, Gabion)(1) Gabion (4 mm dia), Gravel (Aggregate/Cobble Stone) m3 3,500 88.24 308,840

    5-10. Gate (Turnout) unit 17 5,000.00 85,000 Sub-total 510,652

    Total 2,089,053

    Direct Construction Cost (A) Indirect Construction Cost (B = A * 20%)

    C = A + B

    Consultant Fee (D = C * 5%) Physical Contingency (E = C * 5%)

    Grand Total Cost (F = C + D + E)

    (US$)

    125,343 125,343

    2,757,550 2,757,000

    2,089,053 417,811

    2,506,864

    Halecou Irrigation Scheme Bill of Quantity (3/3)

    3-45

  • Halecou irrigation scheme : Plan 2

    3-46

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    1. Preparatory Work1-1. Mobilization (Transportation) to Site(1) Excavator (0.45m3) trip 3 1,500.00 4,500 (2) Excavator (0.10m3) trip 2 750.00 1,500 (3) Bulldozer (4 ton class) trip 2 1,500.00 3,000 (4) Roller Compactor (4 ton) trip 1 1,500.00 1,500 (5) Dump Truck (4 ton) trip 2 135.69 271 (6) Water Tank Truck trip 2 158.28 317 (7) Agitator truck (3.2m3) trip 2 176.76 354 (8) Concrete Pump Truck (30m3/hr) trip 2 148.46 297 (9) Crane Truck (Hydraulic, 20ton) trip 1 189.12 189 (10) Concrete Mixer etc. trip 1 1,500.00 1,500 (11) Others trip 2 1,500.00 3,000 1-2. Site Office etc. set 1 24,445.00 24,445 1-3. Site Clearing (Cutting & Clearing of Grass, Bushes) m2 2,500 0.24 600 1-4. Transportation of Labor day 90 72.00 6,480 1-5. Demobilization (Transportation) from Site(1) Excavator (0.45m3) trip 3 1,500.00 4,500 (2) Excavator (0.10m3) trip 2 750.00 1,500 (3) Bulldozer (4 ton class) trip 2 1,500.00 3,000 (4) Roller Compactor (4 ton) trip 1 1,500.00 1,500 (5) Dump Truck (4 ton) trip 2 135.69 271 (6) Water Tank Truck trip 2 158.28 317 (7) Agitator truck (3.2m3) trip 2 176.76 354 (8) Concrete Pump Truck (30m3/hr) trip 2 148.46 297 (9) Crane Truck (Hydraulic, 20ton) trip 1 189.12 189 (10) Concrete Mixer etc. trip 1 1,500.00 1,500 (11) Others trip 2 1,500.00 3,000

    2. Temporary Work2-1. Temporary Road (Gravel Pavement)(1) Embankment with Compaction m3 6,213 7.20 44,734 (2) Concrete Pipe (Dia. 600mm * 10m) unit 3 1,534.40 4,603 (3) Sand Bag m3 2 105.95 212 (4) Gravel m3 390 36.04 14,056 (5) Gravel Pavement m3 390 4.59 1,790 2-2. Cofferdam(1) Embankment with Compaction for Cofferdam m3 3,900 7.20 28,080 (2) Sand Bag m3 758 105.95 80,310 2-3. Dewatering (by Pumping System) day 65 75.74 4,923

    Sub-total 243,089

    Halecou Irrigation Scheme Bill of Quantity (1/3)

    3-47

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    2. Temporary Work2-4. Removal of Cofferdam(1) Removal for Cofferdam m3 3,900 3.75 14,625 (2) Removal for Sand Bag m3 758 3.75 2,843

    3. Earth Work3-1. Common Excavation for Chipping (Existing Intake & Canal)

    m3 1,680 10.11 16,985 3-2. Chipping Work for Existing Intake & Existing Canal (Excavator 0.4m3)

    m3 367 14.69 5,391 3-3. Common Excavation for Construction of Intake & Spillway

    m3 488 7.83 3,821 3-4. Backfill for Intake & Spillway m3 1,861 2.10 3,908 3-5. Embankment with Compaction m3 840 7.20 6,048 3-6. Sand Bag for Slope Protection m3 586 105.95 62,087 3-7. Common Excavation for Construction of Intake Pit & Pipe Culvert m3 8,228 7.83 64,425 3-8. Backfill for Intake Pit & Pipe Culvert m3 4,670 2.10 9,807 3-9. Excavation for Banking Material (Soil) from Borrow Pit m3 6,200 7.83 48,546 3-10. Loading & Transportation of Banking Material (Soil) from Borrow Pit

