APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY...

77
ENVIRONMENTAL ASSESSMENT ENNIS BIG SKY AIRPORT MADISON COUNTY, MT APPENDICES ROBERT PECCIA & ASSOCIATES

Transcript of APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY...

Page 1: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

ENVIRONMENTAL ASSESSMENT ENNIS BIG SKY AIRPORT MADISON COUNTY, MT

APPENDICES

ROBERT PECCIA & ASSOCIATES

Page 2: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

APPENDIX A ENNIS BIG SKY AIRPORT ENVIRONMENTAL ASSESSMENT

APPENDIX A: RELEVANT CORRESPONDENCE AND

COORDINATION

Page 3: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 4: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

1

Dan Norderud

From: Fechter, Charity <[email protected]>Sent: Tuesday, April 03, 2018 1:39 PMTo: Dan NorderudCc: Madison County CommissionersSubject: Ennis Big Sky EA

Daniel,  The proposed Ennis Big Sky airport improvements were reviewed by the Planning Board at their March 26, 2018 meeting.  The Board did not have any specific comments on the improvements.   Charity Fechter Planning Director  Madison County P.O. Box 278 Virginia City, Montana 59755 406-843-5250 406-843-5229 (fax) Visit us at www.MadisonCountyMT.gov  Machines work.  People think.   

Page 5: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 6: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

1

Dan Norderud

From: Cole, Robert H CIV USARMY CENWO (US) <[email protected]>Sent: Monday, April 02, 2018 3:07 PMTo: Dan NorderudSubject: RE: Corps No. NWO-2018-00319-MTH; Ennis Big Sky Airport Improvements

Mr. Norderud,  The appropriate permits would be based on the impacts of total impacts.  Stream impacts greater than 300 linear feet of cumulative impacts (all stream impacts past and present) cannot be covered by NWP 39 and would be permitted using a Standard Permit and requires mitigation for the current impacts.  Any wetland impacts greater than a cumulative 1/2 acre cannot be covered by a NWP 39 and would require permitting by Standard Permit.  Cumulative wetland loss of greater than 1/10 acre required compensatory mitigation as well.   ‐‐‐‐‐Original Message‐‐‐‐‐ From: Dan Norderud [mailto:DNorderud@rpa‐hln.com]  Sent: Wednesday, March 28, 2018 10:59 AM To: Cole, Robert H CIV USARMY CENWO (US) <[email protected]> Subject: [Non‐DoD Source] Corps No. NWO‐2018‐00319‐MTH; Ennis Big Sky Airport Improvements  Mr. Cole ‐ Thank you for your letter dated March 15, 2018 with comments about the proposed improvements at Ennis Big Sky Airport.       Since we're currently writing an Environmental Assessment for this improvement project, I felt it was important to provide some additional information about anticipated impacts to aquatic resources and get some early feedback from you about the impacts and potential mitigation requirements. With that in mind, I've attached a summary discussing the work anticipated within McDeed Creek, Boulder Creek, and two unnamed tributaries of Boulder Creek. The attachment provides background information about the proposed work locations and generally describes the work required within each of these surface drainages.   Please note, we have not yet prepared a detailed design of the proposed improvements so impacts cannot be exactly quantified.  Design work would not begin until after the EA process has been concluded and the FAA has made an environmental determination that allows the project to move forward.      We would appreciate your comments on the following items:     1.  Will implementing the same type of channel change work at McDeed Creek as was authorized by the Corps on August 4, 2008 for a previous improvement project be acceptable to the Corps?  (The channel change work authorized under Corps File Number NWO‐2008‐825‐WTH is summarized in the attachment). 2.  Are we correct in assuming mitigation requirements for impacts to affected streams will be dictated by the Montana Stream Mitigation Procedure (February 2013)?  3.  Since fringe wetlands exist along the impacted segments of McDeed Creek channel, will mitigation be necessary for both wetland and stream impacts?     

