Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a...

34
Appendices O - Q

Transcript of Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a...

Page 1: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Appendices

O - Q

Page 2: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

CROW BUTTE RESOURCES, INC. Swift Fox Survey Protocol Marsland Expansion Area

1

Appendix O Swift Fox Survey Protocol

The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824 (dated August 19, 2009) issued by the Department of Environmental Quality (NDEQ) to Crow Butte Resources, Inc (NDEQ 2009). This permit primarily addresses impacts associated with drilling of boreholes for purposes of mineral exploration. The primary modification of the Appendix 10 protocol is expanding the type of activities potentially impacting the swift fox to include, in addition to drilling of boreholes, uranium in situ satellite project development activities. Satellite “project development” includes construction of satellite facilities (process building and associated storage structures, evaporation ponds, wellfield development (surface preparation, monitor and injection/recovery wells, wellhouses, and trunklines/piping), well workover, boreholes outside of wellfields, and project roadways. Reference to “project development” in this protocol refers to these activities. Project development activities apply to initial construction/wellfield development, operations and decommissioning. Decommissioning includes decontaminating, dismantling, and removing satellite facilities and associated wellfield buildings/equipment/wells and, site reclamation and groundwater restoration.

Swift fox are typically found in topographically flat (slopes <20%) arid regions. In Nebraska, suitable habitat is in the short-grass prairie ecoregion where vegetation is less than 40 cm tall. They can be found in large expanses of prairie as well as prairie intermixed with agriculture. Dens are also found in anthropogenic areas such as near roads and trails, and in agricultural fields, culverts pipes and buildings (Tannerfeldt et al 2003). Swift fox are highly mobile and will use a variety of dens throughout the year. However, a female swift fox with young pups will typically be tied to one den until the pups are old enough to disperse from the den. Swift fox den entrances have a diameter of 17 to 23 cm.

Required Surveys: CBR will avoid impacting the swift fox species by avoiding certain locations during specific times of the year. Surveys shall be conducted that are consistent with the Nebraska Game and Parks Commission (NG&PC) standard protocol included in CBR’s Mineral Exploration Permit Number NE0210824 as Attachment 1.

The survey form to be used for swift fox surveys is attached to this protocol.

Project development activities will occur within a designated permit boundary. If project development activities within this permit boundary are such that specific protocol requirements (e.g., designated distances from swift fox dens) cannot be avoided as stated in this protocol, CBR will consult with the NDEQ and NG&PC as to the feasibility of

Page 3: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

CROW BUTTE RESOURCES, INC. Swift Fox Survey Protocol Marsland Expansion Area

2

alternate actions. No work will be conducted until any such issue has been resolved with the NDEQ and NG&PC.

Surveyors: Surveys shall be conducted by a qualified individual who has experience working with the species or has been trained to identify swift fox burrows, dens and sign (scat, tracks, etc.).

Location: Surveys shall be conducted at project development sites discussed above where suitable habitat is present within the range of the species.

Season: Surveys shall be conducted year-around in areas of suitable habitat where project development activities are planned.

Timing: Surveys shall be conducted within one week of initiating project development activities described above under Location.

Survey Technique: The “denning season” is defined as the period of time when adult swift fox give birth and raise pups. In Nebraska, the swift fox denning season is from April 1 through August 31.

During the denning season, the area that must be surveyed for dens includes project development activities plus an additional 230 meters around the affected areas. When developing wellfields, numerous boreholes will initially be drilled. In this situation, the “affected area” will be the perimeter of the wellfield for the addition of 230 meters to the survey area, as opposed to each drill site. Under such conditions (i.e. work over multiple days or months), only one survey shall be submitted for that period indicating the duration of planned activities in the survey area. During other periods of time (e.g., operations), when individual boreholes are drilled at one time or a workover rig is used for well maintenance, then the additional 230 meters will be applied to the drill site. The above procedures will allow the operator the option of the most effective type of survey to use - wellfield boundary or individual drill site. The satellite facilities will be located within a 1.8-acre fenced-in site. The swift fox survey will be conducted prior to construction using an additional 230 meters around the fence boundary.

During the non-denning season (September 1 through March 31), the area that must be surveyed for dens includes the project development activities plus an additional 100 meters around the affected areas. When developing wellfields, numerous boreholes will initially be drilled. In this situation, the “affected area” will be the perimeter of the

Page 4: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

CROW BUTTE RESOURCES, INC. Swift Fox Survey Protocol Marsland Expansion Area

3

wellfield for the addition of 100 meters to the survey area, as opposed to each drill site. Under such conditions (i.e. work over multiple days or months), only one survey shall be submitted for that period indicating the duration of planned activities in the survey area. During other periods of time (e.g., operations), when individual boreholes are drilled at one time or a workover rig is used for well maintenance, then the additional 100 meters will be applied to the drill site. The above procedures will allow the operator the option of the most effective type of survey to use - wellfield boundary or individual drill site. The satellite facilities will be located within a 1.8-acre fenced-in site. The swift fox survey will be conducted using an additional 100 meters around the fence boundary.

The survey will consist of walking transects and searching for dens within the survey area. Transects will be no more that 50 meters apart in order to thoroughly cover the area.

An active den may have fresh digging at the entrance, although this is not always the case (Jackson and Choate 2000). Sign, such as scat or tracks, can also be indicate an active den. Swift fox tracks are approximately 2.54 cm wide and 3.8 cm long. Although this is the smallest canid species, tracks can be confused with other species, especially young coyotes. Inactive dens may be overgrown with vegetation, have spider webs over the entrance, or be caving in.

Conservative Measures: If a potentially active swift fox den is identified, one of two conservation measures should be implemented:

1. The area of project development activities shall be done so activities are at least 230 meters from the den during the denning season, or 100 meters from the den during the non-denning season. For drilling sites, these can be moved to an appropriate distance from the den. A survey around any of these new activities must be conducted.

2. A track or scent station can be set up to determine if the den is being used by swift fox. If track or scent stations indicate swift fox are using the den, then project development activities within a minimum of 100 meters or 230 meters (whichever is appropriate for the season) of the den would be postponed until the den is abandoned. For drilling sites, they can be moved as outlined in #1 above. If track or scent stations indicate swift fox are not using the den, then drilling activities may proceed if there are not any other dens or swift fox within the survey area.

Track Station: Den use can be determined by clearing vegetation around the den and sifting a mixture of fine dry sand and unscented glycerin in a circular patter (~1 m in diameter) around the den hole, approximately 0.5 inches thick. Tracks of the animal using the den can then be identified the following morning as most animals using underground dens are nocturnal and will exit the den at night. Track stations are only

Page 5: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

CROW BUTTE RESOURCES, INC. Swift Fox Survey Protocol Marsland Expansion Area

4

good for one night. If the track station cannot be checked the following morning, a new sand and glycerin mixture should be applied to the area around the den hole and surveyed the next morning.

Scent Station: Swift fox scent station surveys can be conducted any time of the year, although tracks will not show on bare, frozen ground. However, snow can be used as a tracking medium in winter. Scent stations are created by clearing any vegetation in an area and sifting a mixture of fine dry sand and unscented glycerin in a circular patter (~1 m in diameter) approximately 0.5 inches thick. A plaster tablet soaked in cod/salmon oil mixture (or either) is placed in the center of the station. Scent stations are then placed at locations selected based on the suitability of the surrounding habitat and the presence of certain structures (fence rows, gates, intersections, trails, etc.) that facilitate movement. Weather permitting, they are reset for 3 consecutive days or until at least one station shows sign of swift fox visitation (tracks, feces). Scent stations should not be used within 300 meters of a known or suspected active den as these methods may attract predators.

Survey Reports A monthly survey report shall be submitted to Nebraska Game and Parks Commission (NG&PC) and Nebraska Department of Environmental Quality (NDEQ) describing all surveys for the swift fox that were conducted during the previous month in connection with project development activities. The survey report shall include the names of the surveyors and their credentials, date and time of the survey, weather conditions, locations surveyed, methods, results, and a discussion of applicable conservation measures implemented. If the swift fox is not identified, the above information must be recorded and included in the report to be submitted at the end of the month. If a swift fox is identified within the survey area, NG&PC must be notified by telephone within twenty-four (24) hours of identification. Written documentation of identification and the survey report shall be submitted with five (5) days of species identification, along with indication of conservation measures. All survey reports shall be submitted no later than the 28th day of the month following the end of the reporting period, even if the species being surveyed are not detected at a particular site. Copies of the reports shall be kept on site for inspection by the NDEQ.