    m3 6,200 4.28 26,536 3-11. Loading & Transportation of Surplus Soil to Borrow Pit m3 6,200 4.28 26,536 3-12. Backfill of Surplus Soil at Borrow Pit m3 6,200 0.89 5,518 3-13. Transportation & Dispose of Chipping Material (Concrete & Reinforcement Bar)

    m3 367 85.00 31,195

    4. Concrete Work (Intake & Connecting Canal)4-1. Concrete Type-A (fc' = 22.5 Mpa) m3 1,000 140.35 140,350 4-2. Reinforcement Bar ton 78 1,425.70 111,205 4-3. Form m2 1,511 20.44 30,885 4-4. Lean Concrete m3 82 126.30 10,357 4-5. Gravel (Leveling) m3 123 36.04 4,433 4-6. Gravel Pavement (Leveling) m3 123 2.25 277 4-7. Supply and Installing Hand Rail, GSP Pipe dia. 2.5 inch m 40 18.70 748 4-8. Gate Facilities(1) Supply and Installing Slide Gate (B2.00 * H2.00) unit 1 10,000 10,000 (2) Supply and Installing Slide Gate (B2.00 * H1.85) unit 1 9,000 9,000 (3) Supply and Installing Slide Gate (B1.50 * H1.50) unit 1 7,000 7,000 (4) Other Gate Facilities set 1 40,000 40,000 4-9. Concrete Block unit 1,921 185.14 355,691

    Sub-total 1,048,217

    Halecou Irrigation Scheme Bill of Quantity (2/3)

    3-48

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    5. Intake Pit & Pipe Culvert5-1. Concrete Type-A (fc' = 22.5 Mpa) m3 1,449 140.35 203,367 5-2. Reinforcement Bar ton 57 1,425.70 81,265 5-3. Form m2 1,793 20.44 36,649 5-4. Lean Concrete m3 577 126.30 72,875 5-5. Gravel (Leveling) m3 865 36.04 31,175 5-6. Gravel Pavement m3 865 2.25 1,946 5-7. Gravel (Aggregate/Cobble Stone) m3 428 25.43 10,884 5-8. Crush Stone m3 179 41.63 7,452 5-9. Sand m3 179 12.81 2,293 5-10. Gabion m3 179 88.24 15,795 5-11. Steel Pipe (Dia. 600mm) m 375 303.62 113,858 5-12. HP Pipe (Dia. 1,200mm) m 300 605.43 181,629

    6. Canal Work (Main Canal)5-1. Common Excavation m3 14,100 7.83 110,403 5-2. Embankment with Compaction (Manual Work) m3 14,100 3.51 49,491 5-3. Concrete Type-A (fc' = 22.5 Mpa) m3 1,858 149.46 277,697 5-4. Reinforcement Bar ton 29 1,425.70 41,345 5-5. Form m2 742 16.03 11,894 5-6. Lean Concrete m3 346 126.30 43,700 5-7. Gravel (Leveling) m3 519 36.04 18,705 5-8. Gravel Pavement m3 519 2.25 1,168 5-9. Slope Protection (River Bank, Gabion)(1) Gabion (4 mm dia), Gravel (Aggregate/Cobble Stone) m3 3,500 88.24 308,840

    5-10. Gate (Turnout) unit 17 5,000.00 85,000 Sub-total 1,707,431

    Total 2,998,737

    Direct Construction Cost (A) Indirect Construction Cost (B = A * 20%)

    C = A + B

    Consultant Fee (D = C * 5%) Physical Contingency (E = C * 5%)

    Grand Total Cost (F = C + D + E)

    (US$)

    179,924 179,924

    3,958,332 3,958,000

    2,998,737 599,747

    3,598,484

    Halecou Irrigation Scheme Bill of Quantity (3/3)

