Form I &IA and Consolidated statement Page 1 APPENDIX- I (See Paragraph - 6) FORM 1 Sr. No. Item Details 1 Name of the Project/s 3/1& D-3/2 ,Kagal-Hatkanangale Five Star 2 S. No in the Schedule 8 (a) 3 Proposed capacity/area/length/tonnge to be handled/command area/lease area/number of wells to be drilled Total Plot Area of the Project: 62,491 Sq. mt. 4 New/Expansion/Modernization New 5 Existing capacity/Area etc. Total Plot Area: 62,491 Sq. mt. Built up Area: - 24381.66 Sq.mt. 6 Category of Project i.e. ‘A’ or ‘B’ B Category Project 7 Does it attract the general condition? If Yes please Specify. Not Applicable 8 Does it attract the specific condition? If yes please specify. Not Applicable 9 Location Plot/survey/Khasra No D-3,D-3/1& D-3/2 , Five Star M.I.D.C Village Tehsil Hatkanangale District Kolhapur State Maharashtra 10 Nearest railway station/airport along with distance in kms Kolhapur Railway junction (30 km SW) 11 Nearest town, city, District Headquarters along with distance in Kolhapur (25 Km) & 9Km From the 12 Village panchyats Zilla Parishad, municipal corporation, Local body (Complete postal addresses with telephone nos. to be given) Kagal-Hatkanangale Company Name, Address, City, State - PinCode xxx (specify if MIDC) yyyy aaa, bbb, ccc, ddd with phone numbers survey No 288/4 Khed Khed Pune

description

sample filled form

Transcript of Annexure II-Sample Filled Form

Page 1: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 1

APPENDIX- I

(See Paragraph - 6)

FORM 1

Sr. No. Item Details

1 Name of the Project/s “M/s. Indus Ferrotech Ltd.” At D-3,D-

3/1& D-3/2 ,Kagal-Hatkanangale Five Star

industrial Area,Dist-kolhapur

( Maharashtra)India.

2 S. No in the Schedule 8 (a)

3 Proposed capacity/area/length/tonnge to be

handled/command area/lease area/number

of wells to be drilled

Total Plot Area of the Project: 62,491 Sq. mt.

4 New/Expansion/Modernization New

5 Existing capacity/Area etc. Total Plot Area: 62,491 Sq. mt.

Built up Area: - 24381.66 Sq.mt.

6 Category of Project i.e. ‘A’ or ‘B’ B Category Project

7 Does it attract the general condition? If Yes

please Specify.

Not Applicable

8 Does it attract the specific condition? If yes

please specify.

Not Applicable

9 Location Kagal-Hatkanangale Five star MIDC

Plot/survey/Khasra No D-3,D-3/1& D-3/2 , Five Star M.I.D.C

Village Talandage

Tehsil Hatkanangale

District Kolhapur

State Maharashtra

10 Nearest railway station/airport along with

distance in kms

Kolhapur Railway junction (30 km SW)

11 Nearest town, city, District Headquarters

along with distance in

Kolhapur (25 Km) & 9Km From the

National Highway 4 (Mumbai –Banglore)

12 Village panchyats Zilla Parishad, municipal

corporation, Local body (Complete postal

addresses with telephone nos. to be given)

D-3, D-3/1& D-3/2, Kagal-Hatkanangale

Five Star industrial Area, Kolhapur.

Company Name, Address,City, State - PinCode

xxx (specify if MIDC)

xxx

yyy

yyyy

aaa, bbb, ccc, ddd with phone numbers

jjj

zzz

survey No 288/4

Khed

Khed

Pune

Page 2: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 3

24 Forest land involved (hectares) Not Applicable

25 Whether there is any litigation pending

against the project and/or land in which the

project is propose to be set up?

(a)Name of the Court.

(b)Case No.

(c) Orders /Directions of the court, if any

and its relevance with the proposed Project.

Not Applicable

Screening Category : 8(a) to sub category B

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sr.

No.

Information/Checklist

confirmation

Yes

/

No

Details thereof (with approximate quantities / rates, wherever

possible) with source of information data

1.1 Permanent or

temporary charge in

land use, land cover or

topography including

increase in intensity of

land use (with respect

to local land use plan)

No No change in Land Use

1.2 Clearance of existing

land, vegetation and

building?