Page 7: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

2

 Thanks in advance for any comments you can provide.  If you prefer, I would be happy to meet with you to discuss this project.      Sincerely,     Dan Norderud      Daniel M. Norderud, AICP | Environmental Studies Group Manager  Robert Peccia & Associates Inc. | PO Box 5653 | Helena, MT 59604  406.447.5007 | 406.447.5036 (fax) |406.465.8909 (cell) |  DNorderud@rpa‐hln.com <mailto:DNorderud@rpa‐hln.com>  Blockedhttp://www.rpa‐hln.com <Blockedhttp://www.rpa‐hln.com/>       The materials transmitted by this electronic mail are confidential, are only for the use of the intended recipient, and may be subject to applicable privileges. Any unauthorized dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, please immediately notify the sender and destroy all copies of the communication and any attachments.      

Page 8: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 9: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 10: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

United States Department of the Interior

FISH AND WILDLIFE SERVICE

In Reply Refer To: File: M.29 Public TAILS: 06E11000-2018-TA-0285; 06E11000-2018-CPA-0063

Montana Ecological Services Office 585 Shephard Way, Suite 1

Helena, Montana 59601-6287

March 15, 2018 Daniel Norderud, Environmental Studies Group Manager Robert Peccia & Associates 3147 Saddle Drive P.O. Box 5653 Helena, Montana 59601 Dear Mr. Norderud: Thank you for your letter of February 22, 2018, received in this office on February 23, requesting U.S. Fish and Wildlife Service (Service) comment regarding proposed improvements at Ennis Big Sky Airport in Madison County, Montana, and your associated preparation of an Environmental Assessment. We received a copy of the October 5, 2016, Ennis Big Sky Airport Biological/Wetland Resources Findings memorandum (Memorandum) on March 12, 2018. Our comments are prepared under the authority of, and in accordance with, the provisions of the Migratory Bird Treaty Act (16 U.S.C. 703 et seq.), Bald and Golden Eagle Protection Act (16 U.S.C. 668-668d, 54 Stat. 250), and the Endangered Species Act (16 U.S.C. 1531 et. seq.). Threatened and Endangered Species Listed and proposed and candidate threatened and endangered species that may be present in Madison County include the listed threatened Canada lynx, red knot, and Ute ladies’ tresses; proposed wolverine; and candidate whitebark pine. No designated or proposed critical habitat occurs in the project area. The Canada lynx and wolverine may occur as rare transients in the general project area. One migratory red knot occurrence at Ennis Lake was recorded several decades ago. We are not aware of documented Ute ladie’s tresses occurrences in the project vicinity, although potential habitat for this species occurs west of the proposed project location. Whitebark pine habitat does not occur in the immediate project vicinity. Based on the project site habitat descriptions provided in the October 2016 Memorandum and confined nature and proposed location of this proposed work in an existing developed airport setting, we do not anticipate its implementation would result in adverse effects to listed, proposed or candidate threatened or endangered species, or listed or proposed critical habitat. In June 2017, the Greater Yellowstone Ecosystem (GYE) grizzly bear population was removed from the List of Endangered and Threatened Wildlife under the authority of the ESA. However, grizzly bears may occasionally occur in the general project area, and to reduce the risk of human-

Page 11: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

2

grizzly bear conflicts related to this project, the Service advises implementation of the following (or similar) voluntary conservation measures as appropriate: 1. Promptly clean up any project related spills, litter, garbage, debris, etc. 2. Allow no overnight camping within the project vicinity, except in designated

campgrounds, by any crew member or other personnel associated with this project. 3. Store all food, food related items, petroleum products, antifreeze, garbage, personal

hygiene items, and other attractants inside a closed, hard-sided vehicle or commercially manufactured bear resistant container.

