APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More. Cindy Bogorad SPIEGEL & MCDIARMID 1333 New Hampshire Ave., NW Washington, DC 20036 (202) 879-4000 November 10, 2005. Electricity Title. Most major overhaul of Federal Power Act and PUHCA since 1935 - PowerPoint PPT Presentation

Transcript of APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

Page 1: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

APPA OVERVIEW OF EPACT APPA OVERVIEW OF EPACT 20052005

Transmission Provisions, Transmission Provisions, Merger Review, and MoreMerger Review, and More

Cindy BogoradSPIEGEL & MCDIARMID

1333 New Hampshire Ave., NWWashington, DC 20036

(202) 879-4000

November 10, 2005

Page 2: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

2 SPIEGEL &

MCDIARMD

Electricity TitleElectricity Title

Most major overhaul of Federal Power Act and PUHCA since 1935

React to various problems—reliability, inadequate transmission, Enron scandals, regulatory gaps, QF machines

Page 3: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

3 SPIEGEL &

MCDIARMD

Recurring ThemesRecurring Themes

Transmission infrastructure

Tradeoffs for PUHCA repeal-enhanced merger review authority

Page 4: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

4 SPIEGEL &

MCDIARMD

Reliability (Reliability (EPAct05 § 1211; FPA EPAct05 § 1211; FPA § 215)§ 215)

Electric Reliability Organization to establish and enforce reliability standards with FERC oversight

Reliability standard “does not include any requirement to enlarge [bulk-power system] facilities or to construct new transmission capacity….”

Page 5: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

5 SPIEGEL &

MCDIARMD

Reliability (cont’d)Reliability (cont’d)

Compliance with standards should prod transmission construction

Recovery of prudently-incurred costs to comply covered in incentive rulemaking

Periodic reports on bulk-power system reliability and adequacy

Page 6: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

6 SPIEGEL &

MCDIARMD

Backstop Siting Authority Backstop Siting Authority (EPAct05 § 1221; FPA § 216)(EPAct05 § 1221; FPA § 216)

DOE to designate National Interest Electric Transmission Corridors- constraints or congestion adversely affects consumers

FERC (or where regional siting compact, DOE) may issue permit with federal eminent domain where state delays/conditions/lacks authority

Page 7: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

7 SPIEGEL &

MCDIARMD

Backstop Siting Authority Backstop Siting Authority (cont’d)(cont’d)

Includes state inability to consider interstate benefits or failure to qualify requestor that does not serve end users

DOE lead agency for federal authorizations/environmental review

Expedition/reporting required

Page 8: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

8 SPIEGEL &

MCDIARMD

Third-Party Finance (EPAct05Third-Party Finance (EPAct05§ 1222)§ 1222)

WAPA/SWPA participation in National Interest Electric Transmission Corridor facilities under certain circumstances

Third party funding, capped at $100 million through 2015

Page 9: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

9 SPIEGEL &

MCDIARMD

Federal Utility RTO Participation Federal Utility RTO Participation (EPAct05 § 1232)(EPAct05 § 1232)

Permits TVA and PMAs to participate in RTOs

Through contracts with protections

Includes ensuring consistency with existing contracts, third-party financing arrangements, and statutory obligations

Page 10: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

10 SPIEGEL &

MCDIARMD

Transmission Infrastructure Rule Transmission Infrastructure Rule (EPAct05 § 1241; FPA § 219)(EPAct05 § 1241; FPA § 219)

Incentive/performance-based rates to benefit consumers by ensuring reliability/reducing delivered power cost by reducing congestion

Promote transmission investment “regardless of the ownership”

Technologies to increase capacity/efficiency

Return that attracts new investment

Page 11: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

11 SPIEGEL &

MCDIARMD

Transmission Infrastructure Transmission Infrastructure Rulemaking – RTO ParticipationRulemaking – RTO Participation

To the extent within jurisdiction, FERC to provide incentives to each transmitting utility and electric utility that joins an RTO/ISO

Ensure any costs recoverable under this subsection may be recovered through utility’s transmission rates or RTO/ISO rates

Page 12: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

12 SPIEGEL &

MCDIARMD

Transmission Infrastructure Transmission Infrastructure RulemakingRulemaking

Little in the way of specifics

All subject to just, reasonable and not unduly discriminatory standard

Flexibility to design rates that get needed transmission built at reasonable cost, e.g., by reducing risks and/or accessing new sources of capital