References: Jackson, V.I. and J.R. Chaote. 2000. Dens and den sites of the swift fox, Vulpes velox.

The Southwestern Naturalist 45(2):212:220).

Nebraska Department of Environmental Quality (NDEQ). 2009. Mineral Exploration Permit Number NE0210824. August 19, 2009.

Tannerfeldt, M., A. Moehrenschlager and A. Angerbjorn. 2003. Den ecology of swift, kit, and arctic foxes. A review. In the Swift Fox: Ecology and conservation of swift foxes in a changing world, M. Sovada and L. Carbyn editors. Canadian Plains Research Center, University of Regima.

Page 6: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Nebraska Department of Environmental Quality

Threatened and Endangered Species Survey Report Surveyor’ Name(s)______________________________________________________

Credentials: (e.g., who certified the surveyor and date of certification or surveyor’s knowledge of surveyed species) __________________________________________________________________ __________________________________________________________________

Date of Survey: ______________________ Time of Survey: ______________________ Weather Condition: Temperature: ________oF Wind Speed & Direction: _____________________ Other

Sunny Partly Cloudy Cloudy Snowing Raining _____________ Legal Location or GPS coordinates (Lat/Long or UTM) of survey area (include datum, i.e., NAD83, WGS84:____________________________________________________ County: _______________________ Vegetative Cover (i.e. corn stubble, plowed field, wetland, short grass prairie 10-20 cm tall Methods used to survey affected area (.i.e. Mountain Plover Survey Protocol, 5 transects 50 ft apart) _____________________________________________________________________________ _____________________________________________________________________________ Were any of the following species identified in the area? Mountain Plover Yes/No

River Otter Yes/No Swift Fox Yes/No

If so, what conservation measures were taken? (Attach if necessary) ______________________________________________________________________________ ______________________________________________________________________________ If species is identified, record the location of the species in GPS coordinates. Also indicate locational certainty (i.e. 3 birds were flushed 50 yards NW from this point). Photographs may be sent with survey reports to aid in site description and species identification.

Submit survey reports monthly to: Nebraska Game & Parks Commission Nebraska Dept. of Env. Quality Attn: Env. Analyst Supervisor Attn: Mineral Exploration Program Nebraska Natural Heritage Program P.O. Box 98922 2200 N 33rd Street Lincoln, NE 68509 Lincoln, NE 68503

August 2009

Page 7: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-1 Primary Assumptions Serving as the basis for Surety Cost EstimatesAssociated with Restoration and Reclamation of One (1) Mine Unit

Assumptions QuantityTotal number of production wellsTotal number of injection wellsTotal number of shallow monitor wellsTotal number of perimeter wellsTotal number of restoration wellsWellfield Area (ft2)Wellfield Area (acres)Affected Ore Zone Area (ft2)Average Completed Thickness (ft)PorosityAffected Volume (ft3)Flare FactorK gallons per Pore VolumeNumber of Patterns in Unit(s)Estimated Number of Pore Volumes for RestorationNumber of Wells per WellfieldTotal Number of WellsAverage Well Depth (ft) - Deep WellsAverage Well Depth (ft) - Shallow Depth

Revised 6/11/2013Estimated costs are summarized in Table P. 1-2*Number of wells per wellhouse typically 4 wellhouses per wellfield

120*2000*

41110

588,00013.5

588,00019.60.29

11,524,8001.2

30,000120II

345345

1,100400

Page 8: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-2 Marsland Total Restoration and Reclamation Cost Estimate - 2013 Surely Estimate

Task Cost $

I. Groundwater Restoration (Sheets 3 to 6)

II. Wellfield Reclamation (Sheets 7 to 10)

il. Commercial Plant Reclamation/Decommissioning (Sheets 1 Ito 14)

IV. Miscellaneous Site Reclamation (Sheets 19 to 21)

V. Deep Disposal Well Reclamation (Sheet 22)

Subtotal Reclamation and Restoration Cost Estimate

Contract Administratioi 10%

Contingency 15%

TOTAL RECLAMATION AND RESTORATION COST ESTIMATE

Revised 6/11/2013

$233,160

$628,175

$757,896

$142,493

$67,593

$1,829,317

$182,932

$274,398

$2,286,647

Page 9: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

TFable I).1-3 Marsland Ground Water Restoration -2013 Surety EstimateTask MUl NILJ2 MU3 NIU4 N1U5 NMU6 NM.17 NIU8 MIU9 11UI0 MUll Total

I. IX Treatment Costs

PV's Required

Total Kgals for Treatment

IX Treatment Unit Cost ($/Kgal)

Subtotal IX Treatment Costs per Wellfield

Total IX Treatment Costs

II. Reverse Osmosis Costs

PV's Required

Total Kgals tor Treatment

Reverse Osmosis Unit Cost ($/Kgal)

Subtotal Reverse Osmosis Costs per Wellfield

Total Reverse Osmosis Costs

Ill. Recirculation Costs

PV's Required

Total Kgals for Treatment

Recirculation Unit Cost ($/Kgall

Subtotal Recirculation Costs per Wellfield

Total Recirculation Costs

(Sheet 25)

(Sheet 26)

3

90000

$0.40

$36,000.00

$36,000.00

6

180000

$1.48

$266,400.00

$266,400.00

2

60000

$0.31

$18,600.00

$18,600.00

7.35

$32,235.72

$32,235.72

$32,235.72

3 3 3 3

0 0 0 0

$0.40 $0.40 $0.40 $0 40

$0.00 $0.00 $0.00 $0.00

$0.00

6 6 6 6

0 0 0 0

$1.48 $1.48 $1 48 $1 48

$0.00 $0.00 $0.00 $0.00

$0.00

2 2 2 2

0 0 ) 0

$0.31 $0.31 $0.31 $0.31

$0.00 $0.00 $0.00 $0.00

$0.00

3 3 3

0 0 0

$0 40 $0.40 $0.40

$0.00 $0.00 $0.00

3

0

$0 40

$0.00

3

0

$0.40

$0.00

3

0

$0.40

$0.00 $0.00

6 6 6 6

0 0 0 0

$1.45 $1.48 $1.48 $1 4S

$0.00 $0.00 $0.00 $0.00

6

0

$1.48

$0.00

6

0

$1.48

$0.00

0

$1.48

$0.00

2 2 2

0 0 0

$0.31 $0.31 $0.31

$0.00 $0.00 $0.00

2

0

$0.31

$0.00

2

0

$0.31

$0.00

0

$0.31

$0.00

(Sheet 27)

0

$0.31

$0.00

i,. Consumables

Spare parts, filters and consuinables = $52,629.75 year

Active restoration period (months)

Consumable usage (months restoration x annual rate estimate)

Subtotal Consumables per Mine Unit

Total Consumables Costs

0.00 0.00 0.00 0.00 0.00 0.00 0.00

$000 $0.00 $0.00 $0.00 $000 $0.00 $000

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00

0.00 0 00 0.00

$0024 $0.00 $0.00

$0.00 $0.00 $0.00

000

$0.01)

Page 10: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-3 Marsland Ground Water Restoration -2013 Surety Estimate, ContinuedTask MUI NIU2 NIU3 Nt14 NIl5 NML16 N1L17 NItl8 NII19 NLtIO NItlIl T'otal

V. Monitoring and Samlpling Costs

Guideline 8 analysis =

6 parameter in-house analysis =

Total restoration wells

Total monior wells

IX Treatmtent duration Imontlis)

Reverse Osmosis duration (months)

Recirculation duration Imonths)

Stabilization duration (montls)

$248 00 analysis

$50.85 analysis

10

25

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0

0

2.05

4.11

1.19

12

0.00 0.00 0.00 0.00 0.00 0.00 It 00

0.00 0.00 0.00 0.00 000 0.00 0.00

000 0.00 0.00 0.00 0.00 0.00 0.00

12 12 12 12 12 12 12

0 0o

0 00

0.00

12

0.00

0.00

0.00

12

0.00

0.00

0.00

12

0 00

0 00

0.00

A. Restoration Well Sampling

1. Well Sampling prior to restoration start

# of Wells

S/sample

2. IX Treatmient Sainpling

0 of Wells

Total 0 saimples

$/sample

3. RO Sampling

0 of Wells

Total 0 samples

S/samiple

4. Recirculation Sampling

H of Wells

Total 8 samples

$/saniple

5. Stabilization Sampling (Guideline 8)

0 of Wells

Total 0 samples

S/sample

6 Stabilization Sampling (6 parameter in-house)

0 of Wells

Total 0 samples

$/santple

7. Monitor Well Sampling

0 of' Wells

S/sample

Total fl samples (2.2/mo for entire period)