4. Remove garbage from the project site daily and dispose of it in accordance with all applicable regulations.

5. Notify the Project Manager of any animal carcasses found in the area. 6. Notify the Project Manager of any grizzly bears observed in the vicinity of the project. Eagles and other Migratory Birds The Service is not aware of any known eagle nests within a mile of the project, although the general surrounding area may receive year round eagle use. Given the developed nature of the immediate project area, we do not anticipate substantive negative project-related effects to bald or golden eagles. The MBTA prohibits the taking, killing, possession, and transportation, (among other actions) of migratory birds, their eggs, parts, and nests, except when specifically permitted. To the extent practicable, necessary wetland and other vegetation clearing, grubbing, and filling construction activities should be scheduled so as to avoid and minimize impacts to nesting birds, if present in the project area. If work is proposed to take place in migratory bird habitats which may result in take of migratory birds, their eggs, or active nests, the Service recommends that the project proponent take all practicable measures to avoid and minimize take. Active nests may not be removed. The Service has developed, and continues to revise and develop, general and industry-specific conservation measures for avoiding and minimizing impacts to birds (https://www.fws.gov/birds/management/project-assessment-tools-and-guidance/conservation-measures.php). We recommend that the proposed project consider and incorporate these measures into project design, construction, and documentation as appropriate. Wetlands We recommend that at any temporary or permanent wetland / riparian / non-wetland water impact areas: 1) any lost wetland functions be quantified and replaced; 2) appropriate native vegetation materials (seed, root stock, containerized stock, etc.) be used in restoration and stabilization efforts; 3) measurable performance standards for such sites be applied (including satisfaction of vegetation, soils, and hydrology wetland delineation criteria [for wetlands], minimum vegetation success / coverage criteria, and maximum weed/invasive species coverage criteria); 4) noxious / invasive vegetation species be suppressed; 5) standardized annual monitoring be conducted until performance standards are met and; 6) corrective actions be applied as necessary. The Service recommends keeping wetland disturbances to the minimum extent and duration possible, with as much occurring “in the dry” as possible. This would reduce impacts to aquatic species relative to disturbance and sediment inputs. We also recommend that appropriate erosion

Page 12: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

3

and sediment control efforts and measures be implemented during and following construction to avoid introducing sediments or other contaminants to adjacent waters. In addition to coordination with the Service, we recommend coordination with Montana Fish, Wildlife and Parks and the Montana Natural Heritage Program. These agencies may be able to provide updated, site-specific information regarding fish, wildlife, and sensitive plant resources occurring in the proposed project area. Contact information for these two agencies is below: Montana Fish, Wildlife and Parks Montana Natural Heritage Program 1420 East Sixth Avenue 1515 East 6th Avenue, Box 201800 P.O. Box 200701 Helena, Montana 59620-1800 Helena, Montana 59620-0701 Phone: (406) 444-5354 Phone: (406) 444-2535 If you have further questions related to this issue, please do not hesitate to contact Jeff Berglund at [email protected] or (406) 449-5225, extension 206.

Sincerely,

for Jodi L. Bush Office Supervisor

Page 13: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 14: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

1

Dan Norderud

From: Dan NorderudSent: Friday, March 09, 2018 9:45 AMTo: 'Brooker, Jay - NRCS, Missoula, MT'Cc: '[email protected]'Subject: RE: Ennis Airport form AD-1006Attachments: AD1006_Ennis_airport_final_030818.pdf

Jay – Attached is a copy of Form AD‐1006 with the Site Assessment Criteria in Part VI completed. Thanks for your help processing this form.  Dan Norderud  

Daniel M. Norderud, AICP | Environmental Studies Group Manager Robert Peccia & Associates Inc. | PO Box 5653 | Helena, MT 59604 406.447.5007 | 406.447.5036 (fax) |406.465.8909 (cell) |  DNorderud@rpa‐hln.com http://www.rpa‐hln.com   The materials transmitted by this electronic mail are confidential, are only for the use of the intended recipient, and may be subject to applicable privileges. Any unauthorized dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, please immediately notify the sender and destroy all copies of the communication and any attachments.  