No Land is leveled.

No demolition of building involved.

No cutting of trees.

1.3 Creation of new land

uses?

No --

1.4 Pre-construction

investigation e.g. bore

houses, soil testing?

Yes Geotechnical Investigation is already conducted.

1.5 Construction works?

Yes 62% construction work done out of 24,381.66 Sq.mt sanctioned

built up area.

1.6 Demolition works?

No There is no demolition work.

1.7 Temporary sites used

for construction works

or housing of

construction workers?

No No residential workers or labor camp.

1.8 Above ground

building, structures or

earthworks including

linear structures, cut

Yes Above ground building, structures and Excavation work only for

the construction of footings & area grading.

Page 3: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 4

Sr.

No.

Information/Checklist

confirmation

Yes

/

No

Details thereof (with approximate quantities / rates, wherever

possible) with source of information data

and fill or excavations

1.9 Underground works

including mining or

Tunneling?

No --

1.10 Reclamation works?

No. --

1.11 Dredging?

No --

1.12 Offshore structures?

No --

1.13 Production and

manufacturing

processes?

Yes Company proposed production capacity –Fettling, Machining,

painting of jobs (1, 00,000 nos.) & surface treatment (Mn

Phosphating(surface treatement),Electroless nickel plating =5000

nos/m),

1.14 Facilities for storage of

goods or materials?

Yes Goods and Material is stored in proper storage facility.

1.15 Facilities for treatment

or disposal of solid

waste or liquid

effluents?

Yes A) During Construction

phase:

• Non Hazardous waste generated from the construction is reused

predominantly for filling and compaction of site. Empty gunny

bags are returned to suppliers. Scrap Mild steels bars/ general

mild steel items to send back for rerolling.

• There is no labor camp. The day workers are served by regular existing sewage treatment plant.

• Hazardous waste was not generated during construction phase

B) During Operation Phase:

• Total solid waste: 166 kg/day

• Biodegradable waste: 116 kg/day. (will be handled over to

authorized vendors for disposal)

• Non-biodegradable waste: 50 kg/day. will be handed over to

authorized contractors.

Use of dried STP sludge as manure.

Non Hazardous Waste :

Sr.

No.

Type Quantity UoM Disposal

1 Griding

/Fettling

powder

25 MT/M Sale

2. Griding

wheel

2000 nos. Sale

3. Shot

blasting

dust

25 MT/M Sale

4. CI boring

/MS

Turning

300 MT/M Sale

Page 4: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 5

Sr.

No.

Information/Checklist

confirmation

Yes

/

No

Details thereof (with approximate quantities / rates, wherever

possible) with source of information data

Hazardous waste Details :

Sr.

No.

Item no.

as per

HW

Schedule

Type of

waste

Quantity Disposal

1. 21.1 Paint

sludge

30MT/A CHWTSDF

2. 5.2 Hand

gloves,oil

soked

rags/cotton

3.7MT/A CHWTSDF

3

5.1 Used

oil/spent

oil

15 KL/A Authorised

reprocesser/recycler

4 33.3 Discarded

containers

6000

nos/A

CHWTSDF

5 12.2 Alkali

residue

1.44MT/A CHWTSDF

6 14.1 Nitrite

containing

sludge

7MT/A CHWTSDF

7 12.3 Spaint bath

sludge

3.6MT/A CHWTSDF

8 12.5 Phosphate

sludge

6.2MT/A CHWTSDF

Sewage:

• Sewage generation : 24 m3/day

• Capacity of STP (CMD): 25 m3/day

• STP Technology: MBR

Effluent:

• Effluent generation: 18 m3/day

• Capacity of ETP (CMD): 4 m3/Hr

• Capital Cost: Rs 80 Lakh

O & M Cost: Rs 11 Lakh / Year

1.16 Facilities for long term

housing of operational

workers?

No -

1.17 New road, rail, or sea

traffic during construction or

operation?