    3-49

  • Halecou irrigation scheme : Plan 3

    3-50

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    1. Preparatory Work1-1. Mobilization (Transportation) to Site(1) Excavator (0.45m3) trip 4 1,500.00 6,000 (2) Excavator (0.10m3) trip 2 750.00 1,500 (3) Bulldozer (4 ton class) trip 3 1,500.00 4,500 (4) Roller Compactor (4 ton) trip 1 1,500.00 1,500 (5) Dump Truck (4 ton) trip 4 135.69 543 (6) Water Tank Truck trip 2 158.28 317 (7) Agitator truck (3.2m3) trip 2 176.76 354 (8) Concrete Pump Truck (30m3/hr) trip 2 148.46 297 (9) Crane Truck (Hydraulic, 20ton) trip 2 189.12 378 (10) Concrete Mixer etc. trip 2 1,500.00 3,000 (11) Others trip 3 1,500.00 4,500 1-2. Site Office etc. set 1 24,445.00 24,445 1-3. Site Clearing (Cutting & Clearing of Grass, Bushes) m2 3,000 0.24 720 1-4. Transportation of Labor day 180 72.00 12,960 1-5. Demobilization (Transportation) from Site(1) Excavator (0.45m3) trip 4 1,500.00 6,000 (2) Excavator (0.10m3) trip 2 750.00 1,500 (3) Bulldozer (4 ton class) trip 3 1,500.00 4,500 (4) Roller Compactor (4 ton) trip 1 1,500.00 1,500 (5) Dump Truck (4 ton) trip 4 135.69 543 (6) Water Tank Truck trip 2 158.28 317 (7) Agitator truck (3.2m3) trip 2 176.76 354 (8) Concrete Pump Truck (30m3/hr) trip 2 148.46 297 (9) Crane Truck (Hydraulic, 20ton) trip 2 189.12 378 (10) Concrete Mixer etc. trip 2 1,500.00 3,000 (11) Others trip 3 1,500.00 4,500

    2. Temporary Work2-1. Temporary Road (Gravel Pavement)(1) Embankment with Compaction m3 8,213 7.20 59,134 (2) Gravel m3 240 36.04 8,650 (3) Gravel Pavement m3 240 4.59 1,102 2-2. Cofferdam for Head Works(1) Cofferdam for Head Works m3 8,300 4.46 37,018 (2) Sand Bag m3 495 105.95 52,445 2-3. Dewatering (by Pumping System) day 150 75.74 11,361 2-4. Removal of Cofferdam(1) Removal for Cofferdam m3 8,300 3.75 31,125 (2) Removal for Sand Bag m3 495 3.75 1,856

    Sub-total 286,594

    Halecou Irrigation Scheme Bill of Quantity (1/3)

    3-51

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    3. Earth Work3-1. Common Excavation for Chipping (Existing Intake & Canal)

    m3 1,680 10.11 16,985 3-2. Chipping Work for Existing Intake & Existing Canal (Excavator 0.4m3)

    m3 367 14.69 5,391 3-3. Common Excavation for Construction of Intake & Spillway

    m3 488 7.83 3,821 3-4. Backfill for Intake & Spillway m3 1,861 2.10 3,908 3-5. Embankment with Compaction m3 840 7.20 6,048 3-6. Sand Bag for Slope Protection m3 586 105.95 62,087 3-7. Common Excavation for Construction of Head Works (HW) m3 18,927 7.83 148,198 3-8. Backfill for Head Works m3 3,411 2.10 7,163 3-9. Excavation for Banking Material (Soil) from Borrow Pit m3 8,200 7.83 64,206 3-10. Loading & Transportation of Banking Material (Soil) from Borrow Pit

    m3 8,200 4.28 35,096 3-11. Loading & Transportation of Surplus Soil to Borrow Pit m3 8,200 4.28 35,096 3-12. Backfill of Surplus Soil at Borrow Pit m3 8,200 0.89 7,298 3-13. Transportation & Dispose of Chipping Material (Concrete & Reinforcement Bar)

    m3 367 85.00 31,195

    4. Concrete Work (Intake & Connecting Canal)4-1. Concrete Type-A (fc' = 22.5 Mpa) m3 965 140.35 135,438 4-2. Reinforcement Bar ton 75 1,425.70 106,928 4-3. Form m2 1,483 20.44 30,313 4-4. Lean Concrete m3 78 126.30 9,851 4-5. Gravel (Leveling) m3 117 36.04 4,217 4-6. Gravel Pavement (Leveling) m3 117 2.25 263 4-7. Supply and Installing Hand Rail, GSP Pipe dia. 2.5 inch m 60 18.70 1,122 4-8. Gate Facilities(1) Supply and Installing Slide Gate (B2.00 * H2.00) unit 1 10,000 10,000 (2) Supply and Installing Slide Gate (B2.00 * H1.85) unit 1 9,000 9,000 (3) Supply and Installing Slide Gate (B1.70 * H1.10) unit 2 7,000 14,000 (4) Other Gate Facilities set 1 50,000 50,000 4-9. Concrete Block unit 20 185.14 3,703

    5. Head Works5-1. Concrete Type-A (fc' = 22.5 Mpa) m3 5,756 140.35 807,855 5-2. Reinforcement Bar ton 224 1,425.70 319,357 5-3. Form m2 2,045 20.44 41,800 5-4. Lean Concrete m3 316 126.30 39,911 5-5. Gravel (Leveling) m3 474 36.04 17,083