10

$248.00

10

30

$50.85

10

40

$50 85

to

20

$248.00

10

120

$248.00

10

120

$50.85

25

$50.85

1064

0 0 0 0 0 0 0 0 0 0

$248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00

0 0 0 0 0 0 0

0 0 0 0 0 0 0

$50.85 $50.85 $50.85 $50.85 $50.85 $50.85 $50.85

0 0 0 0 0 0 0

0 0 0 0 0 0 0

$50 85 $5085 $5085 $50.85 $5085 $50.85 $50.85

0

0

$50.85

0

0

$50.85

0 0

0 0

$50.85 $50.85

0 0

0 0

$50.85 $50.85

0 0 0 0 0 0 0 0 U 0

0 0 0 0 0 0 0 0 0 0

$248.00 $24800 $248.00 $248.00 $248.00 $248.00 $248.00 $248 00 $248.00 $248.00

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

$248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00 $248.00

0 0 0 0 0 0 0

0 0 0 0 0 0 0

$50 85 $50.85 $50.85 $50.85 $5085 $50.85 $50.85

0 0 0 0 0 0 0

$50 85 $50.85 $50.85 $50.85 $50.85 $50.85 $50.85

0 0 0 0 0 0 0

0

0

$50.85

0 0

0 0

$5085 $50 85

0 0 0

$50.85 $50 85 $50.85

0 0 0

Page 11: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.l-3 Marsland Ground Water Restoration -2013 Surety Estimate, ContinuedTask NI II NIU2 NIU3 't-14 NILt5 M116 NILJ7 NIMJ8 N.119 MUlI0 MLIII Total

8. Other Laboratory Costs

Radon, urinalysis, etc. =

Total fbr Other Laboratory Costs:

Subtolal Monitoring and Sampling Costs per Mine Unit

Total Monitoring and Sampling Costs

VI. MIT Costs

MIT Costs per Well

Restoration period, plus stabilization

Remaining MIT's per 5 year cycle

Nuttber of Wells MI'nd for Life of Mine Unit

Subtotal MIT Mine Unit

$940.73 month

$6,914.37

$107,880.27

$107,880.27

$93.53

19.35

345

$32,267.85

$000 $0.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00

$0.00

$0.00

$0.00

$0.00

$93.53 $93.53 $93.53 $93.53 $93.53 $93.53 $93.53

12.00 12.00 1200 1200 1200 12.00 12.00

1 I I I 2 2 2

0 0 0 0 0 0 0

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$93.53

12.00

3

0

$0.00

$93.53

12 00

3

0

$0.00

$93.53

12 00

3S0

$0.00

5-year MIT Costs for Disposal Wells

Nutmhber of DDWs

Number of MITs per DDW

Subtotal MIT DDWN' Costs

Total MIT Costs

VI. Sapervisory Labor Cost

Engineer Supplrl =

IIP Technician support =

$6,425

$6,425

$6,425

$8,042 77 month

$4,553.62 ttotntlh

Active restoration period (tronltls)

Stabilization period (ttonths)

7.35

12

I Engineer support during active restoration

2 lIP Terhtnician support during active restoration

3 Engineer support during final stabilization

4 HP Technician support during final stabilization

5 Cost reduction due to concurrent restoration of Mine Units

Subtotal Supersisory Labor per Mine Unit

Total Supervisory Labor Costs

$59,114.36

$33,469.11

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 000

12 12 12 12 12 12 12 12 12 12

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $000 $000

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$96,513.24 $96,513 24 $)06,513.24 $289,539.72

$54,643 44 $54.643.44 $54.643.44 $163.930 32

000 0 00 0.00 0.00 0 00 -75,578 34 -75,578.34 -75,578.34 -$226,735.02

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $75,578.34 $75,578.34 $75,578.34 $226,735.02

735.02

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $75,578.34 $75,578.34 $75,578.34 $226,735.02

$92,583.47

$243,740.15 $226,

TOTAL RESTORATION COST PER $ELLFIELD$553,699.46

TlOTAL GROUND WATER RESTORATION COSTS $233,160.02Kl=NtIJ thtnvOu

Rt,j,v t,I 61112013

Page 12: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-4 Ndarsland Welifield Reclaniation - 20113 Surety Estimate]%111 MtU2 RiIJ3 NAU4 MIJS $1146 $1147 $114 MU9 511410 Mull Totals

Welllield Piping

Assumptions:Number of WellhousesTotal Mine Unit surface area (acres)Tota) lenglh of'sinall diameter productron and itjection lines (later,Total length of 3/8-inch hose (ft)Total length I-l/4-mnch stinger pipe (I)Total length of 2-inch downhole production pipe (1i1Total Length of Trunkline (6-inch) (fi)Total Length of TrUnkline (8-inch) (ftiTotal Length ofTrunkline (10-inch) (i61Total Length ofTrunkline (I 2-inch) (fi)Total Length ofAII Trunklint (ft)Tota) number of production wellsTotal numher of injection ws'ellsTotal number of shallow rtonitor wellsTotal number of perimeter ttonitor wells

1. Production and Injection PipingA. Removal and Loading

Production and Injection Piping Removal Unit Cost(Sift of pipe)

Subtotal Production and Itjeclion Piping Removal andB. Ptpe Shredding

Production and Injection Piping Shredding Unit Cost(Sift of pipe)

Subtotal Production and Injection Piping Removal and Loading C,C. Equipment Costs

Cat 924G Loader Unit Costs for removal (450/day)Shredder Unit Costs for shredding (450-/day)

Subtotal Equipment CostiD. Transport and Disposal Costs (NRC-Licensed Facility)

Chipped Volume Reduction (ftt/lilCltpped Volume per Welfield (yd')Volume for Disposal Assuming 25% Void Space (yd')

Transportation and Disposal Unit Cost ($/yd')Unpackaged Bulk

Subtotal Production and Injection Piping Transport andDisposal Costs

Total Production and Injection Piping Cosis

413.50

0

0

4800

4000

17600

21600

120

200

14

I1

0000

0

0

0

0

0

0

0000

0

0.00

0

0

0

0

0

0

0

0

0

0

0

0

00.00

0

0

0

0

0

0

000000

00.00

0

0

0

0

0

0

0

00

0

0

0

00.00

0

00

0

0

00

000

0

0

0oo

0

0

0

0

0

0

u

0o

0

0

0

0

0 0o

0

0

0

0

0

0

0

0

0

00

0

0.00

0

0

0

0

0

0

0

0

0

0

0

0

0 00

0

0

0

0

0

0

0

0

00

0

0

0

0 00

0

0

0

0

0

0

0

0

0

0

0

4

13.50

0

0

0

4800

4000

17600

0

0

21600

120

200

14

1i

$0.88 $0 88 $0.88 $0 88 $0.88 $5 88 $088 $0.88 $0 88 $0.88 S0.88

$0.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $0.00 $000 $0.00 S$.00

$0.10 $0.10 s0 10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 $0.10 S0.10

$0.00 $0.00 $0.00 $000 $0.00 $0.00 $0.00 $000 S000 $0.00 $0.00

$0.00 $0.00 SOrb $000 $0.00 $0.00 SO.t) $0.00 SO.O0 $0.00 $00r

$0.00 $0.00 $000 $000 80.00 $0.00 $0.00 $000 $0.00 $O0 $0.00

S0.00 $0.00 $0.00 $000 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $000

0.0069 0.0009 0 0069 0 0069 0 0069 0.0069 0.0069 0.0009 0.000 0.0069 0.0009

00 0.0 0.0 0.0 00 0.0 00 00 0.0 00 00

0.0 0.0 00 00 00 0.0 0.0 0.0 0.0 00 0.0

$221.64 $221.64 $221.64 $221.64 $221.04 $221.64 $221.64 $221.64 $221.o4 $22 I.04 $221.64

$0.00 $0.00 $0.00 $0.00 $o.00 S0.00 so.00 s0 00 $0.00 S0.00 $0.00

$8.88 $8.88 58.00 $o.o8 so.88 $8.00 $o.88 $8.80 So.oo $8.88 $8.80

$0.00

$0.00

$000

00

$0.00

$0.00

Page 13: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-4 Marsland Wellfield Reclamationi - 2013 Surety Estimate, Continued

MNIUI M12 IlMU3 5MU4 MU U5 NIlU6 N1U7 1US MlU9 MUl10 MU I I Totals

II. TruIldmines

A. Reriroval and Loading

Trunkline Removal Unit Cost ($/ft of pipe)