No -

1.18 New road, rail, air

waterborne or other

transport infrastructure

including new or

No Site is already in Kagal-Hatkanangale Five star MIDC; all

transportation facility is easily available.

xxx

Page 5: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 6

Sr.

No.

Information/Checklist

confirmation

Yes

/

No

Details thereof (with approximate quantities / rates, wherever

possible) with source of information data

altered routes and

stations, ports, airports

etc?

1.19 Closure or diversion of

existing transport

routes or infrastructure leading to changes in

traffic Movements?

No No Diversion or closer of existing transport routes or any other

infrastructures to changes.

1.20 New or diverted

transmission lines or

pipelines?

No

-

1.21 Impoundment,

damming, culverting,

realignment or other

change o the hydrology

of watercourses or

aquifers?

No

-

1.22 Stream crossings? No -

1.23 Abstraction or transfers

of water from ground or surface waters?

No For Construction: MIDC During this proposed construction period we may need Water 20 KLD. Total consumption will be within consented

quantity.

For Operational Phase: MIDC

• Daily fresh water requirement = 47 m3/day

• Recycled water reused = 40 m3/day

One time water requirement 87 m3/day

(Source of water is MIDC)

1.24 Changes in water

bodies or the land

surface affecting

drainage or runoff?

No Water drains of appropriate capacity will be designed.

1.25 Transport of personnel

or materials for

construction, operation

or decommissioning?

Yes Transportation of Raw material and final product

Mainly, will be by road. Within factory premises, all

Raw material will be safely transported by carboys

Thorough trolleys.

The movement of vehicular traffic would be restricted

to only during receipt of materials and dispatches of

Materials. Hence the impact due to noise pollution will be occasional. Precautions will be taken to reduce the impact of

the vehicular movement by trying to avoid the vehicular trips

during peak hours.

1.26 Long-term dismantling

or decommissioning or

restoration works?

No --

1.27 Ongoing activity

during

decommissioning

which could have an

impact on the

environment?

No --

Page 6: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 7

Sr.

No.

Information/Checklist

confirmation

Yes

/

No

Details thereof (with approximate quantities / rates, wherever

possible) with source of information data

1.28 Influx of people to an

area in either

temporarily or

permanently?

Yes Total Manpower is on project site 665 nos. including contract

workers and staff.

1.29 Introduction of alien

species?

No --

1.30 Loss of native species

or genetic diversity?

No --

1.31 Any other actions? No --

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or ion short

supply):

Sr.

No. Information/Checklist confirmation

Yes /

No

Details thereof (with approximate

quantities / rates, wherever possible) with

source of information data

2.1 Land especially undeveloped or

agricultural land (ha)

No --

2.2 Water (expected source & competing

users) unit : KLD

Yes During Construction Phase :

During this small construction period we

may need water 20 KLD. Consumption will

be within consented quantity.

During Operational Phase -

Total Daily Water Requirement: 87 m3/ day.

Fresh water intake :

For Domestic : 13 m3/ day.

For Processing: 23 m3/ day.

For Gardening : 34 m3/ day.

(When sewage Treatment Plants is run in the

full-fledged condition treated water will be reused for Gardening. So that extra load on

the MIDC water supply system is reduced)

2.3 Minerals (MT) No --

2.4 Construction material – stone,

aggregates, and / soil (expected source

– MT)

Yes For proposed Building structures, estimated

Construction material like – Cement, Sand,

Grits, Bricks, Steel, etc. shall be purchased

from the local vendors.

2.5 Forests and timber (source – MT) No Recycled shuttering & Carpentry kind of material will be used for Proposed structures

2.6 Energy including electricity and fuels

(source, competing users) Unit: fuel During Operational Phase -

Page 7: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 8

Sr.

No. Information/Checklist confirmation

Yes /

No

Details thereof (with approximate

quantities / rates, wherever possible) with

source of information data

(MT), energy (MW) Source: MSEDC

Connected

Load

2.5 MVA

Maximum

Demand

1 MVA

DG Set 1.5 MVA

2.7 Any other natural resources (use

appropriate standard units)

No --

3. Use, storage, transport, handling or production of substances or materials, which would be

harmful to human health or the environment or raise concern about actual or perceived risks to

human health.

Sr.