    Sub-total 2,027,333

    Halecou Irrigation Scheme Bill of Quantity (2/3)

    3-52

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    5-6. Gravel Pavement m3 474 2.25 1,067 5-7. Supply and Installing Hand Rail, GSP Pipe dia. 2.5 inch m 50 18.70 935 5-8. Gate Facilities(1) Supply and Installing Slide Gate (B1.70 * H1.00) unit 2 7,000 14,000 (2) Other Gate Facilities unit 1 40,000 40,000 5-9. Gabion (4 mm dia), Gravel (Aggregate/Cobble Stone) m3 1,184 88.24 104,476 5-10. Stone Masonry 1:3 m3 213 86.08 18,331 5-11. Plastering 1:3 m2 335 5.47 1,832 5-12. Concrete Type-A (fc' = 22.5 Mpa) for Revetment (Left Bank of River)

    m3 67 149.46 10,014 5-13. Concrete Brock (0.6m*0.6m*0.6m) for Bed Protection Work

    unit 16,032 47.78 766,009 5-14. Embankment with Compaction m3 6,000 7.20 43,200

    6. Canal Work (Main Canal)5-1. Common Excavation m3 14,100 7.83 110,403 5-2. Embankment with Compaction (Manual Work) m3 14,100 3.51 49,491 5-3. Concrete Type-A (fc' = 22.5 Mpa) m3 1,858 149.46 277,697 5-4. Reinforcement Bar ton 29 1,425.70 41,345 5-5. Form m2 742 16.03 11,894 5-6. Lean Concrete m3 346 126.30 43,700 5-7. Gravel (Leveling) m3 519 36.04 18,705 5-8. Gravel Pavement m3 519 2.25 1,168 5-9. Slope Protection (River Bank, Gabion)(1) Gabion (4 mm dia), Gravel (Aggregate/Cobble Stone) m3 3,500 88.24 308,840

    5-10. Gate (Turnout) unit 17 5,000.00 85,000 Sub-total 1,948,107

    Total 4,262,034

    Direct Construction Cost (A) Indirect Construction Cost (B = A * 20%)

    C = A + B

    Consultant Fee (D = C * 5%) Physical Contingency (E = C * 5%)

    Grand Total Cost (F = C + D + E)

    (US$)

    255,722 255,722

    5,625,885 5,625,000

    4,262,034 852,407

    5,114,441

    Halecou Irrigation Scheme Bill of Quantity (3/3)

    3-53

  • Saketo irrigation scheme

    3-54

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    1. Preparatory Work1-1. Mobilization (Transportation) to Site(1) Excavator (0.45m3) trip 2 3,000.00 6,000 (2) Excavator (0.10m3) trip 3 1,500.00 4,500 (3) Bulldozer (4 ton class) trip 1 3,000.00 3,000 (4) Roller Compactor (4 ton) trip 2 3,000.00 6,000 (5) Dump Truck (4 ton) trip 2 271.38 543 (6) Water Tank Truck trip 3 316.56 950 (7) Agitator truck (3.2m3) trip 1 353.52 354 (8) Concrete Pump Truck (30m3/hr) trip 1 296.93 297 (9) Crane Truck (Hydraulic, 20ton) trip 1 378.24 378 (10) Concrete Mixer etc. trip 1 3,000.00 3,000 (11) Others trip 2 3,000.00 6,000 1-2. Site Office etc. set 1 24,445.00 24,445 1-3. Site Clearing (Cutting & Clearing of Grass, Bushes) m2 10,000 0.24 2,400 1-4. Transportation of Labor day 60 72.00 4,320 1-5. Demobilization (Transportation) from Site(1) Excavator (0.45m3) trip 2 3,000.00 6,000 (2) Excavator (0.10m3) trip 3 1,500.00 4,500 (3) Bulldozer (4 ton class) trip 1 3,000.00 3,000 (4) Roller Compactor (4 ton) trip 2 3,000.00 6,000 (5) Dump Truck (4 ton) trip 2 271.38 543 (6) Water Tank Truck trip 3 316.56 950 (7) Agitator truck (3.2m3) trip 1 353.52 354 (8) Concrete Pump Truck (30m3/hr) trip 1 296.93 297 (9) Crane Truck (Hydraulic, 20ton) trip 1 378.24 378 (10) Concrete Mixer etc. trip 1 3,000.00 3,000 (11) Others trip 2 3,000.00 6,000