From: Brooker, Jay ‐ NRCS, Missoula, MT [mailto:[email protected]]  Sent: Friday, March 02, 2018 10:13 AM To: Dan Norderud <DNorderud@rpa‐hln.com> Cc: Gauthier, Melinda ‐ NRCS, Missoula, MT <[email protected]> Subject: Ennis Airport form AD‐1006  Daniel,  I am attaching the AD‐1006 for the Ennis airport expansion.  I have completed the NRCS portion.  You will need to complete Part VI based on answering the questions.  When you  get that completed you should have a total score at the bottom.   You will want to fill out your name at the bottom of the form under Federal Agency representative completing this form.   Please resend the form to me when you have completed it so I can respond.  Thanks, Jay   Jay Brooker – NRCS Resource Soil Scientist 3550 Mullan Road, Suite 106 Missoula, MT 59808 406-303-3443 [email protected]      

Page 15: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

2

This electronic message contains information generated by the USDA solely for the intended recipients. Any unauthorized interception of this message or the use or disclosure of the information it contains may violate the law and subject the violator to civil or criminal penalties. If you believe you have received this message in error, please notify the sender and delete the email immediately.  

Page 16: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

U.S. Department of Agriculture

FARMLAND CONVERSION IMPACT RATING PART I (To be completed by Federal Agency) Date Of Land Evaluation Request

Name of Project Federal Agency Involved

Proposed Land Use County and State

PART II (To be completed by NRCS) Date Request Received By NRCS

Person Completing Form:

Does the site contain Prime, Unique, Statewide or Local Important Farmland?

(If no, the FPPA does not apply - do not complete additional parts of this form)

YES NO

Acres Irrigated

Average Farm Size

Major Crop(s)

Farmable Land In Govt. Jurisdiction

Acres: %

Amount of Farmland As Defined in FPPA

Acres: %

Name of Land Evaluation System Used

Name of State or Local Site Assessment System

Date Land Evaluation Returned by NRCS

Alternative Site Rating PART III (To be completed by Federal Agency) Site A Site B Site C Site D

A. Total Acres To Be Converted Directly

B. Total Acres To Be Converted Indirectly

C. Total Acres In Site

PART IV (To be completed by NRCS) Land Evaluation Information

A. Total Acres Prime And Unique Farmland

B. Total Acres Statewide Important or Local Important Farmland

C. Percentage Of Farmland in County Or Local Govt. Unit To Be Converted

D. Percentage Of Farmland in Govt. Jurisdiction With Same Or Higher Relative Value

PART V (To be completed by NRCS) Land Evaluation Criterion Relative Value of Farmland To Be Converted (Scale of 0 to 100 Points)

PART VI (To be completed by Federal Agency) Site Assessment Criteria (Criteria are explained in 7 CFR 658.5 b. For Corridor project use form NRCS-CPA-106)

MaximumPoints

Site A Site B Site C Site D

1. Area In Non-urban Use (15)

2. Perimeter In Non-urban Use (10)

3. Percent Of Site Being Farmed (20)

4. Protection Provided By State and Local Government (20)

5. Distance From Urban Built-up Area (15)

6. Distance To Urban Support Services (15)

7. Size Of Present Farm Unit Compared To Average (10)

8. Creation Of Non-farmable Farmland (10)

9. Availability Of Farm Support Services (5)

10. On-Farm Investments (20)

11. Effects Of Conversion On Farm Support Services (10)

12. Compatibility With Existing Agricultural Use (10)

TOTAL SITE ASSESSMENT POINTS 160

PART VII (To be completed by Federal Agency)

Relative Value Of Farmland (From Part V) 100

Total Site Assessment (From Part VI above or local site assessment) 160

TOTAL POINTS (Total of above 2 lines) 260

Site Selected:

Date Of Selection

Was A Local Site Assessment Used?

YES NO

Reason For Selection:

Name of Federal agency representative completing this form: Date: (See Instructions on reverse side) Form AD-1006 (03-02)

Page 17: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

STEPS IN THE PROCESSING THE FARMLAND AND CONVERSION IMPACT RATING FORM

Step 1 - Federal agencies (or Federally funded projects) involved in proposed projects that may convert farmland, as defined in the Farmland Protection Policy Act (FPPA) to nonagricultural uses, will initially complete Parts I and III of the form. For Corridor type projects, the Federal agency shall use form NRCS-CPA-106 in place of form AD-1006. The Land Evaluation and Site Assessment (LESA) process may also be accessed by visiting the FPPA website, http://fppa.nrcs.usda.gov/lesa/.