No. Information/Checklist confirmation

Yes /

No

Details thereof (with approximate

quantities / rates, wherever possible)

with source of information data

3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human

health or the environment (flora, fauna, and

water supplies)

Yes Construction : Minimum amount of waste will be

generated during construction which

will be confined within existing

building structure

Operational Phase : Hazardous waste generated from

Production process will be send to CHWTSDF.

3.2 Changes in occurrence of disease or affect

disease vectors (e.g. insect or water borne

diseases)

No Construction only for short

duration with small number of

Workers.

3.3 Affect the welfare of people e.g. by

changing living conditions?

No Positive effect in the Socio economic

conditions.

3.4 Vulnerable groups of people who could be

affected by the project e.g. hospital

patients, children, the elderly etc.,

No --

3.5 Any other causes No --

4. Production of solid wastes during construction or operation or decommissioning

(MT/month)

Sr.

No.

Information/Checkli

st confirmation

Yes /

No

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

4.1 Spoil, overburden or

mine wastes

Yes The Top soil will be used for gardening and other for refilling

the plinth.

4.2 Municipal waste

(domestic and or

commercial wastes)

Yes Construction Phase : There is no labor camp. The day workers waste will be taken

care of in the existing premises.

Page 8: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 9

Sr.

No.

Information/Checkli

st confirmation

Yes /

No

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

Operation Phase:

Sr.

No.

Type Quantity UoM Disposal

1. Griding

/Fettling

powder

25 MT/M Sale

2. Griding

wheel

2000 nos. Sale

3. Shot

blasting

dust

25 MT/M Sale

4. CI boring

/MS

Turning

300 MT/M Sale

4.3 Hazardous wastes (as

per Hazardous waste Management Rules)

Yes Construction Phase: Hazardous waste was not generated from the construction phase.

4.4 Other industrial

process wastes

Yes Sr.

No.

Item no.

as per

Type of

waste

Quantity Disposal

1. 21.1 Paint

sludge

30MT/A CHWTSDF

2. 5.2 Hand

gloves,oil soked

3.7MT/A CHWTSDF

3

5.1 Used

oil/spent

oil

15 KL/A Authorised

reprocesser/recycler

4 33.3 Discarded

containers

6000

nos/A

CHWTSDF

5 12.2 Alkali

residue

1.44MT/A CHWTSDF

6 14.1 Nitrite

containing

sludge

7MT/A CHWTSDF

7 12.3 Spaint 3.6MT/A CHWTSDF

Page 9: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 10

Sr.

No.

Information/Checkli

st confirmation

Yes /

No

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

bath sludge

8 12.5 Phosphate

sludge

6.2MT/A CHWTSDF

4.5 Surplus product No --

4.6 Sewage sludge or

other sludge from

effluent treatment.

Yes Dried sludge from STP will be used as manure for the plants.

4.7 Construction or

demolition wastes.

Yes Only construction wastes. Solid waste would be

mainly due to excavation in the form of rubble and

Soil. This soil and rubble will be reused for leveling

of project site.

4.8 Redundant machinery or equipment.

No --

4.9 Contaminated soils or

other materials.

No --

4.10 Agriculture wastes. No --

4.11 Other solid wastes. No --

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sr.

No.

Information/Checklist

confirmation

Yes /

No

Details thereof (with approximate quantities

/ rates, wherever possible) with source of

information data

5.1 Emissions from combustion of fossil

fuels from stationary or mobile

sources

Yes D.G. Sets will be provided only in case of

power failures during operational phase. The

Pollutants like SO2 that may arise from

emissions from D.G. Sets will be discharged

through vent of proper height.

5.2 Emissions from production processes Yes Nominal emissions are expected from process

plant while operation, as and When operated.

Approval of CTE & CTO will be taken from

MPCB

For pollution control, we will provide the

scrubber.

5.3 Emissions from materials handling

including storage or transport

Yes

The earth moving machineries and dumpers

will be used. Pollution under control ( PUC)

will be ensured .Proper and safe storage as per

the regulation shall be practiced & certificates

are made mandatory

5.4 Emissions from construction

activities including plant and

equipment

Yes /

Marg

inal

Nominal emissions expected from earth

moving machineries and dumpers .Pollution

under control (PUC) certificates are Made

mandatory.