    2. Temporary Work2-1. Temporary Road (as a Permanent Road (Maintenance Road), Gravel Pavement)(1) Embankment with Compaction m3 2,375 7.20 17,100 (2) Gravel m3 300 36.04 10,812 (3) Gravel Pavement m3 300 4.59 1,377 2-2. Dewatering (by Pumping System) day 40 75.74 3,030

    3. Earth Work3-1. Common Excavation for Construction of Sedimentation Pond & Canal

    m3 977 10.11 9,877 3-2. Sand Bag (Excavated Slope Protection) m3 202 105.95 21,402 3-3. Chipping Work for Existing Wall & Existing Canal (Manual)

    m3 12 14.69 176 Sub-total 156,983

    Saketo Irrigation Scheme Bill of Quantity (1/3)

    3-55

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    3. Earth Work3-4. Chipping Work for Existing Canal (Excavator 0.4m3) m3 87 14.69 1,278 3-5. Removal for Sand Bag (H13cm*B35cm*L45cm) m3 202 3.75 758 3-6. Backfill around Structure (Sedimentation Pond etc.) m3 740 2.10 1,554 3-7. Excavation for Banking Material (Soil) from Borrow Pit m3 2,613 7.83 20,460 3-8. Loading & Transportation of Banking Material (Soil) from Borrow Pit

    m3 2,613 4.28 11,184 3-9. Loading & Transportation of Surplus Soil to Borrow Pit m3 237 4.28 1,014 3-10. Backfill of Surplus Soil at Borrow Pit m3 237 0.89 211 3-11. Transportation & Dispose of Chipping Material (Concrete & Reinforcement Bar)

    m3 98 100.00 9,800

    4. Concrete Work (Sedimentation Pond etc.)4-1. Concrete Type-A (fc' = 22.5 Mpa) m3 99 170.00 16,830 4-2. Reinforcement Bar ton 8 1,600.00 12,800 4-3. Form m2 311 20.44 6,357 4-4. Lean Concrete m3 14 140.00 1,960 4-5. Gravel (Leveling) m3 25 36.04 901 4-6. Gravel Pavement (Leveling) m3 25 2.25 56 4-7. Supply and Installing Hand Rail, GSP Pipe dia. 2.5 inch m 60 18.70 1,122 4-8. Gate Facilities(1) Supply and Installing Slide Gate (B1.50 * H2.00) unit 1 8,000.00 8,000 (2) Other Gate Facilities set 1 15,000.00 15,000 4-9. Concrete Pipe (Dia. 1,200mm * 5.82m) unit 1 5,000.00 5,000 4-10. Gabion (4 mm dia), Gravel (Aggregate/Cobble Stone) m3 6 88.24 529 4-11. Stone Masonry 1:3 m3 13 86.08 1,119 4-12. Plastering 1:3 m2 37 5.47 202

    5. Canal Work5-1. Main Canal5-1-1. Common Excavation m3 2,660 7.83 20,828 5-1-2. Embankment with Compaction (Manual Work) m3 11,745 3.51 41,225 5-1-3. Gravel (Leveling) m3 1,317 36.04 47,465 5-1-4. Gravel Pavement (Leveling) m3 1,317 2.25 2,963 5-1-5. Stone Masonry 1:3 m3 1,199 86.08 103,210 5-1-6. Plastering 1:3 m2 8,182 5.47 44,756 5-1-7. Concrete Type-A (fc' = 22.5 Mpa) for Canal m3 812 170.00 138,040 5-1-8. Reinforcement Bar ton 13 1,600.00 20,800 5-1-9. Form m2 75 16.03 1,202 5-1-10. Gravel (Maintenance Road) m3 647 36.04 23,318 5-1-11. Gravel Pavement (Maintenance Road) m3 647 4.59 2,970

    Sub-total 562,912

    Saketo Irrigation Scheme Bill of Quantity (2/3)

    3-56

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    5-2. Canal Structure (Main Canal)5-2-1. Concrete Type-A (fc' = 22.5 Mpa) for Canal 19 170.00 3,230 5-2-2. Form 96 16.03 1,539 5-2-3. Lean Concrete m3 3 140.00 420 5-2-4. Gravel (Leveling) m3 5 36.04 180 5-2-5. Gravel Pavement (Leveling) m3 5 2.25 11 5-2-6. Gate Facilities 0 (1) Supply and Installing Slide Gate (B1.45 * H1.00) unit 4 5,000.00 20,000 (2) Supply and Installing Slide Gate (B0.70 * H0.60) unit 4 2,000.00 8,000 (3) Other Gate Facilities (for Turnout) set 4 5,000.00 20,000 (4) Supply and Installing Slide Gate (B0.80 * H0.80) unit 1 3,000.00 3,000 (5) Other Gate Facilities (for Transition) set 1 2,000.00 2,000