Step 2 - Originator (Federal Agency) will send one original copy of the form together with appropriate scaled maps indicating location(s)of project site(s), to the Natural

Resources Conservation Service (NRCS) local Field Office or USDA Service Center and retain a copy for their files. (NRCS has offices in most counties in the U.S. The USDA Office Information Locator may be found at http://offices.usda.gov/scripts/ndISAPI.dll/oip_public/USA_map, or the offices can usually be found in the Phone Book under U.S. Government, Department of Agriculture. A list of field offices is available from the NRCS State Conservationist and State Office in each State.)

Step 3 - NRCS will, within 10 working days after receipt of the completed form, make a determination as to whether the site(s) of the proposed project contains prime,

unique, statewide or local important farmland. (When a site visit or land evaluation system design is needed, NRCS will respond within 30 working days. Step 4 - For sites where farmland covered by the FPPA will be converted by the proposed project, NRCS will complete Parts II, IV and V of the form. Step 5 - NRCS will return the original copy of the form to the Federal agency involved in the project, and retain a file copy for NRCS records. Step 6 - The Federal agency involved in the proposed project will complete Parts VI and VII of the form and return the form with the final selected site to the servicing

NRCS office. Step 7 - The Federal agency providing financial or technical assistance to the proposed project will make a determination as to whether the proposed conversion is consistent

with the FPPA.

INSTRUCTIONS FOR COMPLETING THE FARMLAND CONVERSION IMPACT RATING FORM (For Federal Agency)

Part I: When completing the "County and State" questions, list all the local governments that are responsible for local land

use controls where site(s) are to be evaluated. Part III: When completing item B (Total Acres To Be Converted Indirectly), include the following: 1. Acres not being directly converted but that would no longer be capable of being farmed after the conversion, because the

conversion would restrict access to them or other major change in the ability to use the land for agriculture. 2. Acres planned to receive services from an infrastructure project as indicated in the project justification (e.g. highways,

utilities planned build out capacity) that will cause a direct conversion. Part VI: Do not complete Part VI using the standard format if a State or Local site assessment is used. With local and NRCS

assistance, use the local Land Evaluation and Site Assessment (LESA). 1. Assign the maximum points for each site assessment criterion as shown in § 658.5(b) of CFR. In cases of corridor-type

project such as transportation, power line and flood control, criteria #5 and #6 will not apply and will, be weighted zero, however, criterion #8 will be weighed a maximum of 25 points and criterion #11 a maximum of 25 points.

2. Federal agencies may assign relative weights among the 12 site assessment criteria other than those shown on the

FPPA rule after submitting individual agency FPPA policy for review and comment to NRCS. In all cases where other weights are assigned, relative adjustments must be made to maintain the maximum total points at 160. For project sites where the total points equal or exceed 160, consider alternative actions, as appropriate, that could reduce adverse impacts (e.g. Alternative Sites, Modifications or Mitigation).

Part VII: In computing the "Total Site Assessment Points" where a State or local site assessment is used and the total maximum number of points is other than 160, convert the site assessment points to a base of 160. Example: if the Site Assessment maximum is 200 points, and the alternative Site "A" is rated 180 points: For assistance in completing this form or FPPA process, contact the local NRCS Field Office or USDA Service Center. NRCS employees, consult the FPPA Manual and/or policy for additional instructions to complete the AD-1006 form.

Total points assigned Site A 180 Maximum points possible 200 = X 160 = 144 points for Site A

Page 18: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

1

Dan Norderud

From: Brooker, Jay - NRCS, Missoula, MT <[email protected]>Sent: Friday, March 02, 2018 10:13 AMTo: Dan NorderudCc: Gauthier, Melinda - NRCS, Missoula, MTSubject: Ennis Airport form AD-1006Attachments: AD1006_Ennis_airport.pdf

Daniel,  I am attaching the AD‐1006 for the Ennis airport expansion.  I have completed the NRCS portion.  You will need to complete Part VI based on answering the questions.  When you  get that completed you should have a total score at the bottom.   You will want to fill out your name at the bottom of the form under Federal Agency representative completing this form.   Please resend the form to me when you have completed it so I can respond.  Thanks, Jay   Jay Brooker – NRCS Resource Soil Scientist 3550 Mullan Road, Suite 106 Missoula, MT 59808 406-303-3443 [email protected]      This electronic message contains information generated by the USDA solely for the intended recipients. Any unauthorized interception of this message or the use or disclosure of the information it contains may violate the law and subject the violator to civil or criminal penalties. If you believe you have received this message in error, please notify the sender and delete the email immediately.  