Subtotal Tirukline Removal and Loading Costs

B. Pipe Shredding

frunkline Shredding Unit Cost (S/ft of pipe)

Subtotal Trunldine Shredding Costs

C. Equipment Costs

Cat 9124G Loader Unit Costs for removal (200/day)

Shredder Unit Costs for shredding (200/day)

Sublutal Equipmentl Costs

D. Transport and Disposal Costs INRC-Licensed Facility)

Chipped Volume Reduction (6-inch) (it'/0)

Chipped Volume Redaction IS-inch)l If'/ft)

Chipped Volume Reduction (I O-inch) (f•l/fi)

Chipped Volume Redaction (12-inch) ((t'/f1

Chipped Volume per Wellfield (ydi)

Volume lbr Disposal Assuating 25% Void Space (fit)

Transportation and Disposal Unit Cost ($/Sft

)

Subtotal Transport and Disposal Costs

Total Trunkline Costs

Ill. Dowlhole Pipe

A. Reriosal and Loading

Doscnhlole Piping Removal Unit Cost $/hf oflrpe)

Dos..nhole Ilosing Reiroval Unit Cost iS/l otfpipel

Removal of t-I/4-inch stinger pipe

Removal of downhole production pipe

Renmosal ofdowvnlhole hose

Subtotal Downhole Piping Removal and Loading Costs

B Pipe Shredding

Dowirlole Piping Shredding Unit Cost (SIft of pipe)

Subtotal Downhole Piping Shredding Costs

C. Equipment Costs

Siteal Unit Costs for removal

Shredder Unit Costs for shredding

Subtotal Equipnment Costs

D. Transport and Disposal Costs (NRC-Licensed Facility)

Chipped Volume Rediction - I - I/4-inch stinger (11'/fl)

Chipped Volume Rediction - 2-inch dosnlhole

production lfl)

Volunie Reduction - 3/8-inch hose (03/0)

Chipped Volume - I-I//4-inch stinger (ft')

Chipped Volume - 2-inch do-,liole production (ft)

Voluime 3/8-inch hose (113)

Voluire for Disposal Assuming 25% Void Space (yd')

Fransportalion and Disposal Unit Cost (S/yd I)

(Unipackaged Bilk)

Subtotal Downhole Piping Transport and Dtispsosal CostsTotal Dowsnhole Piping Costs

$1.99 $1.99 $1.99 $1.99 $1.99 $1.99 $1.99 $1.99 $1.99 $1 99 $1.99

S42.984.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $0.00 $0.00 $42.084.0t)

$1 9) $1.99 $1.99 $1.99 SI.99 $1 99 $1 99 $1 99 $1.99 $1.99 $1.99

$42.084.00 $0.00 $000 $0 00 $0.00 $0.00 $0 00 $000 $0.00 $000 $0 0o $42,9804.00

$157.757.76 $0.00 $000 $000 SO.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00

$6,920.64 $0.00 $0.00 $0.00 S0.00 $0 00 $0.00 $0.00 $0.00 $0.00 SO.00

$164,673.40 $0.00 $0.00 $0.00 $0.00 $000 $000 S.00 $0.00 $0.00 $0.00 $1o4.678.40

0.0651 0.0651 0.0651 0.0601 0.065) 00605 0.0651 0.0651 00651 0 0651 0.0651

0.1103 0.1103 0 1103 0.1103 0.1103 0.1103 0.1103 0.1103 0.1103 0 1103 0.1103

0.1712 0.1712 0 1712 0 1712 0.1712 0.1712 0.1712 0.1712 0.1712 0.1712 0 1712

0.2408 0.2408 02408 02408 0.2408 0.240S 0.2408 0.240t 0.240S 02408 0.2408

81.5 0.0 0.0 0 0 0.0 00 00 0.0 0.0 0.0 0.0

101.9 0.0 0.0 0.0 0.0 00 00 00 00 0.0 0.0 101.9

$221.64 $221.64 $221.64 $221.64 S221.64 $221 64 $221 64 $221 64 $221.64 $221.64 $221.04

$22.585.12 $0.00 $000 $0.00 $0.00 $000 $000 $000 $0.00 $0 00 $0.00 $22,585.12

$273,231.52 $0.01) $0.00 $000 $0.00 $0.00 S0.00 $0.00 $0.00 $0.00 $8.00 $273,231.52

$0.100 $0.100 $0.10o $0S 100 $0.100 $0.100 $0.100 S0.100 $0.100 $0.100

$0.200 $0200 $0.200 $0200 $0.200 $0.200 $0.200 $0.200 $0.200 $0.200 $0.200

$0.00 $0.00 $0.00 $0.00 $0.00 $0 00 $0.00 $0.00 $0.00 $0.00 $0.00

$480100 $0.00 $0.00 $000 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$000 $0.00 $000 $13.00 $0.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00

$480 00 $0.00 $000 $0.00 $0.00 $0.00 $0.00 $0100 $0.00 $0.00 $000 S480.00

$0 090 SO 090 $0090 $0 090 $0090 00.090 $0.090 $0.090 $0.090 $0.090 $0.090

$432.00 $0.00 $0.00 $0.00 $0.00 $0.00 $1 00 $0.00 $0.00 $0.00 $0.00 $432.00

$336.51 $0.00 $000 S000 $0.00 $000 $0.00 $0.00 $0.00 $0100 $0.00

$68.35 $5.00 $1000 $000 $500 $0000 $000 $000 $0.00 $000 $0100

$404.86 $0.00 $0.00 s0.00 $0.00 $0.00 $0 00 $0100 $0.00 $0.00 $000 $404.8o

0.0044 0.0044 0.0044 0.0044 0.0044 0 0044 0.0044 0.0044 0.0044 0.0044 0.0044

0.0074 0.0074 0.0074 0 0074 0.0074 0 0074 0.0074 0.0074 0.0074 0 0074 0 0074

0.0313 00313 00313 0.0313 0.0313 0.0313 0.0313 0.0313 0.0313 00313 00313

0 0 0 0 0 0 0 0 0 0 0

36 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0

1 7 0.0 0.0 00 00 0.0 0.0 0.0 0.0 00 0.0 1.7

$221.64 $221.64 $221 64 $221.04 $221.64 $221 64 $221.64 $221.64 $221 b4 $221.64 $221.64

$376.79 00.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 S376.70

$1,693.65 $0.00 $0.00 $0.00 $0.00 80.00 $0.00 $0.00 00.00 $0.00 $0.00 $1,693.65

Page 14: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-4 Niarslaiid Wellfield Reclamation - 2013 Surety Estimate, ContinuedMUI 51U2 511%3 %114 511U5 MIU6 N11J7 51118 N1U9 UI10 M11llI Totals

IV. Surface ReclamationA. Remooval and disposal of contaminated soil around wells

Volumne of contaiiiinated soil (0.37 yd3 per injectionand production wvell) 118.4 0 0 0 0 0 0 (100 0 0.00 0 11S.40Disposal of contaminated soil $250.05 per yd3 $29.605 92 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $0.00 $0.00 $29,605.92Equipmnent (Cat 924G loader at 2 yd3hr) $10,809.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00Labor (I man-hour per 2 Yd3) $1.473.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal removal aid disposal of conlarninaled soil $41,888.52 $000 $0.00 $0S00 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $0.00 $41,888.52

B. Recontour and seedingRecontour and seeding (est. $300/acre) $4.050.00 $0.00 $0.00 $0.00 $000 $000 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal Recontour and Seeding $4,050.00 $0.00 $0.00 $1.00 $0.00 $0.00 $0.00 $000 $000 $0.00 $0.00 $4,050.00

Total Surface Reclamation $45,938.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $45,938.52

IV. Well HlousesTotal Quantity 4 0 0 0 0 0 0 0 0 0 0

Average Well House Weight (Lbs.) (Includes wellheadcovets for each well) 9200 9200 9200 9200 9200 9200 9200 9200 9200 9200 9200A. Rerosat

Disinantlenienr at 2--man-days per wellhouse (nian-days) 8 0 0 0 0 0 0 0 0 0 0Dismanotlerent Labor Costs $1.502 72 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $0.00 $1,502.72Equipment (Cat 924G at 2 hours per wellhouse) (his) 8 0 0 0 0 0 0 0 0 0 0Equipsent Costs $1.460.72 $0.00 $0.00 $000 $000 $000 $000 $000 $0.00 $0 00 $000 1,400672

Subtotal %ell Ilouse Disutantentent Costs $3,053.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $000 $0.00 $0.00 $0.00 $3,053.44B. Disposal