    5-3. Secondary Canal5-3-1. Common Excavation m3 9,220 7.83 72,193 5-3-2. Embankment with Compaction (Manual Work) m3 3,796 3.51 13,324

    Sub-total 143,897 Total 863,792

    Direct Construction Cost (A) Indirect Construction Cost (B = A * 20%)

    C = A + B

    Consultant Fee (D = C * 5%) Physical Contingency (E = C * 5%)

    Grand Total Cost (F = C + D + E)

    (US$)

    51,828 51,828

    1,140,206 1,140,000

    863,792 172,758

    1,036,550

    Saketo Irrigation Scheme Bill of Quantity (3/3)

    3-57

  • Bikaliu irrigation scheme

    3-58

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    1. Preparatory Work1-1. Mobilization (Transportation) to Site(1) Excavator (0.45m3) trip 1 3,000.00 3,000 (2) Excavator (0.10m3) trip 2 1,500.00 3,000 (3) Bulldozer (4 ton class) trip 1 3,000.00 3,000 (4) Roller Compactor (4 ton) trip 1 3,000.00 3,000 (5) Dump Truck (4 ton) trip 2 271.38 543 (6) Water Tank Truck trip 1 316.56 317 (7) Agitator truck (3.2m3) trip 1 353.52 354 (8) Concrete Pump Truck (30m3/hr) trip 1 296.93 297 (9) Crane Truck (Hydraulic, 20ton) trip 1 378.24 378 (10) Concrete Mixer etc. trip 1 3,000.00 3,000 (11) Others trip 1 3,000.00 3,000 1-2. Site Office etc. set 1 20,105.00 20,105 1-3. Site Clearing (Cutting & Clearing of Grass, Bushes) m2 2,500 0.24 600 1-4. Transportation of Labor day 70 72.00 5,040 1-5. Demobilization (Transportation) from Site(1) Excavator (0.45m3) trip 1 3,000.00 3,000 (2) Excavator (0.10m3) trip 2 1,500.00 3,000 (3) Bulldozer (4 ton class) trip 1 3,000.00 3,000 (4) Roller Compactor (4 ton) trip 1 3,000.00 3,000 (5) Dump Truck (4 ton) trip 2 271.38 543 (6) Water Tank Truck trip 1 316.56 317 (7) Agitator truck (3.2m3) trip 1 353.52 354 (8) Concrete Pump Truck (30m3/hr) trip 1 296.93 297 (9) Crane Truck (Hydraulic, 20ton) trip 1 378.24 378 (10) Concrete Mixer etc. trip 1 3,000.00 3,000 (11) Others trip 1 3,000.00 3,000

    2. Temporary Work2-1. Temporary Road (Gravel Pavement)(1) Embankment with Compaction m3 2,375 7.20 17,100 (2) Gravel m3 300 36.04 10,812 (3) Gravel Pavement m3 300 4.59 1,377 2-2. Dewatering (by Pumping System) day 50 75.74 3,787 2-3. Cofferdam for Head Works(1) Cofferdam for Head Works m3 1,000 4.46 4,460 (2) Sand Bag m3 50 105.95 5,298 2-4. Removal of Cofferdam(1) Removal for Cofferdam m3 1,000 3.75 3,750 (2) Removal for Sand Bag m3 50 3.75 188

    Sub-total 112,295

    Bikaliu Irrigation Scheme Bill of Quantity (1/3)

    3-59

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    3. Head Work3-1. Rock Excavation m3 254 22.32 5,669 3-2. Backfill around Structure m3 144 2.10 302 3-3. Excavation for Banking Material (Soil) from Borrow Pit m3 2,613 7.83 20,460 3-4. Loading & Transportation of Banking Material (Soil) from Borrow Pit

    m3 2,613 4.28 11,184 3-5. Loading & Transportation of Surplus Soil to Borrow Pit m3 137 4.28 586 3-6. Backfill of Surplus Soil at Borrow Pit m3 137 0.89 122 3-7. Concrete Type-A (fc' = 22.5 Mpa) m3 69 180.00 12,420 3-8. Reinforcement Bar ton 5 1,700.00 8,500 3-9. Form m2 103 20.44 2,105 3-10. Lean Concrete m3 8 150.00 1,200 3-11. Gravel (Leveling) m3 11 36.04 396 3-12. Gravel Pavement (Leveling) m3 11 2.25 25 3-13. Supply and Installing Hand Rail, GSP Pipe dia. 2.5 inch m 10 18.70 187 3-14. Gate Facilities set 1 5,000.00 5,000 3-15. Gabion (4 mm dia), Gravel (Aggregate/Cobble Stone) m3 102 88.24 9,000 3-16. VP (Dia. 150mm) m 14 120.00 1,680

