APPELLANT MEMORANDUM file · Web viewAPPELLANT MEMORANDUM

79
I TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY (TIMCCE) 2018 MEMORIAL FOR THE APPELLANT IN THE MATTER OF APPEAL BEFORE THE HON'BLE SUPREME COURT OF INDIANA BETWEEN: STATE OF DELAWARE AND NORTH ATLANTIC EDISON INC ... APPELLANT V. THERMAL POWER CORPORATION (TPC) ... RESPONDENT MEMORANDUM ON BEHALF OF THE APPELLANT

Transcript of APPELLANT MEMORANDUM file · Web viewAPPELLANT MEMORANDUM

I TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY (TIMCCE)

2018

MEMORIAL FOR THE APPELLANT

IN THE MATTER OF APPEAL BEFORE THE HON'BLE SUPREME COURT OF

INDIANA BETWEEN:

STATE OF DELAWARE AND NORTH ATLANTIC EDISON INC ... APPELLANT

V.

THERMAL POWER CORPORATION (TPC) ... RESPONDENT

MEMORANDUM ON BEHALF OF THE APPELLANT

II TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

TABLE OF CONTENTS

TABLE OF AUTHORITIES.......................................................................................................................IV

LIST OF CASES.....................................................................................................................................IV

STATUTES:............................................................................................................................................VI

BOOKS:...................................................................................................................................................VI

MISCELLANEOUS:..............................................................................................................................VII

Conventions:............................................................................................................................................IX

STATEMENT OF JURISDICTION...........................................................................................................XI

125. Appeal to Supreme Court:...............................................................................................................XI

QUESTIONS PRESENTED......................................................................................................................XII

Whether Appellant (State of Delaware) justified in seeking for the cancellation of the long term purchase agreement with Thermal Power Corporation?........................................................................XII

Whether North Atlantic Edison Inc is correct in approaching through UK government to seek relief under Bilateral Agreements?..................................................................................................................XII

Whether State Government has any other option to deal with the situation rather than cancelling the long term agreements?............................................................................................................................XII

STATEMENT OF FACTS.......................................................................................................................XIII

SUMMARY OF PLEADINGS..............................................................................................................XVIII

1. Whether the appellant (State of Delaware) justified in seeking for the cancellation of the long term purchase agreement with Thermal Power corporation?.....................................................................XVIII

2. Whether North Atlantic Edison Inc is correct in approaching through UK government to seek relief under Bilateral Agreements?....................................................................................................XVIII

3. Whether state government has any other option to deal with the situation rather than cancelling the long term agreements?.........................................................................................................................XIX

PLEADINGS.................................................................................................................................................1

1. WHETHER THE APPELLANT JUSTIFIED IN SEEKING FOR THE CANCELLATION OF THE LONG TERM PURCHASE AGREEMENT WITH RESPONDENT?............................................1

I. THAT PPA IS NOT IN ACCORDANCE WITH NATIONAL ELECTRICITY POLICY..........1

II. THAT PPA IS NOT IN ACCORDANCE WITH NATIONAL TARIFF POLICY......................3

III. THAT PPA IS NOT IN ACCORDANCE WITH THE ELECTRICITY ACT, 2003...............6

IV. THAT PPA IS IN VIOLATION OF SECTION 60...................................................................8

MEMORANDUM ON BEHALF OF THE APPELLANT

III TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

V. THAT PPA IS VOID UNDER SECTION 23 OF THE CONTRACT ACT, 1872.....................10

2. WHETHER NORTH ATLANTIC EDISON INC. IS CORRECT IN APPROACHING THROUGH UK GOVERNMENT TO SEEK RELIEF UNDER BILATERAL AGREEMENTS?.......12

I. THAT THE HON’BLE COURT MAY CONSENT FOR ARBITRATION:.............................12

II. THE PARTIES TO THE ARBITRATION AND RELATED ENTITIES:.................................15

III. THE BASIS FOR THE ARBITRATION, THE APPLICABLE LAW AND TREATY V. CONTRACT........................................................................................................................................15

IV. APPELLANTS' CLAIMS AGAINST THE GOVERNMENT...............................................18

3. WHETHER STATE GOVERNMENT HAS ANY OTHER OPTION TO DEAL WITH THE SITUATION RATHER THAN CANCELLING THE LONG TERM AGREEMENT?........................26

PRAYER......................................................................................................................................................33

MEMORANDUM ON BEHALF OF THE APPELLANT

IV TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

TABLE OF AUTHORITIES

LIST OF CASES

1. Adani Power Limited vs. Uttar Haryana BijliVidyut Nigam Limited and ors;Coastal

Gujarat Power Limited vs Gujarat UrjaVikas Nigam Limited and Ors………………41

2. Alpha Projektholding v. Ukraine, ICSID Case No. ARB/07/16, Award, 8 November

2010……………………………………………………………………………………34

3. Burlington Resources Inc. v. Republic of Ecuador (ICSID Case No. ARB/08/5), Decision

on Liability, 14 December 2012, para. 396………………………………………..…..38

4. CIT Bombay v. Mahindra and Mahindra Ltd. (1983) 4 SCC 392 at 394……………...19

5. CMS v. Argentina; National Grid v. Argentina, UNCITRAL, Award ¶ 176-179 (Nov. 3,

2008) [hereinafter CMS Award]……………………………………………………….34

6. El Paso v. Argentina, CMS v. Argentina……………………………………………….38

7. Eureko B.V. v. Poland, Partial Award, and 19 August 2005……………………..…….37

8. Gujarat UrjaVikas Nigam Ltd. v. Solar Semiconductor Power company India Pvt. Ltd.

and ors., Supreme Court, Civil Appeal No. 6399 of

2016…………………………………………………..…………………………..……..40

9. India Financial Assn., Seventh Day Adventists v. M.A Unneerikutty (2006) 6 SCC

351………………………………………………………………………………….…...22

10. International Thunderbird Gaming Corporation v. United Mexican States, UNCITRAL,

Arbitral Award (Jan. 26, 2006)…………………………………………………….……34

11. Lauder v. Czech Republic, UNCITRAL, Award, 3 September 2001, ¶ 221; Plama

Consortium Limited v. Bulgaria, ICSID Case No. ARB/03/24, Award, 27 August 2008, ¶

184……………………………………………………………………………………….34

MEMORANDUM ON BEHALF OF THE APPELLANT

V TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

12. Methanex Corporation v. United States (Final Award of the Tribunal on Jurisdiction and

Merits, 3 Aug. 2005) [Methanex] at Part IV – Chapter C, para. 25……………………..35

13. Noble Ventures, Inc. v. Romania, Award October 12, 2005 ICSID Case No ARB/

01/11…………………………………………………………………………………….37

14. North Delhi Municipal Corporation v. Prem Chand Gupta 2017 Scc Online Del

9154……………………………………………………………………………………..22

15. North Delhi Municipal Corporation v. Prem Chand Gupta 2017 Scc Online Del

9154……………………………………………………………………………………....23

16. Occidental Exploration and Production Company v. Equador, LCIA Case No UN 3467,

Final Award on 1st July 2004………………………………………………………….…34

17. Perenco Ecuador Ltd. v. The Republic of Ecuador and EmpresaEstatalPetróleosdel

Ecuador (Petroecuador) (ICSID Case No. ARB/08/6)……………………………..……38

18. Raja Mohan @ Mohan vs The Divisional Engineer on 9 March, 2016……………….…..42

19. RamakantKini v. Hiranandani Hospital, Case No. 39 of 2012…………………………21

20. Romak S.A. (Switzerland) v. The Republic of Uzbekistan (UNCITRAL, PCA Case No.

AA280), Award, 26 November 2009, para. 207……………………………………..….30

21. Salini v. Morocco……………………………………………………………………..…30

22. Sempra Energy International v. Republic of Argentina, ICSID case No ARB/02/16,

Decision on Objections to Jurisdiction, 11 May 2005……………………………..……36

23. Sempra Energy International v. Republic of Argentina, ICSID case No ARB/02/16,

Decision on Objections to Jurisdiction, 11 May 2005……………………….…………..38

24. SGS SociétéGénérale de Surveillance S.A. v. Islamic Republic of Pakistan (ICSID Case

No. ARB/01/13) Procedural Order No.2 dated 16 October 2002………………………..26

25. SGS SociétéGénérale de Surveillance, S.A. v. the Republic of the Philippines, ICSID

case No. ARB/02/6, Decision on Jurisdiction, 29 January 2004 available at

www.worldbank.org/icsid/cases/SGSvPhil-final.pdf........................................................36

MEMORANDUM ON BEHALF OF THE APPELLANT

VI TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

26. SGS SociétéGénérale de Surveillance, S.A. v. the Republic of the Philippines, ICSID

case No. ARB/02/6, Decision on Jurisdiction, 29 January 2004 available at

www.worldbank.org/icsid/cases/SGSvPhil-final.pdf.......................................................38

27. Starrett Housing v. Iran, Interlocutory Award No. ITL 32-24-1, 19 December 1983, 4

Iran-United States Claims Tribunal Reports 122, p. 154…………………….………….38

28. The Campaign for Nuclear Disarmament v. The Prime Minister of the United Kingdom,

[2002] EWHC 2777 (Admin)……………………………………………………………25

29. Tin Council Case [J.H. Rayner (Mincing Lane) Ltd. v. Department of Trade & Industry

&Ors ,[1990] 2 AC 418 (House of Lords). …………………………………….………24

30. Torrent Power Limited v. Gujarat Electricity Regulatory Commission Appeal No. 68 of

2009………………………………………………………………………………………18

31. TPC Ltd. v. Reliance Infra Ltd. Case No. 13 of 2010…………………………………...21

32. Uttar Haryana BijliVitran Nigam v. CERC 2016 Scc Online APTEL 94 ……………....19

STATUTES:

1. The Electricity Act, 2003.

2. The Competition Act, 2002.

3. The National Electricity Policy.

4. Vienna Convention on the Law of Treaties.

5. Responsibility of States for Internationally Wrongful Acts.

6. UNCITRAL Arbitration Rules 1976.

7. Constitution of India,1950.

BOOKS:

1. BARUCHA, NAUSHIR, “GUIDE TO ELECTRICITY LAWS”.

2. BASU, “COMMENTARY ON ELECTRICITY LAWS OF INDIA”.

MEMORANDUM ON BEHALF OF THE APPELLANT

VII TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

3. BECK, HART, NOMOS, “INTERNATIONAL COMMERCIAL ARBITRATION”.

4. BECK, HART, NOMOS, “INTERNATIONAL INVESTMENT LAW”.

5. CHATTERJEE’S, “THE ELECTRICITY LAWS OF INDIA”.

6. AIYAR, KRISHNAMURTHY, “LAWS RELATION TO ELECTRICITY IN INDIA”

7. CHOUKROUNE, LAILA, “JUDGING THE STATE IN INTERNATIONAL TRADE

AND INVESTMENT LAW”.