Water sprinkling on ground and new

construction will be done at regular intervals to

reduce spreading of dust particles.

5.5 Dust or odours from handling of

materials including construction

materials, sewage and waste

Yes Dust levels are expected during the

construction phase. Proper measures such as

sprinkling of water on the ground and new

Construction will be done at regular intervals

Page 10: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 11

Sr.

No.

Information/Checklist

confirmation

Yes /

No

Details thereof (with approximate quantities

/ rates, wherever possible) with source of

information data

to reduce the Spreading of the dust particles.

Sewage: - It shall be treated in Sewage

treatment Plant.

Effluent: It Shall be treated in Effluent

treatment Plant.

Waste:- Waste is segregated as per category

and disposed off as per Hazardous Waste

(Management, Handling and Transboundry

Movement) Rules, 2008

5.6 Emissions from incineration of waste No --

5.7 Emissions from burning of waste in

open air (e.g. slash materials,

construction debris)

No --

5.8 Emissions from any other sources No --

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr.

No.

Information/Checklist

confirmation Yes / No

Details thereof (with approximate

quantities / rates, wherever possible)

with source of information data

6.1 From operation of equipment e.g.

engines, ventilation plant, crushers.

Yes but

negligible

1. No additional DG set, No Crusher is

planned for construction. No construction

will be undertaken in the night.Use of

equipment generating Noise less than 75

dB (A) in day time.

2. Noise generating constructional

activities would be carried out only during

day time.

3. Installation, use and maintenance of

mufflers on equipment would be ensured.

4. Workers working near noise

construction machinery would be supplied with necessary Personnel protective

Equipments like ear muffs/ear plugs etc. as

per requirement.

6.2 From industrial or similar processes. No --

6.3 From construction or demolition. No There is no demolition activity.

6.4 From blasting or piling. No No blasting will be undertaken.

6.5 From construction or operational

traffic.

Yes During Construction phase: There will be transport of materials for

construction work. Precautions will be

taken to reduce the impact of the vehicular

movement such as vehicular trips will not

be at peak traffic hours.

Operation Phase : The vehicular parking shall be restricted

only in the adequate parking area provided,

which would help in reducing noise and air

pollution due toVehicular

movement. The project proponent has

Page 11: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 12

proposed good tree plantation which will

also help to reduce the noise level and

enhance air quality.

6.6 From lighting or cooling systems. No --

6.7 From any other sources. No --

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea:

Sr.

No. Information/Checklist confirmation

Yes /

No

Details thereof (with approximate

quantities / rates, wherever possible)

with source of information data

7.1 From handling, storage, use or spillage

of hazardous materials.

No Hazardous wastes like Paints sludge as per

Hazardous Waste (Management, Handling

and Transboundry Movement) Rules,2008.

Well equipped Fire fighting system shall

be installed. Risk assessment and disaster

management plan shall be prepared.

Formation of Safety Department under

Safety Officer to take care of Occupation,

Hazard & Hygiene.

7.2 From discharge of sewage or other

effluents to water or the land (expected

mode and place of discharge).

No Treated sewage will be reused for

gardening within the premises.

7.3 By deposition of pollutants emitted to air into the land or into water.

No Dust will be generated during construction phase from earthworks and movement of

vehicles. Appropriate fugitive dust control

measures, including water sprinkling of

exposed areas and dust covers for trucks,

will be provided to minimize any impacts.

7.4 From any other sources. No --

7.5 Is there a risk of long term build up of

pollutants in the environment from

these sources?

No --

8. Risk of accidents during construction or operation of the Project, which could affect human

health or the environment

Sr.

No. Information/Checklist confirmation

Yes /

No

Details thereof (with approximate

quantities / rates, wherever possible) with

source of information data

8.1 From explosions, spillages, fires etc

from storage, handling, use or

production of hazardous substances

No Blasting is not allowed so risk of explosion

does not exist. Fire Fighting system is

operational to control any fire hazard.