    4. Canal Work4-1. Main Canal4-1-1. Common Excavation m3 1,275 7.83 9,983 4-1-2. Embankment with Compaction (Manual Work) m3 1,410 10.02 14,128 4-1-3. Concrete Type-A (fc' = 22.5 Mpa) for Canal m3 108 180.00 19,440 4-1-4. Reinforcement Bar ton 1.7 1,700.00 2,890 4-1-5. Form m2 625 16.03 10,019 4-1-6. Lean Concrete m3 15 150.00 2,250 4-1-7. Gravel m3 30 36.04 1,081 4-1-8. Gravel Pavement m3 30 2.25 68 4-1-9. Gate Facilities (Stop Log) set 1 500.00 500 4-1-10. Transportation & Dispose of Existing Canal m3 40 100.00 4,000

    4-2. Secondary Canal4-2-1. Common Excavation (Manual Work) m3 46 10.02 461 4-2-2. Embankment with Compaction (Manual Work) m3 46 2.75 127 4-2-3. Slope Smoothing (Excavation) m2 1,530 4.35 6,656 4-2-4. Slope Smoothing (Embankment) m2 719 4.35 3,128

    Sub-total 153,567 Total 265,862

    Bikaliu Irrigation Scheme Bill of Quantity (2/3)

    3-60

  • No. Work Description Unit Quantity Unit Price(US$)Total(US$)

    Direct Construction Cost (A) Indirect Construction Cost (B = A * 20%)

    C = A + B

    Consultant Fee (D = C * 5%) Physical Contingency (E = C * 5%)

    Grand Total Cost (F = C + D + E)

    (US$)

    15,952 15,952

    350,938 350,000

    265,862 53,172

    319,034

    Bikaliu Irrigation Scheme Bill of Quantity (3/3)

    3-61

  • Appendix 4

  • THE DEMOCRATIC REPUBLIC OF TIMOR-LESTE

    IRRIGATION DEVELOPMENT PLAN AND

    IRRIGATION ENGINEERING GUIDELINE

    JAPAN INTERNATIONAL COOPERATION AGENCY (JICA)

  • Contents

    Summary .............................................................................................................................................. i

    I. General Description ................................................................................................................... I-1 1. Introduction ................................................................................................................................... I-1 1-1. Background .............................................................................................................................. I-1 1-2. Aim of the Guideline ................................................................................................................ I-1

    2. Feature of Natural Condition and Irrigation Scheme in Timor-Leste ............................................ I-2 2-1. Feature of River Discharge and Intake from River ................................................................... I-2 2-2. Actual Situation of Irrigation for Rice Crop ............................................................................. I-2 2-3. Actual Situation of Irrigation Scheme ...................................................................................... I-3 2-4. Major Point of Irrigation Development Plan in Timor-Leste ................................................... I-5

    3. Water Resources Development and Survey ................................................................................. I-11 3-1. Water Resources Development ............................................................................................... I-11 3-2. Enforcement Process of Water Resources Development ........................................................ I-11 3-3. Survey of Irrigation Project Scheme ...................................................................................... I-12

    II. Engineering Guideline for Irrigation Facilities .............................................................. II-1-1 II-1. Headworks .......................................................................................................................... II-1-1 1. General Description ................................................................................................................... II-1-1 1-1. Definition of Headworks ...................................................................................................... II-1-1 1-2. Basic Consideration of Headworks ...................................................................................... II-1-2

    2. Investigations ............................................................................................................................. II-1-5 2-1. Investigations ....................................................................................................................... II-1-5 2-1-1. Investigations of River Conditions .................................................................................. II-1-5 2-1-2. Investigations on the Influence of Flood Control and Water Use .................................... II-1-7 2-1-3. Topographic Survey ........................................................................................................ II-1-8 2-1-4. Geological Survey ........................................................................................................... II-1-9 2-1-5. Investigations for Natural Conditions ............................................................................. II-1-9 2-1-6. Investigations for Construction Works ............................................................................ II-1-9 2-1-7. Investigations for Managements ..................................................................................... II-1-9

    3. Study of Riverbed Evolution ................................................................................................... II-1-10 3-1. Natural Conditions of Riverbed Formation ........................................................................ II-1-10 3-2. Effect of River Structure on the Riverbed .......................................................................... II-1-11 3-3. Points in Investigation of Riverbed Evolution .................................................................... II-1-11 3-4. Method of Assessing Riverbed Evolution .......................................................................... II-1-12 3-4-1. Necessary Information .................................................................................................. II-1-12 3-4-2. Types of Analysis .......................................................................................................... II-1-12