8. COLLINS, DAVID,“AN INTRODUCTION TO INTERNATIONAL INVESTMENT

LAW”.

9. GAZZINI, TARCISIO, “INJTERPRETATION OF INTERNATIONAL INVESTMENT

TREATIES”.

10. SCHILL STEPHEN, THE MULTILATERALIZATION OF INTERNATIONAL

INVESTMENT LAW.

11. SCHILL, STEPHEN W., “ENABLING PRIVATE ORDERING: FUNCTION, SCOPE

AND EFFECT OF UMBRELLA CLAUSES IN INTERNATIONAL INVESTMENT

TREATIES.” 18 MINN. J. INT’L L.1 (2009), P. 35.

12. TANEJA, RAMNI, “FOREIGN DIRECT INVESTMENT AND GLOBALISATION”.

13. TWEDDALE, TWEDDALE, “ARBITRATION OF COMMERCIAL DISPUTES”.

MISCELLANEOUS:

1. Agreement between the Government of the United Kingdom of Great Britain and

Northern Ireland and the Government of the Republic of India for the Promotion and

Protection of Investments 1994.

2. Amulya K.N. Reddy and Gladys D. Sumithra, Karnataka’s Power Sector: Some

Revelations, Economic and Political Weekly, Vol. 32, No. 12 (Mar. 22-28, 1997), pp.

585-600.

3. Ankita Gupta et. al., Effectiveness of High Voltage in Distribution System: High Voltage

Distribution System, IOSR Journal of Electrical and Electronics Engineering, Volume 1,

Issue 5 (July-Aug. 2012), PP 34-38 (www.iosrjournals.org).

MEMORANDUM ON BEHALF OF THE APPELLANT

VIII TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

4. BerkDemirkol, the Notion of ‘Investment’ in International Investment Law (February 1,

2015). (2015) I Turkish Commercial Law Review 41.

5. Bernasconi-Osterwalder, N. (2014), State-State Dispute Settlement Clause in Investment

Treaties (IISD Best Practices Series). Geneva and Winnipeg: IISD. Retrieved from

http://www.iisd.org/sites/default/files/publications/ best-practices-state-state-dispute-

settlement-investment-treaties.pdf.

6. Consultation paper on Additional Surcharge, Available at

https://powermin.nic.in/sites/default/files/webform/notices/Seeking_Comments_on_Cons

ultation_paper_on_issues_pertaining_to_Open_Access.pdf.

7. Delhi Electricity Regulatory Commission, Approach Paper on Tariff Rationalization,

February 2018,

http://www.derc.gov.in/Public%20Notice/Tariff%20Rationalization/Approach%20Paper

%20on%20Tariff%20Rationalisation.pdf.

8. Delhi Electricity Regulatory Commission, Approach Paper on Tariff Rationalization,

February 2018,

http://www.derc.gov.in/Public%20Notice/Tariff%20Rationalization/Approach%20Paper

%20on%20Tariff%20Rationalisation.pdf.

9. Edward Malley and David Zarider, Decommissioning Obsolete Power Plants Why Do it

Now?; See Also U.S. Energy Information Administration/Electric Power Annual 2009,

North American Electric Reliability Corporation 2010 .

10. Explanatory Memorandum to the draft Central Electricity Regulatory Commission

(Prevention of Adverse Effect on Competition) Regulations, 2012.

11. Expropriation, UNCTAD Series on Issues in International Investment Agreements II- A

Sequel (2012) p. 11.

12. Government of India, Ministry of Power, National Electricity Policy (12th February

2005).

13. Luiz T.A. Maurer and Luiz A. Barroso,ElectricityAuctions:An overview of efficient

practices, A World Bank Study.

14. PoonamShivaji et al., Wireless SCADA: Review Paper, International Journal for

Scientific Research and Development, Volume 5 Issue 11 Pg. 751-753.

MEMORANDUM ON BEHALF OF THE APPELLANT

IX TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

15. Santosh B Belekaret. al., PLC and SCADA based distribution and control,

Multidisciplinary Journal of Research in Engineering and Technology Volume 1, Issue 1

(April 2014) Pg. 105-110.

16. Sarita Singh, PPA Auction for stressed power stations gets bids for 2200 MW, The

Economic Times (Jun 27, 2018).

17. Sethi, SP (2016): ‘We Simply Deserve Better: Challenges in Coal and Power Sectors’,

Economic & Political Weekly, 51(25): 12-16.

18. TarunAgarwal, Scada Applications in Power Sector,Edgefx Technologies Pvt.

Ltd.,Online: https://www.edgefx.in/scada-applications-in-power-system/.

CONVENTIONS:

1. Bilateral Investment Promotion & Protection Treaty

2. United Nations Commission on International Trade Law (UNCITRAL) Arbitration

Rules, 1976

3. Articles on Responsibility of States for Internationally Wrongful Acts.

4. Vienna Convention on Law of Treaties

5. International Centre for Settlement of Investment Disputes

6. Bilateral Investment Treaty

7. UNCTAD

MEMORANDUM ON BEHALF OF THE APPELLANT

X TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

LIST OF ABBREVIATIONS

DEB : Delaware Electricity Board

PPA : Power Purchase Agreement

AT&C : Aggregate Technical & Commercial

CERC : Central Electricity Regulatory Commission

SERC : State Electricity Regulatory Commission

DISCOMS : Distribution Companies

EA : Electricity Act

GENCO’s : Generation Companies

CCI : Competition Commission of India

BIT : Bilateral Investment Treaty

ICSID : International Centre for Settlement of Investment Disputes

VCLT : Vienna Convention on the Law of Treaties,

UNCITIRAL :  United Nations Commission on International Trade Law 

ARSIWA : Responsibility of States for Internationally Wrongful Acts

APTEL : APPELLATE TRIBUNAL FOR ELECTRICITY

SCADA : The Supervisory Control And Data Acquisition

FET : Fair and Equitable Treatment

MEMORANDUM ON BEHALF OF THE APPELLANT

XI TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

STATEMENT OF JURISDICTION

North Atlantic Inc. and State Government of Delaware on its own behalf most respectfully

submit to jurisdiction of this Hon'ble Supreme Court of Indiana under Section 125 of the

Electricity Act, 2003.

Section 125 of the Act reads as follows:

125. Appeal to Supreme Court:

Any person aggrieved by any decision or order of the Appellate Tribunal, may, file an appeal to

the Supreme Court within sixty days from the date of communication of the decision or order of

the Appellate Tribunal, to him, on any one or more of the grounds specified in section 100 of the

Code of Civil Procedure,1908:

Provided that the Supreme Court may, if it is satisfied that the appellant was prevented by

sufficient cause from filing the appeal within the said period, allow it to be filed within a further

period not exceeding sixty days.

MEMORANDUM ON BEHALF OF THE APPELLANT

XII TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

QUESTIONS PRESENTED

-I-

WHETHER APPELLANT (STATE OF DELAWARE) JUSTIFIED IN SEEKING FOR THE

CANCELLATION OF THE LONG TERM PURCHASE AGREEMENT WITH THERMAL

POWER CORPORATION?

-II-

WHETHER NORTH ATLANTIC EDISON INC IS CORRECT IN APPROACHING

THROUGH UK GOVERNMENT TO SEEK RELIEF UNDER BILATERAL

AGREEMENTS?

-III-

WHETHER STATE GOVERNMENT HAS ANY OTHER OPTION TO DEAL WITH THE

SITUATION RATHER THAN CANCELLING THE LONG TERM AGREEMENTS?

MEMORANDUM ON BEHALF OF THE APPELLANT

XIII TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

STATEMENT OF FACTS

A. THE DISPUTE

1. Beginning in 2003, the Republic initiated a process of privatizing certain state-owned

enterprises. This process included representations and promises to foreign investors to

entice and encourage them to invest in the Republic. These representations and promises

were made by and with the approval of the Republic and could only be delivered by the

Republic. Indeed, the then Government, acknowledged the Republic's continuing

responsibility for actions concerning the electricity sector.

2. Since 2003, the Republic reformed and privatized DEB’s generation transmission and

distribution assets. During this time, the Republic established a comprehensive set of

laws and regulations further designed to cause potential investors to invest in the

electricity sector of the Republic and to rely on the regulatory framework that the

Republic created.

3. In 2003, the then Government opened a competitive bidding under which the Delaware

Electricity Board was privatized and was taken over by North Atlantic Edison Inc, an UK

based energy company and this bidding process promised a "regulatory framework,

which will be known by the pre-qualified bidders, and will be the guarantee of the

investments in the sector.

4. The Government has embarked on a bold initiative to restructure the entire electricity

sector. The primary goals of the new structure are to create a competitive market in

generation, create a rational regulatory framework for distribution, and provide capital

needed for needed improvements to the system. The Republic also declared that the

purpose the tariff setting process was to "provide a simplified regulatory scheme and

tariff setting process which limits the discretionary role of the Government through the

establishment of objective criteria for setting prices in a manner which results in an

economically efficient allocation of resources within the electricity sector."

5. The Republic has repeatedly represented that it would enforce the laws and regulations

necessary to reduce the level of theft in the country. The PPA stated "Regulation is in

MEMORANDUM ON BEHALF OF THE APPELLANT

XIV TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

place to ensure that the distribution companies will be able to collect unpaid invoices and

that institution would enforce the legal and regulatory framework that the Republic

established.

6. In its representations to investors, the Republic also repeatedly projected that by today,

AT&C losses would fall to a small fraction of their historically high levels. For example

as per the Government Report, the AT&C Losses have come down from 53% to 9% from

2003 to 2016.

7. During the privatization process, the Republic recognized the problems caused by

electricity theft and the necessity for enforcement of the law to effectively manage the

electricity sector. Likewise, representatives of the Republic have made numerous public

statements regarding the necessity for and importance of preventing the theft of

electricity as well as the problems created due to the Republic's failure to apply the "rules

of the game" that the Republic approved and implemented.