Page 13: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

13 SPIEGEL &

MCDIARMD

Participant Funding Participant Funding (EPAct05 § (EPAct05 § 1242)1242)

Far less prescriptive than last bill

Permissive to FERC-may approve if just and reasonable, not unduly discriminatory and otherwise consistent with §§ 205/206

Consistent with existing law

Page 14: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

14 SPIEGEL &

MCDIARMD

Native Load Service Obligation Native Load Service Obligation (EPAct05 § 1233; FPA § 217)(EPAct05 § 1233; FPA § 217)

Facilitate planning and expansion of transmission to meet reasonable needs of LSEs

Enable LSEs to secure firm transmission rights (or equivalent financial rights) on a long-term basis for long-term power supply arrangements

Page 15: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

15 SPIEGEL &

MCDIARMD

Native Load Service Obligation Native Load Service Obligation (planning/long-term rights)(planning/long-term rights)

Applies in RTO and non-RTO markets (except ERCOT)

Required rulemaking to implement within organized markets

Page 16: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

16 SPIEGEL &

MCDIARMD

Native Load Service Obligation Native Load Service Obligation (existing rights)(existing rights)

LSE is entitled to use existing firm rights or equivalent financial rights to meet service obligation

Preserves resource-to-load rights existing as of date of enactment

Whether through ownership, GFA, or OATT service agreement

Consistent with OATT

Page 17: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

17 SPIEGEL &

MCDIARMD

Native Load Service Obligation Native Load Service Obligation (existing rights)(existing rights)

Not just TO native load

LSEs include everyone in this room; not just those serving enduse load

Include joint action agencies—obligation under long term contracts to municipal utilities that serve endusers

Page 18: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

18 SPIEGEL &

MCDIARMD

Native Load Service Obligation Native Load Service Obligation (existing rights)(existing rights) N/A to PJM, NYISO, ISO-NE, and

CAISO (except certain CA rights protected against conversion)

Not directly applicable to MISO, but FERC must take policies into account when MISO changes FTR allocation methodology

Applies to SPP and other new RTOs

Separate added protections for PNW

Page 19: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

19 SPIEGEL &

MCDIARMD

PUHCA Repeal TradeoffsPUHCA Repeal Tradeoffs

PUHCA, by active and passive restraints, largely restricted utilities to compact vertically integrated entities

PUHCA’s repeal will open up industry to consolidation and fragmentation in ways we can’t imagine

Page 20: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

20 SPIEGEL &

MCDIARMD

Tradeoffs - Mergers (Tradeoffs - Mergers (EPAct05 EPAct05 § 1§ 1289; amending FPA 289; amending FPA §§ 203) 203)

Expanded/clarified authority to review generation acquisitions and holding company mergers

But FERC must act within 180 days, plus 180-day extension period

Page 21: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

21 SPIEGEL &

MCDIARMD

Merger Review (cont’d)Merger Review (cont’d)

Maintains traditional “consistent with the public interest” test

Added test: not result in cross-subsidization of non-utility or pledge/encumbrance of utility assets unless consistent with the public interest

Page 22: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

22 SPIEGEL &

MCDIARMD

Qualifying Facilities (Qualifying Facilities (EPAct05 EPAct05 § 1§ 1253;253; amending PURPA § 210) amending PURPA § 210)

Eliminate restrictions on QF ownership

No obligation to purchase from new QF unless meets new requirements

No mandatory purchase obligation for new contracts if QF has non-discriminatory access to RTO/ISO with competitive wholesale market, or comparable markets

Preservation of existing QF contracts

Page 23: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

23 SPIEGEL &

MCDIARMD

Odds and EndsOdds and Ends

Eliminate 60-day wait for Section 206 refunds

Non-RUS-financed coops with less than 4 million MWh sales removed from FERC jurisdiction

Sense of Congress that FERC should consider state objections to LICAP

Page 24: APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More

24 SPIEGEL &

MCDIARMD

Bottom lineBottom line

Many, many rulemakings

Expanded FERC regulatory and enforcement tools

Costs won’t go down

Life won’t get less complicated