    4. Design of Headworks .............................................................................................................. II-1-13 4-1. Position of Headworks ....................................................................................................... II-1-13 4-2. Select the Position of Headworks ....................................................................................... II-1-14 4-3. Configuration and Arrangement ......................................................................................... II-1-14 4-4. Design Dimension .............................................................................................................. II-1-16

  • 4-4-1. Design Intake Water Level ............................................................................................ II-1-16 4-4-2. Ensuring Creep Length ................................................................................................. II-1-17

    4-5. Fixed Weir .......................................................................................................................... II-1-19 4-5-1. Section Shape ................................................................................................................ II-1-20 4-5-2. External Forces ............................................................................................................. II-1-20 4-5-3. Apron ............................................................................................................................. II-1-21

    4-6. Riprap ................................................................................................................................. II-1-21 4-6-1. Basic Concept for Engineering of Riprap Work ............................................................ II-1-21 4-6-2. Conditions Required for Riprap .................................................................................... II-1-21

    4-7. Foundation Work ................................................................................................................ II-1-22 4-7-1. Function of Foundation Work ....................................................................................... II-1-22 4-7-2. Selection of Construction Method ................................................................................. II-1-22

    4-8. Cut-off Wall and Dwarf Wall .............................................................................................. II-1-22 4-8-1. Cut-off Wall ................................................................................................................... II-1-22 4-8-2. Dwarf Wall .................................................................................................................... II-1-23

    4-9. Intake .................................................................................................................................. II-1-23 4-9-1. Function of Intake ......................................................................................................... II-1-24 4-9-2. Location of Intake ......................................................................................................... II-1-24 4-9-3. Features of Intake Design .............................................................................................. II-1-24

    4-10. Mountain Stream Intake Works ........................................................................................ II-1-25 4-10-1. Types of Mountain Stream Intake Works and Their Selection .................................... II-1-26

    4-11. Enhancement of Apron ..................................................................................................... II-1-34

    II-2. Canal Works ....................................................................................................................... II-2-1 1. Basic Design .............................................................................................................................. II-2-1 1-1. General Concepts ................................................................................................................. II-2-1 1-1-1. Overall Design of Irrigation Canal & Drainage Canal .................................................... II-2-1 1-1-2. Main Item to be Considered in Overall Design ............................................................... II-2-1

    1-2. Procedure of Design ............................................................................................................. II-2-2 1-3. Design Discharge and Designed Level ................................................................................. II-2-6 1-3-1. Design Discharge ............................................................................................................ II-2-6 1-3-2. Designed Level ............................................................................................................... II-2-7

    1-4. Selection of Canal Type ........................................................................................................ II-2-7 1-4-1. Open Channel Type ......................................................................................................... II-2-8 1-4-2. Pipeline Type ................................................................................................................... II-2-8 1-4-3. Compound Type of Open Channels and Pipelines .......................................................... II-2-9

    1-5. Canal Route Selection .......................................................................................................... II-2-9 1-5-1. General Conceptions for the Canal Route Selection ....................................................... II-2-9 1-5-2. General Conditions for the Canal Route Selection .......................................................... II-2-9 1-5-3. Procedure for Canal Route Selection ............................................................................ II-2-10

    1-6. Selection of Canal Structures for Open Channel Type ....................................................... II-2-11 1-6-1. Open Channel ................................................................................................................ II-2-12 1-6-2. Tunnel ........................................................................................................................... II-2-12 1-6-3. Culvert ........................................................................................................................... II-2-13 1-6-4. Siphon / Aqueduct ......................................................................................................... II-2-14 1-6-5. Drop / Chute .................................................................................................................. II-2-14

  • 2. Hydraulic Design ..................................................................................................................... II-2-15 2-1. Allowable Velocity ............................................................................................................. II-2-15 2-1-1. Minimum Allowable Velocity ...................................................................................... II-2-15 2-1-2. Maximum Allowable Velocity ...................................................................................... II-2-16 2-1-3. Items to be Considered in Determining Velocity .......................................................... II-2-17

    2-2. Uniform Flow Calculation and Coefficient of Roughness ................................................. II-2-18 2-2-1. Classification of Open Channel Flows and Mean Velocity Formula ............................ II-2-18 2-2-2. Selection of Coefficient of Roughness .......................................................................... II-2-19 2-2-3. Effects of Canal Curvature, Sediment, and Vegetation on Coefficient of Roughness ........ II-2-21 2-2