8. Despite the Republic's rhetoric about improving enforcement, theft in the electricity

sector has not been curtailed or deterred, and it continues - on a daily and going-forward

basis - to create losses to the Claimants.

9. The Republic consistently has promised measures to curtail the theft and then reneged.

Distributors, such as the Claimants, who have relied upon and continue to rely on such

promises, continue to suffer the consequences of the Republic's actions as well as its

failure to act.

B. THE CREATION OF NORTH ATLANTIC EDISON INC. AND ITS RELATIONSHIP

WITH THE REPUBLIC

10. The purpose of the Republic's promulgation of the laws, resolutions and entities

described above was to establish a predictable regulatory system to attract the funds

needed for the privatization of the Republic's electricity system by foreign investors in

2003 and to maintain a stable framework for the electricity sector's viability.

11. Pursuant to the Reform Law and following the directives issued by Government, the DEB

formed different subsidiaries. The DEB then proceeded to transfer all of its distribution

MEMORANDUM ON BEHALF OF THE APPELLANT

XV TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

assets under the competitive bidding. All generation and transmission assets remained

with DEB.

12. The Republic invited foreign private companies to participate in the privatization by

contributing financial capital to the new electricity distribution companies. In exchange

for their investment, the private investors would receive 51% of the outstanding common

stock of each company.

13. The private investors that invested in the electricity industry were to be given

management control over the newly-formed electricity companies through special

provisions in the companies' by-laws and through the execution of management

agreements between each of the subsidiaries and the individual foreign investors.

C. THE REPUBLIC'S AGREEMENTS WITH NORTH ATLANTIC EDISON INC.

11. In 2003, the Government announced that North Atlantic Edison Inc., a UK based

Company was the winners of the competitive bidding for the selection of the private.

12. The basic contracts are:

a. the PPA, which was signed between the Republic of Indiana and the North

Atlantic Edison Inc.

b. the Privatization Agreement signed between the Republic of Indiana and the North

Atlantic Edison Inc.

13. The Basic Contracts reflected the fulfilment of the Republic's stated public policy to

privatize the electricity sector by forming joint ventures with foreign investors, to

establish a new long-term structure for the electricity sector, and to guarantee certain

rights to North Atlantic Edison Inc. The North Atlantic Edison Inc. relied on the long-

term regulatory structure and the commitments made by the Republic when making

its investment in DEB in 2003. The Republic has renewed publicly its commitment to

these reforms, and Claimants relied on the Republic's repeated affirmations when

investing in the sector in 2003.

D.THE POWER PURCHASE AGREEMENT

MEMORANDUM ON BEHALF OF THE APPELLANT

XVI TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

14. In 2003, the DEB and North Atlantic Edison Inc. executed the Power Purchase

Agreement. In the PPA, the Republic declared that, through the Government, it

intended to: as a matter of policy, involve the private sector in the restructuring and

operation of the electricity distribution permitting new private sector capital to

rehabilitate and extend the distribution system, which creates a competitive electricity

market that awards efficiency and good management.

15. In the PPA, the Republic agreed to establish North Atlantic Edison Inc. and transfer

to it certain electricity distribution assets, including operating licenses, and certain

liabilities.

16. North Atlantic Edison Inc. was fully aware of the contents of the Basic Contracts on

the date of the bid, and its decision to make its bid and subsequently enter into the

PPA was premised upon its understanding that upon its investment in DEB these

agreements would be executed.

MEMORANDUM ON BEHALF OF THE APPELLANT

XVII TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

MEMORANDUM ON BEHALF OF THE APPELLANT

XVIII TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

SUMMARY OF PLEADINGS

1. WHETHER THE APPELLANT (STATE OF DELAWARE) JUSTIFIED IN

SEEKING FOR THE CANCELLATION OF THE LONG TERM PURCHASE

AGREEMENT WITH THERMAL POWER CORPORATION?

It is humbly submitted that the Appellant Company moves this Hon’ble Court to seek the relief

of cancellation of long term power purchase agreement between the Appellant Company and

Respondent (“PPA”) in reversal of the Order passed by the Appellate Tribunal.The PPA in its

present shape is not in accordance withNational Electricity Policy, 2005 (“National Electricity

Policy”),the National Tariff Policy, 2016 (“National Tariff Policy”) and the Electricity Act,

2003 (“Electricity Act”);is in contravention of Section 60 of Electricity Act, as it is anti-

competitive and abuses dominance;against “public policy” in contravention to Section 23 of

Indian Contract Act, 1872.The humble request of termination of PPA is being taken in view of

“public policy” and that termination is not barred by Electricity Act.

2. WHETHER NORTH ATLANTIC EDISON INC IS CORRECT IN APPROACHING

THROUGH UK GOVERNMENT TO SEEK RELIEF UNDER BILATERAL

AGREEMENTS?

It is humbly submitted before this Honorable Court that the appellant seeks permission of the

court to initiate state-state arbitration between Government of UK and Government of Indiana

under Article 10 of Bilateral Investment Promotion & Protection Agreement 1(hereinafter

referred as BIPA) entered on 14 march 1994 under structured rules modeled on the United

Nations Commission on International Trade Law (UNCITRAL) arbitration rules.

1 Agreement between the Government of the United Kingdom of Great Britain and Northern Ireland and the Government of the Republic of India for the Promotion and Protection of Investments 1994.

MEMORANDUM ON BEHALF OF THE APPELLANT

XIX TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

3. WHETHER STATE GOVERNMENT HAS ANY OTHER OPTION TO DEAL WITH

THE SITUATION RATHER THAN CANCELLING THE LONG TERM

AGREEMENTS?

It is humbly submitted that the PPA entered into by the previous government obligate the

appellant to pay a higher purchasing cost than the market price thereby leading to increasing

regulatory assets. However, the state government may also revise the tariff in the PPA in

accordance with Section 61 of the Electricity Act, it may also order pooling of the current source

along with a cheaper source to make the power purchasing cost affordable in the larger public

interest. It may also work towards achieving technological development of the distribution

infrastructure and may order Renovation, Modernization or Decommissioning of costly

generating plants along with replacing them with more efficient and cost effective plants or

doing an Auction of the generating plants through PPA.

MEMORANDUM ON BEHALF OF THE APPELLANT

1 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

PLEADINGS

1. WHETHER THE APPELLANT JUSTIFIED IN SEEKING FOR THE

CANCELLATION OF THE LONG TERM PURCHASE AGREEMENT

WITH RESPONDENT?

It is humbly submitted that the Appellant Company moves this Hon’ble Court to seek the relief

of cancellation of long term power purchase agreement between the Appellant Company and

Respondent (“PPA”) in reversal of the Order passed by the Appellate Tribunal. The PPA in its

present shape is not in accordance with:

(a) relevant laws governing the electricity sector, i.e. the National Electricity Policy, 2005

(“National Electricity Policy”),the National Tariff Policy 2016 (“National Tariff

Policy”) and the Electricity Act, 2003 (“Electricity Act”);

(b) is in contravention of Section 60 of Electricity Act, as it is anti-competitive and abuses its

dominant position;

(c) against “public policy” in contravention to Section 23 of Indian Contract Act, 1872.

The humble request of termination of PPA is being taken in view of “public policy” and

that termination is not barred by Electricity Act.

I. THAT PPA IS NOT IN ACCORDANCE WITH NATIONAL ELECTRICITY

POLICY

It is most humbly submitted before this Hon’ble Court that the PPA between the Appellant

Company and Respondent is not in concurrence with the National Electricity Policy.

MEMORANDUM ON BEHALF OF THE APPELLANT

2 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

1. Relevant objectives of the Policy are:

“(c) Supply of reliable and Quality power of specified standards in an efficient manner

and at reasonable rates;

(f) Financial turnaround and commercial viability of Electricity sector”

A. RETURN ON INVESTMENT:

2. The National Electricity Policy further in Para 5.4.4 states:

“Conducive business environment in terms of adequate returns and suitable transitional

model with predetermined improvements in efficiency parameters in distribution business

would be necessary for facilitating funding and attracting investments in distribution.

Multi-Year Tariff (MYT) framework is an important structural incentive to minimize

risks for utilities and consumers, promote efficiency and rapid reduction of system losses.

It would serve public interest through economic efficiency and improved service quality.

It would also bring greater predictability to consumer tariffs by restricting tariff

adjustments to known indicators such as power purchase prices and inflation indices.

B. ATTRACTING PRIVATE SECTOR INVESTMENT:

3. The National Electricity Policy in Para 5.8.4 states

“Capital is scarce. Private sector will have multiple options for investments. Return on

investment will, therefore, need to be provided in a manner that the sector is able to attract

adequate investments at par with, if not in preference to, investment opportunities in other

sectors. This would obviously be based on a clear understanding and evaluation of

opportunities and risks. An appropriate balance will have to be maintained between the

interests of consumers and the need for investments.”

MEMORANDUM ON BEHALF OF THE APPELLANT

3 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

4. The above are some of the provisions of the National Electricity Policy, which make

it amply clear that the distribution licensee has the right to adequate return on its

investment in order to sustain effectively and efficiently in the power market.2

5. Further, there is a responsibility on the distribution licensee to provide power at a

competitive rate to the consumer3. In addition, the distribution licensee has obligation

to provide subsidies power to rural and to consumers below poverty line below

poverty4. The above obligations can only be satisfied when distribution licensee is

able to procure power at an economic rate.

II. THAT PPA IS NOT IN ACCORDANCE WITH NATIONAL TARIFF POLICY

1. The National Tariff Policy not only aims at ensuring that consumer pay only

reasonable charges but also emphasizes on attracting and maintaining adequate

investments in the market.

2. Para 1.4 of the National Tariff Policy provides:

“Balancing the requirement of attracting adequate investments to the sector and

that of ensuring reasonability of user charges for the consumers is the critical

challenge for the regulatory process. Consistency in approach becomes all the

more necessary considering the large number of States and the diversities

involved.”

3. The National Tariff Policy further lays down the framework for performance based

cost of service regulation in respect of aspects common to generation, transmission as 2Para 5.4.4 and 5.4.8 of National Electricity Policy3Para 1.2 National Electricity Policy4Para 5.5.2 National Electricity Policy

MEMORANDUM ON BEHALF OF THE APPELLANT

4 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

well as distribution in Para 5.11. These are not applicable to competitive bidding

projects.