Total Disposal Weight (9200 lbs per wellhoUse) (Lbs) 36800 0 0 0 0 0 0 0 0 0 0Subtotal Disposal Costs $1,104.00 $0.00 $0.00 $000 $000 $6".00 $000 $0.00 $0.00 $000 $11.00 $1,104 00

Total WVell Ilouse Remosal and Disposal Costs $4,157.44 $0.00 $0.00 $0.00 $0.00 $0.00 80.00 S0.00 $0.00 $0.00 $0.00 $4,157.44

TOlAL REMOVAL AND DISPOSAL COSIS PERWELLIFIELD $325,021.13 $0.00 $0.00 80.00 $0.00 00.00 80.00 S0.00 $0.01) $0.00 $0.00 $325,021.13

TOTAL WVELLFIELD BUILDINGS AND EQUIPMENT$REMOVAL AND DISPOSAL COSTS $325,021.13

Nil . N1w ý lhýI

0k, -d 6cI 1121ý 13

Page 15: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-5 NIarsland Well Abandonment - 2013 Surety Estimale

MU I MU2 NJ [13 MU4 MLIt MNIU M17 ARMU MU9 MUlI MUll Twtt

I WcI Abandonment (Wellfields)0 of PtodUCtion Wells0 of lojection Wells

1 of Perimreter Monitoring WellsSof Shallow Monitoring Wells

Total Numober of Deep WellsTotal Number of Shallow WellsAverage Diameter of Casing (inches)Production, Injection and Perimeter Well Average Depth (11)Shallow Well Average Depth (fi)Total Mine Unit Well Depth 4ii)Well Abandonnment Unil Cost (/f1. of well)

Sultotal Abandonmenl Cost per Wellfield

120 0 0 0 0 0) 0 0 0 0 0200 0 0 0 0 0 0 0 0 0 0

I1 0 0 0 0 0 0 0 0 0 0

14 0 0 0 0 0 0 0 0 0 0331 0 0 0 0 0 0 0 0 0 0 331

14 0 0 0 0 0 0 0 0 0 0 14

5 5 5 5 5 5 5 5 5 5 51100 1100 1100 1100 1100 1100 1100 1100 1100 0 0 900400 400 400 400 400 400 400 400 400 0 0 327

3u9700 0 0 0 0 0 0 0 0 0 0 309700

$0.82 $0.82 $0.82 $0.82 $0.82 $0.82 $0.82 $0.82 $0.82 $0.82 $0.82

5303,154.00 $0.00 S0.00 $0.00 0 $10.00 $0.80 80.08 $0.010 0.00 SO.00 $3036,154.00

0.0221 64

50.00 $0.00

tntll I5.I 1110

II. Downhole Punip Disposal

Numnber of Downolte Punips

Puop Disposal Volumnelli3)Total Puatp Disposal Volutmelyd3)

Dovtnhole Pump Disposal Rate ($/yd3

)

Subtotal Downhale Puitp Disposal

00.50.0

$221 64

'r : 1 W l1rld Ab d t C !. S303 15400NIL] - M'-Uni'V.-d ,!I V2M.'

Page 16: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-6 Marsland Satellite Facility Equipment Decommissioning -

2013 Surety Estimate

1. Removal and Loading CostsTankage

Number of Contaminated Tanks 10Volume of Contaminated Tank Construction Material (ft3) 193Number of Chemical Tanks 0Disposal Void Factor 1.25

A. Labor to Remove and Load TankageNumber of Persons 2Tanks/Day 1Number of Days 10S/Day/Person $199.09

Subtotal Removal Labor Costs $3.981.80B. Labor to Clean Chemical Tankage

Number of Persons ITanks/Day INumber of Days 0S/Day/Person $199.09

Subtotal Cleaning Labor Costs $0.00C. Equipment

Saws, scaffolding, etc. $6,000Subtotal Equipment Costs $6,000

Total Equipment Removal and Loading Costs S9,981.80

II. Transportation and Disposal Costs (NRC-Licensed Facility)A. Tankage

Volume of Tank Construction Material (fit) 193Volume for Disposal Assuming Void Space (yd-') 8.9Transportation and Disposal Unit Cost ($/yd-') (Unpackaged Bulk) $221.64

Subtotal Tankage Transportation and Disposal Costs $1,972.60B. Contaminated PVC Pipe

Volume of Shredded PVC Pipe (fi') 153.6Volume for Disposal Assuming Void Space (yd3) 7.1Transportation and Disposal Unit Cost ($/yd-) (Unpackaged Bulk) $221.64

Subtotal Contaminated PVC Pipe Transportation and Disposal Costs $1,573.64C. Pumps

Volume of Process Pumps (yd3 ) (no void factor used) 2.4Transportation and Disposal Unit Cost ($/yd3) (Unpackaged Bulk) $221.64

Subtotal Pump Transportation and Disposal Costs $531.94D. Filters (injection, backwash and yellowcake filters)

Volume of Filters (yd 3 ) (no void factor used) 0.0Transportation and Disposal Unit Cost ($/yd•) (Unpackaged Bulk) $221.64

Subtotal Filter Transportation and Disposal Costs $0.00E. Dryer

Dryer Volume (yd') (no void factor used) 0.0Transportation and Disposal Unit Cost ($/yd3) (Unpackaged Bulk) $221.64

Subtotal Dryer Transportation and Disposal Costs $0.00Total Contaminated Equipment Transportation and Disposal Costs S4,078.18

Page 17: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-6 Marsland Satellite Facility Equipment Decommissioning -2013 Surety Estimate, Continued

Ill. Transportation and Disposal (Solid Waste for Landfill Disposal)A. Cleaned Tankage

Volume of Tank Construction Material (ft ) 0Number of Landfill Trips ITransportation and Disposal Unit Cost (S/Load) $912.00

Subtotal Tankage Transportation and Disposal Costs S912.00B. Uncontaminated PVC Pipe

Volume of Shredded PVC Pipe (ft') 0Number of Landfill Trips ITransportation and Disposal Unit Cost (S/Load) $912.00

Subtotal PVC Pipe Transportation and Disposal Costs $912.00Total Uncontaminated Equipment Transportation and Disposal Costs $1,824.00

IV. Supervisory Labor Costs During Plant DecommissioningEstimated Duration (months) 6Engineer $48,256.62Radiation Technician $27,321.72

Total Supervisory Labor Costs S75,578.34

SUBTOTAL EQUIPMENT REMOVAL AND DISPOSAL COSTS PER FACILITY $91,462.32Building Area (Ft2) 34,000Building Equipment Removal and Disposal Cost per Square Foot $2.69

TOTAL EQUIPMENT REMOVAL AND DISPOSAL COSTS S91,462.32Revised 6il 1/2013

Page 18: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-7 Marsland Building Demolition - 2013 Surety EstimateSatellite Plant

1. Decontamination CostsA. Wall Decontamination

Area to be Decontaminated (ft2) 30,000HC1 Application Rate (Gallons/ft2) I

HCI Acid Cost $1.54Subtotal Wall Decontamination Materials Costs $46,200.00

B. Concrete Floor DecontaminationArea to be Decontaminated (ft) 9000HCI Application Rate (Gallons/ft&) 2HCI Acid Cost $1.54

Subtotal Floor Decontamination Materials Costs $27,720.00C. Decontamination Labor

Labor (man-days)Subtotal Decontamination Labor Cost $398.18

D. Decontamination Equipment CostsSprayer pump $500Recycle pump $500Sprayer with hose $1,000

Subtotal Decontamination Equipment Costs $2,000E. Decontamination Waste Disposal (to Ponds)

Total gallons HCI waste 48,000Pumping costs (5 HP/30 gpm) $496.33

Subtotal Decontamination Costs $76,814.51Total Decontamination Costs $76,814.51

11. Demolition CostsAssumptions (based on 2007 costs):

Dismantling interior steel, tanks, pumps, etc. $198,800.00Dismantling plant building $99,400.00

A. Building DismantlingDismantle interior components (2007 $'s escalated by CPI) $202.179.60Plant building dismantling (2007 $'s escalated by CPI) $101,089.80

Subtotal Building Dismantling $303,269.40B. Concrete Floor Removal

Area of direct-dispose concrete floors (ft2) 13,400Removal Rate ($/ft2) $14.04

Subtotal Concrete Floor Removal $188,136.00Total Demolition Costs $491,405.40

Page 19: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-7 Marsland Building Demolition - 2013 Surety Estimate, Continued