Secondary containments are provided for all

liquids spillages. Hazardous wastes generated

will be disposed off as per The Hazardous

Page 12: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 13

Waste (Management, Handling and

Transboundry Movement) Rules, 2008.

8.2 From any other causes. No --

8.3 Could the project be affected by

natural disasters causing environmental

damage (e.g. floods, earthquakes,

landslides, cloudburst)?

No There is no history of such a disaster in the

area under reference. However, drains will

be designed of appropriate size. Structures

will be designed as per the Seismic zone

requirements.

9. Factors which should be considered (such as consequential development) which could lead

to environmental effected or the potential for cumulative impacts with other existing or

planned activities in the locality

Sr.

No.

Information/Checklist

confirmation Yes / No

Details thereof (with approximate

quantities / rates, wherever possible) with

source of information data

9.1 Lead to development of supporting, lities, ancillary development or

development stimulated by the

project which could have impact on

the environment e.g.:

• Supporting infrastructure

(roads, power supply, waste or

waste water treatment etc)

• Housing development

• Extractive industries

• Supply industries

• Other

No

Power, water, roads, wastes disposal

approvals are granted by as per State

Government rules hence no impact would be

observed for below mentioned

9.2 Lead to after-use of the site, which

could have an impact on the environment

No --

9.3 Set a precedent for later

developments

No The additional proposed Structures are to

support storage activities. Like, receiving of

materials, dispatch.

9.4 Have cumulative effects due to

proximity to other existing or

planned projects with similar

effects

No

The additional proposed Structures are to

support storage activities. Like, receiving of

materials, dispatch.

(III) Environmental Sensitivity

Sr.

No.

Information/Checklist

confirmation

Name/

Identity

Aerial distance (within 15 km.)

Proposed project location boundary

1 Areas protected under international No --

Page 13: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 14

Sr.

No.

Information/Checklist

confirmation

Name/

Identity

Aerial distance (within 15 km.)

Proposed project location boundary

conventions, national or local

legislation for their ecological,

landscape, cultural or other related

value

2 Areas which are important or sensitive for ecological reasons –

Wetlands, watercourses other water

bodies, costal zone, biospheres,

mounting, forests

Yes There is Panchaganga River at 15 km SE direction from site.

3 Areas used by protected, important

or sensitive species of flora or

fauna for breeding, nesting,

foraging, resting, over wintering,

migration

No --

4 Inland, costal, marine or

underground waters

No --

5 State, national boundaries No --

6 Routes or facilities used by the

public for access to recreation or other tourist, pilgrim areas

Yes State Highway No. 4- Mumbai –Bangalore

within 9 Km.

7 Defence installations No --

8 Densely populated or built-up area No NA

9 Areas occupied by sensitive man-

made land uses (hospitals, schools,

places of worship, community

facilities)

Yes As industry is located in MIDC Area all

infrastructure facilities are available.

.

10 Areas containing important, high

quality or scarce resources (ground

water resources, surface resources,

forestry, agriculture, fisheries,

tourism, minerals)

No --

11 Areas already subjected to pollution

or environmental damage. (those

where existing legal environmental

standards are exceeded)

No --

12 Areas susceptible to natural hazard which could cause the project to

preset environmental problems

(earthquakes, subsidence,

landslides, erosion, flooding

or extreme or adverse climatic

conditions)

No --

(IV). Proposed Terms of Reference for EIA studies: Not Applicable.

a xxx from yyy km distance

Page 14: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 15

Form IA

APPENDIX II

(See paragraph 6)

FORM-1 A (only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary attach

explanatory notes with the Form and submit along with proposed environmental management plan

& monitoring programme)

1. LAND ENVIRONMENT

(Attach panoramic view of the project site and the vicinity)

1.1. Will the existing land use get significantly altered from the project that is not consistent with

the surroundings? (Proposed land use must conform to the approved Master Plan /

Development Plan of the area. Change of land use if any and the statutory approval from the

competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features

of the proposed site (within 500 meters) and (iii) The site (indicating levels & contours) to

appropriate scales. If not available attach only conceptual plans.

Land Use Pattern:

The project falls within Kagal-Hatkanangale MIDC. The site is situated at D-3, D-3/1, D-3/2,

Kagal-Hatkanangle Five Star Industrial area, Dist-Kolhapur (Maharashtra) INDIA.