A. RETURN ON INVESTMENT:

4. Balance needs to be maintained between the interests of consumers and the need for

investments while laying down rate of return. Return should attract investments at par

with, if not in preference to, other sectors so that the electricity sector is able to create

adequate capacity. The rate of return should be such that it allows generation of

reasonable surplus for growth of the sector. The Central Commission would notify,

from time to time, the rate of return on equity for generation and transmission

projects keeping in view the assessment of overall risk and the prevalent cost of

capital which shall be followed by the SERCs also.

5. The rate of return notified by CERC for transmission may be adopted by the SERCs

for distribution with appropriate modification taking into view the risks involved. For

uniform approach in this matter, it would be desirable to arrive at a consensus through

the Forum of Regulators. While allowing the total capital cost of the project, the

Appropriate Commission would ensure that these are reasonable and to achieve this

objective, requisite benchmarks on capital costs should beevolved by the Regulatory

Commissions.

6. The Central Commission may adopt either Return on Equity5 or Return on Capital6

approach whichever is considered better in the interest of the consumers. The State

Commission may consider 'distribution and supply margin' as basis for allowing

5 ROE is better suited in fluctuating interest rate regime because the ROE is insulated from Interest rate changes.6 Under the ROCE approach the utility/project developers has to devise their financial package, i.e., Debt/Equity ratio, sourcing debt at competitive interest rates, etc. Thus, it is a win-win situation for both the project developer and buyers. Moreover, CERC may also exercise prudent check while determining the Capital Employed in the project.

MEMORANDUM ON BEHALF OF THE APPELLANT

5 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

returns in distribution business at an appropriate time. The State Commission may

also consider price cap regulation based on comprehensive study. The Forum of

Regulators should evolve a comprehensive approach in this regard. The

considerations while preparing such an approach would, inter-alia, include issues

such as reduction in Aggregate Technical and Commercial losses, improving the

standards of performance and reduction in cost of supply.

B. MULTI-YEAR TARIFF:

7. Section 61 of the Act states that the Appropriate Commission for determining the

terms and conditions for the determination of tariff shall be guided, inter-alia, by

Multi-Year Tariff (MYT) principles. The framework should feature a five-year

control period. The initial control period may, however, be of 3 year duration for

transmission and distribution if deemed necessary by the Regulatory Commission on

account of data uncertainties and other practical considerations.

8. Once the revenue requirements are established at the beginning of the control period,

the Regulatory Commission should focus on regulation of outputs and not the input

cost elements. At the end of the control period, a comprehensive review of

performance may be undertaken.

9. Uncontrollable costs should be recovered speedily to ensure that future consumers are

not burdened with past costs. Uncontrollable costs would include (but not limited to)

fuel costs, costs on account of inflation, taxes and cess, variations in power purchase

unit costs including on account of adverse natural events.7

10. In view of the above, please note that the tariff for the PPA was initially determined

by the regulatory body in accordance with the Electricity Act and the National Tariff

Policy. However, subsequently, the government in violation of the above National

Tariff Policy and Electricity Act, froze the tariff thus resulting in accumulations of

regulatory assets. As a result of which power purchase cost has increased threefold

whereas the tariffs has risen only 90% so far.

7 Torrent Power Limited v. Gujarat Electricity Regulatory Commission Appeal No. 68 of 2009

MEMORANDUM ON BEHALF OF THE APPELLANT

6 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

III. THAT PPA IS NOT IN ACCORDANCE WITH THE ELECTRICITY ACT,

2003

1. The tariff is governed by provision of Chapter 7 of the Electricity Act, 2003. Section

62 of the Act sets out the various parameters for Regulatory body to determine the

tariff. The Appropriate Commission is guided by the following:

(b) the generation, transmission, distribution and supply of electricity are conducted

on commercial principles;

(c) the factors which would encourage competition, efficiency, economical use of

the resources, good performance and optimum investments;

(d) safeguarding of consumers' interest and at the same time, recovery of the cost

of electricity in a reasonable manner;

(f) multi-year tariff principles;

2. It is most respectfully brought to the attention of the Court that the tariff under the

PPA does not reflect the above requirements set out in law:

A. COMMERCIAL PRINCIPLES:

3. The tariff charged by the Respondent does not follow any commercial principle as the

Appellant Company is unable to recover the cost of power purchase. Very high level

of technical and commercial losses and lack of commercial approach in management

of utilities has led to unsustainable financial operations of distribution

entities.8Discoms’ financial mess is more because of their operational inefficiencies

and high wholesale price of power in India.9 The tariff at which the Appellant

Company is procuring electricity will not prove to be financially feasible.

8National Electricity Policy9Sethi, SP (2016): ‘We Simply Deserve Better: Challenges in Coal and Power Sectors’, Economic & Political Weekly, 51(25): 12-16.

MEMORANDUM ON BEHALF OF THE APPELLANT

7 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

4. Financial viability consists of 3 interdependent elements of equal importance i.e.

profitability, liquidity and solvency which are represented by cash profit or loss, net

working capital and net worth respectively.10 The Appellant Company has regulatory

assets worth Rs. 15000 Crores and as per estimates, for liquidation of which they

would need to hike tariff by 10% every year for 5 years.11

5. In LancoAmarkantak Power Ltd. v. Haryana Electricity Regulatory Commission12,

the Aptel highlighted the importance of the commercial viability13 of a project under

PPA and henceforth, allowed the petition for re-determination of tariff as it was

commercially infeasible to continue at the agreed rates under PPA.

6. Presently, Delaware is incurring 60% more cost on buying power compared with

other states because of long term power purchase agreements.14 Therefore, it is not

commercially viable, and has led to declaration of regulatory assets of nearly

15000cr.

B. ENCOURAGE COMPETITION:

7. The high cost of tariff makes the power of the appellant commercially unattractive in

the market and therefore, leads to operational losses with respect to open access and

non-open access consumers.

C. CONSUMER INTEREST:

8. The Policy and the Act ultimately aim at providing electricity to the consumers at

affordable prices. Moreover, the while ensuring that investment is safeguarded in a

reasonable manner, the consumers are the ones who shall ultimately bear the loss in

form of payment of addition surcharge for compensating the high energy charges that

the Discoms bear.15

10CIT Bombay v. Mahindra and Mahindra Ltd. (1983) 4 SCC 392 at 39411 Moot Problem Page 2 Para 212Appeal no. 65 of 201313Uttar Haryana BijliVitran Nigam v. CERC 2016 Scc Online APTEL 94 14 Moot Problem Page 2 Para 115Consultation paper on Additional Surcharge, Available at https://powermin.nic.in/sites/default/files/webform/notices/Seeking_Comments_on_Consultation_paper_on_issues_pertaining_to_Open_Access.pdf

MEMORANDUM ON BEHALF OF THE APPELLANT

8 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

D. MULTI-YEAR TARIFF:

9. Government has frozen the tariff in violation to the requirement that when tariff is

determined by regulatory body, such tariff needs to be revised at regular interval.

Considering the sales forecast approved by the Appropriate Commission during Multi

Year period, the Appellant entered into long term Power Purchase Agreements (PPA)

with the Respondent so as to ensure supply of power for the envisaged increase in the

load. Whenever any consumer opts for open access and takes intermittent supply

through open access, the DISCOMs continue to pay fixed charges in lieu of its

contracted capacity with generation stations.

10. However, DISCOMs are unable to sufficiently recover such fixed cost obligation

from the open access consumers. The cost recovered from fixed charges in the tariff

schedule is generally less than the fixed cost incurred by the DISCOM for supplying

energy. This leads to the situation where the DISCOM is saddled with the stranded

cost on account of its universal supply obligation. In such cases, fixed charges for

such stranded assets should be borne by the customers as part of additional surcharge

E. REFLECTING THE COST OF SUPPLY:

11. CERC has fixed the tariff in such a manner that is detrimental to the Appellant

Company and therefore the entire burden of the high cost of supply of the Respondent

Company shall potentially form the debt burden of the Appellant Company.

IV. THAT PPA IS IN VIOLATION OF SECTION 60

i. It is most humbly submitted that Section 60 of EA 2003 relates to market domination

and it refers to prevention of adverse effect on competition in electricity industry. For

this, the provisions of Competition Act, 2002 have been submitted to be relevant.16

16 TPC Ltd. v. Reliance Infra Ltd. Case No. 13 of 2010

MEMORANDUM ON BEHALF OF THE APPELLANT

9 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

A. PPA IS ANTI-COMPETITIVE:

ii. It is humbly submitted that PPA entered into between the parties is anti-competitive,

in contravention to Section 3(4) read with Section 3(1) of the Competition Act, 2002

by creating barrier for new entrants in the market and foreclosing the market.

iii. With the existing PPA, the respondent is trying to foreclose the market for other

competitorsas other DISCOMs are not free to enter into PPA with power producers

at competitive prices.80% of the revenue of Appellant Company goes into

purchasing power from the Central entities leaving behind no other option for the

Appellant to procure electricity from other sources at competitive prices within the

relevant market.

iv. There is no doubt that to enter into generation sector in itself involves high capital

expenditure and catering maximum portion of the market demand, Respondent is

trying to put barriers to the entry for new power producers who are willing to supply

at lower rates, thus causing an adverse effect on the competition in the market.

B. THAT RESPONDENT COMPANY ABUSES DOMINANCE:

5. It is most humbly submitted before this Hon’ble Court that the respondent has been

and is trying to abuse its dominance through the long term PPA which hinders

competition and affects the independent power producers who are interested in

supplying electricity at lower rates and is thus, in violation of Section 4(2)(c) and

Section 4(2)(e) of the Competition Act, 2002. For the purposes of establishing

dominance, relevant market shall be the ‘supply of electricity by GENCOs’ and

geographical market is State of Delaware.

6. Section 19(4) lays down various factors to determine the dominant position of any

enterprise in the relevant market. Consequently, it might be said that market share,

though a major factor, is not the sole yardstick in determination of dominance. In

RamakantKini v. Hiranandani Hospital17, CCI clarified that the market shares of an

17RamakantKini v. HiranandaniHospital,Case No. 39 of 2012.

MEMORANDUM ON BEHALF OF THE APPELLANT

10 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

entity is 'only one of the factors that decides whether an enterprise is dominant or

not, but that factor alone cannot be decisive proof of dominance.

7. The market share of the licensee or generating company, size and importance of the

competitors, level of concentration in the market, supply capacity of the competitors

are a few factors that need to be considered in order to ascertain the dominant

position of the entity alleged.18

8. The Respondent Company has largest market share in generation of thermal

electricity with installed capacity significant enough to be the largest procurer of coal

from Coal India Limited. This demonstrates that extremely long term PPA grants

immense de facto market power to the Respondent Company.