Il1. Disposal CostsA. Concrete Floor

Area of Direct-Dispose Concrete Floor (f12) 13,400Average Thickness of Concrete Floor (ft) 0.75Volume of Concrete Floor (ft3) 10,050Volume of Concrete Floor (Yd3) 372Transportation and Disposal Unit Cost ($/Yd 3) (Unpackaged Bulk) $221.64

Subtotal Concrete Floor Disposal Costs S82,450.08Total Disposal Costs $82,450.08

IV Plant Site ReclamationA. Plant Site Earthwork

Material to be Moved (Yd3) 20.000D8N Bulldozer Earthwork Rate (Yd3/hr) 700D8N Hourly Rate $509.74

Subtotal Plant Site Earthwork $14,564.00

B. RevegetationArea requiring Revegetation (Ac) 4Revegetation Unit Cost ($/Ac) $300

Subtotal Plant Site Revegetation $1,200.00Total Plant Site Reclamation Costs $15,764.00

SUBTOTAL BUILDING DEMOLITION AND DISPOSAL COSTS $666,433.99Building Area (Ft2) 34,138Building Demolition Cost per Square Foot $19.52

TOTAL BUILDING DEMOLITION AND DISPOSAL COSTS $666,433.99

Revised 6/11/2013

Page 20: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-8 Marsland Miscellaneous Site Reclamation - 2013 Surety Estimate

Access Road ReclamationAssumptions

Road Reclamation production rate (Yd3/hr) 200Length of Main Access Roads (ft) 500Average Main Access Road width (ft) 25Depth of Main Access Road Gravel Surface (ft) ISurface Area of Main Access Road (Ac) 0.3Length of Wellfield Access Roads (ft) 500Average Wellfield Access Road width (ft) 12Depth of Wellfield Access Road Gravel Surface (ft) 0.5Surface Area of Wellfield Road (Ac) 0.1

A. Main Access Road DirtworkMain Access Road Gravel Volume (Yd3) 463Total reclamation time (hrs) 2D8N Unit Operating Cost ($/hr) $509.74

Subtotal Main Access Road Gravel Roadbase Removal Costs $1,019.48

B. Wellfield Road DirtworkWellfield Road Gravel Volume (Yd3) )l1Total reclamation time (hrs) 1D8N Unit Operating Cost ($/hir) $509.74

Subtotal Wellfield Road Gravel Roadbase Removal Costs $509.74E. Discing/Seeding

AssumptionsSurface Area (acres) 0.4Discing/Seeding Unit Cost (S/acre) $300.00

Subtotal Discing/Seeding Costs $120.00Total Access Road Reclamation Costs $1,649.22

11. Wastewater Pipeline ReclamationAssumptions

Pipeline Removal Rate (ft./man-day) 67Pipeline Shredding Rate (ft./man-day) 1,500Number of Pond Pipelines 2Length of Pond Pipelines (ft) 2,000Average Pipe Size (Sch 40) 4

A. Pipeline Removal CostsLength of Pipelines (ft) 4,000Removal Rate (ft/man-day) 67Removal Labor Rate (S/man-day) $199.09Cat 924G Loader Use (days) 60Cat 924G Loader Cost $87,643.20

Subtotal Pipeline Removal Costs $99,588.60B. Pipeline Shredding Costs

Length of Pipelines (ft) 4,000Shredding Rate (ft/man-day) 1,500Shredding Labor Rate (S/man-day) $199.09Shredder Use (days) 3Shredder Cost $192.24

Subtotal Pipeline Shredding Costs $789.51

Page 21: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-8 Marsland Miscellaneous Site Reclamation - 2013 Surety Estimate, Continued

C. Pipeline Transportation and Disposal (NRC-Licensed Facility)Pipe Diameter (inches) 4Chipped Volume Reduction (ft'/ft) 0.0103Subtotal Volume of Shredded PVC Pipe (yd') 1.5Disposal Void Factor 1.25Final Disposal Volume (yd3) 1.88Transportation and Disposal Unit Cost ($/yd&) (Unpackaged Bulk) $221.64

3uuotuai ripenne oisposau Losts $416.68Total Wastewater Pipeline Reclamation Costs $100,794.79

11. Electrical Distribution System RemovalAssumptions

Length of High Voltage Lines 500High Voltage Line Removal Rate ($/ft.) $2.17High Voltage Line Removal Cost (S/ft.) $1,085.003uosLaLion memovai S1.175.00

Subtotal Electrical Distribution System Removal Costs $2,260.00

IV. Supervisory Labor Costs During Miscellaneous ReclamationEstimated Duration (months) 3Engineer Rate ($/month) $8,042.77Total Engineer Labor $24,128.31Radiation Technician Rate ($/month) $4,553.62Total Radiation Technician Labor $13,660.86

Total Supervisory Labor Costs $37,789.17

TOTAL MISCELLANEOUS RECLAMATION COSTS $142,493.18Sch = Schedule

Revised 6/11/2013

Page 22: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-9 Marsland Deep Disposal Well Reclamation - 2013 Surety Estimate

I. Cost Basis

A. Plugging and Abandonment

Cost Estimate from April 2009 2nd Well Permit Application for plugging and abandonment $60,292

April 2009 CPI 213.2

June 2011 CPI 229.5

Subtotal Escalated April 2009 Plugging and Abandonment Costs $64,901.57

B. Site Reclamation

Cost Estimate from April 2009 2nd Well Permit Application for site reclamation $2,500

April 2009 CPI 213.2

June 2011 CPI 229.5

Subtotal Escalated April 2009 Reclamation Costs $2,691.14

Subtotal Abandonment cost per well $67,592.71

TOTAL DEEP DISPOSAL WELL RECLAMATION COSTS $67,592.71CPI: Consumer Price Index

Revised 6/11/2013

Page 23: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-10 Marsland Groundwater IX Treatment (GIX) Restoration (Unit Costs) - 2013 Surety Estimate

Assumptions:I. All pumps are 5 hp pumping at 32 gpmn

2. Cost of electricity =3. Horsepower to kilowatt conversion =4. Operator labor costs =5. Labor costs are based on 36 pumps at 1,150 gpm

Wellfield Pumping Electrical Costs per 1000 Gallons (Includes bleed to the Deepwvell / Evaporation Pond)1000 gal X 5 hp X I hr X 0.746 kwh X $ 0.0830

32 gpm 60 rain hp kwh

$0.0830 Kw hr0.746 Kw/HP

$199.09 man-day

Wellfield Pumping Labor Costs per 1000 Gallons1000 gal X I ain X man-day X

1150 gal 1440 mmin

=$ 0.161

=$ $0.240$199.09

man-day2 operatorsx

Groundwater IX Production Rate1000 gal X 60 rain X

nin hr24 hr

dayX 365 day x

year112

yearmonth

43,800,000 gallonsmonth

TOTAL GWS COSTS PER 1000 GALLONS = $ 0.40

Revised 6/11/20 13

Page 24: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-1l Marsland Groundwater Reverse Osmosis (RO) Treatment (Unit Costs) - 2013 Surety Estimate

Assumptions:I. All purnps are 5 lip pumping at 32 gpm2 Membrane Replacement3 Cost of electricity =4 Horsepower to kilowatt conversion =

5 Operator labor costs =6 RO System horsepower requirements for 600 gpm rated llowv based upon:

RO Unit PumpPermeate/Injection pumpWaste purnp (lI(Bleed - Deepwell / Evap Ponds)TOTAL:

7 Chemical costs:ReduIctant =

Antiscalant

$0.015 per 1000 gal$0.0830 Kw hr

0.746 Kw/IHP$199.09 man-day

195 lip60 hp12 hp

267 lip

$0.240 lb$15.45 gal

Membrane Replacement Costs per 1000 Gallons1000 gal X $660 membrane

cost / mont1Ih

Wellfield IPumping Electrical Costs per 1000 Gallons1000 gal X 5 lhp

32 gpin

Reverse Osmosis Electrical Costs per 1000 Gallons1000 gal X 267 lip

600 gpni

Reverse Osmosis Labor Costs per 1000 Gallons1000 gal I rnin

X 600 gal

/ 43,800,000 gallonslmonth1

I hr60 riin

I hr60 rain

0.746 kwh $ 0.0830x hp kwh

0.746 kwh $ 0.08301hlp kwh

=$ 0.015

=$ 0.161

= $ 0.459

per Kgal

per Kgal

per Kgal

per Kgal

per Kgal

per Kgal

I man-day $199.091440 rnin man-day

"2 operators = $ $0.461

Treatment chemical costs per 1000 GallonsAntiscalant:

1000 gal X 0.000008330 gal antiscalant, ga x $15.45I gal

Reductant:1000 gal X 0.001040 lbs reductant

I gal

gal antiscalant

x $0240lb reductant

=$ $0.129

$ $0250

Reverse Osmosis production Rate1000 gal X

ittn60 rain

hr x24 hr X 365 day

day yearx I year

12 month43.800,000 gallons

111o01th

TOTAL RO COSTS PER 1000 GALLONS = 1.48RO = Re\'rse Usmosis

Revised 6/111/201

Page 25: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-12 Marsland Groundwater Recirculation (Unit Costs) - 2013 Surety Estimate

Assumptions:1. All pumps are 5 lip pumping at 32 gpm2. Cost of electricity =3. Horsepower to kilowalt conversion4. Operator labor costs =5. System horsepower requirements for 1, 150 gpmn rated flow based upon:

injection pump

$0.0830 Kw hr0.746 Kw/HIP

$199.09 man-day

30 lip

Wellfield Pumping Electrical Costs per 1000 Gallons1000 gal X lip

32 gpni

Wellfield Injection Electrical Costs per 1000 Gallons1000 gal X 30 lip

1150 gpm

Recirculation Labor Costs per 1000 Gallons1000 gal X I mII

1150 gal

1 hr60 min

1 hr60 m1i

I man-dayX 1440 maiM

24 hrday

0.746 kwvh $ 0.0830lhp kwh

0.746 kwvhi $ 0.0830lip kwh

= 0.161 per Kgal

= 0.027 per Kgal

= $ 0.120 per Kgal$199.09man-day

I operators

Recirculation Production Rate1150 gal X

min60 ain

hr365 day X

yearI year12 month

50.370,000 gallonsmonth

TOTAL RECIRCULATION COSTS PER 1000 GALLONS = S 0.31Revised 6/11/2013

Page 26: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-13 Marsland Well Abandonment (Unit Costs) - 2013 Surety Estimate

Assumptions:I Use backhoe for 0.25 hr/well to dig, cut off, and cap well.2 Drill rig used 2.5 hrs to plug well.3 Labor for installing chips, etc. will require 2 workers at 0.5 hrs per well

Well Abandonment Costs Cost per ft (based on 700 ft wells)

Labor Costs I hours X $ 24.89 per hour =$ 24.89 $0.0356

Cat 416 Backhoe0.25 hours X $ 122.98 per hour =$ 30.75 $0.0439

Drill rig2.5 hours

Well Cap I each

Materials per foot of well (Variable Cost)Cement 0.0714 lbs/ftBentonite Chips 0.007 tubes/ft

Plug Gel 0.0086 sacks/ft

Total Estimated Cost per Foot:Revised 6/11/2013

163.34

12.20

per hour

each

per poundper tube

per sack

=$ 408.35

=$ 12.20

0.1408.50

8.50

$0.5834

$0.0174

$0.0100$0.0595

$0.073 1

$0.82

Page 27: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-14 Marsland Five Year Mechanical Integrity Tests (MIT)

Assumptions:

1 Pulling Unit for 8 hr/day

2 MIT Unit for 8 hr/day

3 Labor for operation of pulling unit requires 2 workers ( one operator & one laborer)

4 Labor for operation of MJIT Unit requires I worker

MIT Costs per Well

Equipment and Labor:

Pulling Unit includes one operator

8 hours X $ 22.63 per hour -$ 181.04

Laborer

8 hours X $ 24.89 per hour =$ 199.12

MITT Unit includes one operator

8 hours X $ 22.63 per hour =$ 181.00

TOTAL MIT COST PER DAY =S 561.16

Wells Completed 6 per day

MIT COSTS PER WELL =S 93.53

MIT COSTS PER DEEP DISPOSAL WELL (2013 Cost) =$ 6425Revised 6/11/2013

Page 28: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-15 NIarsland Master Cost Basis - 2013 Surety EstimateNuLlI NII2 NIU3 N1U4 1%115 MU6 N1L17 MU18 5IU9 NUIO NI I1-)

Total number oflproduction wolls

Total numbrer of injection wells

Total number of shallow monitor we lls

Total number of perimeter monitor wells

Totl numtlber of restoration , ells

Welfitld Area 1012)Wellield Area (acres)

Allfcted Ore Zone Area M12)Avg. Completed 11ickness

Porosity

Afflicted Volume (113)Flare Factor

Kgallons per Pore Volume

Number of Patterns il Unitrst

Number of Wells i Unit(s)

Production Wells

hrjcetino Wells

Shallo- Mslonitot Wells

Perinteter Monritor Wells

Nttbr of Wells per WeltfieldTotal Number of Wells

Average Well Dpthl (Rl - Deep Wells

Asgerse Well Dptlh (1il - Shallo-s Wells

120l2100

14

IIllt

5.11)15,42.000

13.I05SH,m)(1)

19.6

02911.524.8101)

1.2

1201211

0110)

D)

II

0

1)

I)11.(11)1

19.6

0.29

1.2

UI

01.001

(I

19.6,019.'

0I

1.21)

0I

0I0I

(I

0I0I

0t0I

4)

01.001

0I

19.610.29

0I

1.2It

0IIt

II

II

II

1)0I0I

I00

0I0I

I)

0(I0I

0II-I

II

1)111111

1)

11.60.29

I.)1.2

11

0I01101

0

191.601.29

1)

1.21)

NoII*.

01291)

1.2

1)

1;01.001

(I

19.

10.290I

1.2

0

150

11.2

I.2

II

0.29

120l

(0010

1)(1.1l)1

11.29

1.2

CurrentEstimated next report

Total Estimated

Current

Estimated next report

Total Estimated

Current

Estimated next report

Total Estijated

Current

Eslimated next reportTotal Estimated

Currenst

Estitnated text reportTotal Estimated

01211

1201

20112{111

1)I)IF

O

I)

1)

1)00

00(I

0

0

0

0

(I

0

(I

0I

0

0

0

0

00

0I1414

II

I)

0

0

0

0

0

000

II

0)0

0

It

II0

0

1)

0

DI

0I

0I

0pI

(I

{I

It

(I

00I

0II0It

345

349

I)l)I)

II

1100 11 [(lo 1100 I l1l 11 011 110 I1 U 11 011 111M) I 100 t

41)0 40U 4010 4111) 400 4001 4111 40110 4010 0

Page 29: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-I5 Marsiand NIaster Cost Basis - 2013 Surety Estimate (continted)

Electrical Costs CPI Escalators (CPI-tl. UtS. City Average)

Pin-r cost adji fitr current actual cost)

Kileoatt tw Ilursepasvet

I lorscpolser per gallon per titilate

2012 Rate 201 3 cr Rate

$0.11797 $0.0t30t

0.746 0.746

It 167 0.167

wiltr

I-IP/gpnr

19189 CPI (average) 118.3June 2012 CPI (deep well estitate) 213.2

2011 CPt (June 2011 used in last 225.7

Current CPI (June 20111 229.5

21)12 Escalation Factor 1 117Labor |tales

2,,12 Rate 21013 cEst Rate (CPI

Operator Labor Cost $193.76 $1991109 dca

Pulling Unit Operator $179.00 S1 181.03 day

Engineer Cost $7.,98.33 $8.0142.77 uondl

Radiation Technician Costs $4,477 50 $4,553.62 nthttl

Chermical Costs

2(t 12 Rate 201(3 Est Rote

Aoliscalant for RO tadi for currelt actual cost) $15.45 $15.45 gal

Reductant (adj for current actual cost) $11.24 $0.24 lb

Cement (adi for currcnt actual cost) $1.14 S10.14 pound

Benronite loubes (ad) for current actual cost) $6.35 S) 510 tube

Salt adj for current actual cost) $128.52 $128 52 ten

Plug Gel (ad) for current actual cost) $6.411 S 50 sack

Well Cap ladp for current actual cost) $12 011 $ 12.201 each

I lsdroehloric Acid tladl fbr current actual cost) $1.54 $1.54 gallon

Analytical Costs

Guideline 6 (contract lab adiustcd for currelt contract cost) $248 0l $249.00 aatrlsis

b paratncter (in-house) Est Rate (CPIl 50.110 $51.85 an- sis

Other (radon. hio, tec.) Est Ritec CPI) $9231.00 $940.73 totlt

Spurn Parts

2012 Rate 1l03 Es2 Rat9 s(PI$5 1.750.,00 S52.629 75 .,carRestoration spare pans esttlnate

Page 30: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-15 Marsland Master Cosl Basis - 2013 Surely Estimate (continued)Bossittosrst Costs

loots er!Rottal Labor Costs Rltnit Reserte Costs Fuel Costs Mob & Dettob Total IStir

Rate 1IS/t) So 010o Mlltr

Cat 2124G Loader

Cat 416 Backhoe

ShredderCat DON Bulldezer

Pulling Unit

Mitetng Unit

Drill Rig

$36.50t $24.89

$21.Stt $24.8)$8.01

$1I tt.0t $24.09

$52.58 ine

$163 34 tc

$64 50 $1209

incS330.00 $44.85

inc unc

ilnc i11¢

inc

inc

inc

in,

in,

$1$42.59

$122.98$0 Ill

$S509 74

$52.50

$6.t10

$16334

Basis:Drill rig based on current 2011 contract.