The project is an Industrial construction activity for manufacturing of Fettling, Shot blasting, Painting, &

machining Casting of ancillaries for tractors and farm equipments automotives and Engineering products.

The additional proposed structures are to support Storage activities like, receiving of materials, Separate

Storage and dispatch.

Agriculture / Livestock:

There is no agricultural activity in the vicinity of the proposed area. Industry is located in Kagal –

Hatkanangale five star MIDC.

Please refer the enclosed maps showing the following:

(i) Google Image

(ii) Layout of the site

Page 15: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 16

1.2. List out all the major project requirements in terms of the land area, built up area, water

consumption, power requirement, connectivity, community facilities, parking needs etc.

I. PROJECT DETAILS :

a. Name & Location: “M/s. Indus Ferrotech Ltd.”

A. Plot History:

This project is located at D-3, D-3/1, D-3/2, Kagal-Hatkanangle Five Star Industrial area, Dist-

Kolhapur (Maharashtra) INDIA, having plot area 62,491.00 Sq. mt.

• The Built-up area of the Project is 24,381.66 Sq.mt. Now we are applying for Obtaining

Environmental Clearance for the industrial construction project under 8(a) category of schedule.

b. Area Statement:

No. Description Area Sq. Mt.

a. Total Plot Area: 62,491

b. Built-up area approved by MIDC 24,381.66

c. Parking Statement:

As an Industry is in Kagal-Hatkanangale five star MIDC, Management has provided transportation Pick

and drop facility to their staff. so required parking area (6300.68 m2) is provided for bus, cars & two

wheelers.

d. Occupancy

665 nos. of staff including Contract and permanent.

a. Water Consumption: (Domestic and flushing requirement)

1. During Construction Phase: MIDC Source

• From MIDC: 20 KLD

2. During Operation Phase:

Total Water requirement of the project is:

Sr.

No.

Description Quantity of water required

m3/day

Source of water supply

a. Domestic 13 m3/day MIDC

b. Gardening 34 m3/day MIDC

c Processing 23 m3/day MIDC

Total 87 m3/day

Page 16: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 17

f. Sewage Generation:

Sewage:

• Sewage generation : 24 m3/day

• Capacity of STP (CMD): 25 m3/day

• STP Technology: MBR

Effluent:

• Effluent generation: 18 m3/day

• Capacity of ETP (CMD): 4 m3/Hr

g. Solid Wastes:

During Construction phase:

The total quantities of solid waste generated will be210 MT in the project; it will be disposed off

through existing authorized and local contractor.

During Operation Phase:

Total solid waste: 166 kg/day

Biodegradable waste: 116 kg/day. (will be handled over to authorized vendors for disposal)

Non-biodegradable waste: 50 kg/day. will be handed over to authorized contractors.

Use of dried STP sludge as manure.

Non Hazardous Waste

Sr.

No.

Type Quantity UoM Disposal

1. Griding /Fettling powder 25 MT/M Sale

2. Griding wheel 2000 nos. Sale

3. Shot blasting dust 25 MT/M Sale

4. CI boring /MS Turning 300 MT/M Sale

Hazardous waste Details:

Sr.

No.

Item no.

as per

HW

Schedule

Type of waste Quantity Disposal

Page 17: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 18

1. 21.1 Paint sludge 30MT/A CHWTSDF

2. 5.2 Hand gloves,oil soked rags/cotton 3.7MT/A CHWTSDF

3

5.1 Used oil/spent oil 15 KL/A Authorised

reprocesser/recycler

4 33.3 Discarded containers 6000 nos/A CHWTSDF

5 12.2 Alkali residue 1.44MT/A CHWTSDF

6 14.1 Nitrite containing sludge 7MT/A CHWTSDF

7 12.3 Spaint bath sludge 3.6MT/A CHWTSDF

8 12.5 Phosphate sludge 6.2MT/A CHWTSDF

h. Power requirement:

For Construction Phase:

During Construction Phase -

Source: MSEDC

During Operational Phase – Source: MSEDC

Sr. No. Details Unit

1. Connected Load 2.5 MVA

2. Maximum Demand 1.0 MVA

3. D.G set 1.5 MVA

1.3. What are the likely impacts of the proposed activity on the existing facilities adjacent to

the proposed site? (Such as open spaces, community facilities, details of the existing landuse,

disturbance to the local ecology).