9. By imposing unfair conditions and onerous clauses in the PPAs, including absence of

exit clause for the Appellant and 30 years long duration of the contract, the

Respondent Company has contravened the provisions of Section 4(2)(a)(i) of the Act.

Further, delay in commercial operation of plants and charging of higher rates by the

Respondent Company for supply of electricity in State of Delaware is also alleged to

be violative of Section 4 of the Competition Act.

V. THAT PPA IS VOID UNDER SECTION 23 OF THE CONTRACT ACT, 1872

i. It is most humbly submitted that Section 23 of the Indian Contract Act shows that

where a contractual provision is against a specific statutory provision or if a

contractual clause is allowed to be implemented the same will result in

frustration of a right conferred by law or if the contractual clause is immoral or

oppose to public policy, then, in such cases the contractual clause is invalid and

void.19

18 Explanatory Memorandum to the draft Central Electricity Regulatory Commission (Prevention of Adverse Effect on Competition) Regulations, 201219 North Delhi Municipal Corporation v. Prem Chand Gupta 2017 Scc Online Del 9154

MEMORANDUM ON BEHALF OF THE APPELLANT

11 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

ii. In India Financial Assn., Seventh Day Adventists v. M.A Unneerikutty20, the Apex

Court looked into the ambit of public policy while holding the agreement to be

void under Section 23 of the Contract Act, 1872.

“The primary duty of a Court of a law is to enforce a promise which the

parties have made and to uphold the sanctity of contract which form the

basis of society, but in certain cases, the Court may relieve them   of   their

duty on a rule founded on what is called the public policy; … but the

doctrine is extended not only to harmful cases but also to harmful

tendencies.

This doctrine of public policy is only a branch of common law, and just like

any other branch of common Law it is governed by precedents. The

principles have been crystallized under different heads and though it is

permissible for Courts to expound and apply them to different situations, it

should only be invoked in clear and incontestable cases   of   harm to the

public.”

iii. In the present case, greater public interest is put at stake so as to ensure that

the Respondent earns considerable amount of profits, the PPA in its present

form clearly displays unprofitable tendencies for the consumers. Consumer

while referred to in the Electricity Act includes both the Appellant Company

and domestic consumers.21

iv. Under Section 23, the object of an agreement becomes unlawful if it was of

such a nature that, if permitted, it would defeat the provisions of any law.22 As

contended above, the PPA is in contravention to provisions of Electricity Act,

against the objectives if National Electricity Policy, National Tariff Policy

20India Financial Assn., Seventh Day Adventists v. M.A Unneerikutty (2006) 6 SCC 35121Section 2(15), Electricity Act, 2003

"consumer" means any person who is supplied with electricity for his own use by a licensee or the Government or by any other person engaged in the business of supplying electricity to the public under this Act or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity with the works of a licensee, the Government or such other person, as the case may be;

22 North Delhi Municipal Corporation v. Prem Chand Gupta 2017 Scc Online Del 9154

MEMORANDUM ON BEHALF OF THE APPELLANT

12 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

and Competition Act. If PPA of such a nature in its current form is continued

shall defeat the legislative intent behind the welfare legislations. Therefore,

with operation of Section 23, PPA is hit by the provisions of Indian Contract

Act, 1872.

2. WHETHER NORTH ATLANTIC EDISON INC. IS CORRECT IN

APPROACHING THROUGH UK GOVERNMENT TO SEEK RELIEF

UNDER BILATERAL AGREEMENTS?

1. It is humbly submitted before this Honorable Court that the appellant seeks permission of

the court to initiate state-state arbitration between Government of UK and Government of

Indiana under Article 10 of Bilateral Investment Promotion & Protection Agreement 23(hereinafter referred as BIPA) entered on 14 march 1994 under structured rules modeled

on the United Nations Commission on International Trade Law (UNCITRAL) arbitration

rules.24

I. THAT THE HON’BLE COURT MAY CONSENT FOR ARBITRATION:

2. The National Courts of Indiana inherently lacked the jurisdiction to entertain any dispute

arising out of a Treaty between two sovereign countries. The Union of Indiana was a

party to BIPA, a Treaty between two sovereign governments and the obligations under

such treaties were not subject to domestic laws and disputes arising out of such treaties

were not subject to the jurisdiction of the National Courts. The Courts can not interpret

and/or enforce the provisions of Bilateral Investment Treaties as the law made such

issues non-justiciable.

23 Agreement between the Government of the United Kingdom of Great Britain and Northern Ireland and the Government of the Republic of India for the Promotion and Protection of Investments 1994.24Bernasconi-Osterwalder, N. (2014), State-State Dispute Settlement Clause in Investment Treaties (IISD Best Practices Series). Geneva and Winnipeg: IISD. Retrieved from http://www.iisd.org/sites/default/files/publications/ best-practices-state-state-dispute-settlement-investment-treaties.pdf.

MEMORANDUM ON BEHALF OF THE APPELLANT

13 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

3. As held in The Campaign for Nuclear Disarmament v. The Prime Minister of the United

Kingdom25, &Tin Council Case [J.H. Rayner (Mincing Lane) Ltd. v. Department of Trade

& Industry &Ors.26, as under: -

" ......if there existed a rule of international law which implied in a treaty or imposed

on sovereign states which enter into a treaty, an obligation....to discharge the debts of

an international organization established by that treaty, the rule of international law

could only be enforced under international law. Treaty rights and obligations

conferred or imposed by agreement or by international law cannot be enforced by the

Courts of the United Kingdom...One has only to envisage a dispute, possibly between

the member states and the I.T.C. or possibly between the member states inter se, as to

the scope and consequence of the authority so agreed to be granted. This must

necessarily be a question of the effect of the treaty on the plane of international law

and a domestic court has not the competence so as to adjudicate upon the rights of

sovereign states.”

4. In SGS SociétéGénérale de Surveillance S.A. v. Islamic Republic of Pakistan27,

held: ...However, although the Supreme Court Judgment of July 3, 2002 is final as a

matter of the law of Pakistan, as a matter of international law, it does not in any way bind

this Tribunal...It is essential for the proper operation of both the BIT and the ICSID

Convention that the right of access to international adjudication be maintained. The right

to seek access to international adjudication must be respected and cannot be constrained

by an order of a national court. Nor can a State plead its internal law in defence of an act

that is inconsistent with its international obligations.

25The Campaign for Nuclear Disarmament v. The Prime Minister of the United Kingdom, [2002] EWHC 2777 (Admin)26Tin Council Case [J.H. Rayner (Mincing Lane) Ltd. v. Department of Trade & Industry &Ors ,[1990] 2 AC 418 (House of Lords).

27SGS SociétéGénérale de Surveillance S.A. v. Islamic Republic of Pakistan (ICSID Case No. ARB/01/13) Procedural Order No.2 dated 16 October 2002.

MEMORANDUM ON BEHALF OF THE APPELLANT

14 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

5. The Indiana National Courts neither have the jurisdiction over the subject matter of the

dispute (which is a dispute arising out of an alleged breach of a Treaty by the Union of

Indiana), nor did they have jurisdiction Ratione Personae (i.e. over the Defendants).

6. Under Articles 2628 and 2729 of the Vienna Convention on the Law of Treaties, the

obligations of a State, under a bilateral or multilateral international treaty, are owed by a

Sovereign State to one or more other Sovereign States. A breach of treaty obligations was

a violation of international law and the remedy for this wrong had to be found in

international law. The two principles which had been unanimously accepted are that a

State cannot plead provisions of its municipal law to escape international responsibility,

and legislative, judicial as well as executive acts are all capable of giving rise to State

responsibility.

7. Even when the obligations under a treaty overlapped with domestic law (for example the

procedure under the internal criminal law, or specific laws enacted as measures to give

effect to Treaty Obligations) and the domestic law involved the actions of National

Courts, the action of the Courts themselves could be considered as a violation of the

Treaty under Articles 330 and 431 of the Responsibility of States for Internationally

Wrongful Acts (ARSIWA).

8. Under Article 1032 of the BIPA laid out the procedure to be followed in the case of a

dispute between the Contracting Parties (in this case the United Kingdom) and (Union of

Indiana). The dispute resolution procedure was an element of the bilateral treaty, and thus

any conduct by a State whether by legislation, executive action or resort to a National

Court which interfered with this process would in itself be a violation of the Treaty.

28Article 26 of VCLT.29Article 27 of VCLT.

30Article 3 of ARSIWA.

31Article 4 of ARSIWA.32Article 10 of BIPA.

MEMORANDUM ON BEHALF OF THE APPELLANT

15 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

9. The BIPA specifically provided for the UNCITRAL Arbitration Rules 1976 to apply and

Article 2133 incorporated the principle of kompetenzkompetenz.

II. THE PARTIES TO THE ARBITRATION AND RELATED ENTITIES:

10. The Respondent is the Government of Indiana. That the Government has violated BIPA

both directly and through its instrumentalities and related slate enterprises and entities.

These instrumentalities and related state enterprises and entities qualifies for the term

“other authorities’34, and are therefore State under article 1235 of Constitution of Indiana:

Thermal Power Corporation (hereinafter TPC): TPC is a state run generation

entity and therefore is a state. It is a Public Sector undertaking of Central

Government under Government of Indiana.36

III. THE BASIS FOR THE ARBITRATION, THE APPLICABLE LAW AND

TREATY V. CONTRACT

A. THE BASIS FOR THE ARBITRATION:

11. Appellants’ hereby request arbitration of the dispute set forth herein pursuant to the state-

state dispute settlement provisions Article 10 of BIPA and in accordance with Articles

3(3)(a) and (3)(c) of the UNCITIRAL Arbitration Rules.

33Article 21 of UNCITRAL Arbitration Rules 1976.

34Article 12 of Constitution of India 1950.35Id.36AIR 1975 SC 1331

MEMORANDUM ON BEHALF OF THE APPELLANT

16 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

12. Pursuant to Article 10.1 of BIPA, states37 have agreed to resort to state-state arbitration

for matters “concerning the interpretation or application” of the treaty.38

“Interpretation” is the determination of the meaning of particular provisions of

an agreement in concrete or proposed situations. “Application” relates to the

extent to which the actions or measures taken or proposed by the contracting

parties comply with the terms of an agreement, its object and purpose 39 . These

two interact closely because application inevitably involves interpretation of

treaty provisions, and application could in turn feed into interpretation. The

scope set by these two phrases is “all-encompassing” 40 , capable of covering all

disputes arising from the treaty at issue, such as disputes regarding the

interpretation of a treaty provision in an abstract manner or for a specific case,

whether an act amounts to a treaty violation either based on direct claims or

indirect, diplomatic protection claims...41

13. Pursuant to Article 10(1) of BIPA, it applies to measures adopted or maintained by a

Party relating to certain "investors" and "investments" of another Party (the United

Kingdom), as defined in Article 1(b) and Article 1(c) of BIPA. Appellants are clearly

"investors" of the United Kingdom as defined in Article 1(c)4243 with an "investment" as

defined by that same Article 1(b)44.