Page 19: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 20: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

U.S. Department of Agriculture

FARMLAND CONVERSION IMPACT RATING PART I (To be completed by Federal Agency) Date Of Land Evaluation Request

Name of Project Federal Agency Involved

Proposed Land Use County and State

PART II (To be completed by NRCS) Date Request Received By NRCS

Person Completing Form:

Does the site contain Prime, Unique, Statewide or Local Important Farmland?

(If no, the FPPA does not apply - do not complete additional parts of this form)

YES NO

Acres Irrigated

Average Farm Size

Major Crop(s)

Farmable Land In Govt. Jurisdiction

Acres: %

Amount of Farmland As Defined in FPPA

Acres: %

Name of Land Evaluation System Used

Name of State or Local Site Assessment System

Date Land Evaluation Returned by NRCS

Alternative Site Rating PART III (To be completed by Federal Agency) Site A Site B Site C Site D

A. Total Acres To Be Converted Directly

B. Total Acres To Be Converted Indirectly

C. Total Acres In Site

PART IV (To be completed by NRCS) Land Evaluation Information

A. Total Acres Prime And Unique Farmland

B. Total Acres Statewide Important or Local Important Farmland

C. Percentage Of Farmland in County Or Local Govt. Unit To Be Converted

D. Percentage Of Farmland in Govt. Jurisdiction With Same Or Higher Relative Value

PART V (To be completed by NRCS) Land Evaluation Criterion Relative Value of Farmland To Be Converted (Scale of 0 to 100 Points)

PART VI (To be completed by Federal Agency) Site Assessment Criteria (Criteria are explained in 7 CFR 658.5 b. For Corridor project use form NRCS-CPA-106)

MaximumPoints

Site A Site B Site C Site D

1. Area In Non-urban Use (15)

2. Perimeter In Non-urban Use (10)

3. Percent Of Site Being Farmed (20)

4. Protection Provided By State and Local Government (20)

5. Distance From Urban Built-up Area (15)

6. Distance To Urban Support Services (15)

7. Size Of Present Farm Unit Compared To Average (10)

8. Creation Of Non-farmable Farmland (10)

9. Availability Of Farm Support Services (5)

10. On-Farm Investments (20)

11. Effects Of Conversion On Farm Support Services (10)

12. Compatibility With Existing Agricultural Use (10)

TOTAL SITE ASSESSMENT POINTS 160

PART VII (To be completed by Federal Agency)

Relative Value Of Farmland (From Part V) 100

Total Site Assessment (From Part VI above or local site assessment) 160

TOTAL POINTS (Total of above 2 lines) 260

Site Selected:

Date Of Selection

Was A Local Site Assessment Used?

YES NO

Reason For Selection:

Name of Federal agency representative completing this form: Date: (See Instructions on reverse side) Form AD-1006 (03-02)

Page 21: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps

STEPS IN THE PROCESSING THE FARMLAND AND CONVERSION IMPACT RATING FORM

Step 1 - Federal agencies (or Federally funded projects) involved in proposed projects that may convert farmland, as defined in the Farmland Protection Policy Act (FPPA) to nonagricultural uses, will initially complete Parts I and III of the form. For Corridor type projects, the Federal agency shall use form NRCS-CPA-106 in place of form AD-1006. The Land Evaluation and Site Assessment (LESA) process may also be accessed by visiting the FPPA website, http://fppa.nrcs.usda.gov/lesa/.