No impact on adjacent facilities due to proposed development. All required pollution control

equipments in the proposed facility to control liquid, solid and air pollutant parameters.

1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability?

(Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc. may be given).

No significant land disturbance as the site is flat land. As per the Seismic Zoning Map of India,

Kolhapur region falls under Zone-II. Stability Certificate, as per prevalent IS Code will be

obtained for these buildings from registered Consulting Structural Engineer considering the

seismic forces and wind forces etc.

aaa

Page 18: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 19

1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour

map showing the natural drainage near the proposed project site)

For building structure there will not be any alteration in existing natural drainage systems.

1.6.

1.7

What are the quantities of earthwork involved in the construction activity-cutting, filling,

reclamation etc. (Give details of the quantities of earthwork involved, transport of fill

materials from outside the site etc.)

Excavation in the form of rubble and soil. Part of this soil and rubble will be used

for back filling and remaining material will be disposed within the site.

Give details regarding water supply, waste handling etc during the construction period.

During Construction Phase -

• Approximate 20 KLD water is required for proposed construction during construction phase.

Water will be utilized from existing source and it will be well within consented quantity.

• Sewage will be treated in Sewage treatment plant and reused for gardening/horticulture. And it

will well within demand.

• Non Hazardous waste generated from the construction is reused predominantly for filling and

compaction of site.

1.8

Will the low lying areas and wetlands get altered? (Provide details of how low lying and

wetlands are getting modified from the proposed activity)

There is no low laying area and wetlands are available in the existing site which is going to be

affected due to the project

1.9

Whether construction debris & waste during construction cause health hazard? (Give

quantities of various types of wastes generated during construction including the

construction labour and the means of disposal)

Page 19: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 20

Excavated material will be generated as mentioned below; same would be used within premises

for land leveling.

Nominal dust level is expected during the construction phase. Proper measures such as sprinkling

of water on the ground and new construction will be done at regular intervals to reduce the

spreading of the dust particles.

Wastes generated by Construction labor-

Biodegradable garbage = 20m3 /day

Non-biodegradable garbage = NIL

Total : 20 m3 /day

The total quantities of Non-biodegradable waste generated in the project will be disposed off

through existing authorized contractor.

2. WATER ENVIRONMENT

2.1. Give the total quantity of water requirement for the proposed project with the breakup of

requirements for various uses. How will the water requirement be met? State the sources

& quantities and furnish a water balance statement.

Water Requirement & Sources :

For Construction : From MIDC

MIDC: 20 KLD (depending upon the activity).

During Operational Phase -

Total Water Requirement. :

For Domestic : 13 m3/ day.

For Gardening : 34m3/ day.

For processing : 23 m3/ day

Total Water Requirement: 87 m3 /day.

(When sewage Treatment Plants will run in the full-fledged condition treated water is reused for

flushing, paint shop & gardening. So that extra load on the MIDC water supply system will be

reduced)

Page 20: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 21

Net water Demand from local water supply body will be 47 m3 /day only.

• Water demand for fire fighting is one time and occasional. Therefore water requirement for fire

fighting has not been considered while calculating daily water requirement.

Sr.

No. Description Input

M3/day Loss

M3/day Reason for

Loss Effluent

M3/day

Remark

1 Domestic 13.00

Consumption

2 Flushing 17

7.2

Loss

22.8 Domestic

Effluent

3 Gardening 34 NIL Loss 0 -------

4 Process 23 5.9 Processing 17.1 Industrial

Effluent

TOTAL 87 13.1 ------- 39.9 -------

Page 21: Annexure II-Sample Filled Form

Form I &IA and Consolidated statement

M/s. Indus Ferrotech Ltd.” At D-3, D-3/1& D-3/2, Kagal-Hatkanangale Five Star industrial Area, Kolhapur. Page 22

Water Balance daily Requirement