14. Herein, the definition is an asset based definition45. North Atlantic Edison Inc. (NAEI), is

an UK based energy company which has acquired Delaware Electricity Board NAEI is a

37 The Government of the United Kingdom of Great Britain and Northern Ireland and the Government of the Republic of India 38Article 10 of BIPA.39 UNCTAD, 2003, p. 14.40Id.41Supra note no 23.42 Article 1(c) of BIPA.43 Two fundamental considerations arise with respect to the definition of ‘Investor’: (a) types of persons who may be considered as investors; and (b) availability of a link to connect the investor with the contracting party to the BIT.44 Article 1(b) of BIPA describes “investment”.

45BerkDemirkol, the Notion of ‘Investment’ in International Investment Law (February 1, 2015). (2015) I Turkish Commercial Law Review 41

MEMORANDUM ON BEHALF OF THE APPELLANT

17 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

“company”46 incorporated or constituted under the laws of the United Kingdom. In

addition, DEB constitutes a legal entity incorporated in the territory of Indiana in

accordance with its legislation and is indirectly owned and controlled by Appellants.

15. Appellants fulfill the requirements, among others, of Article 1(b) and the definition of

"investment" under subparts (i), (ii) and (iii), of that same Article. More specifically:

i. Appellants directly own and control North Atlantic Edison Inc.

ii. Appellants directly own and control 51% of the "stock and other forms of

equity participation" in North Atlantic Edison Inc., a legal entity

incorporated in Indiana in conformity with its legislation.

iii. Appellant can make rightful claims to money or to any performance under

contract having a financial value; and

iv. Appellant' controlling interest in the Power Purchase Agreement by virtue

of their controlling interest in NAEI also clearly qualifies as Appellants'

"investment" under BIPA under Article 1(c);

16. Appellants' directly own and control assets that possess the characteristics of an

investment, including, but not limited to, (l) the commitment of capital or other resources,

(2) the expectation of gain or profit, and (3) the assumption of risk (4) duration of

investment or assumption of risk. These characteristics, in addition to contribution of

investment to economic development of the Host State, are together widely referred to as

the Salini47 criteria. Although this test was used to interpret the definition of Investment

under the ICSID Convention, it has been frequently used by arbitral tribunals beyond the

auspices of the ICSID Convention.48

B. THE APPLICABLE LAW:

17. Under Article 11(1) of BIPA, investment is governed by laws of Indiana.

18. Pursuant to Article 12 of BIPA and Article 3349 of the UNCITRAL Arbitration Rules, the

law governing this dispute consists of the provisions of BIPA, the principles of

46ARTICLE 1(a) (i) of BIPA.47Salini v. Morocco.48Romak S.A. (Switzerland) v.The Republic of Uzbekistan (UNCITRAL, PCA Case No. AA280), Award, 26 November 2009, para. 207.49Article 33 of the UNCITRAL Arbitration Rules.

MEMORANDUM ON BEHALF OF THE APPELLANT

18 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

international law agreed upon and designated by the Contracting Parties to BIPA, as well

as other applicable principles of international law.

C. TREATY VERSUS CONTRACT CLAIMS:

19. An investment is governed both by a treaty and the contract in particular. In the event of a

dispute, it is logical that both claims can arise out of the same factual matrix. In such

cases, Tribunals have encountered difficulty in distinguishing breaches of treaty from

breaches of contract. Nevertheless, they have emphasized upon the importance of

drawing a line between the two.

20. In Compania De Aguas Del Aconquija S.A and Vivendi Universal versus Argentine

Republic50 the Adhoc Committee held that, “where the fundamental basis of the claim is

a treaty laying down an independent standard by which the conduct of the parties has to

be judged, the existence of an exclusive jurisdiction clause in a contract between the

claimant and the state or its subdivisions cannot operate as a bar to the application of the

treaty standard.” Referring to importance of assessing contractual issues, the Ad hoc

committee held that the terms of the contract in municipal law were relevant to assess

whether there has been a treaty breach. It distinguished between exercising contractual

jurisdiction (in this case, in the Tucuman courts) and between “taking into account the

terms of a contract” to determine whether it results in breach of an independent treaty

standard. Thus, the Vivendi Ad hoc Committee found that the fundamental basis of the

Claim lay in the BIT.

IV. APPELLANTS' CLAIMS AGAINST THE GOVERNMENT

A. THAT THE GOVERNMENT HAS FAILED ON ITS COMMITMENT TO PROTECT FOREIGN

INVESTMENT

Under BIPA:

50ICSID Case No. ARB/97/3

MEMORANDUM ON BEHALF OF THE APPELLANT

19 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

21. BIPA is bilateral agreement designed to encourage and protect foreign investment and to

promote the rule of law. In the preamble to BIPA, the contracting parties, including the

Government of the United Kingdom of Great Britain and Northern Ireland -and the

Government of the Republic of India, expressly resolved tocreate conditions favourable

for fostering greater investment by investors of one State in the territory of the Other

State under Preamble of BIPA. Further, Recognizing that the encouragement and

reciprocal protection under international agreement of such investment will be conducive

to the stimulation of individual business initiative and will increase prosperity in both

States;51

a) Moreover, the objectives of the Treaty, as elaborated more specifically through its

principles and rules, including national treatment, most favored-nation treatment,

and transparency, are to: substantially increase investment opportunities in the

territories of the Parties;

b) Under article 3(1) the parties have agreed to encourage and create favourable

conditions for investors of the other Contracting Party to make investments in its

territory.

c) The Parties shall interpret and apply the provisions of the Treaty in light of its

objectives and in accordance with applicable rules of international law under

Article 12 of BIPA.

d) The violations of BIPA must be viewed in light of these clearly-stated objectives

of the Contracting Parties read with ‘good faith principle under Article 31 (1) of

the VCLT52.

e) The wrongful actions of the Government described herein were intentional,

willful, evinced a reckless indifference to the rights of Appellant, and violated the

principles and the specific provisions of BIPA.

B. THAT THE GOVERNMENT’S ACTIONS CONSTITUTE A VIOLATION OF THE FAIR AND

EQUITABLE TREATMENT OBLIGATION IN ARTICLE 3(2) OF BIPA:

51Preamble of India-UK BIT, 199452Article 31, VCLT.

MEMORANDUM ON BEHALF OF THE APPELLANT

20 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

22. The Government’s ongoing actions constitute a violation of the "fair and equitable"

treatment obligation in clear contravention of Article 3(2) of BIPA.53

23. Under this doctrine there are two principles:

i. "Minimum Standards of Treatment": The US-Mexico Claims Tribunals

recognized existence of such standard in its decisions.54 A part of the decision in

Neer v. Mexico is often cited as laying down the minimum standard. In this case,

the Commission held that for the treatment “to constitute an international

delinquency, it should amount to an outrage, bad faith, willful neglect of duty, or

an insufficiency of governmental action so far short of international standards that

every reasonable and impartial man would readily recognize its insufficiency.”55

ii. The basic premise of Minimum Standard of Treatment is that an alien is protected

against excessive and unacceptable measures of the host State by established rules

and standards of customary international law which are independent of the laws of

the host State.56

iii. The doctrine of legitimate expectations holds that public authorities should be

bound by the representations made to parties, and must therefore protect the

reasonable expectations they create in the public towards government activities.

Subsequent retraction on the representation and decisions inconsistent with such

expectations trigger state liability.

iv. The concept of legitimate expectations comes into play in two different ways in

international investment law:

i. The first category is state conduct in the form of specific

representations or declarations made by state authorities relating to the

investment, relied upon by investor to make or expand an investment and

53Article 3(2) of BIPA.

54Neer(1926)IV RIAA 60;Faulkner (1927)21 AJIL 349;Harry Roberts(1927)21 AJIL 357;Hopkins(1927)21 AJIL 160; Way (1929)23 AJIL 466;cited in Ibid.,1455Neer(1926)IV RIAA 60,p6156 SCHILL STEPHEN, THE MULTILATERALIZATION OF INTERNATIONAL INVESTMENT LAW.

MEMORANDUM ON BEHALF OF THE APPELLANT

21 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

later retracted by the State. In this sense, legitimate expectations operates on

lines of

ii. The second category deals with the state’s existing legal

framework in the form of legislations, rules, regulations, contractual

undertakings, and executive grants such as licenses.

v. Arbitral decisions that have admittedly interpreted legitimate expectations largely

in favour of the foreign investor.57

vi. The other key exclusion is the ground of ‘arbitrariness’ to challenge regulatory

measures of the host State. Protection against arbitrariness of a regulatory

measure has been recognized in the narrower customary international law

standard58 as well as the autonomous FET standard,59 indicating the importance of

this standard of protection even after taking into account the regulatory

obligations of the State.

vii. The Occidental tribunal explicitly renounced the need of a competitive

relationship in the same business sector to establish like circumstance.60

viii. In Alpha Projektholding v. Ukraine the tribunal stated that discrimination could

arise de jure or de facto.61

ix. In particular, the Government’s action to freeze tariff, its inability to fulfill its

promises it had promised to encourage foreign investment, its inefficiency to

regulate on high power purchasing cost, bill collection inefficiencies, its changes

to the regulatory regime without Claimants' consent, by failing to enforce its laws

that require NAEI’s customers to pay for the electricity they consume, by failing

to implement new laws designed to reduce theft of electricity, all constitute

violations of the fair and equitable treatment required under international law.

57CMS v. Argentina; National Grid v. Argentina, UNCITRAL, Award ¶ 176-179 (Nov. 3, 2008) [hereinafter CMS Award].58 International Thunderbird Gaming Corporation v. United Mexican States, UNCITRAL, Arbitral Award (Jan. 26, 2006).59Lauder v. Czech Republic, UNCITRAL, Award, 3 September 2001, ¶ 221; Plama Consortium Limited v. Bulgaria, ICSID Case No. ARB/03/24, Award, 27 August 2008, ¶ 18460Occidental Exploration and Production Company v. Equador, LCIA Case No UN 3467, Final Award on 1st July 2004.61Alpha Projektholding v. Ukraine, ICSID Case No. ARB/07/16, Award, 8 November 2010.