Equiptent rates based on Cost Reference Guide - Equipoteot Watch 2tt12 updated additiOiL.

Aug 12 costs for off-road fitel. $3 '4S1) gallot

Labor rate based on currctt operator labor rate

Pip V'olomns

ttttn l Pttte Sine W all T htlkt-tenso D rNoLinal Pitte Dittt Illn/l1t

3/8-ioch 02 bose 0.37553 0.03 1310

2-melh Sch. 40 dohole 0 15 4i00 2 375tt0 0,01t740

1-1/4-1elt SchtI.4tt stng.I I 0.14000 I66t 000440

2-tch SDR 13.3 inj & prod. (I. 14815 2.29h3tt (tO00tt0

4-Inch SDR 35 0 114310 4 22960 t0.I1t30t-inch Sch. d4t process pipe 0I.28lt110 6.560tt0 0t.03840

6-incht Tronklino 0.49it100 56t60,0tt (1t0s6ll

8-tnch Ttonkline (I 63900(I t.54xtt 0 11030

It-htch Trunkline 0t.79600 1 .654110 0.17120

12-inch Trunklttc ( Y94400I 12 6357010 0I 240t4

Page 31: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-15 Marsland Master Cost Basis - 2013 Surety Estimate (continuced)Pipe 11omovl icd Shredding Conis

Aecicice Rcnno'al Race (Iltman- Shreddin- Race Labor Rare (da Aeci icr CarlAan A,(•lhcrar-dar

2-inch SDR 13.5 inj & prod Remoral 225 $1119.9 S0.88

2-inch StDR 13.5 inj & Prod Shredding 1920) $199.019 $11.1)

Trunklinc Rcnoval I ()O $191113 s I.1`9

T.rcoline Shredding 1WO $199.119 $1.99

Doiclcolc Pipe Remooal 201)10 $S199.09 $9.10

Doerhole Pipe Shredding 225) $1991.01 $(}.1

Doar nhole tose Reina'al ... I10 $199 (11) $0.201

Whasce and RO Boinding Pipeline Remrnal 1i7 $199 011 $2.97

Waste ad RO Building Pipeline Shredding 1500 $S199019 $01.13

Waste Disposal Costs

Dlernic Tarnal

Waste Fanri Fee Falctrr Fee iier Cubic Yard Transpnn Con TrclcorationFavr ard Disnpn...l

Soil, Bell Brproducl Malerial SIM6 75 per Ton 11.54 $9115 $6I00 111 per Yd3 $25 0i5 per, d3

trnpackaged Bulk Bepreducl Matrial leg., pipe. equipanal) $141.75 perTonr 0.42 $61.64 SIbt) II) per Yd3 S221.64 per Yd3

Solid Waste (landfill) $(0.03 per Lb Incl. per Lb $I.(13111111 per Lb

Solid Wsade (lndcfill) $912.011 per Lead Inel. per Load $912 0l) per Load

Void Faccor fbr disposal) 1.25

Plant Dismconling

Plamr Cowon.ents... Nculer Unitics Esated Dislosad Units AciMIrr Unirs 2012CastVolun¢ -

Cantrariinared Tanrks I each 19.23 F3 eacci cSnnn-.onc o.',. 190811"0rlecd,.11,ei-c lciar-Unr(nnlcanclccaced Tieler II eachc 9..3 Fc3 cachc m..u 9. cc4l)(r

Piuotps I3 each 5 Ec3 caclcDanho.,loe PU.npr 0 each O..S F3 eacc 'n-c"rc'a.. Cnrrentc Coar $S/112 14 04

Containinated Piping 40001(1 feel See estincate by piping size and

Unccecccanccnared Piping 9 feel noaterial

filhrs 0r each 1li0 FO3 each

Diner 0 each 4001 Fc3 eaeb

A% erge PVC Pipe Diarncer (inclcs)c3

Page 32: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Table P.1-15 Marsland Master Cost Basis - 2013 Surety Estimate (continued)Plat D)eoM.ta.mitfatiocn

Diruct Disirose Plant Fleer Area

UncontamlnaLed Plant Floor Area

Decontaminated Plant Floor Area

A•lemgc concrcte thickness

Plant Wall Area

134tttt Rt2

90111tI 112ut 75 tI

Dacon Solution 11('1) Fluor Application Rate

Decon Solution (MICI) Wall Application Rate

2 g.al1I1

i gal/IC2

Page 33: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Crow Butte Resources

Marsland Project

Page 1 of 2

April 23, 2012

Rhonda Grantham

Supervisor Radiation Safety & Regulatory Affairs/RSO

86 Crow Butte Rd

Crawford, NE 69339

Subject: United States Nuclear Regulatory Commission (USNRC) Regulatory Guide 4.14 Lower

Limits of Detection for the Marsland Baseline Samples.

Dear Rhonda:

As requested in conversation with David Blaida, Energy Laboratories, Inc. (ELI) Radiochemical

Supervisor on April 20, 2012, the following is an explanation verifying the reported Minimum

Detectable Concentrations/Lower Limits of Detection (MDC/LLD) values for the Marsland Baseline

Project samples are in compliance with the USNRC regulatory guide 4.14, Section 5 “LLD” for the

following requested analytes:

Analyte MDC/LLD MDC/LLD Matrix Water Water

Radium 226 2E-10 uCi/ml 0.2 pCi/L

Thorium 230 2E-10 uCi/ml 0.2 pCi/L

Polonium 210 1E-9 uCi/ml 1.0 pCi/L

Lead 210 1E-9 uCi/ml 1.0 pCi/L

Uranium 2E-10 uCi/ml 0.2 pCi/L

Matrix Soil/sediment (dry) Soil/sediment (dry)

Radium 226 2E-7 uCi/g 0.2 pCi/g

Thorium 230 2E-7 uCi/g 0.2 pCi/g

Polonium 210 No guidance No guidance

Lead 210 2E-7 uCi/g 0.2 pCi/g

Uranium 2E-7 uCi/g 0.2 pCi/g

Matrix Vegetation, food &

Fish (wet)

Vegetation, food &

Fish (wet)

Radium 226 5E-8 uCi/kg 0.05 pCi/g

Thorium 230 2E-7 uCi/kg 0.2 pCi/g

Polonium 210 1E-6 uCi/kg 1.0 pCi/g

Lead 210 1E-6 uCi/kg 1.0 pCi/g

Uranium 2E-7 uCi/kg 0.2 pCi/g

ELI has met the criteria per the guidance suggested by the USNRC when reasonably achievable by available conventional laboratory methodology. If for some reason the MDC/LLD was not be met on the original analysis, the samples were recounted or re-analyzed until the 4.14 MDC/LLDs were achieved. If after

Page 1 of 2

Page 34: Appendices O-Q - Environmental Report Marsland Expansion Area. · The following protocol is a modification of a swift fox protocol included in Mineral Exploration Permit Number NE0210824

Crow Butte Resources

Marsland Project

Page 2 of 2 reanalysis these criteria still could not be met, the laboratory report included a narrative explanation with respect to one or more of the following:

1. Matrix interferences

2. Matrix effects

3. Inadequate sample volumes

4. Radiochemical concentrations were reported above the MDC/LLD

In addition, some of the analytes were reported to two significant figures. Regulatory Guide, 4.14

lists the LLDs to only one significant figure, therefore, it is of ELI’s opinion that these should be

rounded to the nearest significant figure. For example, 1.3 pCi/L equals 1 pCi/L.

Also, as mutually agreed, the concept of MDC vs. LLD is effectively a “non-issue” in that each

calculation is slightly different but clearly generates identical sets of results.

Hopefully this is an adequate explanation of the issues as it pertains to the Marsland Expansion Area.

If you have any questions, please do not hesitate to contact Dave Blaida or me.

Thank you,

Steve Dobos

Senior Project manager/Client Relations

Page 2 of 2

Thank you, Digitally signed bySteve DobosDate: 2012.04.25 15:21:29 -06:00