Step 2 - Originator (Federal Agency) will send one original copy of the form together with appropriate scaled maps indicating location(s)of project site(s), to the Natural

Resources Conservation Service (NRCS) local Field Office or USDA Service Center and retain a copy for their files. (NRCS has offices in most counties in the U.S. The USDA Office Information Locator may be found at http://offices.usda.gov/scripts/ndISAPI.dll/oip_public/USA_map, or the offices can usually be found in the Phone Book under U.S. Government, Department of Agriculture. A list of field offices is available from the NRCS State Conservationist and State Office in each State.)

Step 3 - NRCS will, within 10 working days after receipt of the completed form, make a determination as to whether the site(s) of the proposed project contains prime,

unique, statewide or local important farmland. (When a site visit or land evaluation system design is needed, NRCS will respond within 30 working days. Step 4 - For sites where farmland covered by the FPPA will be converted by the proposed project, NRCS will complete Parts II, IV and V of the form. Step 5 - NRCS will return the original copy of the form to the Federal agency involved in the project, and retain a file copy for NRCS records. Step 6 - The Federal agency involved in the proposed project will complete Parts VI and VII of the form and return the form with the final selected site to the servicing

NRCS office. Step 7 - The Federal agency providing financial or technical assistance to the proposed project will make a determination as to whether the proposed conversion is consistent

with the FPPA.

INSTRUCTIONS FOR COMPLETING THE FARMLAND CONVERSION IMPACT RATING FORM (For Federal Agency)

Part I: When completing the "County and State" questions, list all the local governments that are responsible for local land

use controls where site(s) are to be evaluated. Part III: When completing item B (Total Acres To Be Converted Indirectly), include the following: 1. Acres not being directly converted but that would no longer be capable of being farmed after the conversion, because the

conversion would restrict access to them or other major change in the ability to use the land for agriculture. 2. Acres planned to receive services from an infrastructure project as indicated in the project justification (e.g. highways,

utilities planned build out capacity) that will cause a direct conversion. Part VI: Do not complete Part VI using the standard format if a State or Local site assessment is used. With local and NRCS

assistance, use the local Land Evaluation and Site Assessment (LESA). 1. Assign the maximum points for each site assessment criterion as shown in § 658.5(b) of CFR. In cases of corridor-type

project such as transportation, power line and flood control, criteria #5 and #6 will not apply and will, be weighted zero, however, criterion #8 will be weighed a maximum of 25 points and criterion #11 a maximum of 25 points.

2. Federal agencies may assign relative weights among the 12 site assessment criteria other than those shown on the

FPPA rule after submitting individual agency FPPA policy for review and comment to NRCS. In all cases where other weights are assigned, relative adjustments must be made to maintain the maximum total points at 160. For project sites where the total points equal or exceed 160, consider alternative actions, as appropriate, that could reduce adverse impacts (e.g. Alternative Sites, Modifications or Mitigation).

Part VII: In computing the "Total Site Assessment Points" where a State or local site assessment is used and the total maximum number of points is other than 160, convert the site assessment points to a base of 160. Example: if the Site Assessment maximum is 200 points, and the alternative Site "A" is rated 180 points: For assistance in completing this form or FPPA process, contact the local NRCS Field Office or USDA Service Center. NRCS employees, consult the FPPA Manual and/or policy for additional instructions to complete the AD-1006 form.

Total points assigned Site A 180 Maximum points possible 200 = X 160 = 144 points for Site A

Page 22: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 23: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 24: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 25: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 26: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 27: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 28: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 29: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 30: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 31: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 32: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 33: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 34: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 35: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 36: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 37: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 38: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 39: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 40: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 41: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 42: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 43: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 44: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 45: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 46: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 47: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 48: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 49: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 50: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 51: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 52: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 53: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 54: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 55: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 56: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 57: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 58: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 59: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 60: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 61: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 62: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 63: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 64: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 65: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 66: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 67: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 68: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 69: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 70: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 71: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 72: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 73: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 74: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 75: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 76: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps
Page 77: APPENDICES - Robert Peccia & Associates Airport EA/Appendix A.pdf · To: Cole, Robert H CIV USARMY CENWO (US)  Subject: [Non‐DoD Source] Corps