MEMORANDUM ON BEHALF OF THE APPELLANT

22 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

C. THAT THE GOVERNMENT’S ACTIONS CONSTITUTE A VIOLATION OF NATIONAL

TREATMENT UNDER ARTICLE 4(1) OF BIPA:

24. Under Article 4(1) of BIPA,”62A National Treatment obligation arises out of a treaty

obligation. As observed in the Methanex case:

“As to the question of whether a rule of customary international law prohibits a

State, in the absence of a treaty obligation, from differentiating in its treatment of

nationals and aliens, international law is clear. In the absence of a contrary rule

of international law binding on the States parties, whether of conventional or

customary origin, a State may differentiate in its treatment of nationals and

aliens.”63

25. Therefore, any discernible national treatment rule in international law cannot override a

specifically drafted national treatment clause in a BIT. Such clauses, usually state that the

foreign investor will be accorded treatment no less favourable than that which the host

State accords to its own investors.

26. In Al Tamimi v. The State of Oman64, the Tribunal determined that the treatment accorded

to foreign investment and a State’s control over the investment made by its own investors

ought to be “materially different”, in order to attract a violation of the national treatment

protection.

27. The Government’s freezing of tariffs for period has resulted in accumulations of

regulatory assets. Moreover, the government is not allowing the Appellants to scrap Long

term PPAs and enter into short term PPAs in order to save its state entity TPC. There is

discrimination between a foreign entity and a state owned entity. The distributors of other

states have liberty to enter into Short term PPAs with Generators and sell electricity to

consumers at lower costs while Appellant is not allowed to do so. Due to this

discrimination the foreign entity is suffering huge losses.

62Article 4 of India-UK BIT 1994.63Methanex Corporation v. United States (Final Award of the Tribunal on Jurisdiction and Merits, 3 Aug. 2005) [Methanex] at Part IV – Chapter C, para. 2564ICSID Case No. ARB/11/33

MEMORANDUM ON BEHALF OF THE APPELLANT

23 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

D. THAT THE GOVERNMENT’S ACTIONS CONSTITUTE A VIOLATION OF UMBRELLA

CLAUSE UNDER ARTICLE 3(3) OF BIPA:

28. Under Article 3(3)65 of BIPA: Breach by a State to observe its obligations under contract

can amount to a treaty breach by virtue of the aforementioned “observance of obligations

clause” in the BIT. As these clauses transform contract claims into treaty claims, they are

known as umbrella clauses.

29. These clauses serve as a mechanism to enforce obligations undertaken by the Host State

and are often construed as catch- all provisions that arguably enable investors to bring a

pure investment contract claim under the breach of a BIT.66

30. In his Hague lecture, Prosper Weil presented the idea that an investment treaty would

transform a mere contractual obligation between state and investor into an international

law obligation, in particular if the treaty included a clause obliging the state to respect

such contract.67

31. At the same time as the SGS brought the claim against Pakistan, it brought another case

against the Philippines.68. The Tribunal examined the interpretation of the clause in the

SGS v. Pakistan decision and although it recognized that the language of the clause was

not the same, it found the decision unconvincing69 and highly restrictive.70 However,

while the Tribunal took a wider reading of the scope of the umbrella clause, than the SGS

v. Pakistan Tribunal, it required at the end that if the contract vests exclusive jurisdiction

over disputes arising under its terms to another tribunal (domestic court or a contractual

arbitral tribunal) then this tribunal has the primary jurisdiction.

65Article 3(3) of BIPA.

66Schill, Stephen W., “Enabling Private Ordering: Function, Scope and Effect of Umbrella Clauses in International Investment Treaties.” 18 Minn. J. Int’l L.1 (2009), p. 35.67Recueil des Cours III 1969 pp. 132 et seq.68 SGS SociétéGénérale de Surveillance, S.A. v. the Republic of the Philippines, ICSID case No. ARB/02/6, Decision on Jurisdiction, 29 January 2004 available at www.worldbank.org/icsid/cases/SGSvPhil-final.pdf.69Ibid. at para. 125.70Ibid. at para.119 and 120.

MEMORANDUM ON BEHALF OF THE APPELLANT

24 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

32. The Tribunal in Sempra Energy International v. Argentina71 recognized that these

contractual claims were also treaty claims and was reinforced in its view by the fact that

“the Treaty also includes the specific guarantee of a general ‘umbrella clause’, [such as

that of Article II(2)(c)], involving the obligation to observe contractual commitments

concerning the investment, creates an even closer link between the contract, the context

of the investment and the Treaty”.72

33. The Partial Award in Eureko B. V. v. Poland73, Noble Ventures, Inc v. Romania74was the

question of whether contractual obligations also amounted to international obligations by

virtue of the “umbrella clause” in the US-Romania BIT. The tribunal held that the BIT

intended to create obligations and “obviously obligations beyond those specified in other

provisions of the BIT itself” and by doing so it referred clearly to investment contracts. It

also noted that such an interpretation was also supported by the object and the purpose

rule “a clause that is readily capable of being interpreted in this way and which would

otherwise be deprived of practical applicability is naturally to be understood as protecting

investors also with regard to contracts with the host State generally in so far as the

contract was entered into with regard to an investment”.

34. Herein, the foreign entity is unable to fulfill its obligations under contract due to hurdles

put by government regulations and therefore the government is in violation of “umbrella

clause”.

E. THE GOVERNMENT’S ACTIONS CONSTITUTE AN EXPROPRIATION IN VIOLATION OF

ARTICLE 5 OF BIPA:

Appellants allege indirect expropriation under Article 575 of BIPA.

35. The UNCTAD study on ‘Taking of Property’ has described the term creeping

expropriation:

71 Sempra Energy International v. Republic of Argentina, ICSID case No ARB/02/16, Decision on Objections to Jurisdiction, 11 May 2005.72Idem, para. 101.73Eureko B.V. v. Poland, Partial Award, and 19 August 2005.74 Noble Ventures, Inc. v. Romania, Award October 12, 2005 ICSID Case No ARB/ 01/11.75Article 5 of BIPA.

MEMORANDUM ON BEHALF OF THE APPELLANT

25 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

This may be defined as the slow and incremental encroachment on one or more of the

ownership rights of a foreign investor that diminishes the value of its investment. The

legal title of the property remains vested in the foreign investor but the investor’s rights

of use of the property are diminished as a result of the interference by the state.76

36. One of the most exhaustive definitions of indirect expropriation was laid out by the

tribunal in Metalclad v. Mexico:

“Expropriation includes not only open, deliberate and acknowledged takings of

property such as outright seizure, formal or obligatory transfer of title in favour of the

Host State, but also covert or incidental interference with the use of property which has

the effect of depriving the owners, in whole or in significant part of the use or

reasonably-to-be-expected economic benefit of property even if necessarily to the

obvious benefit of the Host State.”77

37. Indirect expropriation involves total or near-total deprivation of an investment but

without a formal transfer of title or outright seizure.78 A classic definition for the same

was given by the Starrett Housing79and in Perenco80.

38. A necessary condition for indirect expropriation is “the neutralisation of the use of the

investment”.81 In order to qualify as indirect expropriation, the measure must constitute a

deprivation of the economic use and enjoyment, as if the rights related thereto, such as

the income or benefits, had ceased to exist.”

76UNCTAD (n.41) 11, 12.77ICSID Case no. ARB/(AF)/ 97/178Burlington Resources Inc. v. Republic of Ecuador (ICSID Case No. ARB/08/5), Decision on Liability, 14 December 2012, para. 396.79Starrett Housing v. Iran, Interlocutory Award No. ITL 32-24-1, 19 December 1983, 4 Iran-United States Claims Tribunal Reports 122, p. 15480Perenco Ecuador Ltd. v. The Republic of Ecuador and EmpresaEstatalPetróleosdel Ecuador (Petroecuador) (ICSID Case No. ARB/08/6)81 El Paso v. Argentina, CMS v. Argentina

MEMORANDUM ON BEHALF OF THE APPELLANT

26 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

39. Creeping expropriation is a form of indirect expropriation and is defined as the

incremental encroachment on one or more of the ownership rights of a foreign investor

that eventually destroys (or nearly destroys) the value of investment, or deprives him or

her of control over the investment. A series of separate State acts, usually taken within a

limited time span, are then regarded as constituent parts of the unified treatment of the

investor or investment.82

40. By requiring Appellant to distribute electricity below its actual costs, particularly after

disadvantaging appellant by freezing tariffs for period is resulting in accumulations of

regulatory assets. Power purchase cost has increased threefold and every unit of power

supplied add to distributor’s debt burden because the regulated power tariff charged to

the consumer does not reflect the actual cost of power purchase. Cash flow problem is

affecting distribution Company’s ability to buy power and to invest in infrastructure

maintenance leading to supply disruptions.

41. The Government is engaging in a "creeping expropriation" of NAEI through this

accumulated debt, which is usurping the investment and depriving Appellants of the

value of their investment. Through the actions described above, the Government has

violated Article 5 of BIPA and the Government is continuing to destroy the value of

NAEI of cash flows and revenues. Cash flow problem is affecting distribution

Company’s ability to buy power and to invest in infrastructure maintenance leading to

supply disruptions.

3. WHETHER STATE GOVERNMENT HAS ANY OTHER OPTION TO

DEAL WITH THE SITUATION RATHER THAN CANCELLING THE

LONG TERM AGREEMENT?

1. The Appellant most humbly submits that the PPA entered into by the previous

government obligate the appellant to pay a higher purchasing cost than the market price

82 Expropriation, UNCTAD Series on Issues in International Investment Agreements II- A Sequel (2012) p. 11

MEMORANDUM ON BEHALF OF THE APPELLANT

27 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

thereby leading to increasing regulatory assets. Thereby the most viable option is to

cancel the same and enter into cost efficient short duration PPAs.

2. However, the state government could also work towards the prima facie requirement of

making an integrated strategy for appropriate pricing of electricity which is being sold by

generating stations which can be achieved through Revision of Tariff in accordance with

Section 61, it may also order pooling of the current source along with a cheaper source to

make the power purchasing cost affordable in the larger public interest.

