Anvil Sample Problem
-
Upload
gpskumar22 -
Category
Documents
-
view
222 -
download
6
description
Transcript of Anvil Sample Problem
Anvil International, Piping & Pipe Hanger Design and Engineering 5www.anvilintl.com
H-4
H-5
BGate
Valve
H-6
H-8
H-3
5'-0"
15'-0"
7'-0"
2'-0"
5'-0"
10'-0"
40'-0"
5'-0"
5'-0"
5'-0"
2'-0"
2'-0"
3'-0"
8'-0"
5'-0"
12" Pipe5'-0"
5'-0"
1'-0"11'-0"
2'-0"
3'-0"
A
4'-0"
H-2
H-1
Check
Valve 6'-0"
H-7
6" Pipe
4'-0"
5'-0"
3'-6"
12'-0"
12'-0"
4'-0"
To SuitH-9
C
GateValve
45°
three fourths the suggested maximum span shown in the table
on the previous page.
In considering the vertical section of the pipe on which H-3 and
H-4 are shown, it should first be noted that this section of the
pipe could be supported by one hanger rather than two as
indicated. Two hangers will certainly provide greater stability
than will a single hanger. Another deciding factor as to whether
one hanger or a multiple hangers should be used is the
strength of the supporting steel members of the structure. The
use of two hangers will permit the total riser weight to be
proportioned to two elevations of the structure, avoiding the
concentration of all the riser load at one building elevation.
The locations for hangers H-5 and H-6 are governed by the
suggested maximum span as well as the position of the
concentrated valve weight. Consequently, H-6 has been
located adjacent to the valve, and H-5 at a convenient location
between the valve and the 12 inch riser.
The location of hanger H-7 will be determined by calculation to
satisfy the condition that no pipe load is to be applied to
terminal connection C. It is obvious that by moving the hanger
along the 12 foot section of pipe, the amount of load on
connection C will vary. One support location exists where the
entire section will be "balanced", and the load at C equal to
zero.
The calculations to determine the exact location of H-7 are
shown in the section entitled "Hanger Load Calculation".
NOTE:
Allowable load at connection A is 500 lbs.
Allowable load at connection B and C is zero.
All bends are 5 diameter bends.
All elbows are L.R. Ells.
Operating temperature is 1,050°F.
All pipe is Sch. 160 A 335 P12.
FIGURE 1 – SAMPLE PROBLEM
The spans in table are in accordance with MSS Standard
Practice SP-69. They do not apply where concentrated
weights such as valves or heavy fittings or where changes in
direction of the piping system occur between hangers.
For concentrated loads, supports should be placed as close
as possible to the load in order to minimize bending stresses.
Where changes in direction of the piping of any critical system
occur between hangers; it is considered good practice to keep
the total length of pipe between the supports less than 3⁄4 the
full spans in table below.
When practical, a hanger should be located immediately
adjacent to any change in direction of the piping.
SAMPLE PROBLEM
In the sample problem (Figure 1) seven supports are shown on
the 12 inch line, and two on the 6 inch pipe.
Note that the hanger H-1 has been placed adjacent to the
valve weight concentration. The proximity of the hanger to the
valve is helpful in keeping the load at terminal connection A to
a minimum. Also, the bending stresses induced in the pipe by
the valve weight are kept to a minimum.
The selection of the location for hanger H-2 entails a change in
direction of the pipe between two hangers. In order to avoid
excessive overhang of the pipe between hangers H-1 and H-2,
the length of pipe between these hangers is made less than
THE DESIGN OF PIPE HANGERS