3. The government may also work towards achieving technological development of

distribution infrastructure as the current infrastructure is providing huge losses due to

theft etc., the government may also the government may order Renovation,

Modernization or Decommissioning of costly generating plants and replacing them with

more efficient and cost effective plants or doing an Auction of such plants through a PPA

which shall in a long run reduce the cost incurred by such generating units when

compared with the present costs thereby reducing the price to be paid by the Appellants.

I. REVISION OF TARIFF IN ACCORDANCE WITH SECTION 61

4. It is hereby submitted that Section 61 provides for setting Terms and Conditions for

determination of tariff, and provides to be guided by the factor that the tariff

progressively reflects the cost of supply of electricity,83 and safeguards the consumer’s

interest along with recovery of the cost of electricity at a reasonable manner.84

5. In the present case the rate of increase between the power purchasing cost and the

consumer tariff is 10:3 which has led to a further increase in the debt than could have

been anticipated.

83 Section 61(g), The Electricity Act 200384 Section 61(d), The Electricity Act 2003

MEMORANDUM ON BEHALF OF THE APPELLANT

28 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

6. The State Government should thereby work towards bridging the gap by:

a) Revising the Tariff in the PPA in a manner as prescribed by the Electricity Act;85

b) Instead of freezing the tariffs provide for a tariff regime in accordance with the multi-

year principles;86

c) Making the Retail Tariff reflect the actual costs incurred;87

d) Introducing the concept of Peak Hour Tariffs through time-of-the-day metering and

differential tariffs;88

e) Setting up a separate committee to finalize a compensatory tariff to be made

applicable until the hardship is lessened or removed;89

II. POOLING THE CURRENT SOURCE OF FUEL WITH A CHEAPER FUEL TO

MAKE POWER PURCHASING COST AFFORDABLE IN LARGER PUBLIC

INTEREST

7. It is most humbly submitted that for the purpose of ensuring that the power is generated

at a reasonable rate the state government may pass a policy ordering the introduction of

pooling the power generated within the PPA along with power generated at a cheaper

rate, this shall lead to the power purchasing cost being maintained at an affordable rate.

8. The state government is required to intervene as the appellant is facing huge losses due to

such increasing rate of power purchasing cost, such an intervention has been upheld by

the Supreme Court in the case of Essar Steel Limited v. Union of India and ors,.90whereby

a policy providing for guidelines to pool gas to provide a uniform delivered price was

85 Gujarat Urja Vikas Nigam Ltd. v. Solar Semiconductor Power company India Pvt. Ltd. and ors., Supreme Court, Civil Appeal No. 6399 of 201686 Section 61 (f), The Electricity Act 200387 Delhi Electricity Regulatory Commission, Approach Paper on Tariff Rationalization, February 2018, http://www.derc.gov.in/Public%20Notice/Tariff%20Rationalization/Approach%20Paper%20on%20Tariff%20Rationalisation.pdf88 Amulya K.N. Reddy and Gladys D. Sumithra, Karnataka’s Power Sector: Some Revelations, Economic and Political Weekly, Vol. 32, No. 12 (Mar. 22-28, 1997), pp. 585-60089 Adani Power Limited vs. Uttar Haryana Bijli Vidyut Nigam Limited and ors;Coastal Gujarat Power Limited vs Gujarat Urja Vikas Nigam Limited and Ors.90 Essar Steel Limited v. Union of India and ors., Civil appeal no. 4609 of 2009 as decided on 19th April 2016

MEMORANDUM ON BEHALF OF THE APPELLANT

29 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

held to be valid,91 thereby providing a uniform average pooled price within long term

contracts.

9. The same can be made applicable under the present case for the purpose of providing an

affordable cost for purchasing power from the respondent, i.e. the generating company.

III. TECHNOLOGICAL DEVELOPMENT OF DISTRIBUTION INFRASTRUCTURE

10. It is hereby submitted before the honorable court that along with the high power

purchasing cost a major factor for increase in aggregate technical and commercial losses

has been Power Thefts and Bill Collection inefficiencies and lack of monitoring

infrastructure.

11. The State Government should thereby work towards developing and timely implementing

technologies which may lead to reducing the losses faced by the appellants. The same can

be achieved by-

a. Providing SCADA,92 Wireless SCADA93 or MATLAB,94 systems for

distribution utilities- These technologies in the power sector provide for efficient

controlling and monitoring and are highly beneficial for large scale industries

with a requirement of a high monitory health.95 These softwares can be used for

the purpose of gathering data from devices, aggregating and organizing the data

91 Policy decision dated 06.03.200792 Santosh B Belekar et. al., PLC and SCADA based distribution and control, Multidisciplinary Journal of Research in Engineering and Technology Volume 1, Issue 1 (April 2014) Pg. 105-110;

SCADA is The Supervisory Control And Data Acquisition is an industrial control system which organizes multiple technologies thereby allowing the processing, gathering and monitoring data together at the same time and then sending the information regarding the information collected to the control system where the same shall be analyzed as the real time data thereby leading to efficiently acknowledging the faults and quick solutions being provided. Refer Annexure I ‘SCADA in Distribution’ for a detailed map;

93 WIRELESS SCADA is the application of SCADA through wireless technologies like Radio Microwave or Satellite; Refer Annexure II ‘A practical SCADA Structure’; 94 MATLAB is a further updated version of SCADA95 Poonam Shivaji et al., Wireless SCADA: Review Paper, International Journal for Scientific Research and Development, Volume 5 Issue 11 Pg. 751-753

MEMORANDUM ON BEHALF OF THE APPELLANT

30 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

from local or geographically disperse assets and systems into a consolidated and

well organized solution.96

A consolidated version of the plan being proposed has been perused as being marked

Annexure I and Annexure II.

b. Providing provision for a High voltage transmission and distribution system-

Keeping in view the techno-economic considerations a high voltage power flows

is required for long distances transmission with minimum possible losses. It shall

prove being an effective method for reducing technical losses, preventing theft of

power, improving the voltage of power being supplied and providing a better

service to the consumers.97

IV. RENOVATION, MODERNIZATION, AUCTION OR DECOMMISSIONING OF

PLANTS PERFORMING BELOW THE ACCEPTABLE STANDARDS OR

COSTLY GENERATING PLANTS

12. It is hereby submitted that the Power purchasing Cost within the agreement is triple the

cost available in the market. Thereby, the State Government may order renovating,

modernizing or decommissioning generating plants which are less cost effective and

highly uneconomical.98

13. Replacing such plants by generating stations located near the fuel sources such as pithead

locations or load centers working in accordance with upgraded acceptable standards shall

in turn help in meeting the objective of cost-benefit analysis.99 The factors which play the

major role in determining and justifying the decommissioning and demolition are

96 Tarun Agarwal, Scada Applications in Power Sector, Edgefx Technologies Pvt. Ltd. Available at https://www.edgefx.in/scada-applications-in-power-system/97 Ankita Gupta et. al., Effectiveness of High Voltage in Distribution System: High Voltage Distribution System, IOSR Journal of Electrical and Electronics Engineering, Volume 1, Issue 5 (July-Aug. 2012), PP 34-38 (www.iosrjournals.org)98 Indronil Roychowdhury, 27 ‘sick’ thermal power plants to be scrapped, Financial Express, November 13 2014; See Also E-REP Market Research Report, Decommissioning Thermal Power Plants in India- Evaluating New Industry Segment & Estimating USD 5 Billion Dollar Opportunity, June 2017 99 Government of India, Ministry of Power, National Electricity Policy (12th February 2005)

MEMORANDUM ON BEHALF OF THE APPELLANT

31 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

Economic, environmental and corporate social responsibility concerns. 100 The right to

electricity at an affordable rate is an integral achievement of socio-economic rights.101

14. This is often termed as the Universal Service Obligation (USO), and to attain this

objective a portion of cheaper sourced power plants should be encouraged as is being

followed in Singapore.102

15. In the United Kingdom under the New Electricity Trading Arrangement Project of 2001

various old plants were closed or collapsed as they delivered a market price which was

too high and newer plants were established with a better efficiency.103

A. Auction of a generating plant through a PPA

16. The state government may order for an auction of the plants performing below the

acceptable level by a process of bidding, it shall provide such plants better maintenance

and operations along with handling the costs incurred for the same in a more efficient

manner, thereby bringing such plants at par with the latest plants which shall further lead

to reducing the purchasing costs charged from the DISCOMS.104

ANNEXURE I - SCADA in Distribution105

100 Edward Malley and David Zarider, Decommissioning Obsolete Power Plants Why Do it Now?; See Also U.S. Energy Information Administration/Electric Power Annual 2009, North American Electric Reliability Corporation 2010 Special Reliability Scenario Assessment: Resource Adequacy Impacts of Potential U.S. Environmental Regulations, October 2010, Credit Suisse, Growth from Subtraction, Impact of EPA Rules on Power Markets, 23 September 2010101Raja Mohan @ Mohan vs The Divisional Engineer on 9 March, 2016102 Delhi Electricity Regulatory Commission, Approach Paper on Tariff Rationalization, February 2018, http://www.derc.gov.in/Public%20Notice/Tariff%20Rationalization/Approach%20Paper%20on%20Tariff%20Rationalisation.pdf103 Luiz T.A. Maurer and Luiz A. Barroso,Electricity Auctions:An overview of efficient practices, A World Bank Study104 Sarita Singh, PPA Auction for stressed power stations gets bids for 2200 MW, The Economic Times (Jun 27, 2018)105Id at 9

MEMORANDUM ON BEHALF OF THE APPELLANT

32 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

ANNEXURE II- A practical SCADA structure106

106Id

MEMORANDUM ON BEHALF OF THE APPELLANT

33 TILA INTERNATIONAL MOOT COURT COMPETITION ON ENERGY 2018

PRAYER

Wherefore in the light of the Questions presented, pleadings submitted and Authorities

Cited, the Hon’ble Supreme Court may be pleased to:

1. Terminate the Long term Power Purchase Agreement for the reasons pleaded herewith

2. Declare that North Atlantic Inc is correct in approaching UK Government to seek relief under

the India-UK Bilateral Investment Promotion and Protection Treaty

3. Direct Concerned Government to exercise any other option that this Hon’ble Court may deem

fit in the best commercial interests of the Appellants

AND/OR

Pass any other order, direction or relief that it deems fit in the interest of Justice, Equity and

Good Conscience.

For this act of kindness, the Appellants shall duty bound forever pray.

Sd/-

(Counsel for the Appellants)

MEMORANDUM ON BEHALF OF THE APPELLANT